Citation : 2011 Latest Caselaw 833 Del
Judgement Date : 11 February, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: 13th January, 2011
Date of decision: 11th February, 2011
+ FAO (OS) 714/2010
MIC ELECTRONICS LTD. & ANR. .....Appellants
Through: Mr. Ramji Srinivasan, Sr. Advocate
with Mr. Rajeev Kumar,
Mr. Zeyaul Haque and Ms. Alka
Srivastava, Advocates.
-versus-
MUNICIPAL CORPORATION OF DELHI & ANR. .....Respondents
Through: Ms. Pinky Anand, Sr. Advocate
with Ms. Mini Pushkarna,
Advocate.
% CORAM:
HON'BLE MR. JUSTICE VIKRAMAJIT SEN
HON'BLE MR. JUSTICE SIDDHARTH MRIDUL
1. Whether reporters of local papers may be allowed to see
the judgment? No.
2. To be referred to the Reporter or not? Yes.
3. Whether the judgment should be reported in
the Digest? Yes.
JUDGMENT
SIDDHARTH MRIDUL, J.
1. The present is an appeal under Section 37 of the
Arbitration and Conciliation Act, 1996 (hereinafter referred to
as „the said Act‟) against the judgment dated 15th December,
2010 in OMP No. 742/2010 whereby the application of the
Appellant under Section 9 of the said Act was dismissed.
2. The petition under Section 9 of the said Act filed by the
Appellant prayed for the following reliefs:
"(i) stay the operation of the letter dated 25/11/2010 cancelling the contract for display of advertisement through LED screens in market areas and forfeiture of the security amount, by the Respondent MCD.
(ii) direct the parties to maintain status quo in respect of the possession and operation of the 9 sites.
(iii) restrain the respondent MCD from taking any steps for recovery of the impugned demand in terms of the letter dated 25/11/2010, pending the disposal of arbitration proceedings.
(iv) injunct the Respondent MCD from calling any tender for remaining 41 sites till the conclusion of the arbitration proceeding.
(v) pass ex-parte orders in respect of prays at serial Nos. (i) to (iv).
(vi) pass such other or further order(s) as it may deem fit and proper keeping in view the fact and circumstances of the case."
3. The facts as are necessary for the adjudication of the
present appeal are that:
(a) A contract was entered into between the Appellant
and the Respondent for display of advertisement
through 50 LED screens at selected market areas of
Delhi under the jurisdiction of Municipal
Corporation of Delhi (MCD), Respondent herein, for
a period of five years at the monthly licence fee of
`1,01,750/- per screen per month totaling up to
`50,87,500/- for all the screens. In this behalf it is
stated that the tender notice dated 19th March, 2009
with details of sites to be provided for setting up of
the LED screens was issued by the Respondent. It is
further pertinent to note that the terms and
conditions prescribed by the Respondent under the
heading „Terms and Conditions‟ itself contained the
expression „under the jurisdiction of MCD‟.
(b) Clause 2(a) of the terms and conditions prescribed
the incubation period as two months of contract
whereby no licence fee was to be charged for this
period. The clause further provided that payments
were to be made from the third month for the actual
number of screens which had been set up by then.
However, from the seventh month onwards payment
had to be made for all 50 LED screens.
(c) Clause 5 of the terms and conditions contains
description of the sites wherein it was prescribed
that inspection of sites before filing of tender to be
made and if required clarifications be sought
thereupon. This clause debarred any objection,
dispute or grievance to be raised regarding the sites
after submission of tenders.
(d) Clause 6 relied upon by the Appellant provided for
flexibility in the contract to the effect that it was
specified that there may be an increase or decrease
in the number of sites and, therefore, the licence fee
would accordingly be charged in relation to the
number of sites available. This clause further
provided that if any site was removed in public
interest or for any other reason, alternate site would
be provided to the Appellant by the Respondent
herein. If for any other reason site was not available
their licence fee/ground rent was to be remitted
back according to pro-rata basis.
(e) Clause 10 of the agreement provided that if payment
was not made in the stipulated manner, a late fee of
2% per month was liable to be charged. It further
provided that if the licence fee/ground rent are not
received by the 10th of the succeeding month, the
contract would be liable to be terminated.
(f) Clause 16 of the said agreement provided that the
LED screens would be displayed only at the allotted
sites and positions as may be determined by the
Respondent. Clause 28 of the agreement provided
for arbitration.
(g) On 4th August, 2009 consequent upon deposit of
security the Respondent issued an allotment letter in
respect of the 50 LED display screens and after the
grant of allotment on 25th June, 2009 the parties
entered into the agreement in respect of these
screens. Thereafter, the Appellant states that, out of
the 50 designated sites 25 sites did not fall either
within the jurisdiction of the MCD or were not
permitted by traffic police as violating the Supreme
Court guidelines in this behalf.
(h) The Appellant also states that it paid licence fee to
the Respondent from 10th October, 2009 to 13th July,
2010 amounting to `2,95,07,747/-(first seven
months). Since payment were not made for all the
50 sites and the cheques furnished to the
Respondent were dishonoured when presented for
encashment, show cause notice dated 27th October,
2010 was issued to the Appellant as to why the
contract be not cancelled and the security amount
not forfeited for violation of the terms and
conditions of the contract. The Respondent also
demanded a balance outstanding payment of
`3,05,25,000/- towards arrears of licence fee.
(i) A reply was filed on behalf of the Appellant through
letters dated 27th October, 2010 and 28th October,
2010 wherein the Appellant stated that they were
liable to pay for only the 20 operational sites.
(j) The subject contract was cancelled by the
Respondent vide letter dated 25th November, 2010
and the said cancellation order provided for
recovery of dues within a period of three days from
the receipt of the said order dated 25th November,
2008.
(k) The Appellant challenged the cancellation of
contract vide Writ Petition (Civil) No.8114/2010. The
writ petition was disposed of on 3rd December, 2010
as the agreement between the parties contained an
arbitration clause. The arbitration proceedings were
invoked by the Appellant and Arbitrator has been
appointed on 11th January, 2011.
(l) Aggrieved by the action of the Respondent, the
Appellant, thereafter, filed OMP No.742/2010 under
Section 9 of the said Act praying for interim
protection as set out hereinabove. Vide the
impugned order dated 15th December, 2010 the
learned Single Judge came to the conclusion that the
Appellant had been unable to make out a prima facie
case for the grant of any interim relief and thereby
dismissed the said OMP.
(m) Aggrieved by the dismissal of its petition under
Section 9 of the said Act, the Appellant has
preferred the present appeal as aforesaid.
4. On behalf of the Appellant Mr. Ramji Srinivasan, learned
Senior Counsel, first submitted that out of the 50 sites provided
by the Respondent 25 sites were either not under the control of
the Respondent or objections were raised by the traffic police,
market associations and car parking contractors. In this behalf,
it was submitted that various letters had been addressed to the
Respondents enumerating the various hurdles faced by the
Appellant and the objections to the sites provided by the
Respondent. In this behalf the Appellant further submitted that
only 9 sites could be successfully installed by the end of
October, 2010 and 16 sites were under consideration at that
time. With regard to the remaining 25 sites, according to the
Appellant, work could not even be started due to the non-
viability from technical, commercial or other reasons. It was
next urged by the learned Senior Counsel appearing on behalf
of the Appellant that clauses 6 and 16 of the subject contract
provided for an increase or decrease in the number of sites and
payment of licence fee proportionally thereto and, therefore, the
impugned order fell into error in not appreciating that the
Appellant could have been allowed to continue to operate the
licence in respect of 9 chosen sites and not in respect of others.
5. Per contra, on behalf of the Respondent, Ms. Pinky Anand,
Senior Counsel, submitted that Section 14(1)(c) of the Specific
Relief Act specifically provided that a contract which is in its
very nature determinable could not be specifically enforced,
which is what the Appellant were seeking by way of the present
Appeal.
