Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Bhanu Construction Co. ... vs National Thermal Power Corp. Ltd. ...
2011 Latest Caselaw 961 Del

Citation : 2011 Latest Caselaw 961 Del
Judgement Date : 18 February, 2011

Delhi High Court
M/S Bhanu Construction Co. ... vs National Thermal Power Corp. Ltd. ... on 18 February, 2011
Author: Rajiv Sahai Endlaw
            *IN THE HIGH COURT OF DELHI AT NEW DELHI

                                      Date of decision: 18th February, 2011.

+                           CS(OS) No.1998 of 1993

%        M/S BHANU CONSTRUCTION CO. PVT.LTD.    .... Plaintiff
                     Through: Mr. Ali Naqvi & Mr. Abhishek
                              Singh, Advocates.

                                   Versus

    NATIONAL THERMAL POWER CORP. LTD.
    SINCE SUCCEEDED BY POWER GRID CORP. OF
    INDIA LTD.                        .... Defendant/Objector
                 Through: Mr. B. Datta, Sr. Advocate with Mr.
                           R.K. Joshi & Mr. Jyotinder Kumar,
                           Advocates.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1.       Whether reporters of Local papers may
         be allowed to see the judgment?                    No.

2.       To be referred to the reporter or not?             No.

3.       Whether the judgment should be reported            No.
         in the Digest?

RAJIV SAHAI ENDLAW, J.

1. The suit was registered upon arbitration award dated 22 nd July, 1993

being filed by the arbitrators in this Court. Notice of filing of the award CS(OS) No.1998/1993

was issued. Objections (I.A. No.4972/1994) under Section 30&33 of the

Arbitration Act, 1940 of the defendant to the award are for consideration.

No objections to the award have been preferred by the plaintiff. Usual

issues were framed on 8 th March, 1995. Synopses of submissions were

filed by the parties. I.A. No.12307/1999 has been filed by the plaintiff

under Section 17 of the 1940 Act contending that Arbitral Tribunal had

sent intimation to the parties also of the filing of the award in this Court;

that the objections to the award ought to have been filed by the defendant

within 30 days from such intimation and not within 30 days of the service

of the notice of filing of the award issued by this Court; that the objections

are liable to be dismissed on this ground only and seeking to immediately

make the award rule of the court. The said application was also directed to

be taken up for hearing along with the objections. However no arguments

on the said application were urged at the time of hearing or in the written

synopsis. The counsels for the parties have been heard on the objections to

the award.

CS(OS) No.1998/1993

2. The disputes and differences arose between the parties out of the

contract for the work of 400 KV Single Circuit Transmission Line from

Cuddapah to Bangalore against Specification No.CC-35-176. The Arbitral

Tribunal comprised of three technical experts with two being nominees of

each of the parties and the third having been nominated by the President of

the Institution of Engineers India in terms of the agreement between the

parties. Both parties filed claims against each other before the Arbitral

Tribunal. The time for making of the award was extended from time to

time; 24 sittings held and a unanimous award announced allowing ten out

of sixteen claims of the plaintiff and disallowing all the claims of the

defendant.

3. Objections to the award running into 67 pages have been preferred

by the defendant. It is pleaded that the work was to be completed by 1 st

January, 1985; however the progress of the work from the very beginning

was not commensurate with the Bar chart/work programme agreed upon

under the contract; that the plaintiff did not accelerate the progress of the

work inspite of repeated reminders of the defendant; on the contrary the

CS(OS) No.1998/1993

plaintiff requested for financial assistance and the defendant though not

bound to, agreed to and advanced monies on the condition that the same

shall be paid directly to the producers and suppliers nominated by the

plaintiff and the plaintiff shall furnish bank guarantee for equivalent

amount to the defendant; that the plaintiff still delayed the completion even

beyond the extension of 13 months, causing huge loss to the defendant;

that resultantly some part of the work was off-loaded from the scope of the

work of the plaintiff and awarded at the risk and cost of the plaintiff to M/s

Best & Crompton on 15th July, 1985; that the plaintiff could not improve

the progress of the remaining work inspite thereof; that resultantly some

more work was off-loaded on 15th November, 1985, again to M/s Best &

Crompton with the consent of the plaintiff; that the plaintiff could complete

the work only on 30th June, 1986 and sought extension of time for

completion till 31st August, 1986. It is further pleaded that the plaintiff

while filing claims before the Arbitrators, preferred new claims (i.e. 17 to

25) and which were not raised earlier and for which the Arbitral Tribunal

CS(OS) No.1998/1993

had not been constituted; that upon objection being taken by the defendant,

the Arbitral Tribunal also held the said claims to be beyond its jurisdiction.

4. The senior counsel for the defendant has at the outset contended that

the award is liable to be set aside (i) because two claims have been allowed

on equity inspite of finding the claims to be contractually impermissible;

(ii) The Arbitral Tribunal has itself given extension of time for completion

of work and which was beyond its jurisdiction; (iii) inspite of the letter of

the plaintiff that it will not claim any escalation, allowed the claim for

escalation; (iv) claims have been allowed inspite of finding under Issue

No.15 of there being no proof; (v) allowed interest at the high rate of 18%

per annum which itself runs into crores of rupees.

5. The senior counsel has thereafter made submission claim-wise.

6. Claim No.I of the plaintiff of `.18.623 lacs for reimbursement of extra expenditure for vetting the designs by a foreign company has been allowed for `6.18 lacs.

The Arbitral Tribunal found that though collaboration with a specific

foreign party was not envisaged in the invitation to tender, in the bid or

CS(OS) No.1998/1993

even in the extensive post bid and pre-award correspondence but the

defendant had prevailed upon the plaintiff to qualify themselves by suitable

collaboration. However the Arbitral Tribunal in para 52.1.3 of the award

agreed with the defendant that the collaboration was not under duress as

pleaded by the plaintiff. It was however held that since the defendant had

reaped the benefit of access to diversified foreign know-how in design, it

was liable to pay 50% of the foreign exchange expenditure incurred by the

plaintiff in this regard i.e. `6.18 lac and which has been awarded to the

plaintiff.

7. The senior counsel for the defendant has argued that the plaintiff

cannot possibly be entitled to expenditure incurred by it for being eligible

to bid or to enter into the contract with the defendant and in the face of the

finding that the defendant had not so compelled the plaintiff, the award for

`6.18 lac is bad. It is further contended that the contract was an item rate

contract and there is no item providing for the said claim; that the Arbitral

Tribunal under Issue No.10 has held that contractually the expenditure is

not reimbursable but has sought to justify the claim by holding that neither

CS(OS) No.1998/1993

of the parties at the time of award of the work were aware of the

implications of adopting U.S. practice in carrying out the design and since

there were difficulties and delays in obtaining release of foreign exchange

and different practices in working out L/R ratio etc.; in equity, extra

expenditure is to be considered for reimbursement in the relevant context.

It is yet further shown that the Arbitral Tribunal under Issue No.29 held

that the plaintiff did not possess the qualifying requirement as per NIT

when it made the offer and became qualified only in March, 1982 when

entered into the foreign collaboration and owing whereto the work was

awarded to them. It is further shown that under Issue No.31 the Arbitral

Tribunal has held that the plaintiff was contractually obliged to furnish to

the defendant designs duly vetted by the foreign collaborators.

8. Per contra, the counsel for the plaintiff has contended that once an

award is found to be fair and honest and not based on unsound legal

proposition, the Court should not sit in appeal over it and no case of

misconduct can be said to be made out. Reliance is placed on U.P. State

Electricity Board v. Pateshwari Electricals and Associated Industries (P)

CS(OS) No.1998/1993

Ltd. 1991 (Supp) 2 SCC 718 to contend that the Arbitrator can award any

compensation/claim on the basis of equity. Reliance is also placed on

Section 70 of the Indian Contract Act, 1872 to contend that it itself is an

equitable law and its scope is much larger than the principle of quantum

meriut as explained in Food Corporation of India v. Vikas Majdoor

Kamdar Sahkari Mandli Ltd. (2007) 13 SCC 544.

Reliance is also placed on:-

a) Ispat Engineer and Foundry Works v. SAIL (2001) 6 SCC 347

(paras 3,4&5);

b) Pure Helium India Pvt. Ltd. v. Oil & Natural Gas Commission

(2003) 8 SCC 593 (paras 19,20,22,23,25,27,31,32,33&36);

c) N. Chellappan v. Secretary, Kerala State Electricity Board

(1975) 1 SCC 289 (paras 11,12&13);

d) State of UP v. Allied Constructions (2003) 7 SCC 396 (para 4);

e) Smt. Santa Sila Devi v. Dhirendra Nath Sen AIR 1963 SC 1677

(paras 10&13);

CS(OS) No.1998/1993

f) Goa, Daman & Diu Housing Board v. Ramakant V.P.

Darvotkar AIR 1991 SC 2089 (para 12);

g) Food Corporation of India v. Joginderpal Mohinderpal Singh

AIR 1989 SC 777 (paras 7,8 & 10);

h) Coimbatore Dist. P.T. Sangam v. Bala Subramania Foundry

AIR 1987 SC 2045 (para 7);

i) Vikas Majdoor Kamdar Sahkari Mandli Ltd. (supra) (para

5,11,16,19,20 & 21);

j) K.N. Sathyapalan v. State of Kerala (2007) 13 SCC 43

(distinguishes Alopi Parshad & Sons Ltd. v. UOI AIR 1960 SC

588) - (paras 5,6,11,14,15,16,17,18,24,25,26,27 & 31);

k) Civil Engineers (India) v. DDA 60 (1995) DLT 26 (para 6);

l) MCD v. Jagan Nath Ashok Kumar (1987) 4 SCC 497 (paras

2,3,4,5 & 6);

CS(OS) No.1998/1993

m) Arosan Enterprises Ltd. v. UOI (1999) 9 SCC 449 (paras

1,13,14,15,21,24,26,27 & 39).

n) Sudarsan Trading Co. v. Govt. of Kerala (1989) 2 SCC 38

(paras 28,29 &30).

9. The settled position in law is that an Arbitral Tribunal is a creature

of the agreement. Reference in this regard may also be made to -

(a) Rajasthan State Mines & Minerals Ltd. v. Eastern Engineering

Enterprises (1999) 9 SCC 283;

(b) Steel Authority of India Ltd. v. JC Budharaja, Govt. & Mining

Contractor (1999) 8 SCC 122;

(c) Grid Corporation of Orissa Ltd. v. Balasore Technical School

(2000) 9 SCC 552; and

(d) Ramnath International Construction (P) Ltd. v. UOI (2007) 2 SCC

453.

CS(OS) No.1998/1993

The Arbitral Tribunal cannot award beyond the agreement. Once the

Arbitral Tribunal had concluded that under the contract the plaintiff was

not entitled to the expenses incurred on foreign collaboration, the Arbitral

Tribunal had no jurisdiction to allow the said claim for the reason of the

defendant having benefited therefrom. Moreover once it was found that the

plaintiff, to be eligible to enter into the contract, was required to have a

foreign collaboration, the senior counsel for the defendant is correct in

contending that the expenses for becoming eligible could not be claimed. I

have therefore no hesitation in allowing the said objection and in setting

aside of the award in so far as allowing Claim No.I of the plaintiff for

`6.18 lacs.

10. The Claim No.II of the plaintiff for `50.86 lacs towards reimbursement of extra expenditure incurred on account of difference in weight of fabricated tower parts and bolts & nuts i.e. difference between the actual weights and those as per LOA has been allowed for `10.40 lacs.

It was the case of the plaintiff that the foreign collaborator while

following the defendant's specifications worked out the L/R ratio

according to the practice prevailing in America - had Indian design CS(OS) No.1998/1993

practice been followed, there would have been a reduction in the tower

height; owing thereto excess expenditure had to be incurred and which the

plaintiff computed to be of 319 tonnes costing ` 50.86 lacs. The defendant

though admitted increased weight owing to the US practice having been

followed, contended that they had nothing to do with it. The Arbitral

Tribunal without giving any reason under Claim No.II as to why the

plaintiff was entitled to the said amount assessed extra weight and the

expenditure incurred thereon to be of ` 10.40 lacs which were awarded to

the plaintiff.

