Citation : 2012 Latest Caselaw 4366 Del
Judgement Date : 24 July, 2012
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Date of Decision: 24.07.2012
% FAO(OS) 328/2012
VIPUL LTD & ANR ..... Appellants
Through: Mr. R.K. Varmani, Senior Advocate,
with Mr. Manish Sharma, Mr. Rohan
Sharma & Mr. Vishal Malhotra,
Advocates.
versus
RAKESH GUPTA ..... Respondent
Through:
CORAM:
HON'BLE MR. JUSTICE SANJAY KISHAN KAUL
HON'BLE MR. JUSTICE VIPIN SANGHI
VIPIN SANGHI, J. (Oral)
C.M. No.12428/2012 (Exemption)
Allowed, subject to just exceptions.
FAO(OS) 328/2012 & C.M. Nos. 12427/2012
1. The appellant assails the order dated 20.04.2012 passed by the
learned Single Judge in O.M.P. No. 364/2012, whereby the objections
preferred by the appellant to the arbitral award dated 11.01.2012
passed by the sole Arbitrator, under Section 34 of the Arbitration &
Conciliation Act, 1996 (the Act) have been dismissed.
2. The parties had entered into a contract on 18.01.2005
whereunder the respondent had been allotted Unit No. 102 on the first
floor in Tower No. 3 of "Orchid Petals" - a residential group housing
complex in Sector 4, Gurgaon, Haryana. The appellant is the builder
who had made the allotment to the respondent. It appears that the
respondent made certain payments on 14.07.2005 and 17.11.2004
and consequently, the appellant issued an allotment letter on
18.01.2005 allotting the aforesaid unit having super area of 1724
square feet for a total consideration of Rs.29.82 Lakhs to the
respondent. The respondent was called upon to make certain deposits
which were made on 18.02.2005. It appears that, thereafter, the
respondent defaulted in making payment of subsequent installments.
When the respondent sought to tender payments on 01.05.2006 under
cover of letter sent by speed post, the appellant did not accept the
same. The appellant returned the payment tendered by the
respondent vide a notice dated 03.05.2006 and informed the
respondent that the booking of the apartment in his favour has been
cancelled. The respondent did not accept the said cancellation and re-
tendered the pay orders to the appellant on 31.05.2006, however, the
appellant once again returned the payments tendered by the
respondent on 07.06.2006 and also sought to refund the amounts
earlier deposited by the respondent and accepted by the appellant by
tendering a cheque. In these circumstances the dispute arose
between the parties, and the Court appointed the sole Arbitrator (a
retired Judge of this Court) on 22.02.2007 in O.M.P. No. 322/2006.
3. The respondent claimed the relief of specific performance of the
contract and, in the alternative, a sum of Rs.30 Lakhs as damages
along with refund of the amount received by the appellant.
4. In its defence the appellant pleaded that the payments, even
earlier made by the respondent, were belated, however, they were
accepted and receipt issued. The appellant issued demand letters for
the installment of Rs.2,23,650/- on 01.06.2005 followed by another
letter dated 12.07.2005 but no payment was received. The reminders
were sent on 14.09.2005 and 07.12.2005. By letter of 01.03.2006, the
respondent was asked to make payment of the outstanding amount of
the two installments of Rs.2,23,650/-. A reminder was sent on
22.03.2006 asking the respondent to pay Rs.6,70,950/- which was due
as on 06.04.2006. By letter dated 21.04.2006, the respondent was
asked to pay Rs.8,94,600/- on or before 08.05.2006.
5. The Arbitral Tribunal did not accept the defence of the appellant,
inter alia, on the ground that the appellant itself had granted time to
the respondent vide the letter dated 21.04.2006 to make the payment
on or before 08.05.2006. When the respondent tendered payment on
01.05.2006, the appellant sought to backtrack by refusing to accept
the payment and purporting to terminate the agreement. Accordingly,
the Arbitral Tribunal passed an award directing specific performance of
the agreement between the parties and requiring the respondent to
make payment of the entire outstanding amount along with interest @
15% per annum, which was the agreed rate of interest between the
parties, after granting adjustment of the amount already paid by the
respondent.
6. The appellant relies upon the decision of the Hon'ble Supreme
Court in Mrs. Saradamani Kandappan Vs. Mrs. S. Rajalakshmi &
Others, AIR 2011 SC 3234, wherein the Hon'ble Supreme Court has
taken a view contrary to the earlier held view that, generally, time is
not of the essence of an agreement to sell or purchase immovable
property. The Hon'ble Supreme Court in Saradamani Kandappan
(supra) has held that keeping in view the rapid increase in prices of
immovable property in the present time, the earlier held view that time
is, generally, not of the essence of an agreement to sell, cannot be
accepted. On this basis it is argued by learned senior counsel for the
appellant that the award proceeds on a wrong legal premise as
declared by the Hon'ble Supreme Court and, therefore, the same is
opposed to the public policy and liable to be set aside.
7. We have heard learned senior counsel for the appellant, perused
the award and the impugned order as well as perused the judgment of
the Hon'ble Supreme Court in Saradamani Kandappan (supra). The
award primarily is founded upon the act and conduct of the appellant
in itself granting time to the respondent to make payment of the
outstanding amounts along with interest @ 15% per annum. The said
communication dated 21.04.2006 issued by the appellant to the
respondent is pertinent and the relevant extract thereof reads as
follows:
"Subject: Installment Due for Flat No. 102, TOWER NO.3, ORCHID PETALS, SECTOR-49, SOHNA ROAD, GURGAON, Haryana.
Dear Sir/Madam,
This has reference to your booking of the above mentioned Flat the following amount is due as per our record.
Installment Due Date Amount
Outstanding as on date (to be calculated on 670950.00
receipt of installment due)
CASTING OF FOURTH 08-May-2006 223650.00
FLOOR ROOF SLAB
Amount Payable 894600.00
You are requested to kindly clear the dues of Rs.894600.00 (Rupees Eight Lakh Ninety Four Thousand Six Hundred Only) in favour of "VIPUL ORCHID PETALS SALES A/C" Payable at New Delhi, As per due date.
An interest of 15% shall be payable on all delayed payments. However, if the allottee(s) fails to pay interest on delayed payment the same shall be charged by the company either at the time of delivery of possession or at the time of transfer of aforesaid, which ever is earlier.
Thanking You & assuring you of our best service.
For Orchid Infrastructure Developers Pvt. Ltd"
8. The aforesaid communication shows beyond doubt that the
appellant itself granted time to the respondent to make payment of
the outstanding amount by 08.05.2006. The appellant also stated that
interest @ 15% per annum shall be payable on all belated payments,
meaning thereby that the appellant is agreeable to accepting belated
payments along with interest @ 15% per annum. It also notes that if
the allottee fails to pay interest on belated payment, the same shall be
charged by the appellant either at the time of delivery of possession or
at the time of transfer of unit, whichever is earlier. Therefore, non-
payment of interest on belated payments itself was also not reserved
as a ground to terminate the agreement. Pertinently, there is nothing
in this letter to show that the appellant ever put the respondent to
notice that the agreement may be terminated in case of non-payment
of the outstanding amount.
9. The appellant has itself disclosed the various occasions on which
time was extended by it from time to time to enable the respondent to
make payment. The learned Arbitrator on the basis of the aforesaid
conduct of the appellant concluded that it could not be said that time
was of the essence of the agreement. The said finding has been
arrived at by learned Arbitrator by appreciation of the facts and
evidence before him. It is not for the Court, while dealing with the
objections under Section 34 of the Act, to interfere with the factual
findings based on the evidence led before the Arbitral Tribunal,
particularly when it cannot be said that the said finding is not
supported by any evidence.
10. The decision in Saradamani Kandappan (supra), in our view, is
of no avail in the facts of this case since the conduct of the parties
shows that neither of them considered time to be of the essence of the
contract. The Hon'ble Supreme Court in Saradamani Kandappan
(supra) has not held that in all contracts relating to sale & purchase of
immovable property, necessarily, time is always of the essence. The
said aspect would have to be determined upon examination of, inter
alia, the conduct of the parties and upon examination of the manner in
which the parties have understood and worked out their contract.
11. For the aforesaid reasons, we find no merit in this appeal and
dismiss the same, leaving the parties to bear their own costs.
VIPIN SANGHI, J
SANJAY KISHAN KAUL, J
JULY 24, 2012 'BSR'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!