6. It was then urged on behalf of the Respondent that
Section 41(e) of the Specific Relief Act categorically provided
that an injunction could not be granted to prevent the breach of
a contract, the performance of which would not be specifically
enforced. In this behalf the Respondent relied upon the
decisions of this Court in Rajasthan Breweries Ltd.-vs.-The Stroh
Brewery Company, reported as 2000(3)Arb. LR 509(Delhi) and
Raj Electricals (Regd.)-vs.-BSES Rajdhani Power Ltd. reported as
142(2007) Delhi Law Times 687. It was further urged on behalf
of the Respondent that the 50 sites which were the subject
matter of the contract had been identified by the Appellant
themselves and were all within the jurisdiction of the
Respondent. It was also urged that although the agreement was
entered into in the month of June, 2009 the first objection with
regard to the purported non-viability of the sites were raised
only in the month of December, 2009. It was lastly urged on
behalf of the Respondent that if the Arbitral Tribunal came to
the conclusion that the cancellation of the contract was bad, in
that event, the Appellant would be entitled to damages.
7. In rejoinder, it was urged on behalf of the Appellant that
the Respondent were performing a public function or a public
duty and that while discharging such a public duty Article 14 of
the Constitution of India required it to act fairly, justly and
reasonably. In other words, it was urged that the Respondent
being State cannot cast off its personality and exercise
unbridled power unfettered by the requirement of Article 14 in
the sphere of contractual matters and claim to be governed
therein only by private law principles applicable to private
individuals whose rights flow only from the terms of contract
without anything more. In this behalf, the Appellant relied on
the decision of the Supreme Court in ABL International Ltd. and
another-vs.-Export Credit Guarantee Corporation of India Ltd.
and others reported as (2004) 3 SCC 553.
8. Before considering the submissions made on behalf of the
parties, it would be appropriate to refer to the relevant extract
of the decisions cited on their behalf. In ABL International
Ltd.(supra) the Supreme Court observed as follows:
"52. On the basis of the above conclusion of ours, the question still remains why should we grant the reliefs sought for by the appellants in a writ petition when a suitable efficacious alternate remedy is available by way of a suit. The answer to this question, in our opinion, lies squarely in the decision of this Court in the case of Shrilekha Vidyarthi wherein this court held:
The requirement of Article 14 should extend even in the sphere of contractual matters for regulating the conduct of the State activity. Applicability of Article 14 to all executive actions of the State being settled and for the same reason its applicability at the threshold to the making of a contract in exercise of the executive power being beyond dispute, the State cannot thereafter cast off its personality and exercise unbridled power unfettered by the requirements of Article 14 in the sphere of contractual matters and claim to be governed therein only by private law principles applicable to private individuals whose rights flow only from the terms of the contract without anything more. The personality of the State, requiring regulation of its conduct in all spheres by requirement of Article14, does not undergo such a radical change after the making of a contract merely because some contractual rights accrue to the other party in addition. It is not as if the requirement of Article 14 and contractual obligations are alien concepts, which cannot co-exist. The Constitution does not envisage or permit unfairness or unreasonableness in State actions in any sphere of its activity contrary to the professed ideals in the Preamble. Therefore, total exclusion of Article 14 - non-arbitrariness which is basic to rule of law - from State actions
in contractual field is not justified. This is more so when the modern trend is also to examine the unreasonableness of a term in such contracts where the bargaining power is unequal so that these are not negotiated contracts but standard form contracts between unequals.
Unlike the private parties the State while exercising its powers and discharging its functions, acts indubitably, as is expected of it, for public good and in public interest. The impact of every State action is also on public interest. It is really the nature of its personality as State which is significant and must characterize all its actions, in whatever field, and not the nature of function, contractual or otherwise, which is decisive of the nature of scrutiny permitted for examining the validity of its act. The requirement of Article 14 being the duty to act fairly, justly and reasonably, there is nothing which militates against the concept of requiring the State always to so act, even in contractual matters. This factor alone is sufficient to import at least the minimal requirements of public law obligations and impress with this character the contracts made by the State or its instrumentality. It is a different matter that the scope of judicial review in respect of disputes falling within the domain of contractual obligations may be more limited and in doubtful cases the parties may be relegated to adjudication of their rights by resort to remedies provided for adjudication of purely contractual disputes. However, to the extent, challenge is made on the ground of violation of Article 14 by alleging that the impugned act is arbitrary, unfair or unreasonable, the fact that the dispute also falls within the domain of contractual obligations would not relieve the State of its obligation to comply with the basic requirements of Article 14. To this extent, the obligation is of a public character invariably in every case irrespective of there being any other right or obligation in addition thereto. An additional contractual obligation cannot divest the claimant of the guarantee under Article 14 of non-arbitrariness at the hands of the State in any of its actions."