11. The senior counsel for the defendant has drawn attention again to the

finding of the arbitrators on Issue No.10 holding that contractually the

extra expenditure incurred is not reimbursable and the finding on Issue

No.13 to the effect that the design was to be made by the plaintiff in

collaboration with the foreign party and the plaintiff was liable to execute

the work at quoted rates. It is shown that the basis of the price payable

under the contract was per tower basis and no claim for extra expenditure if

CS(OS) No.1998/1993

any incurred by the plaintiff in designing and manufacturing the tower

could be claimed.

12. The arguments of the counsel for the plaintiff in opposition are the

same as in the case of Claim No.I above.

13. I am of the opinion that the award of `10.40 lacs under Claim No.II

is not only inconsistent to the findings under Issues No.10&13 but again

beyond the agreement and thus the said award also cannot be sustained and

is set aside. The Apex Court decision in Union of India v.

Pundarikakshudu & Sons (2003) 8 SCC 168 is also an authority on the

proposition that arriving at inconsistent findings as regards breach of

contract is a legal misconduct.

14. Claim No.III of the plaintiff for `2.04 lacs towards reimbursement of extra expenditure incurred on excavation and concreting has been allowed for `51,000/- .

It was the case of the plaintiff itself that excess work was caused

owing to intervention of U.S. practice. The arbitrators for the same reasons

CS(OS) No.1998/1993

as for Claim No.II, scaling down the amount of the claim, awarded

`51,000/-.

15. The arguments of the counsels with respect to the said claim are the

same as with respect to Claim No.II. The award for Claim No.II having

been set aside, the award of `51,000/- under Claim No.III has to

necessarily go.

16. Claim No.IV of `52.92 lacs for balance amount payable towards price variation i.e. difference of the amount entitled to and actually paid has been allowed for `49.86 lacs.

The Arbitral Tribunal held that the date of completion was 1 st

January, 1985; owing to prevailing conditions the same was extended till

31st January, 1986; that the defendant however withheld further extension

to pressurize the plaintiff into completion; that subsequent evidence and

behaviour of the parties justified extension of the completion period up to

30th June, 1986 and the insistence of the defendant for completion by 31st

January, 1986 was not justified. On the said basis price variation was

allowed and the claim of ` 49.86 lacs accepted.

CS(OS) No.1998/1993

17. The senior counsel for the defendant has with reference to Clauses

22.3, 22.4.3, 13.7 of the GCC Volume-I and Clause 6 of Letter of Award

dated 31st March, 1982 contended that no escalation was payable for the

period of time between the scheduled date of shipment and the actual date

of shipment. Attention is next invited to the finding returned under Issue

No.12 holding the off-loading of part of the work as justified and the

targets given being very high and incapable of performance. It is argued

that the Arbitral Tribunal cannot re-write the contract or extend time of

performance of the contract. It is also argued that once the targets had been

agreed to, the question of arbitrators holding the same to be high did not

arise. It is argued that there is no calculation or formula or basis given for

arriving at the figure of `49.86 lacs awarded. It is urged that the price

variation granted is for the extension allowed from 1st February, 1986 to

30th June, 1986. It is also urged that while on the same evidence Claim

No.V also on account of price variation has been rejected, Claim No.IV has

been allowed. Attention is also invited to the finding under Issue No.15

where the risk between the owner and the contractor was directed to be

CS(OS) No.1998/1993

borne in the percentage of 60% by the defendant and 40% by the plaintiff.

It is argued that even if the Claim No.IV were to be allowed, there is no

reason why the entire burden has been put on the defendant and at least

40% not directed to be shared by the plaintiff.

18. The counsel for the plaintiff has argued that the findings of the

arbitrators with respect to the time for performance cannot be interfered

with. Reliance in this regard is placed on:-

            i.    Jagan Nath Ashok Kumar (supra);

           ii.    Arosan Enterprises Ltd. (supra);

          iii.    McDermott International Inc. v. Burn Standard Co. (2006)

                  11 SCC 181 (paras 86,87 &88)

          iv.     J.K. Industries Ltd. v. Texmaco Ltd. MANU/DE/1314/2009

           v.     Hind Construction Contractors v. State of Maharashtra

                  (1979) 2 SCC 70 (paras 7,8,9 & 10).




CS(OS) No.1998/1993

19. Though I agree with the contention of the plaintiff that the findings

regarding time of performance returned in the award are not to be

interfered but I am unable to find any reason in the award for allowing the

claim for `49.86 lacs. The award does not state that the defendant had

admitted the said claim, for there being no need for the plaintiff to prove

the same. The award does not even state as to how and in accordance with

which formula price variation has been worked out.

20. It is also not the case that the arbitrators were required to give a non-

speaking award. The arbitrators are required to give reasons and not

finding any reason whatsoever for allowing the claim in entirety of `49.86

lacs, there is no option but to set it aside.

21. Claim No.VI of `11,29,711/- was for refund of amount recovered unjustly on account of off-loading portion of the work of tower erection and stringing to M/s Best & Crompton.

The said claim has been allowed in entirety for the findings under

Issue No.12 i.e. of the targets set being high.

CS(OS) No.1998/1993

22. It is undisputed that the work was off-loaded with the consent of the

plaintiff and at the cost and risk of the plaintiff. Once that was so, the

reasoning of the arbitrators that the targets were high and incapable of

achievement is nothing but misconduct. The arbitrators again have entered

into the arena of changing the contract between the parties and of which

the Arbitral Tribunal being itself a creature of the contract, could not have

done. Once the plaintiff had agreed to the targets, it did not lie in the mouth

of the plaintiff to plead that the targets were unrealistic or beyond

achievement. The plaintiff could have been relieved of the said targets only

on the ground of a contributory failure on the part of the defendant. That is

not the case here. Without that being the case, the defendant was justified

in deducting from the amounts due to the plaintiff the extra amount

incurred by it in off-loading part of the work to M/s Best & Crompton at

the risk of the plaintiff. The award against Claim No.VI is also accordingly

set aside.

CS(OS) No.1998/1993

23. Claim No.VII of `.20.46 lacs for reimbursement of extra expenditure incurred on extra cut points for single and double circuits of the transmission line has been allowed for `13,81,000/- .

The defence of the defendant to the said claim was that such

variation was a normal feature. The Arbitral Tribunal found the variation to

be against the industry norm and assessed in Appendix-12 to the award the

amount to which the plaintiff was entitled to on this account at

`13,81,000/-.

24. The senior counsel for the defendant has argued that the arbitrators,

for allowing the said claim have relied on their own professional

experience in the matter and also claimed to have consulted practicing

professionals in the field. It is argued that neither any notice of the same

was given to the defendant nor the defendant given any opportunity to

cross examine the said professionals. From the Tender documents/contract

it is shown that there is no mention of cut points. It is thus urged that no

award for additional work for excess cut points could have been made.

CS(OS) No.1998/1993

25. I am unable to agree. The parties had chosen technical persons as

their own nominees as arbitrators and had entrusted the appointment of the

third arbitrator also to an expert body. The appointment of such experts

was not without reason. The parties understood that the adjudication

required expert knowledge possessed by the Arbitral Tribunal and relied on

that for making of the award. The defendant cannot now be heard to state

that such experts ought not to have used their knowledge and expertise in

the field. The Division Bench of this Court in Em & Em Associates Vs.

DDA AIR 2003 Delhi 128 has held that the modern tendency especially in

commercial arbitrations is to uphold the awards of skilled persons that the

parties themselves have selected. Similarly the consultation by the

arbitrators with professionals currently in the field also cannot tantamount

to misconduct. The arbitrators though experts were no longer in active

practice. No error can be found in their re-assuring themselves that their

knowledge/expertise had not been outdated and as to the prevalent norms.

The arbitrators were not required to involve the parties or to give an

opportunity of cross examination qua the said consultation. The arbitrators

CS(OS) No.1998/1993

have in Appendix-12 given the reasons for arriving at the awarded amount

of `13,81,000/-. Thus the objections qua award on Claim No.VII are

without any merit and are dismissed.

26. Claim No.IX of `15.03 lacs for reimbursement of extra cost incurred in fabricating extra tonnage of tower parts has been allowed for `9 lacs.

It was the admitted position that in the exigencies and urgencies of

the project the plaintiff was required to carry out the said work. The

arbitrators as aforesaid had apportioned the said liability as 60% of the

defendant and 40% of the plaintiff. There does not appear to have been any

dispute of the amount spent in the same. The arbitrators accordingly

apportioned the liability of the defendant as 60% i.e `9 lacs.

27. The senior counsel for the defendant has argued that the said claim is

the same as Claim No.II (supra). I am unable to agree. The said claim was

not on account of the American design but owing to extra cost admittedly

incurred owing to exigencies and urgencies of the project.

CS(OS) No.1998/1993

28. The senior counsel has next argued that the arbitrators have

overlooked the contention of the defendant, of the plaintiff under the

contract being required to take out insurance against such risks. Attention

is invited to the terms of the contract in this regard. It is also argued that

the award is in ignorance of the pleadings. It is thus contended that the

responsibility for the risk was to be solely of the plaintiff and 60% thereof

could not have been saddled on the defendant.

29. The courts have held that merely because an arbitrator has wrongly

construed a contractual provision is no ground for setting aside of the

award. When the parties agree to refer their disputes to arbitration they are

bound by the interpretation by the Tribunal of the terms of the contract

whether right or wrong. Reference in this regard can be made to -

(a) Hindustan Construction Co. Ltd. v. State of J&K (1992) 4 SCC

217;

CS(OS) No.1998/1993

(b) Himanchal Pradesh State Electricity Board v. R.J. Shah & Co.

(1999) 4 SCC 214 .

If such grounds were to be permitted, then the jurisdiction exercised in the

matter of the perversity would be appellate and which the legislature has

not provided for. A case for interference is made out only when perversity

is shown. I am unable to find any element of perversity in the award qua

Claim No.IX. The objections of the defendant to the award under the said

claim are accordingly dismissed.

30. Claim No.XII for `124.21 lacs towards extra expenditure incurred on overheads beyond the stipulated agreement period has been allowed for `23 lacs.

While it was the contention of the defendant that the delays beyond

1stJanuary, 1985 were attributable to the plaintiff and thus the plaintiff

should bear the entire costs in full, the plaintiff attributed the delays to the

defendant. The Arbitral Tribunal in view of the finding aforesaid that

insistence by the defendant on completion by 31 st January, 1986 was not

justified, and further in view of the finding that the plaintiff after 31st

CS(OS) No.1998/1993

January, 1986 repeatedly promised performance to agreed levels and then

repeatedly failed, held that both parties should share the overheads equally.

The Arbitral Tribunal computed the overheads for 18 months of delay i.e.

from 1st January, 1985 to 30th June, 1986 at `44.34 lacs and accordingly

passed an award for half of that amount i.e. `22.17 lacs say `23 lacs as

aforesaid.

31. The senior counsel for the defendant has argued that the heading of

the claim itself shows that the claim is de hors the contract. It is contended

that the said claim again amounts to re-writing of the contract by the

arbitrators. Reliance is placed on:-

1) Rickmers Verwaltung GMBH v. Indian Oil Corporation Ltd.

1999(1) SCC 1 (para 13);

2) Asstt. Excise Commissioner v. ISSAC Peter 1994(4) SCC

104;

3) Shin Satellite Public Co. Ltd. v. Jain Studios Ltd. (2006) 2

SCC 628 (para 15);

CS(OS) No.1998/1993

4) Forbes Gokak Ltd. v. Central Warehousing Corporation 2003

(1) RAJ 200 (Del) (paras 50,51).

32. It is further urged that though in para 35.1 the arbitrators have held

that the damages for respective breaches have to be arrived at on the basis

of actual loss sustained, in paragraphs 52.12.2, "in the absence of hard

unchallengeable evidence" assessment has been made on rough estimates.

It is thus argued that the award is without any basis. Claiming

inconsistency and relying on:-

1) K.P. Poulose v. State of Kerala AIR 1975 SC 1259;

2) V.G. George v. Indian Rare Earths Ltd. AIR 1999 SC 1409 ;

3) Bombay Ammonia Pvt. Ltd. v. UOI AIR 1987 Delhi 148,

setting aside of the award is sought.

33. Reliance is also placed on:-

A. Sikkim Subba Associates v. State of Sikkim (2001) 5 SCC

629;

         B.       Bombay Ammonia Pvt. Ltd. (supra)

CS(OS) No.1998/1993

to contend that award without evidence is liable to be set aside.

34. It is yet further pleaded that the contract period having been

extended from 1st January, 1985 to 31st January, 1986, no overhead for the

said period in any case could have been awarded. Attention is also invited

to para 52.12.2 (a) of the award where it is recorded that the PV formula

applied by the arbitrators comprised of overheads also.

35. Per contra, the counsel for the plaintiff has contended that the

arbitrators having recorded that full and fair opportunity had been given to

the parties, no case for misconduct can be said to have been made out.

Reliance is also placed on paras 85 to 88 of McDermott International Inc.

(supra) to contend that time is not of the essence in construction contracts.

Attention is invited to the letter dated 3rd September, 1984 listing delays

attributable to the defendant and to the bid proposal to show that the prices

were valid for six months. It is contended that all specifications were as per

Indian standards and arbitrators having returned a factual finding of

CS(OS) No.1998/1993

American standards having been used and the defendant having benefitted

therefrom, there is no defect capable of interference in the award.

36. The senior counsel for the defendant has rejoined by drawing

attention to para 108 of the judgment in McDermott International Inc. to

contend that in that case also the Ld. Arbitrator had insisted that sufferance

of actual damages must be proved by bringing on record books of

accounts.

37. Having held the extension of period of performance from 1 st

February, 1986 to 30th June, 1986 by the arbitrators to be bad, the award

awarding overheads for the said period has to be axiomatically set aside.

The question which arises is whether the award for the period 1 st January,

1985 to 31st January, 1986 requires interference or not. Need is not felt to

go into the said question since from the award as it stands, the amount

awarded of `23 lacs cannot be segregated. Thus the entire award under

Claim No.XII has to be set aside.

CS(OS) No.1998/1993

38. I am also of the opinion that no award could have been made on

"imponderables and rough estimate" admittedly used by the arbitrators.

The PV formula used of 25% was for the fixed elements "including"

overheads and not overheads alone. There is no basis whatsoever for the

arbitrators assuming that overheads formed 50% of the fixed elements.

Similarly, the other formula adopted was also on estimates. The arbitrators

failed to render an award of the claim on merits and to return a finding on

whether the claim of the plaintiff of overheads of `124.21 lacs was

established or not. The only conclusion which follows is that the plaintiff

had failed to establish the claim. The arbitrators instead of dismissing the

claim tried to make out a new case and which is not permissible in law.

39. Claim No.XIII of `.3.40 lacs towards reimbursement of extra expenditure incurred in furnishing bank guarantee beyond the stipulated agreement has been allowed for ` 1,51,526/-

The said amount was claimed by the plaintiff for expenses incurred

in furnishing Bank Guarantee beyond the originally stipulated completion

date of 1st January, 1985. The arbitrators on the basis of finding that both

CS(OS) No.1998/1993

parties were equally to blame for the delays awarded half of that amount

i.e. `1,51,526/-.

40. The senior counsel for the defendant has contended that as per the

contract the plaintiff was bound to keep the Bank Guarantee alive for a

period of 15 months from the original date of completion; that the plaintiff

had completed the line on 30 th June, 1986 and as such was bound to keep

the bank guarantee alive in any case till 30 th September, 1987 and thus the

claim for expenses incurred could not have been allowed. The counsel for

the plaintiff has again contended that the findings are factual in nature not

capable of interference. The senior counsel for the defendant also invited

attention to statement XIII A giving the computation of the amount of

`3.40 lacs claimed by the plaintiff. It is shown that though the claim was in

respect of contract performance guarantee only but the amount claimed

included expenses of other guarantees also and with respect to which no

claim was made.

CS(OS) No.1998/1993

41. The counsel for the plaintiff has not argued that the objections now

raised by the defendant did not form the defence of the defendant to the

claims before the arbitrators. The award is completely silent with respect to

the defences of the defendant. I find the arbitrators to have misconducted

themselves in not adjudicating the dispute raised before them and in not

even considering the pleas of the defendant. The award is liable to be

dismissed on this ground alone.

42. The Arbitral Tribunal has awarded interest (i) at 18% per annum pre

reference amounting to ` 25,07,436/-, (ii) at 18% per annum pendente lite

from the date of reference i.e. 20 th June, 1988 to the date of award and also

(iii) at 18% per annum from the date of the award i.e. 22 nd July, 1993 till

the date of actual payment or date of decree whichever is earlier.

43. The senior counsel for the defendant has contended that the award

of pre reference interest is contrary to the Interest Act, 1978; it is urged

that the notice claiming interest as mandated by Section 3 (b) of the

Interest Act, 1978 was given only on 15 th November, 1987 and thus

CS(OS) No.1998/1993

interest prior thereto could not have been awarded. Reliance in this regard

is placed on Superintending Engineer v. B. Subba Reddy AIR 1999 SC

1747. Objection is also taken to the rate of interest awarded claiming it to

be highly excessive. Lastly, it is contended that no interest could have been

awarded for the period for making the award Rule of the Court. Reference

in this regard is made to Section 29 of the Arbitration Act, 1940.

44. I am unable to, in exercise of jurisdiction under Sections 30&33 of

the 1940 Act find a ground for interference with the award of interest for

pre reference period. The Supreme Court recently in Sree Kamatchi

Amman Constructions v. Railways (2010) 8 SCC 767 relying upon the

Constitution Bench judgment in Dhenkanal Minor Irrigation Division v.

N.C. Budharaj (2001) 2 SCC 721 held that the arbitrator has the

jurisdiction to award interest pre-reference, pendente lite and future if there

is no express bar in the contract regarding award of interest. No such bar

has been shown in the present case. As far as award of interest pendente

lite is concerned also, in view of the judgments in (a) M/s. Manalal

Prabhudayal v. Oriental Insurance Co. Ltd. AIR 2006 SC 3026;

CS(OS) No.1998/1993

(b) Bihar Sponge Iron Ltd. (BSIL) v. Rail India Technical & Economic

Services Ltd. 132 (2006) DLT 489 (DB); (c) MMTC Ltd. v. Sineximco

Pte. Ltd. 2009 (V) AD (Del.) 748; (d) Union of India v. Saraswat

Trading Agency JT 2009 (9) SC 648 and (e) Sayeed Ahmed & Co. v. State

of U.P. (2009) 12 SCC 26, interference with rate awarded is

impermissible. Section 29 of the Act only empowers the Court to award

interest from the date of the decree to the date of payment. However the

fact remains that the proceedings for making the award Rule of the Court

have remained pending in the Court for an unusually long time. On

account thereof only, it is deemed appropriate to balance the equities. The

Supreme Court in (i) Pure Helium India (P) Ltd.(supra) (ii) Krishna

Bhagya Jala Nigam Ltd. v. G. Harish Chandra Reddy (2007) 2 SCC 720

and (iii) U.P. Coop. Federation Ltd. v. Three Circles (2009) 10 SCC 374

has reduced the rate of interest from 18% per annum. In the facts and

circumstances of the case, it is deemed expedient to vary the rate of

interest from the date of filing of the award in this Court and till this date

from 18% per annum to 10% per annum. The plaintiff shall also be entitled

CS(OS) No.1998/1993

to interest from the date of the decree till the date of payment at 10% per

annum.

45. In so far as the counter claims of the defendant are concerned, the

senior counsel for the defendant has made submissions only with respect to

the rejection of the Counter Claim No.V of ` 22.99 lacs for liquidated

damages. The Arbitral Tribunal has rejected the said counter claim of the

defendant on account of the defendant being equally responsible for the

delays.

46. The finding of the Arbitral Tribunal of the defendant also being

responsible for delay, is a finding of fact and cannot be interfered with in

exercise of jurisdiction under Sections 30 & 33 of the Act. No merit is

therefore found in the objections of the defendant to the rejection of the

said counter claim. The said objection is accordingly rejected.

47. No other arguments have been raised.

CS(OS) No.1998/1993

48. The award as modified hereinabove is accordingly made Rule of the

Court and a decree in terms thereof is passed as aforesaid. The plaintiff

shall be entitled to interest on the principal amount from the date of the

decree till the date of payment @10% per annum. No order as to costs.

RAJIV SAHAI ENDLAW (JUDGE)

FEBRUARY 18th, 2011 pp..

CS(OS) No.1998/1993

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter