Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Mahagun (India) Pvt. Ltd. vs M/S Infiniti Retail Limited
2011 Latest Caselaw 2718 Del

Citation : 2011 Latest Caselaw 2718 Del
Judgement Date : 20 May, 2011

Delhi High Court
M/S Mahagun (India) Pvt. Ltd. vs M/S Infiniti Retail Limited on 20 May, 2011
Author: Manmohan Singh
*           HIGH COURT OF DELHI : NEW DELHI

+                      ARB. P. 364/2010

%                                  Judgment decided on: 20.05.2011

M/S MAHAGUN (INDIA) PVT. LTD.               ......Petitioner
               Through: Mr Atul Nigam, Adv.


                       Versus


M/S INFINITI RETAIL LIMITED                    .....Respondent
                  Through: Mr Mohit Chaudhary and Ms Rashi
                           Bansal, Advs.
Coram:
HON'BLE MR. JUSTICE MANMOHAN SINGH

1. Whether the Reporters of local papers may
   be allowed to see the judgment?

2. To be referred to Reporter or not?                     Yes

3. Whether the judgment should be reported
   in the Digest?                                         Yes

MANMOHAN SINGH, J.

1. By this order I propose to decide the arbitration petition filed

under Section 10 and 11 (5) & (6) of the Arbitration and Conciliation Act,

1996, praying to make an order of appointment of an independent person

as a sole arbitrator for adjudication of the disputes in view of high cost

likely to be incurred by referring the claim/dispute to the Arbitral Tribunal

or refer it to the Delhi High Court Arbitration Centre for appointment of a

sole arbitrator.

2. It was submitted by the learned counsel for the petitioner that

in view of the high cost involved in the entire dispute resolving

mechanism through the constitution of an Arbitral Tribunal of three

arbitrators, it would be in the interest of the parties that a sole arbitrator

be appointed which was the intention of the parties but could not be

agreed to in respect of the choice of the sole arbitrator. It was further

submitted that as per the nature of the dispute which involves

determination of damages, it is likely to take many hearings leading to

high cost of arbitral proceedings and incidental expenses which cannot be

borne by the petitioner.

3. As per the parties, the following are the brief facts:

i. The petitioner company is carrying on business of real

estate and construction etc. The respondent was desirous

of opening one of its retail showrooms in the Mahagun

Metro Mall. The petitioner and respondent company had

entered into an MOU dated 07.08.2007 for the purpose of

leasing out the premises by the petitioner to the respondent.

It is specifically mentioned in the MOU that both the

parties shall be bound by the terms and conditions thereof.

As per Article III of the MOU, it was specifically provided

that if the terms and conditions of the would be breached

by the petitioner company, then the respondent shall be at

liberty to terminate the agreement by giving notice and in

the said eventuality, the security deposit (deposited by the

respondent with the petitioner) shall be refunded by the

petitioner to the respondent.

ii. The Article X of the MOU deals with the dispute clause.

The same is reproduced below:

"Any divergence of opinion or dispute on the interpretation or application of the present MOU shall be resolved amicably by means of consultation or negotiation between the contracting parties.

In the event where the dispute cannot be resolved in the manner aforementioned, the parties will present the dispute to an arbitration tribunal in accordance with the following provisions: each of the parties designate a member and the two designated members will in turn, by consensus, elect a third member, who will act as president of the tribunal of arbitration."

iii. According to the respondent, the petitioner had breached

various terms and conditions of the MOU and the

respondent terminated the same vide letter dated

11.08.2008 and by reminder letter dated 04.02.2009, the

petitioner was asked to refund the security amount within

15 days. The petitioner, on the other hand, stated that

MOU can only be terminated as per conditions stated in

Article III of the MOU. It was also stated that the

petitioner carried out massive alterations and change of

design keeping in view that the expense would be

recovered through the lease rent and therefore, refused to

refund the security deposit.

iv. The respondent thereafter issued notice under Section 433

and 434 of the Companies Act, 1956 dated 15.04.2009 and

demanded payment of Rs.8,25,000/- from the petitioner on

account of refund of security deposit within 21 days of the

receipt of the notice failing which the respondent will file

the petition for liquidation of the petitioner company.

v. The petitioner replied to the notice by reply dated

08.05.2009 by stating that the petitioner had incurred

heavy expenses on massive alterations, redesigning and

modification of the mall as per the requirements of the

respondent and if the respondent terminated the MOU,

then the respondent would be liable to damage to the tune

of Rs.5,04,74,100/- and the security deposit had to be

adjusted in the said claim. The respondent, on the other

hand, by letter dated 11.06.2009, denied any liability

towards any amount of damages as according to the

respondent, the respondent had never asked the petitioner

to incur any extra cost for modification or redesigning the

premises.

vi. Vide letter dated 18.08.2010, the petitioner company sent a

notice for appointment of an arbitrator as per Article X of

the MOU wherein the petitioner company had informed the

respondent company that the petitioner nominated Mr

Justice R.C. Chopra (retd. Judge of Delhi High Court) as a

member of the Arbitral Tribunal and asked the respondent

company to appoint its arbitrator. Consequently, vide

letter dated 29.09.2010, the respondent informed the

petitioner that the respondent nominated Justice M.R. Calla

(retd. Judge of Gujarat High Court) as a member of the

Arbitral Tribunal.

vii. It is a matter of fact that both the members of the Arbitral

Tribunal, i.e., Justice R.C. Chopra (retd.) and Justice M.R.

Calla (retd.), nominated and appointed Justice Ajit Prakash

Shah (former Chief Justice of Delhi High Court) as the

Presiding Arbitrator. It was intimated to both, the

petitioner and the respondent, that the preliminary meeting

of the Arbitral Tribunal had been fixed on 13.12.2010 at

5:30 p.m.

viii. According to the petitioner's counsel, the petitioner, via an

e-mail to the respondent's counsel, proposed to the

respondent that instead of appointment of arbitrators by

both sides, let a sole Arbitrator be appointed by the Delhi

High Court Arbitration Centre instead of Arbitral Tribunal,

considering the high cost of the Arbitral Tribunal and its

incidental cost. The petitioner has received the letter

dated 02.11.2010 from Justice A.P. Shah (retired Chief

Justice) informing the constitution of the Arbitral Tribunal

which was despatched on 12.11.2010 and by letter dated

18.11.2010, the petitioner informed the members of the

Arbitral Tribunal and the respondent's counsel about the

inability to meet the high cost of the Arbitral Tribunal and

seeking to refer the matter to the Delhi High Court

Arbitration Centre for appointment of a sole arbitrator to

which no reply was received from the respondent side.

4. As per the record, on 13.12.2010, a preliminary meeting was

held as per schedule wherein the Advocate of the respondent informed the

Arbitral Tribunal that the suggestion given by the petitioner to have

dispute adjudicated by the Single Arbitrator under the aegis of Delhi High

Court Arbitration Centre was not agreeable to his client. According to

him, the dispute between the parties had to be adjudicated by this Arbitral

Tribunal. He further made the statement before the Arbitral Tribunal that

the said information had been communicated to the petitioner as well as

petitioner's counsel Mr Atul Nigam. The Arbitral Tribunal through their

secretariat contacted Mr Atul Nigam on phone who informed that he

intended to move Delhi High Court for obtaining orders for reference of

the disputes to the single arbitrator and therefore, he had not appeared in

the meeting. The Arbitral Tribunal felt that as it was already constituted

the proceedings have to be continued in the absence of any stay orders,

thus, the following dates were appointed for taking the steps by the

parties:

      On or Before                        Steps to be Taken
      10th January, 2011    Statement of Claim/s to be filed by the
                            Claimant
      7th February, 2011    Reply to the Statement of Claim and Counter
                            Claim, if any, to be filed by the Respondent
      7th March, 2011       Reply to the Counter Claim and Rejoinder to
                            the reply of the Respondent to be filed by the
                            Claimant.
      21st March, 2011      Rejoinder to the reply to the Counter Claim to
                            be filed by the Respondent.





5. The Tribunal had also directed to the parties to complete on or

before 31.03.2011 the process of seeking any inspection or production of

documents in possession of the opposite party and they would also file

the draft/proposed issues on the next date of hearing, i.e., 15.04.2011 at

5:30 p.m. for settlement of issues and issuing the directions in the matter

of mode and procedure for trial of the issues arising for determination. As

regard the fees and expenses were concerned, an order was passed that an

amount of Rs.1,00,000/- be deposited on account with each of the

member of the Tribunal for the time being on or before 13.01.2011. The

amount was to be shared in equal proportion by both the parties.

6. The above mentioned order was passed on 13.12.2010. The

petitioner thereafter on 20.12.2010 filed the present under Section 10 and

11(5) and (6) of the Arbitration and Conciliation Act which was listed

first time before Court on 23.12.2010. On 23.12.2010 the Court issued

notice to the respondent while observing that though the MOU containing

the arbitration clause which had been relied upon by the petitioner was

not signed by the respondent but, from the letters of the respondent dated

20.09.2010 and 29.09.2010 it was clear that the respondent had given its

consent for adjudication of the dispute in view of the Article X of the

MOU. Thereafter, the reply was filed on 11.04.2011 by the respondent

and petitioner filed the rejoinder on 29.04.2011.

7. In rejoinder, it has been alleged by the petitioner that there are

no justified reasons for opposition by the respondent to the prayer made

by the petitioner for appointment of a sole arbitrator in view of the fact

that the respondent's claim is limited to Rs.8,25,000/- for which the

respondent had already instituted a winding up petition before this Court

bearing Company Petition No.03/2010. As far as the petitioner is

concerned, no ceiling arbitration cost had been disclosed by the Arbitral

Tribunal constituted of three retired High Court Judges and it shows that

the respondent has no justified defence over the substantive claim of the

petitioner and wants to non-suit the petitioner or otherwise, being a public

limited company, has scant regard for public funds and is ready to spent

unknown fund of money. It is the petitioner who since appointment of its

nominee has been concerned of high cost of dispute redressal for which it

has been making repeated inquiries and on assumption of high cost is not

shirking from the dispute redressal through arbitration but simply praying

for appointment of a sole arbitrator in view of expected high arbitration

cost as the petitioner is not in a position to bear the same as it suffering

losses on account of termination/rescission of the memorandum of

understanding by the respondent.

8. In support of submission, the learned counsel for the petitioner

has referred to the following judgments:

(i) Northern Railway Administration, Ministry of Railway, New Delhi Vs. Patel Engineering Company Ltd; (2008) 10 SCC 240.

(ii) Union of India Vs. Singh Builders Syndicate; (2009) 4 SCC 523

(iii) Abdul Gaffar Vs. Sri Jaichandlal Ashok Kumar & Co. Pvt. Ltd. & Anr.; JT 2000 (8) SC 152.

9. It is a matter of fact that as per the minutes of the meeting held

on 13.12.2010, the petitioner was required to file the statement of claim

on or before 10.01.2011. But till date, the petitioner did not file any

statement of claim before the Tribunal. It is apparent that the same is not

done as the petitioner has approached this Court for appointment of a sole

arbitrator despite the fact that the Arbitral Tribunal had already been

constituted. It is also a matter of fact that there is no order by the Court

for stay of the proceedings pending before the Tribunal. Tribunal had

again issued the direction at the hearing held on 15.04.2011 and after

having considered the submissions of the parties, they inclined to grant

further time to the petitioner till 16.05.2011 as a last chance to file the

statement of claim. The Tribunal has also modified the schedule

On or Before Steps to be Taken 16.05.2011 Statement of Claim(s) to be filed by the Claimant 20.06.2011 Reply to the Statement of Claim and Counter Claim to be filed by the Respondent 20.07.2011 Reply to the Counter claim and Rejoinder to the reply to the Statement of Claim to be filed by the Claimant.

08.08.2011 Rejoinder to the reply to the Counter claim to be filed by the Respondent.

22.08.2011 Process of admission/denial of documents to be completed by the parties.

25.08.2011 Draft/proposed issues to be filed by the counsel for the parties.

10. The next date of hearing fixed by the Arbitral Tribunal is

26.08.2011 at 4:00 p.m.

11. It is true that the Arbitral Tribunal should be constituted in the

manner laid down in the arbitration agreement. Such an arrangement has

to be given effect subject to requirements of independence and

impartiality and in a particular case, there could be exception and in case

the present case falls under such exception, then the prayer made in the

petition can be allowed.

12. It was held in the case of Northern Railway Administration

(supra) that the Chief Justice or his designate should first ensure that the

remedies provided under the arbitration agreement are exhausted, but at

the same time also ensure that the twin requirements of Sub-section (8) of

Section 11 of the Act are kept in view. Thus, in view of settled law, it is

to be considered as to whether the petitioner's case as per the facts is

covered under both requirements of Sub-Section 8 of Section 11 of the

Act.

13. The Supreme Court in the case of SVG Molasses Co. B.V. Vs.

Mysore Mercantile Co. Ltd. & Ors. reported in 2007 (5) R.A.J. 1 (SC)

dealt with the issue of the alternation of terms of the agreement by the

Hon'ble Court and held that "the parties entered into the arbitration

agreement with their eyes wide open. They knew the terms thereof. The

Court in exercise of its jurisdiction under Section 11(6) of the 1999 Act

cannot alter the terms of the contract".

14. In the present case, it is undisputed fact that the procedure for

appointment of the arbitrators is already settled in the agreement which

was agreed by the parties. It is also undisputed fact that the petitioner,

vide letter dated 18.08.2010, itself had appointed Justice R.C. Chopra

(retd.) as a member of the Arbitral Tribunal and asked the respondent to

appoint a member within the statutory period and itself initiated the

arbitration proceedings. Hence, as on 18.08.2010, the petitioner had full

intention to follow the procedure to appoint the arbitrator which was

already settled in the agreement and had virtually agreed for the same. If

that is the position, it appears that after one and half years of the said

knowledge, the petitioner has now changed its stand which prima facie

appears to be an afterthought and is not proper. It is the petitioner who is

claiming the damages for more than Rs.5 crores and the procedure of

appointing the Arbitral Tribunal is already settled in the memorandum of

understanding which was agreed by the petitioner itself. The petitioner

itself initiated the arbitration proceedings as per the agreement and now

the petitioner cannot step back from the proceedings and take the

different lead and ask the Court to appoint the sole arbitrator. The

intention of the petitioner is not bonafide. It is the admitted position that

the disputes between the parties first time arose in August 2008. It

appears from the material available on record that up to August, 2010 was

agreeable to appoint the Arbitrator as per the arbitration clause of the

MOU.

15. Hence, the petitioner's case is not covered within the two

requirements of Sub-Section 8 of Section 11 of the Act. Therefore, the

request of the petitioner cannot be allowed. As far as the judgments

referred to by the petitioner are concerned; in the first judgment of

Northern Railway Administration (supra) it has been specifically held

that the Chief Justice or his designate should first ensure that the remedies

provided under the arbitration agreement are exhausted. There is only

exception that if the Court feels that exceptions, i.e., requirement of

independence and impartiality, which does not appear to be possible in

this case. Therefore, the said judgment of Northern Railway

Administration (supra) does not help the case of the petitioner; in the

second case Union of India Vs. Singh Builders Syndicate (supra), the

Court has given its finding due to peculiar facts of the case and held that

the case falls under the exceptions because it had chequered history, but

in the present case, the facts are materially different. The relevant paras 4

to 10 of the judgment in this regard read as under:

4. Let us refer to the facts briefly:

The respondent made a request for arbitration in the year 1999. As the appellant failed to take necessary steps as mandated by clause 64, the respondent filed an application under Section 11 of the Arbitration and Conciliation Act, 1996 ("the Act" for short) in AA No. 202/2000.

5. In pursuance of the directions issued on 11.11.2002 by the designate of the Chief Justice of the Delhi High Court, an Arbitral Tribunal was constituted in terms of clause 64, consisting of Shri A.K. Mishra, (Chief Engineer/TPS) nominated by the contractor, Shri S.P. Virdi (Dy.F.A. & CEO) nominated by the appellant, and Shri H.K. Jaggi (Chief Bridge Engineer) as the Umpire. But even before the proceedings could commence before the Arbitral Tribunal, Shri A.K. Mishra, one of the Arbitrators, was transferred and consequently he tendered resignation in May, 2004.

6. As the appellant failed to provide a fresh panel to enable the respondent to make a fresh nomination, the respondent again approached the High Court by filing AA No.240/2004. A fresh panel was made available thereafter from which the respondent nominated Shri Ashok Gupta as its Arbitrator. Hardly after one sitting of the Arbitral

Tribunal, Shri Ashok Gupta was also transferred and he tendered his resignation on 21.7.2005.

7. As the appellant again failed to take steps for filling the vacancy, the respondent approached the Court again by filing IA No. 6511/2005 in AA 240/2004. In pursuance of an order dated 24.8.2005 passed by the High Court, again a panel was made available and the respondent made its choice on 9.9.2005.

8. As no steps were taken in pursuance of it by the appellant, the respondent sent a reminder on 14.10.2005. There was no response. In this background, the respondent again approached the High Court on 10.11.2005 in Arbitration Petition No. 256 of 2005 for appointment of an independent sole arbitrator. During the pendency of the said petition, the General Manager of Northern Railways appointed Sri Ved Pal as the contractor's nominee arbitrator on 22.11.2005.

9. The High Court was of the view that no useful purpose will be served by again reconstituting a three Member Arbitral Tribunal in accordance with clause 64. The High Court found that the matter has been pending from 1999 when the respondent first made the request for reference to Arbitration and that the cumbersome process of constituting an Arbitral Tribunal in terms of the Arbitration agreement and the delays on the part of Railways in complying with the provisions of the arbitration agreement, led to the arbitration becoming virtually a non-starter.

10. Therefore, the High Court allowed the petition on 27.3.2006 and appointed Justice Jaspal Singh, a retired Judge of the Delhi High Court as the arbitrator. Justice Jaspal Singh recused himself and the High Court on 19.7.2006, appointed Justice R.C. Chopra, another retired Judge of the Delhi High Court as the arbitrator. The said order is challenged in this appeal by special leave. On

6.11.2006, this Court stayed the arbitration proceedings before the sole Arbitrator."

16. After considering the case of Northern Railway

Administration (supra) and Union of India Vs. M.P. Gupta: (2004) 10

SCC 504, the Hon'ble Supreme Court in para 15 of the judgment

observed as under:

"15. The object of the alternative dispute resolution process of arbitration is to have expeditious and effective disposal of the disputes through a private forum of parties' choice. If the Arbitral Tribunal consists of serving officers of one of the parties to the dispute, as members in terms of the arbitration agreement, and such Tribunal is made non-functional on account of the action or inaction or delay of such party, either by frequent transfers of such members of the Arbitral Tribunal or by failing to take steps expeditiously to replace the arbitrators in terms of the Arbitration Agreement, the Chief Justice or his designate, required to exercise power under section 11 of the Act, can step in and pass appropriate orders."

17. If the entire judgment is read carefully, one can easily come to

the conclusion that the present case is not a case where any finding can be

avered to the effect that the Arbitral Tribunal has failed to take steps

expeditiously to replace the arbitrators in terms of the arbitration

agreement. The present case is not a fit case wherein the Court should

exercise power under Section 11 of the Act or the Court can step in and

pass appropriate orders. The facts in the present case are very straight

and simple. There is no delay on the part of the respondent or by the

Arbitral Tribunal in any manner whatsoever. The case referred to above

had a chequered history and this Court respectfully is in agreemnt with

the judgment passed by the Supreme Court which fell under those

exceptions which are referred to in the judgment. But the present case is

not in the nature of such exceptions. Therefore, the decision referred to

by the petitioner does not help the case of the petitioner. As regard the

third judgment Abdul Gaffar vs. Sri Jaichandlal Ashok Kumar & Co.

Pvt. Ltd. & Anr. (supra) is concerned, the order in the said matter was

passed with the consent of the parties as no objection was raised by the

respondent qua replacing the earlier arbitrator in the arbitration

proceedings. In the present case, the prayer of the petitioner is strongly

opposed by the respondent and it appears prima facie that the opposition

of the respondent is bonafide and the respondent is justified for the same

and the procedure for appointment of arbitrator is already settled in the

agreement. Therefore, the third case referred to is also not applicable in

the facts and circumstances of the present case.

18. The present petition devoids any merit and the same is

dismised with cost of Rs.10,000/-.

19. Since the Arbitral Tribunal has granted the petitioner time till

16.05.2011 as last chance to file the statement of claim and admittedly the

petitioner has not file the statement of claim, the said period is extended

for two weeks as a last opportunity to file the statement of claim. The

reply to the statement of claim and counter claim has to be filed by the

respondent by 20.06.2011. The rest of the schedule shall remain as

maintained by the Arbitral Tribunal. The parties shall appear before the

Arbitral Tribunal on 26.08.2011 at 4:00 p.m., the date already fixed at A-

384, Lower Ground Floor, Defence Colony, New Delhi. As far as the

apprehension of the petitioner about high cost likely to be incurred as

alleged in the petition which is the main submission of the petitioner, he is

granted liberty to approach the Arbitral Tribunal with a request to charge

the fee as per the schedule maintained by the Delhi High Court

Arbitration Centre. This Court is very hopeful that such request would be

considered positively.

20. The petition stands disposed of.

MANMOHAN SINGH, J.

May 20, 2011 jk

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter