Citation : 2011 Latest Caselaw 1086 Del
Judgement Date : 23 February, 2011
R-6
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Date of Decision: 23.02.2011
% CS(OS) 1233A/2001
ENCON THERMAL ENGINEERS (P) LTD. ..... Petitioner
Through: Mr. Sandeep Srivastava with Mr.
Ujjwal K. Jha and Mr. Kanwaljit
Singh, Advocates.
versus
INDIAN RAILWAY CONSTRUCTION CO.LTD ..... Respondent
Through: Ms. Anusuya Salwan with Ms. Neha
Mittal, Advocates.
CORAM:
HON'BLE MR. JUSTICE VIPIN SANGHI
1. Whether the Reporters of local papers may
be allowed to see the judgment? :
2. To be referred to Reporter or not? :
3. Whether the judgment should be reported
in the Digest? :
VIPIN SANGHI, J. (Oral)
I.A. 11671/2001 & 2117/2003
1. These are objections preferred by the respondent under Sections
30 and 33 of the Arbitration Act, 1940 in respect of some of the claims
allowed by the learned Arbitrators, Shri A.K.Mittal and Shri M.P.Mongia.
2. The petitioner was awarded the work of fabrication of steel
structures at Rail Coach Factory, Kapurthala vide agreement dated
17.05.1986. Disputes arose between them and a joint meeting was
held for settlement of those disputes on 16.06.1998. In that meeting it
was concluded that a sum of Rs.27,17,657.22 was payable by the
respondent to the petitioner. However, recoveries had to be made
under the contract by the respondent from the petitioner, and after
accounting for those recoveries, the petitioner had to pay a sum of
Rs.1,85,098/- to the respondent. The respondent called upon the
petitioner to pay the said amount but since the petitioner did not make
the payment, the respondent encashed the petitioner's bank
guarantee and after recovery of a sum of Rs.1,85,098/- from the bank
guarantee proceeds, the remaining proceeds were returned to the
petitioner.
3. The petitioner then preferred Suit No.4506A/92 before this Court
under Section 20 of the Arbitration Act, 1940 to seek the appointment
of an Arbitrator. That suit was disposed of vide order dated
10.01.1997. The operative part of the order dated 10.01.1997 reads
as follows:-
"Having regard to the controversy raised by the parties, I am of the opinion that it would be necessary to appoint an Arbitrator for the adjudication of the questions as to whether the decisions taken in the meeting dated June 16, 1988 were implemented or not and in case they were not implemented, to what sum of money the petitioner will be entitled to receive from the respondents.
Accordingly, the respondents are directed to appoint an Arbitrator in terms of the arbitration clause within four
weeks. the petition stands disposed of."
4. Consequently, the joint Arbitrators were appointed who have
considered the various claims made before them and passed the
impugned award. The objections raised by the respondent relate to
the award made on Claim Nos. 8(ii), 8(v), 8(vii), 8(xii), 8(iv) only.
5. Claim no. 8(ii) was made by the petitioner to challenge the
recovery made by the respondent towards cost of paint supplied by the
respondent, amounting to ` 5,16,888/-. The submission of the
petitioner was that the respondent had issued a letter dated
23.01.1987 in which the respondent had stated that it would supply
zinc chromates yellow paint at the rate of ` 30.05 per lt. plus sales tax,
and synthetic enamel paint at the rate of ` 32.70 per lt. plus sales tax.
However, in the final bill raised by the respondent in March, 1989, the
rate charged by the respondent in certain cases was much higher. The
learned arbitrators held that the rate of paint to be charged from the
petitioner should be as committed by the respondent vide their letter
dated 23.01.1987. Consequently, the learned Arbitrators directed a
refund of Rs. 62,240/- from the recovered amount.
6. The submission of Ms. Salwan, learned counsel for the
respondent-objector is that the respondent's letter communicating the
rates of zinc chromates yellow paint at the rate of ` 30.05 per lt. and
that of synthetic enamel paint at the rate of ` 32.70 per lt., apart from
taxes, was issued in pursuance of the undertaking given by the
petitioner on 03.01.1987. The said undertaking was enclosed with the
letter dated 23.01.1987. However, the learned Arbitrators have
ignored the petitioner's own undertaking which was also placed on the
Arbitrator's record and which clearly stated that "we would request
you to kindly procure the same through your sources and the cost of
the paint may be recovered from our running bill to the extent paint is
used. The supply of paint may be made at our work site." She submits
that in the face of the said document, the award of the learned
Arbitrators, binding the respondent down to the rate communicated in
the communication dated 23.01.1987 was erroneous as the learned
Arbitrators have ignored the said undertaking and thereby
misconducted themselves.
7. On the other hand the submission of learned counsel for the
petitioner is that the learned Arbitrators have taken a plausible view by
placing reliance on the respondent's own letter dated 23.01.1987
wherein they stated that they were placing orders for supply of paint,
i.e. zinc chromate and synthetic enamel at the rates indicated in the
letter, and they were therefore bound by the said rates and could not
recover higher rates.
8. Having heard learned counsel for the parties and perused the
letter dated 23.01.1987 and its enclosure, namely, the undertaking
given by the petitioner dated 03.01.1987, I am of the view that the
learned Arbitrators have ignored the undertaking of the petitioner and
thereby misconducted themselves. A perusal of the said undertaking
would show that the petitioner had requested the respondent to
procure the paint on account of its non-availability for 40-45 days. The
obligation to procure the paint under the contract was primarily that of
the petitioner. It was on the petitioner's request that the respondent
had agreed to procure the paint. The conduct of the respondent in
procuring the paint was founded on the undertaking of the petitioner,
that the cost of the paint would be recovered from its running bills to
the extent paint is used. It is not the petitioner's case that the
recovery was effected at rates higher than that actually paid by the
respondent. From the arbitral record, it appears that the material
transfer challans in relation to the paint supplied by the respondent
were raised from time to time indicating the rate at which zinc
chromate and synthetic enamel paint had been procured. Had the
learned Arbitrators given due weight to the undertaking of the
petitioner dated 03.01.1987, they would not have come to the
conclusion that they did, namely, that the respondents should be
bound to make a recovery only at the rate indicated in their letter
dated 23.01.1987. For the aforesaid reasons, I set aside the award
made by the learned Arbitrators at Claim No.8(ii), as the learned
arbitrators misconducted themselves by ignoring material evidence on
record, viz. the petitioners own communication dated 03.01.1987.
9. The next challenge raised by the respondent is to the award
made in Claim 8(v). The petitioner-claimant had disputed the recovery
towards electricity charges of Rs.1,00,617/-. The learned Arbitrators
had taken note of the Minutes of the meeting held on 16.06.1988. In
the said Minutes, the stand of the respondent was recorded to the
effect that the electricity charges recovered were earlier based on pro
rata distribution of connected loads of various associates, and
thereafter on the basis of meter reading as per actual consumption,
and in cases where meters were defective, approximation on the basis
of basic consumption for the previous months. The petitioner had
made a request for inspection of the actual records for verifying the
amount sought to be recovered by the respondent, to which the
respondent had agreed. However, the respondent did not provide
scrutiny of its records as is evident from the respondent's letters dated
09.12.1988 and 13.12.1988. These letters had been taken note of by
the learned Arbitrators.
10. The learned Arbitrators have awarded an amount of Rs.92,693/-
to the petitioner-claimant under this claim on the basis that the scope
of the petitioner's work was reduced from 1500 MT of steel to 1082 MT
of steel. Consequently the tribunal has made a proportionate deduction
in the electricity charges which could be recovered from the petitioner.
11. Learned counsel for the respondent has not been able to make
out any ground to challenge the award made under Claim 8(v). To me
it appears that the learned Arbitrators have reasonably taken into
account the reduction in the scope of the petitioner's work and,
consequently, the pro rata charges recoverable from the petitioner
towards electricity had been reduced, as admittedly, the charges, till
the installation of separate electricity meters were being recovered on
pro rata basis from different contractors.
12. The next challenge raised by the respondent is to the award
made on claim No.8(vii). This claim had been made for refund of
recovery made towards other miscellaneous advances of Rs.3,35,711/-.
13. Here again I find absolutely no merit in the objection raised by
the respondent. A perusal of the award on this claim shows that the
learned Arbitrators have proceeded on the basis of the minutes of the
meeting held on 18.06.1988 and on the basis that for recoveries
towards payment of staff and watchman amounting to Rs.14,500/- and
miscellaneous recoveries amounting to Rs.6,152/- (aggregating to Rs.
20,652/- ), the respondent had not been able to substantiate the same.
Pertinently, in the meeting held on 18.06.1988, the respondent had
agreed to withdraw the recoveries as per para 10 and 13 of the
Minutes of that meeting. The award made by the learned Arbitrators
to grant credit to the petitioner for Rs.2,00,408/-, therefore, does not
call for any interference.
14. The next challenge by the respondent is to the award made on
claim 8(xii). In this regard, the challenge is restricted to the award of
Rs.1,60,165/- awarded to the petitioner-claimant. Under the contract
it was the duty of the petitioner-claimant to arrange the steel.
However, as they were not able to arrange the same on their own,
steel was supplied by the respondent and recovery therefor was made
from the petitioner. 1939.973 MT steel was supplied by the
respondent to the petitioner. Out of this, the petitioner transferred
617.512 MT of steel to other contractors of the respondent. The steel
as supplied to the petitioner was on weighment basis, whereas that
supplied by the petitioner to the other contractors was on
measurement basis. The learned Arbitrators took note of IS 1852-
1985 which lays down the tolerance limits for steel. The reasoning in
the award made by the learned Arbitrators, while awarding the
amount of Rs.1,60,165/- reads as follows:-
"(d) The arbitrators are of the view that keeping the above fact in view, on the quantity of 617.512 M.T transferred by the Claimants to the other vendors of the Respondents, they are entitled to claim tolerance variation in weight as per IS 1852- 1985 which are as under:-
S.No. Section Tolerance
(i) Beams, column & channels (+)2.5% to (-)2.5%
(ii) Angles (+)5% to (-)5%
(iii) Plates (+)5% to (-)2.5%
(iv) Bar (+)3% to (-)3%
(e) Normally, it was found that the tolerances in the steel are always on the (+) side. The arbitrators, therefore, are of the view that tolerances on the (+) side should be taken for working out the claim of the Claimants on the quantity of steel of 617.512 M.T transferred to the other vendors of IRCON. The item wise break up of the steel transferred is summarized as under:-
Item Quantity Tolerance Variance
transferred in Variation admissible
M.T in M.T
Angles 244.946 5% 12.25 M.T.
Plates 174.333 5% 8.72 M.T.
Round Bar 39.333 3% 1.18 M.T.
ISMC 74.761 2.5% 1.87 M.T.
Rails 84.139 - -
Total 617.512 24.02
As per final bill the average value per tonne of the steel supplied by the defendants to the Claimants works out to Rs. 6668/- (85,94,000÷1288.756 M.T.). Thus value of the steel due to tolerance variation on the quantity of steel transferred to the other vendors of the defendants works out to Rs.1,60,165/-. The arbitrators are of the view that credit for Rs.1,60,165/- is admissible to the Claimants on this account."
15. The submission of learned counsel for the respondent is that the
award made by the learned Arbitrators is based on pure conjecture and
is devoid of any evidence. She further submits that even if IS
standards, as aforesaid, were applicable, it did not mean that in the
application of those standards in relation to supplies effected by the
petitioner to other contractors, it could be assumed that there were
excess supplies i.e. tolerances were always on the plus side and that
too to the maximum limit. On the other hand, the submission of
learned counsel for the petitioner is that the view taken by the learned
Arbitrators is a plausible view and therefore, it should not be interfered
with by this Court as there is no misconduct by the Arbitrator.
16. In the light of the aforesaid submissions, the question which
arises for consideration is whether the view taken by the learned
Arbitrators could be taken as a plausible view. No doubt, the learned
Arbitrator could have adopted IS 1852-1985 which lays down the
tolerance limits for different kinds of steel. However, the issue is not
with regard to adoption of the said standards but with regard to their
application. The manner in which the said standard has been adopted
would mean that in every case of supply of steel by the petitioner to
the other contractors on measurement basis, there was excess
quantity supplied to the maximum limit. In my view, such an
assessment is not only not plausible but attaches to it the highest
degree of improbability. The learned Arbitrators have not proceeded
on the basis of any evidence, contemporaneous or otherwise, while
making the aforesaid award of Rs.1,60,165/-. Just as the tolerance
could be on the plus side, it could also be on the negative side in case
of some of the supplies. Without any material and evidence, in my
view, the learned Arbitrators could not have proceeded on the basis of
conjecture as they have done. By doing so, they have certainly
misconducted themselves. Accordingly the award made at Claim
No.8(xii), in so far as the amount of Rs.1,60,165/- has been awarded, is
set aside.
17. It is lastly submitted by Ms. Salwan that the award made under
Claim No.8(xiv) is erroneous and contrary to the record. She submits
that the learned Arbitrators have held that the respondent was entitled
to claim interest at the rate of 10% per annum on the interest bearing
advance of Rs.3,00,000/- upto the date of meeting held on 16.06.1988,
yet the entire recovery of Rs.50,434/- has been set aside on the ground
that the computation of Rs.50,434/- provided by the respondent had
been made for the period upto 31.05.1990.
18. I have heard the submissions of both the parties on this
computation, and it is agreed by both the parties that the award made
on Claim No.8 (xiv) be clarified in the following manner:-
19. The computation filed by the respondent before the learned
Arbitrator giving the detail of interest on interest bearing advance
shows that interest has been computed on the amount of Rs.3,00,000/-
upto 31.03.1988 amounting to Rs. 34,027/-. In relation to this
computation, there is no dispute between the parties. From
01.04.1988 onwards, interest has been computed on the amount of
Rs.1,44,923/- after taking into account various recoveries to be
effected from the petitioner, and credits to be given to the petitioner. I
may note that there is no dispute even with regard to the amount of
Rs.144,923/- on which further interest is to be calculated. In terms of
the award, interest from 01.04.1988 t0 16.06.1988 (the date on which
the meeting was held between the parties) shall be calculated on the
amount of Rs.1,44,923/- at the rate of 10% per annum. The amount
already recovered is Rs.15,000/-. Accordingly the petitioner will be
entitled to the following amount:-
Rs.50,434 (-) Rs.19,027 (-) the amount computed as interest on the amount of Rs.1,44923/- at the rate of
10%per annum from 0.1.04.1998 to 16.06.1988.
To the aforesaid extent, the award made at Claim No.8(xiv)
stands modified.
20. Learned counsel for the petitioner submits that the learned
Arbitrators have not awarded any interest in their award. The
petitioner has filed I.A. No.2117/2003 to seek a direction to the
respondent to pay pre-reference pendente lite and post award interest
till final payment at the rate of 24% per annum.
21. I may note that before the Arbitrators the petitioner had made a
claim for interest. That claim had been disallowed by observing that
the aspect of interest had been referred to the Arbitrators. The
petitioner did challenge the said aspect of the award by filing
objections. This application has been moved much belatedly. The
power to grant pre-reference, pendente lite, and post award interest
upto the date when the court makes the same a Rule of the Court and
passes a decree in terms therefore lies with the arbitrator. The
Arbitrators have specifically declined the claim of the petitioner for
grant of interest. The petitioner has neither challenged the award nor
taken other proceedings to make a claim for interest. In my view this
application has no merit and is accordingly dismissed.
22. Considering the nature of disputes in the award, I direct that the
petitioner shall also be entitled to interest from the date of decree till
the date of realization at the rate of 10% per annum. The award
stands modified in the aforesaid terms and, to the extent it is not set
aside, is made a Rule of the Court. A decree is passed in terms
thereof.
VIPIN SANGHI, J FEBRUARY 23, 2011 as
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!