Wednesday, 29, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S B.R. Arora & Associates Pvt. ... vs National Highways Authority Of ...
2011 Latest Caselaw 5346 Del

Citation : 2011 Latest Caselaw 5346 Del
Judgement Date : 4 November, 2011

Delhi High Court
M/S B.R. Arora & Associates Pvt. ... vs National Highways Authority Of ... on 4 November, 2011
Author: S. Muralidhar
*      IN THE HIGH COURT OF DELHI AT NEW DELHI

#

+              O.M.P. 170/2009 and I.A. Nos. 2999/2011 & 11475/2010



                                              Date of order: November 4, 2011

       M/S B.R. ARORA & ASSOCIATES PVT. LTD.     ..... Petitioner
                        Through:   Ms. Anusuya Salwan, Advocate.


                       versus


       NATIONAL HIGHWAYS AUTHORITY
       OF INDIA (NHAI)                               ..... Respondent
                       Through: Ms. Garima Malhotra, Advocate for the
                       applicant in I.A. No. 2999/2011.
                       Mr. Mukesh Verma with Ms. Meenakshi Sood,
                       Advocates for NHAI.

       CORAM: JUSTICE S. MURALIDHAR

                                ORDER

% 04.11.2011

IA No. 11475/2010 (u/S 151 CPC filed by the Respondent NHAI)

1. OMP No. 170 of 2009 by M/s. B.R. Arora & Associates Private Limited has been filed under Section 9 of the Arbitration & Conciliation Act, 1996 („Act‟) seeking for interim relief against the Respondent National Highways Authority of India („NHAI‟) in relation to the construction of balance work of 8 laning of KM 16.500 to KM 29.300 of NH-1 in Delhi. The specific prayer is to restrain NHAI from preventing the Petitioner from using the batch mixed plant at Jagdish Pur, Sonepat (Haryana) and wet mixed plant at Jind Pur, Delhi and various other equipments like pavers, vibratory rollers, PTR, loaders, bitumen sprayer, diesel generator set, lab etc.

2. At the hearing of the petition on 19th November 2009, on the oral request of learned Senior counsel for the Petitioner, this Court permitted M/s. Bhola Singh Jaiprakash Construction Limited to be impleaded as party Respondent. It was stated the Petitioner‟s plant and machinery were not being utilized by NHAI and were lying idle and that the Petitioner would like to utilize them. Learned Senior counsel for the

Respondent then sought time to obtain instructions.

3. On 23rd December 2009 the following directions were issued by this Court:

"5. After hearing both the parties it is considered appropriate that the interest of justice would be served in case the Petitioner is allowed to use the plant and machinery lying at the site subject to the following:

(a) The Petitioner would use the plant and machinery lying at different sites of the Respondent as detailed in Annexure-A, subject to the condition that the Petitioner would not remove the same from the site till further orders by the disputes resolution board/Arbitrator/Court. The machinery shall remain in the custody and possession of the Respondent (NHAI).

(b) In case the Respondent requires to use any of the plant and machinery, the Respondent would notify the Petitioner whereupon the Petitioner would within 72 hours of such notice stop use and thereupon the Respondent may use the said plant and machinery.

(c) In case the said machinery is again not required by the Respondent, the Respondent would again allow the Petitioner to use the same.

(d) This permissive use shall not confer any equities in favour of the Petitioner."

4. The parties were given liberty to approach the Court in case they wished to seek any further direction.

5. The NHAI filed the present application, IA No. 11475 of 2010, on 27th August 2010 seeking direction to the Petitioner to pay for usage of plant and machinery as well as watch and ward expenses to the NHAI for letting it use the plant and machinery at the site of NHAI in furtherance of the Order dated 23rd December 2009 and also a proportionate amount of rent borne by the NHAI for land on which the plant and machinery have been retained. A further direction sought is that the Petitioner will use the plant and machinery lying at the site of NHAI only for undertaking the projects in its own name and to the exclusion of any party to which it may have sub-contracted the work. The NHAI also seeks a clarification of the duration and the projects for which the order dated 23rd December 2009 shall be applicable. It is further prayed that the Petitioner should be directed to undertake any repair/maintenance/ overhaul the equipments only at the site of NHAI and at the cost of the Petitioner.

6. In reply to the application, the Petitioner stated that the NHAI had not obeyed the order dated 23rd December 2009 and had not allowed the Petitioner to utilize the plant and machinery lying at the different sites despite several requests made by the Petitioner.

7. In its rejoinder, the NHAI stated that it has not disobeyed the order dated 23rd December 2009. It is further stated that it has filed this application only to seek clarification.

8. This Court has considered the submissions of learned counsel for the parties. The reliefs sought in this application are not merely by way of a clarification of the order dated 23rd December 2009 passed by this Court. They seek to expand the scope of the proceedings as well as the order dated 23rd December 2009. The order is self- explanatory and ambiguous and does not require any further clarification or modification. The liberty given to the parties to approach this Court was only if there could be any difficulty in implementing the directions contained in the said order. The NHAI does not explain why it waited for over eight months to file this application. It does not state that there is any particular difficulty in implementing the directions issued by this Court. The parties should first work out the order. As regards the allegation made by the Petitioner that the NHAI disobeyed the order dated 23rd December 2009 it will be open to the Petitioner to seek appropriate legal remedy in respect thereof in accordance with law.

9. With the above observation, the application is disposed of.

IA No. 2999/2011 (u/O 1 Rule 10 CPC read with Section 151 CPC for impleadment)

10. This is an application by Applicant/M/s. Starcon Infra Projects (I) Private Limited seeking impleadment in OMP No. 170 of 2009. It is stated that the Petitioner which is in joint venture with M/s. Bhola Singh Jai Prakash Limited hired the vibrator roller of the Applicant in the month of October 2007 and a memorandum of understanding („MOU‟) was also executed between the parties on 18th October 2007. It is alleged by the Applicant that the Petitioner failed to make the payment in terms of the said MOU.

The Applicant sent a legal notice to the Petitioner on 4th April 2009. In reply to the legal notice the Petitioner informed the Applicant that the NHAI had retained the said machinery. The subsequent legal notice sent by the Applicant to the NHAI on 21st July 2009 was not responded to by the NHAI.

11. The Applicant states that it has filed a suit for recovery of Rs. 18,00,000/- against the Petitioner and the NHAI in the court of the learned Additional District Judge at Delhi. In the circumstances, the Applicant seeks impleadment and a direction that the machine (vibrator roller) be released immediately in its favour.

12. The above application has been opposed by the NHAI by referring to Clause 63.1 of the Contract which permits that the NHAI to enter upon the site and retain the equipments and materials belonging to the Petitioner. It was in that background that the order dated 23rd December 2009 was passed by this Court. With the Applicant not being a party to the contract, it cannot seek any relief against the NHAI.

13. Having considered the above submissions it appears to this Court that the Applicant cannot possibly seek impleadment in the present OMP No. 170 of 2009. Not being the party to the Contract entered between the Petitioner and the NHAI, the applicant cannot possibly seek any relief against the NHAI. In any event the Applicant has filed an independent suit and has to work out its remedies in the said suit.

14. Consequently, this application is without merit and it is dismissed as such. It is however clarified that the dismissal of this application will not come in the way of the civil court dealing with any application the Applicant may file in the pending suit on its own merits.

S. MURALIDHAR, J NOVEMBER 4, 2011 RK

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter