Citation : 2011 Latest Caselaw 2463 Del
Judgement Date : 9 May, 2011
THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment Reserved on: 29th April, 2011
Judgment Pronounced on: 9th May, 2011
+ CS(OS) No. 1353/1999
KAPCO ARTS PVT. LTD. .....Plaintiff
- versus -
WORLD EXPO & CONVENTIONS
MANAGEMENT LTD. & ORS. .....Defendants
Advocates who appeared in this case:
For the Plaintiff: Ms. Shantha Devi, Advocate
For the Defendant: None
CORAM:-
HON'BLE MR JUSTICE V.K. JAIN
1.
Whether Reporters of local papers may be allowed to see the judgment? Yes.
2. To be referred to the Reporter or not? Yes.
3. Whether the judgment should be reported in Digest? Yes.
V.K. JAIN, J
1. This is a suit for recovery of Rs.33,97,247/-. The
plaintiff company is engaged in business of providing
various exhibition related services including consultancy
technical and architectural services to the organizers and
participants. Defendant No.1 company is engaged in
business of organizing the exhibitions at different places.
Defendant No.2 is the Chairman of Defendant No.1 whereas
Defendants No.3 & 4 are its Directors. Defendant No.5 is
the Vice President of Defendant No.1. Pursuant to
discussions between the parties, Defendant No.1 issued a
letter of intent dated 30.5.1998 which was followed by a
General Purchase Order (GPO) dated 20.6.1998 for
construction of hangars and shells scheme stalls for various
exhibitions scheduled to be held between July, 1998 and
April, 1999. The contract awarded to the plaintiff company
was in respect of 06 exhibitions, first of which was to be
held at Chennai from 22nd July, 1998 to 26th July, 1998. As
per the terms of the contract Defendant No.1 was to be paid
an advance amounting to 20% of the total expenditure, one
month prior to the exhibition. The next 25% payment was
to be made at erection of hangars and satisfactory
installation of air-conditioners and other facilities whereas
the balance payment was to be paid within 45 days of
completion of exhibitions. It is alleged that the plaintiff
company constructed 2880 sq. m. of air-conditioned and
1071 sq. m. of non air-conditioned tentages. As per the
terms of GPO and subsequent correspondence, the plaintiff
company sent performa invoices of amount of
Rs.36,72,247/- split into three bills. It is alleged that the
defendant company cancelled the contract relating to other
exhibitions and awarded the same to another company. It
is claimed that by that time the plaintiff company had
already incurred expenditure to the tune of Rs.7 lac for the
exhibitions BangaloreIT.com-1998. The case of the plaintiff
is that an amount of Rs.33,97,247/- is still due to it and
this includes Rs.7 lac spent by it in respect of exhibitions
which were scheduled to be held subsequent to the
exhibition at Chennai.
2. The defendants filed WS contesting the suit and
took a preliminary objection that the suit has not been
instituted, and has not been verified and signed by a
competent person. Another preliminary objection taken by
the defendants is that the suit is bad for misjoinder of
causes of action as the plaintiff has wrongly joined the claim
on account of Bangalore exhibition with its claim in respect
of Chennai exhibition. On merits, the defendants admitted
having issued a GPO dated 20.6.1998 for construction of
hangars/shell scheme stalls for various exhibitions to be
organized by defendant no.1. It is alleged that the plaintiff
could not fulfill its obligations as envisaged under the GPO
and major discrepancies were found in the arrangement
made by it. It is claimed that malfunctioning was detected
in air-conditioning and hangars were not made water proof.
According to the defendants, the plaintiff was intimated that
a) there was shortage of about 25-30 tons of air-
conditioners b) Cloth sides had been provided in non air-
conditioned tentages which was not as per standard
practice in international exhibitions and is practically
unsafe c) water leakage was observed at many points and d)
air-conditioners were found to be tripping due to
unbalanced load on generators. It is alleged that the air-
conditioners were not tested for their effective operations
nor the thermometers and phychometers were available
with the plaintiff. It has been alleged that out of 26 air-
conditioners installed by the plaintiff company only 03 were
found operational. It is further alleged that cable supplying
the electricity had become very hot due to uneven
distribution of load and had resulted in snapping of wires
and disruption of supply to hall No. F, which was forced to
shut down during exhibition hours, for replacement of the
cable. It is also alleged that it was agreed between the
parties that the most appreciable way of doing air-
conditioning was through a packaged air-conditioner of 7.5-
10 tons or by ducting. It is also claimed that on account of
breach by the plaintiff the goodwill and reputation of
defendant suffered heavily and the popularity of the
exhibition dwindled over the years, both in terms of total
collection as well as the number of exhibitors. This is also
the case of the defendant that all the deficiencies found in
the work executed by the plaintiff were agreed to by Mr.
Tilak Raj, a Director of the company in meeting held on
26.7.1998. It is also claimed that as per standard practice
the area of the passage is 35-40% of the total exhibition
area and therefore area of air-conditioning of hangars works
out to be about 2600 sq. m. whereas the non air-
conditioned hangars works out to be 825 sq. m. It is
however admitted that it was the defendant company which
had provided generators for Autofest 1998. It is also
claimed by the defendant that though the exhibition was to
commence from 23.7.1998 the work was in progress upto
2.30 pm on the previous day.
3. As regards expenditure related to BangaloreIT-
.com-1998, the case of the defendants is that as per the
GPO the plaintiff company was to provide architectural
assistance for plan lay out on complimentary basis and
therefore cannot claim any compensation for lay-out plant
of Bangalore exhibition and in any case the GPO was
cancelled before the work for Bangalore exhibition was to be
taken up.
4. The following issues were framed on the pleadings
of the parties:
1. Whether the suit has been instituted, plaint
signed and verified by duly authorized person? -
OPD
2. Whether the suit is bad for mis-joinder of cause
of action? - OPD
3. Whether the agreement dated 20.06.1998 was
altered and/or modified by the corrigendum
dated 7th July, 1998 executed between the
parties? If so, what is its effect? - OPP
4. Whether the defendant had failed to provide the
electricity supply in terms of the agreement? If
so, what is its effect on the claim of the plaintiff?
- OPP
5. Whether the defendant committed the breach of
the terms of the agreement entitling the plaintiff
to claim the amount in this suit? - OPP
6. Whether the plaintiff had failed to provide air-
conditioning system for the entire complex for
exhibition and the defendant had terminated the
contract for that reason in terms of the
agreement? - OPD
7. What amount including the rate of interest, if
any, the plaintiff is entitled to? - OPP
Issue No.1
5. The plaint has been signed, verified and instituted
by Shri Ajay Kapoor, Director of the plaintiff company. Exh.
PW-1/A is the copy of the resolution passed by the Board of
Directors of the plaintiff company in its meeting held on
15.5.1999 authorizing Mr. Kapoor to institute the suit and
sign and verify the documents. Even otherwise in view of
provisions contained in Order 29 Rule 1 of Code of Civil
Procedure (CPC), in a suit by a company, pleadings can be
signed and verified by Secretary/Director or other Principal
Officer of the company. The suit therefore has been
instituted, and the plaint signed and verified by a competent
person. The issue is decided against the defendants and in
favour of the plaintiff.
Issue No.2
6. Order 2 Rule 3 of the Code of Civil Procedure to the
extent it is relevant provides that a plaintiff may unite in the
same suit several cause of action against the defendant or
the same defendants jointly. Hence, the plaintiff company
could have joined the cause of action in respect of its dues
for Chennai exhibition as well as its claim for the expenses
alleged to have been incurred in connection with Bangalore
exhibition in the same suit. The issue is decided against the
defendants and in favour of the plaintiff.
Issues No. 3-6
These issues are inter connected and can be decided
together.
7. The plaintiff has examined five witnesses. The
defendants filed affidavit of one witness viz. Mr. Mukesh
Arora by way of evidence but did not produce him for cross
examination and therefore the affidavit cannot be taken into
consideration.
8. In his affidavit by way of evidence Mr. Vijay Kapoor
(PW-4) stated that there was no deficiency in providing
services on the part of the plaintiff. He has further stated
that it was for the defendant company to provide power
supply but the supply provided by the defendant was
neither proper nor adequate. He has claimed that the
defendant company has illegally withheld the balance
payment for the work done for it by the plaintiff company.
9. PW-5 Mr. Ashok Chitkara was an employee of the
plaintiff company and supervising the general work at the
site during Autofest-1998 organized by the defendant
company. In his affidavit he has stated that the
requirement of power was sent to the defendant company
vide letter Exh. PW-1/D and the plaintiff company had
completed its part of the contract for the above show in all
respects, without there being any inefficiency or deficiency.
According to him there was no adequate/efficient power
supply at the site due to which some air-conditioners were
not functioning.
10. PW-2 Mr. Rakesh Gaind is the consultant who was
engaged by the plaintiff company for air-conditioning of the
exhibition. He has stated that they completed their job but
there were some deficiencies. According to him they had
completed the entire job of fixing the air-conditioners but
the same could not be tested since there was no power
supply and whatever supply was available, its voltage was
not proper. According to him while staying at Chennai from
16.7.1998 to 26.7.1998 he had brought these difficulties
and drawbacks in relation to the power supply to the notice
of the plaintiff as well to the defendant and Exh. PW- 2/1 is
the report which he had submitted to the plaintiff company
with respect to the work. During cross examination, he
stated that they had made arrangement for 2500 sq. m. of
area for which 400 tons of air-conditioners was required
and the air-conditioners provided by the plaintiff were of
good quality. According to him different voltage was require
for different air-conditioners, some of which required 220 V
while others required 440 V. He has stated that 10
generators were supplied to them which were giving 40-45
Kws. He stated that though the labels on the generators
indicated 60 Kws, during testing by his persons in his
presence, the outcome was found to be 40-45 Kws and
these generators were capable of giving 440 V. According to
him the total power was 500 Kws as against required of 900
Kws and therefore the power provided was not sufficient to
run 400 tons of air-conditioners. During cross examination,
he admitted that in one of the halls, the air-conditioners
had to be shut down because of heating up of wires but
this, according to him, might have happened because there
were too many halogens lamps. He stated that the plaintiff
as well as exhibitors was told that excess halogen lamps
should not be put in the exhibition. He has claimed that
installation of air-conditioners was complete in the night of
21.7.1998 but the air-conditioners were not tried since full
power load was not available. He admitted that temperature
in halls was not comfortable since air-conditioners were not
functioning properly.
11. PW-3 Shri J.C.Bhalla was working with the
plaintiff company from June, 1998 to June 2003 and was
Manager In-charge for the work at the site of Autofest-1998.
He was supervising the general work from 11.7.1998 to
26.7.1998. He has stated that the plaintiff company had
completed its part of the work in all respects and there was
no inefficiency or deficiency of any kind in work provided by
the plaintiff company, though there was
inadequate/insufficient power supply at the site which was
the responsibility of the defendant company. PW-4 Mr.
Vijay Kapoor is another Director of the plaintiff company.
He has stated that he was controlling the affairs of Autofest-
1998 work and was the Director In-charge at the site from
13.7.1998 to 24.7.1998. He also maintained that there was
no deficiency in service in part of the plaintiff company and
it was the defendant company which did not provide
sufficient power supply to run the air-conditioners.
12. A perusal of Exh. P-2 which is the GPO dated
20.6.1998 would show that as per the agreed rates between
the parties the plaintiff company was to be paid as follows:
Sheds/Tentages with Air-condition Rs.750/- per sq.m
Sheds/Tentages without Air-condition Rs.550/- per sq.m
Standard Shell Scheme Rs.400/- per sq. m
Synthetic Gangway Carpet-New Rs.90/- per sq. m
Synthetic Gangway carpet - Old Rs.65/- per sq. m
13. Exh. PW-4/A (colly) are the invoices by the plaintiff
company on the defendant company for the work done for
Autofest-1998. A perusal of invoices would show that the
plaintiff company raised invoices for 2880 sq. m. AC
Tentages, 1071 sq. m. Non-AC Tentages, 892 Sq. m for
Exhibitors' Area, 145.5 sq. m for Organiser's office, business
lounge and 1535.42 sq. m for Gangway Carpet area making
of total sum of Rs.32,34,752.30. The plaintiff company also
raised invoices of Rs.2,72,495/- for the furniture,
TV/VCR/Refrigerator etc. and for the carpet and additional
panels. The plaintiff company raised another invoice of
Rs.1,65,000/- for erection of welcome gate, main gate,
sponsored tower, ramp at entry gate in parking area, special
pillar fabrication in Bajaj Auto Stand and general lighting
near main gate, lily pond area etc. This is not the case of
the defendants that the plaintiff company had not provided
tentages for the quantity mentioned in the invoices dated
4.8.1998 nor do they claim that the plaintiff company did
not provide stand construction and gangway carpet as
claimed in this invoice. Similarly this is not the case of the
defendants that chairs and other materials mentioned in the
invoice for Rs.2,72,495/- were not provided by plaintiff
company. They also do not claim that the work charges for
which have been claimed in the invoices for Rs.1,65,000/-
were not executed by the plaintiff company. The entire
defence taken by the defendants is that there were gross
deficiencies in the work executed by the plaintiff company
and in particular adequate air-conditioning was not
provided which resulted in discomfort to the visitors and
had the consequences on goodwill and reputation of the
Defendant Company besides resulting in reduction in
number of exhibitors and visitors. This is also the case of
the defendants that instead of laminated panels, cloth
panels in non air-conditioned tentages were provided by the
plaintiff company. The third deficiency claimed by the
defendants is that water leakage was observed at a number
of points though very light shower had occurred during the
night and early morning. No evidence has however been led
by the defendants to prove the alleged deficiencies. As
regards air-conditioning the deposition of Mr. Rakesh Gaind
(PW-2) corroborated by testimonies of Mr. J.C.Bhalla and
Mr. Ashok Chitkara would show that the electricity was to
be provided by the defendant company and not by the
plaintiff and the supply provided at the site was grossly
inadequate the same being only 440 Kws as against
requirement of 900 Kws. The generators at the site were
provided by the defendant company as is evident from the
WS wherein this fact has been expressly admitted as also
from Exh. PW-5/A, which are the minutes of the meeting
held with Mr. Ashok Chitkara of the plaintiff company. A
perusal of the bill dated 25th July, 1998 raised by Bharathi
Electrical on Mr. Mukesh Arora, President of the defendant
company; a copy of which has been filed by the defendant
and therefore can be read against it, would show that only
one generator was provided for three hours on 19.7.1998,
three generators; one for twelve hours, the second for three
hours and the third for three hours were provided on
20.7.1998 and ten generators; four for thirteen hours each,
one for twelve hours, three for ten hours each and two for
14 hours each were provided on 21.7.1998. Thus, adequate
generators were not provided in time. In the absence of
generators, air-conditioning could not have been checked
prior to 21.7.1998. The deposition of Mr. Gaind and other
witnesses would show that the generators provided by the
defendant company were capable of giving only 440 V
whereas some of the air-conditioners required generators
capable of giving 220 V. It is evident from his deposition
and the report Exh. PW-2/1 furnished by him that had the
defendant company provided adequate power supply and
had the generators been provided on time, in sufficient
number and been giving required voltage the air-
conditioners could have been tested well in time and would
also have properly functioned during the festival. There is
no evidence on record to prove that the air-conditioners
provided by the defendant company were inadequate for the
air-conditioning of tentages provided by it and/or were not
of good quality. If some of the air-conditioners could not
function or were malfunctioning due to non-availability of
power and the generators being of inadequate capacity and
not capable of giving required voltage the plaintiff company
cannot be faulted for the air-conditioned tentages not being
comfortable and temperature therein being rather high. No
doubt the temperature in hall was not comfortable and the
air-conditioners were not functioning properly as admitted
by Mr. Gaind but the responsibility for this malfunctioning
cannot be attributed to the plaintiff company.
14. It has come in the deposition of Mr. Gaind that
some air-conditioners had to be shut down because of
heating up of wires this however according to the witness
might have happened on account of how many halogen
lamps have been put in the halls despite the exhibitors
having been told that excess halogen lamps could not be
put. There is no evidence before the Court to indicate that
heating up of the wires could not have been on account of
excess number of halogen lamps. It has come in the
evidence of the plaintiff that extra halogen lamps were put
in the hall. There is no evidence to indicate that the
halogen lamps put in the halls were not in excess quantity.
Therefore, shutting down of air-conditioning in one of the
halls cannot be attributed to the plaintiff company.
15. As regards, partitions in tentages area being of
cloth instead of being laminated there is no evidence to
prove the alleged deficiency. The plaintiff has claimed that
the partitions were not of fabric. Moreover, there is no
evidence of the exhibitors or visitors facing any discomfort
in non air-conditioned tentanges on account of the
partitions being of fabric instead of being made of laminates.
Regarding alleged water leakage, again there is no evidence
to prove the alleged leakage or its extent as well as the
points from where the water is alleged to have leaked.
16. The main defence taken by the defendants seems
to be that Mr. Tilakraj, a Director of the plaintiff company in
a meeting held on 26.7.1998 had admitted the deficiencies
claimed by the defendants. A perusal of the minutes would
show that on 19.7.1998 it was found that the air-
conditioners had not been tested for their effective
operations and the air-conditioners were tripping after some
time and the defendant was asked to check the effectiveness
of the air-conditioning system. As noted earlier, neither
delay in testing the efficiency of air-conditioners nor their
tripping can be attributed to the plaintiff company. These
minutes also show that on 26.7.1998, it was found that air-
conditioners had not been put into operation except in Hall
A, where 10% of the air-conditioners were operational and
the representatives of the plaintiff were asked to take all
possible efforts to ensure that the air-conditioners were in
working condition with proper load distribution. As noted
earlier the deficiency in air-conditioning was attributable to
failure of the defendant to provide adequate power and is
not attributable to the plaintiff company. There is an
observation recorded in these minutes that the wires had
become very hot. It has come in evidence that this was due
to excess number of halogen lamps having been put in the
hall. There is no material to indicate that this was
attributable to any deficiency on the part of the plaintiff
company. It has been noted in these minutes that Mr. Tilak
Raj affirmed that he also had come to know that the
temperature inside the hangars could not be brought down
to a comfortable condition and at certain places equipment
had to be replaced and he further confirmed that air-
conditioning was not satisfactory, despite all possible efforts
and right system of doing air-conditioning would have been
through packaged air-conditioners of 7.5 to 10 tons or by
ducting. It was further noted in these minutes that the side
walls of non air-conditioned hangars had been covered by
cloth which was torn at many places and as a result the
hangars could not be closed. It is also noted that Mr. Tilak
Raj agreed that it would have been better, if they had made
electrical load diagram so that uneven distribution and
overloading at certain points could have been avoided. In
his affidavit by way of evidence Mr. Tilak Raj has stated that
he was not concerned with Autofest at Chennai and had no
connection or coordination with the defendants in this
regard. According to him during the casual visit on
26.7.1998 Mr. Mukesh Arora of the defendant compelled
him to sign the minutes in spite of the fact that other
General Manager, Dy. General Manager and other officials
of the plaintiff company were present at the site. He has
stated that no other official of the plaintiff company present
at the site was allowed to enter into the cabin where the
minutes were signed and he was threatened by Mr. Mukesh
Arora that if he did not sign the minutes, the plaintiff
company would not be allowed to remove the goods placed
at the site. He has further stated that on repeated requests
Mr. Mukesh Arora allowed him to call Mr. Ajay Kapoor who
told him that goods lying at the site worth crores of rupees
and non-removal of those goods from the site after specified
time would attract penalty of Rs.75,000/- per day in terms
of the GPO and therefore he signed those minutes on the
advice of Mr. Kapoor. Thus, according to him these minutes
were signed by him under coercion and duress. The
deposition of Mr. Tilak Raj finds corroboration from the
deposition of Mr. J.C.Bhalla and Mr. Ashok Chitkara. The
defendants have not come forward to produce any evidence
and therefore the aforesaid deposition of Mr. Tilak Raj
corroborated by testimonies of Mr. Ashok Chitkara and Mr.
J.C.Bhalla remains uncontroverted and unchallenged. I,
therefore see no reason to disbelieve the plea and
accordingly hold that these minutes were not agreed by
Tilak Raj of his free consent and he was made to sign under
coercion since without Mr. Tilak Raj signing the minutes,
the plaintiff would not have been allowed to remove its
goods worth crores of rupees from the site and also would
have been liable to pay damages amounting to Rs.75,000/-
per day for not removing them from the exhibition site.
17. Exh. D-2 is a bill of Rs.38,500/- raised by
Bharathi Electrical on the plaintiff company in respect of
electrical services and hiring of fans whereas Exh. D-3 is a
letter addressed by Mr. Tilak Raj of the plaintiff company to
Bharathi Electrical agreeing to pay a sum of Rs.1,20,000/-
towards additional generators and cable etc. The case of the
plaintiff is that this letter was also obtained under coercion
when the minutes dated 26.7.1998 were got signed from Mr.
Tilak Raj. The expression used in this letter coupled with
the date which appears on it, tend to support the case of the
plaintiff in this regard. Ordinarily, there would be no reason
for the plaintiff company to write such a letter to Bharathi
Electrical and give it to the defendant, in case the additional
generators were hired by the plaintiff company. Moreover,
as noted earlier the defendant has admitted that the
generators were to be provided by the defendant company
and this is also borne out by Exh. PW-5/A i.e. minutes of
the meeting with Mr. Ashok Chitkara. Also, there is no
evidence on record to prove that requirement of additional
generators arose on account of some deficiency on the part
of the plaintiff company in providing services for Autofest-
1998 therefore, nothing really turns on these documents.
18. Admittedly the invoices raised by the plaintiff
company in respect of Autofest-1998 were of total sum of
Rs.36,72,247/- out of which a sum of Rs.9,75,000/- stands
paid to the plaintiff company leaving a balance of
Rs.26,97,247/- which remained payable to the plaintiff
company in connection with Autofest-1998. The plaintiff
company has also claimed a sum of Rs.7 lac in connection
with the exhibition which was scheduled to be held at
Bangalore. This comprises a sum of Rs. 2 lac as advance as
per lay out and another sum of Rs.5 lac for making
arrangements of material site visits, site measurements etc.
for Bangalore exhibition. A perusal of the payment terms
contained in GPO dated 20.6.1998 would show that 20%
advance payment was to be made one month prior to
exhibition. Had the plaintiff company actually executed the
Bangalore exhibition, this advance payment if made by the
defendant company, would have been adjusted in the bill of
the plaintiff company. Therefore, since the work was not
actually executed, the plaintiff company is not entitled to
this amount. Assuming that there was a breach on the part
of the defendant company when it cancelled the GPO, the
plaintiff company would be entitled only for compensation of
the actual loss, if any, suffered by it on account of
cancellation of work in respect of other exhibitions. No
evidence has been led by the plaintiff company to prove that
it had incurred expenditure of Rs.2 lac on preparation of lay
out plan. Similarly, no evidence has been led by the
plaintiff company to prove that it had incurred expenditure
of Rs.5 lac for arrangement of material and on site
visits/site measurements etc., in absence of such evidence,
the plaintiff company is not entitled to any amount on
account of cancellation of the purchase order. The issues
are decided accordingly.
ORDER
19. For the reasons given in the preceding paragraphs
a decree of Rs. 26,97,247/- with proportionate costs and
pendent lite and future interest @ 12% p.a. is passed only
against defendant no. 1, as the contract was only between
plaintiff company and defendant no.1 company. The
plaintiff is not entitled to recover any amount from the other
defendants. The suit against defendants no. 2 to 5 is
therefore dismissed with no orders as to costs.
Decree Sheet be prepared accordingly.
(V.K. JAIN) JUDGE MAY 09, 2011 vn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!