Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Kalinga Power Corporation Ltd. vs Union Of India & Ors
2012 Latest Caselaw 2400 Del

Citation : 2012 Latest Caselaw 2400 Del
Judgement Date : 13 April, 2012

Delhi High Court
Kalinga Power Corporation Ltd. vs Union Of India & Ors on 13 April, 2012
Author: Rajiv Sahai Endlaw
*      IN THE HIGH COURT OF DELHI AT NEW DELHI
                                         Date of decision: 13th April, 2012
+                         W.P.(C) No. 4489/2005

%      KALINGA POWER CORPORATION LTD.         .....Petitioner
                  Through: Mr. C.S. Vaidyanathan, Sr. Adv. with
                           Mr. K.B. Rohtagi, Ms. Aparna
                           Rohtagi, Mr. Mahesh Kasana, Mr.
                           S.K. Dhingra & Mr. Anand Verma,
                           Advs.
                                   Versus
       UNION OF INDIA & ORS.                              ..... Respondents
                    Through:           Mr. Piyush Sanghi, Adv. for Mr.
                                       A.S. Chandhiok, ASG for R-1.
                                       Ms. Aishwarya Bhati with Gp. Capt.
                                       Karan Singh Bhati, Advs. for R-5&6.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW


RAJIV SAHAI ENDLAW, J.

1. This petition impugns the letter dated 02.07.2003 of the Ministry of

Coal, Government of India, de-allocating the "Utkal-A captive coal block

for supply of coal to the proposed Duburi Thermal Power Station" of the

petitioner. The petition also seeks to restrain the respondents from allotting

„the area in question‟ to anyone else including the respondent No.5

Mahanadi Coalfields Ltd. or to the respondent No.6 Coal India Ltd. (CIL).

The petitioner also seeks mandamus directing the respondents to allow the

petitioner to carry on the development and other activities necessary for the

project. Before the notice of this petition could be issued, Jindal Thermal

Power Company Ltd. And Jindal Vijaynagar Steel Ltd. applied for

impleadment averring that the „coal mine in question‟ after de-allocation

from the petitioner stood allotted to them and any decision in this petition

would affect their rights. They were impleaded as respondents No.7&8.

Notice of the petition was issued. Pleadings have been completed and the

counsels have been heard. The counsel for the petitioner has also filed a

synopsis of submissions.

2. The petitioner proposes to set up a 2x250 MW coal based thermal

power plant at Duburi in Jajpur district of Orissa; the capacity of the power

plant is proposed to be expanded by another 500 MW in the second phase.

For meeting the coal requirement for the power plant, the Ministry of Coal,

Government of India vide letter dated 10.08.1993 allotted the aforesaid

Utkal-A Coal Block to the petitioner under the Scheme for Allotment of

Captive Coal Mining Blocks to Power, Steel and Cement Sectors.

3. The letter dated 02.07.2003 impugned in this petition, while

cancelling the aforesaid allotment in favour of the petitioner, records:

(i) that the progress of the coal mining development project as

well as the proposed captive thermal power station was

reviewed in the various meetings of the Screening Committee

from time to time;

(ii) that in the meeting on 03.04.1996, it was informed by the CIL

that the petitioner had not made any progress with regard to the

development of the captive block and even the exploration cost

had not been paid to CIL; accordingly a decision was taken that

unless the exploration cost was paid within thirty days, the

offer for the captive mining block shall be liable for

cancellation;

(iii) that in the meeting held on 14.11.1996, the Director of the

petitioner Company had informed that no steps for

development of the captive mining block had been taken till

then i.e. for three years, since the Power Purchase Agreement

in respect of the proposed Duburi Thermal Power Station was

under revision and further since the requisite approvals for the

mining project had not been received till then;

(iv) in the meeting of the Screening Committee held on 26-

27.09.1997, it was noted that the petitioner inspite of several

communications had not paid the exploration charges till then;

it was again decided that unless the exploration charges were

paid within three months, the allotment will be cancelled;

(v) that in the meeting of the Screening Committee held on

03.04.1998, it was observed that in the absence of a fixed time

frame, the said block may be considered for other applicants;

the representative of the petitioner present in the said meeting

had also explained the problem being faced by the petitioner in

implementing the power project inasmuch as the Government

of Orissa had backed out of the MOU on purchase of power;

the Screening Committee deferred the decision by three

months;

(vi) in the meeting of the Screening Committee held on 24.08.1998,

the matter was again deferred;

(vii) in the meeting of the Screening Committee held on

18/19.06.1999, it was again noticed that the petitioner had not

paid the exploration charges till then and that the representative

of the petitioner had informed that though the mining plan had

been submitted by the petitioner but had been found to be

based on inadequate geological data;

(viii) that in the meeting of the Screening Committee on 06.03.2000,

it was again noted that the petitioner had not paid the

exploration cost till then; the representative of the petitioner

however committed payment by 31.03.2000;

(ix) in the meeting of the Screening Committee held on 31.05.2001,

representative of the petitioner informed that the submission of

the mining plan was delayed because the viability of the project

was being determined, though the petitioner was confident of

implementing the power project; the petitioner further

represented that the financial closure would be achieved by

December, 2001 and the power plant would come into

operation in 2005;

(x) that in the meeting of the Screening Committee held on

28.11.2001, it was informed by the representative of the

petitioner that mega power projects were coming up in Orissa

whose power would be cheaper than of the proposed plant of

the petitioner; it was also informed that financial closure even

of the power plant of the petitioner had not been achieved till

then;

(xi) that in the meeting of the Screening Committee held on

26.05.2003, the representative of the petitioner informed that

the commissioning of the power plant had been tentatively

postponed till 2007 and the actual coming up of the plant

would depend upon the petitioner obtaining the approvals for

selling the power; the petitioner requested for being allowed to

mine and sell coal pending the setting up of the power plant but

which permission was refused, the allocation being for captive

mining for specified end user.

The Screening Committee accordingly decided that since the very

coming up of the power plant of the petitioner was uncertain and further

since nine years had elapsed since the allocation of the captive block, the

same be de-allocated.

Accordingly, the letter dated 02.07.2003 (supra) of de-allocation was

sent to the petitioner.

4. The senior counsel for the petitioner has challenged the de-allocation

on the ground of;

(i) violation of principles of natural justice. It is contended that

neither any notice nor any hearing was given to the petitioner

before de-allocation;

(ii) discrimination i.e. no such action has been taken against others

similarly situated;

(iii) that the principle of first come first served applied to coal also;

(iv) that though by now all the clearances for setting up of the

power project have been received but without the assurance of

supply of coal, the petitioner is not in a position to set up the

power plant; it is argued that the de-allocation has created a

chicken and egg situation;

(v) that the petitioner has already paid a sum of `3.8 crores for

surveys;

(vi) that the petitioner has already made investment of `10/- crores

in the project on the assurance of supply of coal.

5. The respondent No.1 Ministry of Coal in its counter affidavit has

inter alia stated that, the coal mines in the country were nationalized in

1973 except the leases held by the Iron and Steel producers for use of coal

in producing iron and steel; that in June, 1993 the Coal Mines

(Nationalization) Act, 1973 was amended whereby a company engaged in

power generation was also permitted to do mining of coal for captive use in

the power plant; subsequently cement producers were also permitted to do

coal mining for captive use; that the Screening Committee was constituted

to consider proposals / requests for allocation of coal blocks for captive use

in the specified end-uses; the said Screening Committee is a inter-

ministerial and inter government body having representatives from the

Ministry of Power, Ministry of Commerce and Industries, Ministry of

Railways, Ministry of Steel and Representatives of the State Government

concerned; that the basic concern of the Government is that the coal mine

and the end use plant should be developed / installed in such a manner that

there is no imbalance resulting in coal stocks lying unused while the end use

capacity still remains to come into being; mismatch in timing of coal

production and end use plant commissioning can lead to disposal of coal by

the allocatee in the open market on the pretext that the coal cannot be

stacked for long without being a fire hazard; that therefore the Screening

Committee holds meetings for review of progress of development of coal

mines and installation of the intended end use project of the allocatee and in

case finds prolonged unsatisfactory progress, considers de- allocation of the

block.

6. It is further the stand of the Ministry of Coal that since the proposed

power plant of the petitioner was nowhere in sight inspite of ten years

having elapsed and further since other entrepreneurs with existing power

generation capacity need the coal block, there was no rationale in waiting

indefinitely for the uncertain power plant of the petitioner. It is further

pleaded that such de-allocation does not bar the petitioner from applying for

available coal blocks when its power plant becomes a reality. It is yet

further pleaded that after de-allocation, the said coal block was displayed on

the website of the Ministry of Coal on 29.05.2003 for aspiring entrepreneurs

and the applications received were considered by the Screening Committee

in the meeting held on 10.01.2005 and subsequently in a meeting held on

20.01.2005 the block was allotted to three companies selected by the

Screening Committee.

7. The respondents No.7&8 have pleaded that as opposed to the

petitioner which has not even been able to get a single approval and sanction

for its proposed power project, they have an operational 260 MW power

plant as well as an operational 1.6 million tonne steel plant for which they

have to import coal; that the coal from the „aforesaid area‟ would be utilized

for the additional 2x250 MW power plant that is proposed to be added to the

existing capacity of their Power Plant as per the expansion project; that all

the requisite sanctions and approvals for such expansion save allocation of

coal mine block had been received; that recommendation for allotment of

Utkal-A Coal Block in their favour had already been made; that the coal

block allotted to the petitioner has since been merged into an adjoining coal

mine block and been re-allocated. The said respondents in their counter

affidavit have also set out the various clearances already received by them

for their expansion project.

8. The Mahanadi Coal Fields Ltd. and CIL have also in their written

submissions opposed the petition.

9. At this stage, the nature of allocation in favour of the petitioner

(impugning cancellation of which this petition has been filed) may be seen.

The petitioner was, vide letter dated 10.08.1993 of the Ministry of Coal,

with reference to its application dated 06.05.1992 informed, that the

Screening Committee had identified the aforesaid coal block as suitable for

development by the petitioner as a captive source for supply of coal to the

proposed thermal power plant of the petitioner and requested to approach

CIL / Mahanadi Coal Fields Ltd. for more detailed information and then

contact the concerned State Government authorities for completing the

necessary formalities with regard to obtaining the lease of mining rights.

Vide subsequent letter dated 07.02.1996 of the Government of Orissa, the

petitioner was informed of the decision of the State Government to allot

mining lease of the specified area in favour of the petitioner and the

petitioner was requested to furnish the mining plan and take other steps.

However no mining lease came to be executed in favour of the petitioner

since the petitioner failed to complete the requisite formalities for execution

thereof.

10. Thus the right of the petitioner is only under a document of allocation

and not under any mining lease. The said allocation itself was subject to

fulfillment of various conditions and which have not been fulfilled by the

petitioner.

11. I have therefore wondered as to what is the right of the petitioner. It

is the settled position in law that such minerals including coal are a national

asset to be used for the good / betterment of public at large. The Supreme

Court in Centre for Public Interest Litigation v. Union of India (2012) 3

SCC 1 held that public trust doctrine enjoins upon the Government to

protect the resources for enjoyment of general public rather than to permit

their use for private ownership or commercial purposes. It was further held

that this doctrine puts an implicit embargo on the right of the State to

transfer public property to private party if such transfer affects public

interest and mandates affirmative State action for effective management of

natural resources. Reliance was placed on M.C. Mehta v. Kamal Nath 1997

(1) SCC 388 laying down that it is the duty of the Government to provide

complete protection to natural resources as trustee of people at large. I have

wondered as to what public good is being served or will be served by

keeping the coal reserved for the petitioner when till date, after nearly ten

years have passed, the power plant of the petitioner is nowhere in sight. The

intent of the petitioner became clear when the petitioner as aforesaid without

even setting up the power plant for captive use of coal wherein allocation

was made in favour of the petitioner, wanted mining rights with permission

for sale of the coal. It is thus clear that the petitioner itself did not want to

preserve the coal for captive use in the power plant and rather wanted to

profiteer therefrom. The same was / is impermissible.

12. As far as the ground of violation of principles of natural justice is

concerned, the decision aforesaid was a purely administrative decision. The

Scheme of allocation as explained in the counter affidavit of the Ministry of

Coal requires the Ministry to, from time to time assess the situation. It is

clearly borne out from the Minutes of the Meetings of the Screening

Committee that the petitioner was aware of and was participating in the said

assessment being done. Once the petitioner was part of the assessment, law

does not require pedantic compliance of such principles by still insisting on

a notice being given. Moreover, as aforesaid, the petitioner even now has

precious little to explain and no prejudice is shown to have been suffered by

the petitioner.

13. As far as the ground of discrimination is concerned, no basis therefor

has been laid in the writ petition. Moreover even if that be so, once the

decision of de-allocation is found to be correct, merely because a wrong is

being perpetuated qua others would not be a ground or reason to interfere

with the same. There is no negative equality (See Union of India v. M.K.

Sarkar 2010(2) SCC 59) and the remedy if any, of the petitioner is to

challenge the continuance of allocation in favor of those no longer eligible.

In Union of India v. M.K. Sarkar 2010(2) SCC 59 the Supreme Court

observed that a claim on the basis of guarantee of equality, by reference to

someone similarly placed, is permissible only when the person similarly

placed has been lawfully granted the relief and the person claiming relief is

also lawfully entitled for the same.

14. This writ petition has remained pending for eight years. The

petitioner even during the said time has been unable to report any progress

in the setting of its power project. It is now more than twenty years since

when the petitioner had conceived the thermal power plant. In the said two

decades, there has been a sea change in the industrial and economic sector.

The Indian economy has opened up to foreign investments. Nuclear Power,

then a distant dream is available. Environmentalists are requiring a relook

at thermal power plants. Coal reserves have been depleting. The petitioner

cannot act on projections / estimates which are decades old. This Court is

thus unable to assume that merely because the petitioner had twenty years

ago conceived setting up of a power plan, it will definitely be set up.

Moreover, if the petitioner ultimately sets up, it will be entitled to apply

again. Even if it were to be held that the supply of coal is limited, in that

case too it is better that existing supplies are used by / saved for plants

already in existence rather than allowing new coal based plants to come up.

15. The argument of first come first served is also misconceived. The

allocation in favour of petitioner was not because petitioner was first to

apply but because the petitioner had then represented that it was soon going

to be a specified end user of coal. That representation of the petitioner has

not borne fruit. Moreover, in today‟s time, the principle of first come first

served is being frowned upon, as commented in Centre for Public Interest

Litigation (supra).

16. The petitioner in its written submissions has referred to various

judgments but the said written submissions having been placed on record

and in view of the above, need is not felt to burden this judgment with the

same.

17. No ground for interference with the decision of the high level

Screening Committee is made out. There is no merit in the petition; the

same is dismissed with cost of `25,000/- to the Ministry of Coal.

RAJIV SAHAI ENDLAW, J APRIL 13, 2012 „gsr‟

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter