Citation : 2012 Latest Caselaw 2599 Del
Judgement Date : 20 April, 2012
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO 159/2012
% Date of Decision: 20.04.2012
METRO BUILDTECH PVT LTD ..... Appellant
Through : Mr. Ravinder Sethi, Sr. Advocate
with Mr. Ashish Mohan and
Mr. Puneet Sharma, Advocates
versus
STANDARD CHARTERED BANK ..... Respondent
Through : Mr. Neeraj Kishan Kaul, Sr. Advocate
with Mr. Nakul Mohta, Advocate
CORAM:
HON'BLE MS. JUSTICE VEENA BIRBAL
VEENA BIRBAL, J. (ORAL)
*
1. Present is an appeal under section 37(2)(a) of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as „the Act‟) against the
impugned order dated 16th March 2012 passed by the learned Arbitrator
under Section 17 of the Act in an arbitration matter between the parties.
2. The relevant factual background is as under:-
The State Bank of India had extended loan facility to one M/s
Vishal Global Ltd. An equitable mortgage was created by the aforesaid
borrower by deposit of title deeds of property bearing No. C-4, West End,
New Delhi. On default of non-payment, the recovery proceedings were
initiated by the State Bank of India against borrower M/s Vishal Global
Ltd before the D.R.T-I, Delhi. On 5th June, 2002, recovery certificate in
the sum of Rs.7,37,84,093.13 along with pendent lite interest @ 17% p.a.
with quarterly interest was issued in favour of SBI with liberty to recover
the certificate amount inter alia by sale of the suit property. The State
Bank of India assigned the said debt to respondent bank on 29.03.2006
acquired by way of a registered Assignment Deed. In view of the
Assignment Deed dated 29.3.2006, respondent was substituted in place
of State Bank of India in R.C.No.263/2002 and respondent started
pursuing the matter for recovery of outstanding amount pending before
D.R.T-I, Delhi from the borrower and its guarantors. During the
pendency of the proceedings, a Memorandum of Understanding
(hereinafter referred to as the MOU) dated 29th September, 2008 was
executed between the appellant and the respondent wherein all the rights,
title, interest acquired by respondent under the assignment deed dated
29.03.2006 were transferred in favour of appellant and for the said
purpose appellant was required to pay Rs. 18 crores to respondent in the
following manner:-
(i) Rs.4 crore at the time of signing and execution of the MOU vide draft/cheque no.254362 drawn in favour of Standard Chartered Bank a/c Vishal Global Ltd.
(ii) Rs.1 crore on or before 29th December, 2008;
(iii) Rs.2 crores on or before 29th January, 2009
(iv) Rs.2 crores on or before 29th February, 2009
(v) Rs.9 crores on or before 29th March, 2009.
3. The second instalment of Rs.1 crore which was given by way of
cheque was honoured. Two cheques of Rs. 2 crore each were
dishonoured on account of insufficient funds and cheque of Rs.9 crore
was not presented by the respondent at the request of the appellant. It is
stated that on 3rd April, 2009, appellant approached respondent for
rescheduling the payment of balance consideration due to economic
recession. It is stated that on 16th April, 2009, appellant came to know of
the judgment in Kotak Mahindra Bank Ltd Vs O.L. of APS Star Ind.Ltd.
(2009) 3 Comp LJ (Guj) wherein it is held that an assignment deed
whereby a debt is assigned by a bank to a private third party along with
the underlying security is not a valid instrument. Accordingly, appellant
got worried as they had already made huge payment and appellant
immediately sent a letter dated 16th April, 2009 to the respondent bringing
to its notice the aforesaid facts.
4. It is alleged that the MOU was permitting extension of time.
Despite that, respondent did not extend the time and rather sent a letter
dated 15.04.2009 which was received by the appellant on 18.04.2009
whereby it was intimated that the respondent had terminated the MOU
and also informed having forfeited Rs. 5 crores. It is alleged that the
respondent refused to accept the request of the appellant vide letter dated
16.04.2009 and again reiterated its stand of forfeiture of Rs. 5 crores. On
12.05.2009, appellant sent a notice for referring the dispute to Arbitration
in accordance with Clause 9 of MOU. Thereafter, appellant filed a
petition before this court under Section 9 of the Act seeking interim
injunction. On 14.12.2009, the counsel for respondent stated before this
court that as the talks for settlement between the parties were going on
before Mediation and Conciliation Centre, respondent would maintain
status quo as regards alienation/parting with possession of property in
question. Thereafter, the petition under Section 9 was disposed of with
liberty to respondent to file an application under Section 17 of the Act in
respect of the status quo order. Thereupon, respondent filed an
application under Section 17 of the Act before the learned Arbitrator
seeking an order vacating the status quo order dated 14.12.2009. The
learned Arbitrator vide impugned order dated 16.03.2012 vacated the
status quo order and directed that the respondent is free to sell the
property in question subject to deposit of Rs. 5 crores with the Registrar
to be deposited within four weeks of the sale.
5. Aggrieved with the said order, present appeal is filed.
6. The learned counsel for the appellant has contended that when the
main claim of specific performance of MOU dated 29.09.2008 is pending
consideration before the learned Arbitrator, the learned Arbitrator ought
not have ordered that the bank is free to sell the property in question. It is
contended that if the status quo order as was granted earlier, is not
restored, third party interest would be created and it will complicate the
matter further. It is further contended that in any event the impugned
order does not fully protect the interest of respondent. It is contended that
the learned Arbitrator ought to have ordered for the deposit of interest
also which has accrued on Rs.5 crores which is admittedly lying with the
respondent. It is contended that by not securing the accrued interest on
the aforesaid amount, a great prejudice has been caused to the appellant.
7. On the other hand, the stand of the respondent is that vide MOU
dated 29.09.2008, the appellant was supposed to pay Rs.18 crores in the
manner provided under clause 2.1 of the MOU and the last payment of
Rs.9 crores was to be paid on 29.03.2009. It is contended that extension
of time under clause 5.1 was permissible, however, the same was subject
to payment of interest @ 24% per annum on the delayed amount, with the
limitation that the extension of time under no circumstances could exceed
beyond 29.03.2009. It is further contended that clauses 5.2 and 5.3 of
MOU dated 29.09.2008 clearly provide the right to the respondent to
terminate or rescind the MOU and also for forfeiture of amount in case of
violation of terms of MOU. It is contended that in the present case the
appellant has sought initially extension of time on the ground of
economic recession which was not a valid ground. It is contended that
the letter dated 16.04.2009 was sent by the appellant rescinding the MOU
when the time for payment under MOU had already elapsed. It is further
contended that even the grounds stated therein are also not valid grounds.
8. I have heard the learned senior counsel for the parties.
9. The challenge in this appeal has been made to the impugned order
dated 16.03.2012 wherein it is ordered that interim relief continuing the
order of status quo in respect of the property in question cannot be
granted. The learned Arbitrator has further noted that whether the
forfeiture of Rs.5 crores by the bank is justified and is in the nature of
penalty is one of the issues that is to be determined in the arbitration
proceedings and as such as an interim measure, out of sale proceeds, Rs.5
crores were directed to be deposited by the respondent bank with the
Registrar of this court.
10. It is admitted position that the parties have entered into MOU dated
29.09.2008. The mode of payment under the MOU under the clause 2.1
is as under:
"(a) Rs.40 million at the time of signing and execution of the MOU vide cheque no.254362 drawn in favour of Standard Chartered Bank a/c Vishal Global Ltd.
(b) Rs.10 million on or before 29th December, 2008;
(c) Rs.20 million on or before 29th January, 2009.
(d) Rs.20 million on or before 29th February, 2009.
(e) Rs.90 million on or before 29th March, 2009."
11. The clause 2.3 of the MOU clearly provides that time is the essence
of the agreement. It is clearly provided therein that the agreement
remains in force till 29.03.2009. The clause 5.1 provides that extension
of time for payment under no circumstances will exceed 29.03.2009. The
right to terminate MOU and forfeiture of amount paid by Assignee is
provided under Clause 5.2 of MOU. The relevant clauses of MOU are
reproduced as under:-
"2.3 That the parties have agreed that the present MOU shall remain valid and in force till 29th March 2009. It is agreed and understood by the parties that the time is the essence of this Agreement and the payment schedule as specified hereinabove shall be strictly adhered to by the Assignee. Unless entire amount is paid by the Assignee in terms of this MOU, the Assignee waives all of its right to claim specific performance of this MOU.
xxxxx xxxxx xxxxx xxxxx
xxxxx xxxxx xxxxx xxxxx
5.1. That the Assignee assures the Assignor that it shall make all efforts to ensure the payment of the consideration strictly as per the details and schedule agreed under clause 2 (supra) of this MOU. However, in the event of any delay being caused and a request being made in writing by the Assignee to the Assignor for extending the time for payment of any installment, except the last installment, the Assignor may SOLELY at its discretion agree to such extension, however, subject to the payment of interest @ 24% per annum on the delayed amount and with limitation that the extension of time under no circumstances will exceed 29.03.2009. The Assignor will not be obliged to provide an explanation of any kind for refusal in granting extension.
5.2 That in case the Assignee fails to make the payment of the consideration in terms of clause 2 (Supra) of this MOU or the Assignor refuses to grant extension in terms of clause 5.1 (Supra) of this MOU or any of the cheque tendered by the Assignee is dishonoured upon presentation, the Assignor shall have the exclusive right to terminate and rescind the present MOU and to forfeit the amount which the Assignee has paid up till that date."
12. The terms of MOU as noted above are very clear. Perusal of
record shows that earlier appellant had requested for rescheduling the
payment of balance consideration and thereafter vide its letter dated
16.4.2012, it had recalled the offer. Even extension of time for making
balance payment was sought after the time limit for payment under the
MOU had already expired. After considering the relevant material on
record, the learned Arbitrator had modified the status quo order and has
observed that default has undeniably occurred on the part of the appellant
and for the said reason, continuing of the status order cannot be granted.
The learned Arbitrator had exercised his discretion in modifying the
interim order. Nothing has been placed to show that discretion has been
exercised in arbitrary, capricious or in perverse manner. Further the same
has been exercised after considering the material on record. In these
circumstances, it will not be appropriate to reassess the material on record
and reach a conclusion other than the one arrived at by the learned
Arbitrator especially when the conclusion arrived at is reasonably
possible on the basis of material on record. Reference is made to
Wander Ltd. and Another vs. Antox India P. Ltd.; 1990 (Supp) Supreme
Court Cases 727.
Further the learned Arbitrator has fully protected the interest of the
respondent by ordering that out of the sale proceeds Rs.5 crore shall be
deposited by the respondent with the Registrar of this court and same
shall be invested in short term interest bearing fixed deposit during the
pendency of the proceedings. The entitlement of the appellant for the
amount paid under the MOU is yet to be decided in the arbitration
proceedings. In these circumstances, even if no order has been made for
the deposit of interest on the amount of Rs. 5 crore, the impugned order
cannot be said to be illegal.
In view of the above discussion, no illegality is seen in the
impugned order.
Appeal stands dismissed.
VEENA BIRBAL, J APRIL 20, 2012 ssb/srb
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!