In Rajasthan Breweries Ltd.(supra) a Division Bench of this
Court held as follows:
"19. Even in the absence of specific clause authorising and enabling either party to terminate the agreement in the event of happening of the events specified therein, from the very nature of the agreement, which is private commercial transaction, the same could be terminated even without assigning any reason by serving a reasonable notice. At the most, in case ultimately it is found that termination was bad in law or contrary to the terms of the agreement or of any understanding between the parties or for any other reason, the remedy of the appellants would be to seek compensation for wrongful termination but not a claim for specific performance of the agreements and for that view of the matter learned Single Judge was justified in coming to the conclusion that the appellant had sought for an injunction seeking to specifically enforce the agreement. Such an injunction is statuorily prohibited with respect of a contract, which is determinable in nature. The application being under the provisions of Section 9(ii)(e) of the Arbitration and Conciliation Act, relief was not granted in view of Section 14(i)(c) read with Section 41 of the Specific Relief Act. It was rightly held that other clauses of Section 9 of the Act shall not apply to the contract, which is otherwise determinable in respect of which the prayer is made specifically to enforce the same. Consequently, therein no merit in the appeal, the same is dismissed."
In Raj Electrical (Supra) a Single Judge of this Court held
as follows:
"11. Like any other contract this contract is also to be governed by the commercial interest of the parties. If the respondent considers that the arrangement which was made by DVB of Single Point Distribution seeking services of the contractor has outlived its utility and the respondent was in a
better position to serve the people of the area, the respondent can terminate the contract and suffer the consequences in terms of agreement between the parties. The Court cannot compel the respondent to continue with an agreement. The respondent who is a company incorporated for supply and distribution of electricity has a better infrastructure available with it to fulfill the needs of the electrification of the areas. While the contractors who are either individuals or firms in fact were introduced merely to overcome a problem which erstwhile DVB could not tackle at the time. A contractor cannot be made a permanent feature of the electricity supply system. It is a right and obligation of the respondent to supply electricity in the area for which respondent is a licensee under Delhi Electricity Reforms Act, 2000. If the respondent considers it can provide better services and facilities it can always terminate the contract of the contractors.
12. Even otherwise in order to grant any injunction under Section 9 of the Arbitration Act, the Court can grant such a relief only if an irreparable loss or injury is going to be caused to the party. In the present case, there is no question of irreparable loss or injury since the agreement itself provides that in case of wrongful termination of the agreement either party shall be entitled to the damages. Damages in such case can be determined by the arbitrator to whom the dispute is referred. Even otherwise where the party can be compensated by way of damages, the Court should refrain from issuing interim injunction."
9. Coming to the submissions made on behalf of the parties,
the principal contention of the Appellant is that the relationship
between the parties would be governed by public law principles
and not by the private law principles governing contractual
matters. In this behalf, it is observed that in ABL International
Ltd.(supra), whilst relying on the law laid down in Shrilekha
Vidyarthi-vs.-State of U.P., (1991) 1 SCC 212, the Supreme Court
held that the requirements of Article 14 extends even in the
sphere of contractual matters and the claim of the parties to be
governed therein does not undergo a radical change merely
because some contractual rights accrue to the other party in
addition. Therefore, in other words, it was held that total
exclusion of Article 14 - non-arbitrariness which is basic rule of
law - from State actions in contractual field is not justified.
Thus, the Supreme Court held that the fact that the dispute also
falls within the domain of contractual obligations would not
relieve the State of its obligation to comply with the basic
requirements of Article 14. To this extent, the obligation is of a
public character invariably in every case irrespective of there
being any other right or obligation in addition thereto. However,
it is observed that the decision of the Supreme Court in ABL
International Ltd.(supra) is not an authority for the proposition
that the mutual rights and liabilities of the parties where the
contracts are freely entered into with the State are exclusively
governed by public law principles and not by the terms and
conditions of the contracts and the laws relating to contracts.
10. Further, in Assistant Excise Commissioner -vs.-Issac Peter
reported as (1994) 4 SCC 104, the Supreme Court held:-
"26. Learned Counsel for Respondents then submitted that doctrine of fairness and reasonableness must be read into contracts to which State is a party. It is submitted that the State cannot act unreasonably or unfairly even while acting under a contract involving State power. Now, let us see, what is the purpose for which this argument is addressed and what is the implication? The purpose, as we can see, is that though the contract says that supply of additional quota is discretionary, it must be read as obligatory - at least to the extent of previous year's supplies - by applying the said doctrine. It is submitted that if this is not done, the licencees would suffer monetarily. The other purpose is to say that if the State is not able to so supply, it would be unreasonable on its part to demand the full amount due to it under the contract. In short, the duty to act fairly is sought to be imported into the contract to modify and alter its terms and to create an obligation upon the State which is not there in the contract. We must confess, we are not aware of any such doctrine of fairness or reasonableness. Nor could the learned Counsel bring to our notice any decision laying down such a proposition. Doctrine of fairness of the duty to act fairly and reasonably is a doctrine developed in the administrative law field to ensure the Rule of Law and to prevent failure of justice where the action is administrative in nature. Just as principles of natural justice ensure fair decision where the function is quasi-judicial, the doctrine of fairness is evolved to ensure fair action where the function is administrative. But it can certainly not be invoked to amend, alter or vary the express terms of the contract between the parties. This is so, even if the contract is governed by statutory provisions, i.e., where it is a statutory contract - or rather more so. It is one thing to say that a contract - every contract - must be construed reasonably having regard to its language. But this is not what the licencees say. They seek to create an obligation on the other party to the contract, just because it happens to be the State. They are not prepared to apply the very same rule in a converse case, i.e., where the State has abundant supplies and wants the licencees to lift all that stocks. The licencees will undertake no obligation to lift all those stocks even if the State suffers loss. This one-
sided obligation, in modification of express terms of the contract, in the name of duty to act fairly, is what we are unable to appreciate. The decisions cited by the learned, counsel for the licencees do not support their proposition. In Dwarkadas Marfatia v. Board of Trustees of the Port of Bombay, (1989) 3 SCC 293, it was held that where a public authority is exempted from the operation of a Statute like Rent Control Act, it must be presumed that such exemption from the statute is coupled with the duty to act fairly and reasonably. The decision does not say that the terms and conditions of contract can be varied, added or altered by importing the said doctrine. It may be noted that though the said principle was affirmed, no relief was given to the appellant in that case. Shrilekha Vidyarthi v. State of U.P., (1991) 1 SCC 212, was a case of mass termination of District Government Counsel in the State of U.P. It was a case of termination from a post involving public element. It was a case of non-government servant holding a public office, on account of which it was held to be a matter within the public law field. This decision too does not affirm the principle now canvassed by the learned Counsel. We are, therefore, of the opinion that in case of contracts freely entered into with the State, like the present ones, there is no room for invoking the doctrine of fairness and reasonableness against one party to the contract (State), for the purpose of altering or adding to the terms conditions of the contract, merely because it happens to be the State. In such cases, the mutual rights and liabilities of the parties are governed by the terms of the contracts (which may be statutory in some cases) and the laws relating to contracts. It must be remembered that these contracts are entered into pursuant to public auction, floating of tenders or by negotiation. There is no compulsion on anyone to enter into these contracts. It is voluntary on both sides. There can be no question of the State power being involved in such contracts. It bears repetition to say that the State does no guarantee profit to the licencees in such contracts. There is no warranty against incurring losses. It is a businesses for the licencees. Whether they make profit or incur loss is no concern of the State. In law, it is entitled to its money under the Contract. It is not as if the
licencees are going to pay more to the State in case they make substantial profits. We reiterate that what we have said hereinabove is in the context of contracts entered into between the State and its citizens pursuant to public auction, floating of tenders or by negotiation. It is not necessary to say more than this for the purpose of these cases. What would be the position in the case of contracts entered into otherwise than by public auction, floating of tenders or negotiation, we need not express any opinion herein."
11. The decision in Issac Peter(supra) was re-stated with
approval and affirmed by the Supreme Court in S.K. Jain-vs.-
State of Haryana and Anr. reported as (2009) 4 SCC 357. These
decisions of the Supreme Court therefore affirm the view that in
case of contracts freely entered into with the State, there is no
room for invoking the doctrine of fairness and reasonableness
against one party to the contract (State), for the purpose of
altering or adding to the terms of the contracts, merely because
it happens to be the State. In such cases the mutual rights and
liabilities of the parties are governed by the terms of the
contracts and the law relating to contracts. It is seen that the
contract in the present case was entered into pursuant to
floating of tender and there was no compulsion on anyone to
enter into the contract. Therefore, there can be no question of
State power being involved in such a voluntary contract.
Therefore, there is no force in the submission made on behalf of
the Appellant that only public law principles would exclusively
apply to the relationship between the parties and that private
law principles flowing from the terms of the contract would
have no application to the subject contract. Even otherwise it is
noted that the cancellation of the licence had taken place after
issuance of a show cause notice and calling for the reply of the
Appellant.
12. The next question that needs to be considered is the
contention of the Respondent that the contract between the
parties was in its very nature determinable and consequently
could not be specifically enforced by way of the present
proceedings. In this behalf, it is observed that the Appellant did
not pay the agreed licence fee in terms of the licence
agreement. Consequently, after issuance of the show cause
notice and calling for a reply from the Appellant the Respondent
cancelled the licence under the terms of the agreement between
the parties. Therefore, the licence stood terminated, as correctly
observed by the learned Single Judge, in the impugned order,
and the legality or illegality of termination would be a matter to
be determined in arbitration. Further, the justification given by
the Appellant for not paying the licence fee will be examined in
the arbitral proceedings. The case of the Appellant that, owing
to the failure of the Respondent to perform obligations under
the agreement, and the latter‟s refusal to decrease the number
of LED screens in terms of clause 6 of the agreement, would
also be considered by the Arbitral Tribunal. In this behalf, we,
therefore, find considerable merit in the submission made on
behalf of the Respondent that if the cancellation of the contract
by the Respondent constitutes a breach of contract on their
part, the Appellant would be entitled to damages. In other
words, the questions whether the termination is wrongful or not
or whether the Respondent was not justified in terminating the
agreement, are yet to be decided. However, from the facts of
the case there is no manner of doubt that the contract was by its
very nature terminable, in terms of the contract between the
parties themselves.
13. In Rajasthan Breweries Ltd.(supra), a Division Bench of
this Court observed that, at the most, in case ultimately it is
found that termination is bad in law or contrary to the terms of
agreement or of any understanding between the parties or for
any other reason, the remedy of the Appellant was to seek
compensation for wrongful termination and not a claim for
specific performance of the agreement. Further, in this view of
the matter, there was every reason to come to the conclusion
that the relief sought by the Appellant in terms of an injunction
seeking to specifically enforce the agreement, by permitting the
Appellant to continue to operate the 9 LED screens installed
them, was statutorily prohibited with respect to a contract
which is determinable in nature.
14. Thus, the learned Single Judge correctly declined to grant
interim relief as sought for by the Appellant in view of Section
14(1)(c) read in conjunction with Section 41(e) of the Specific
Relief Act, 1963.
15. For the aforesaid reasons, we find no merit in the present
Appeal and the same is hereby dismissed, however, with no
order as to costs.
SIDDHARTH MRIDUL, J.
VIKRAMAJIT SEN, J.
February 11, 2011 mk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!