Citation : 2011 Latest Caselaw 2801 Del
Judgement Date : 25 May, 2011
35.
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ W.P.(C) 3613/2011 & CM No.7562/2011 (for stay).
M/S CHATTERJEE CLEANING ARTS
SERVICES PVT. LTD ..... Petitioner
Through: Mr. Biswajit Das & Ms. Mayarika
Pathak, Advocates.
versus
ASSISTANT PROVIDENT FUND
COMMISSIONER (DAMAGE) & OTHERS ..... Respondents
Through: None.
CORAM:
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
ORDER
% 25.05.2011
1. The petition impugns the order dated 3rd March, 2011 of the
Employees' Provident Fund Appellate Tribunal, New Delhi impleaded as
respondent no.2. The said Tribunal is not required to be impleaded as a
party and is deleted from the memo of parties. An endorsement to the said
effect be made by the Court Master today itself.
2. The first contention of the counsel for the petitioner is that the
Tribunal has not heard the petitioner and refused the adjournments sought
by the petitioner.
3. No merit is found in the said contention. The petitioner has no right to
adjournment and if chooses, when the appeal comes up for hearing, to seek
adjournment, does so at its own risk and no error is found in the refusal of
adjournment and the Tribunal proceeding to reserve the order. The
contention that because the appeal had come up after five years,
adjournment should have been granted, cannot be accepted.
3. The appeal was preferred against the order dated 30th August, 2006 of
the respondent no.1 whereby the petitioner was directed to deposit a sum of
`6,60,132/- towards damages under Section 14B of the Employees'
Provident Funds and Miscellaneous Provisions Act, 1952 (EPF Act) and a
sum of `2,93,229/- towards interest under Section 7Q of the Act.
4. A perusal of the paper book at pages 47 to 60 indicates that the
default for which damages and interest have been computed exists from
February, 1998 till March, 2004. It is the contention of the petitioner that
though in the order dated 30th August, 2006 it was held that the petitioner is
entitled to benefit of pre-discovery period from February, 1998 to
September, 2000 but the same has not been given while making the
computation.
5. However as far as the period from October, 2000 to March, 2004 is
concerned, the contention of the counsel for the petitioner is that since the
Section 7A assessment itself was done vide order dated 11 th April /17th June,
2002 at page 43 of the paper book; prior thereto the petitioner could not be
expected to know with respect to which employees and what amount had to
be deposited and as such there could be no default inviting damages and
interest prior to the 7A assessment vide order dated 11th April/17th June,
2002. It is contended that the petitioner since the year 1998 had been
representing to the respondent no.1 for registration but was earlier informed
that the responsibility is of the principal employer for whom the petitioner
was running services and the petitioner was registered only on 26 th
September, 2000. It is contended that the petitioner as such could not know
that the provident fund with respect to which employees was being
deposited by the principal employer and for which employees it was liable
to deposit the provident fund.
6. The contention of the petitioner aforesaid if accepted would
tantamount to no proceeding under Sections 14B and 7Q of the Act being
maintainable till the Section 7A order. The said position cannot be accepted
in law. The petitioner is to make the requisite deposit of its own and at least
since the allotment of the Code number, was required to make the said
deposit and the explanation offered for the default after September, 2000
cannot be accepted.
7. Yet another argument offered by the counsel for the petitioner is that
the petitioner pursuant to the order under Section 7A was permitted to pay
the amount in installments. The Tribunal has in the order impugned in this
petition held that no material in this regard was placed by the petitioner. The
petitioner before this Court also has not placed any such material. The
counsel for the petitioner contends that it was an informal understanding
between the petitioner and the respondent no.1. The said argument cannot
be accepted. The Section 7A order itself records that the same was "without
prejudice to the rights" of the respondent no.1 to levy and recover damages
under Section 14B and interest under Section 7Q of the Act. Had there been
any such understanding, at least the said part of the order would not have
been then in existence.
8. Even otherwise if a view were to be taken that contribution is to be
deposited only after assessment and not in advance as is required under the
law, the same would be contrary to the statutory provision and do away with
the provision of self-assessment and deposit.
9. This Court in Ajanta Offset and Packaging Ltd. Vs. RPFC 110
(2004) DLT 757 held that the provisions of the EPF Act apply proprio
vigore and all that the respondents are required to do, is to allot a Code number;
that even if there be any delay on the part of the respondents in allotting a
Code number, that will not absolve the petitioner of its liability under the
Act. The EPF Act thus applies to the notified establishments with effect
from the date from which the Notification makes the Act applicable and not
from the point of time the competent authority holds the employer of such
establishment liable and determines the amount payable. The Act comes
into operation by its own vigour and its operation is not dependent on any
decision being taken by the authorities under the Act. The petitioner was
under a legal obligation to make deposits to the Fund within the time
prescribed, the moment the Act and the Scheme became applicable to it and
no intimation or notice of any kind in that respect was necessary to be
issued by the authorities concerned. Reference may also be made to S.K.
Nasiruddin Beedi Merchant Ltd. Vs. Central P.F. Commissioner (2001) 2
SCC 612 laying down that the applicability of the Act is not determined or
decided by any proceeding under Section 7A of the EPF Act but under the
provisions of the Act itself; what is done under Section 7A is only
determination or quantification of the same; the assessee cannot rely upon
his own laches in not making the deposit.
10. Thus no merit is found in the petition in so far as impugning the levy
of damages and interest for the period after September, 2000.
11. Issue notice limited to the period February,1998 to September, 2000
to the respondents by all modes including dasti, returnable on 15th
November, 2011.
12. There shall be stay of recovery only qua damages and interest till
September, 2000.
13. It is clarified that there is no stay for recovery of damages and interest
for the balance period.
14. The petitioner is at liberty to approach the respondents for bifurcation
of the amount.
CM No.7563/2011 (for exemption).
Allowed, subject to just exceptions.
RAJIV SAHAI ENDLAW, J
MAY 25, 2011 pp..
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!