Citation : 2011 Latest Caselaw 5981 Del
Judgement Date : 8 December, 2011
THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment Pronounced on: 08.12.2011
+ CS(OS) No. 2215/2007
M/S SUBROS LIMITED ..... Plaintiff
Through: Mr. R.C. Beri with Mr. S.K. Beri,
Advs.
versus
M/S GLASNOST HYDRAULIC EQUIPMENTS(INDIA) PVT.
LTD. ..... Defendant
Through: None
CORAM:-
HON'BLE MR JUSTICE V.K. JAIN
V.K. JAIN, J. (ORAL)
1. This is a suit for recovery of Rs.23,43,000/-.
2. The case of the plaintiff is that the plaintiff
company placed a purchase order on the defendant
company for purchase of 7 machines, detailed in Purchase
Order dated 12.12.2002, at a total basic cost of
Rs.65,90,625/- and subject to the terms and conditions
mentioned in the Purchase Order.
The Purchase Order was amended vide letter dated
16.12.2002, thereby changing the delivery date from
25.3.2003 to 30.3.2003. The order in respect of two
equipments, Manual Core Assy. Machine and Wire Winding
Machine was cancelled. The basic value of the order was
thus reduced to Rs.46,55,000/-. The plaintiff made
payment of Rs.18,62,000/- to the defendant being 40% of
the basic value of the order as was agreed between the
parties. The defendant agreed to deliver the machines latest
by 07.7.2003. Later, the dispatch date in respect of
Caulking Machines was changed by the defendant to
30.7.2003. This, however, was not acceptable to the
plaintiff, which insisted on dispatch of the machines by
07.7.2003. Since, there was delay in dispatch of machines,
in a meeting held on 31.7.2003, it was agreed that all the 5
machines will be dispatch on or before 30.9.2003 and they
were likely to be ready for inspection by 20.9.2003. On
confirmation of final date of inspection by the defendant, the
plaintiff was to depute its representative for inspection and
trial of the machines and thereafter, they were to be packed
in the presence of representative of M/s Subros
Ltd./plaintiff and payment was to be delivered to the
defendant after loading of machines in the truck and
creation of excise documents. In case of delay in dispatch
beyond 30.9.2003, a penalty @ 1% per week was to be
imposed on the defendant.
3. The defendant, however, failed to adhere even to
the revised delivery schedule and thereby became liable for
payment of penalty at a stipulated rate @ 1% of the basic
value of the order per week. Since, the defendant failed to
adhere even to the revised delivery schedule, the plaintiff
after awaiting for one month, served a legal notice dated
01.11.2003 on the defendant informing that it had been
forced to make alternative arrangements for procuring the
machines from another source and their Purchase Order
dated 12.12.2002 as modified on 25.4.2003 stood cancelled.
The defendant was required to refund the advance of
Rs.18,62,000/- along with the penalty @ 1% of the basic
value of the order per week as well as the interest @ 18%
per annum. Since, the defendant failed to pay the aforesaid
amount, the plaintiff is now claiming the advance of
Rs.18,62,000/- along with the interest on that amount @
10% per annum, amounting to Rs.4,81,000/-.
4. The defendant was proceeded ex-parte vide order
dated 08.8.2011. The plaintiff has filed affidavit of Mr.
Virender Kumar by way of ex-parte evidence. In his
affidavit, Mr. Virender Kumar has supported on oath the
case set-out in the plaint.
5. 'Ex.PW1/2' is the quotation, which the defendant
had submitted to the plaintiff company for supply of
machines, whereas, 'Ex.PW1/3' is the Purchase Order dated
12.12.2002. 'Ex.PW1/5' is the revised Purchase Order
dated 25.4.2003 issued by the plaintiff to the defendant.
6. A perusal of the initial Purchase Order dated
12.12.2002 would show that timely delivery of the machines
was made essence of the order, failing which, the plaintiff
reserved the right to withdraw the order and, in that case,
the defendant was to refund the entire advance paid to it
against the order. The term making the timely delivery
essence of the contract was not modified at the time revised
purchase order was issued on 25.4.2003.
7. A perusal of the E-mail dated 08.5.2003 sent by
the defendant to the plaintiff would show that the delivery
period was two months from the date of receipt of advance,
i.e. 07.5.2003. The defendant, thus, was required to deliver
the machined to the plaintiff latest by 07.7.2003.
'Ex.PW1/8' is an E-mail sent by the plaintiff to the
defendant, whereby it declined to change of dispatch date
from 07.7.2003to 30.7.2003 and maintained that the
delivery period will be two months from 07.5.2003.
'Ex.PW1/10', are the Minutes of Meeting held on 31.7.2003
in the office of the defendant company. A perusal of the
Minutes would show that it was agreed between the parties
that all the 5 machines would be dispatched by the
defendant on or before 30.9.2003. They also agreed that the
machines were likely to be ready for inspection by
20.9.2003. The final date of inspection was to be confirmed
by the defendant, whereupon the plaintiff was to depute its
official representative for inspection and trial of the
machines. After trials and final clearance, the machines
were to be packed in the presence of the representative of
the plaintiff company and the payment, as per the purchase
order was to be handed over to the defendant on the
machines being loaded on the truck and creation of the
excise documents.
8. It has come in the affidavit of Mr. Virender Kumar
that the defendant had failed to adhere even to the revised
delivery schedule and did not supply the machinery within
time, agreed in the Meeting held on 31.7.2003.
9. 'Ex.PW1/11' is the notice sent by the plaintiff to
the defendant informing it that since it had failed to adhere
even to the revised delivery schedule, the purchase order be
cancelled. The defendant was also called upon to refund
the advance of Rs.18,62,000/- along with penalty @ 1% of
the basic value of the order per week and interest @ 18%
per annum.
10. The testimony of Mr. Virender Kumar coupled with
the documents filed by the plaintiff company would show
that though time was made essence of the contract between
the parties and the defendant was required to deliver all the
machines latest by 30.9.2003, in terms of the decision
taken in the meeting held on 31.7.2003, the defendant
failed to adhere to this revised schedule as well. Hence, in
terms of the Purchase Order dated 12.12.2002 as well as
the revised Purchase Order dated 25.4.2003, the plaintiff
was entitled to cancel the purchase order and thereupon the
defendant was required to refund the entire advance
payment received by it from the plaintiff.
Since the purchase order has been cancelled on
failure of the defendant to adhere to the schedule agreed
between the parties for delivery of machines, the defendant
is required to refund the advance of Rs.18,62,000/-, which
it had received from the plaintiff.
11. As regards interest, admittedly, there is no
agreement between the parties for payment of interest by
the defendant on the advance which it received from the
plaintiff. No custom or usage of trade for payment of
interest has been proved by the plaintiff. Section-3 of the
Interest Act, 1978 to the extent it is relevant provides that in
any proceedings for the recovery of any debt or damages or
in any proceedings in which a claim for interest in respect of
any debt or damages already paid is made, the Court may, if
it thinks fit, allow interest to the person entitled to the debt
or damages or to the person making such claim, as the case
may be, at a rate not exceeding the current rate of interest.
It further provides that if the proceedings relate to a debt
payable otherwise than by virtue of a written instrument at
a certain time, then, interest can be granted from the date
mentioned in this regard in a written notice given by the
person entitled or the person making the claim to the
person liable that interest will be claimed, to the date of
institution of the proceedings. Since the plaintiff gave
notice envisaged in Section 3 of the Interest Act, 1978
claiming interest from the defendant, it is entitled to interest
in terms of the aforesaid provision.
In the facts and circumstances of the case and
considering the nature of the transaction between the
parties, I am of the view that the plaintiff is entitled to
interest @ 10% per annum w.e.f. 30.4.2003 to 30.11.2005,
which comes to Rs.4,81,000/-. The plaintiff, thus, is
entitled to recover a total sum of Rs.23,43,000/-.
12. In view of the above discussions, a decree for
recovery of Rs.23,43,000/- with pendentilite and future
interest @ 10% per annum is hereby passed in favour if the
plaintiff and against the defendant.
Decree sheet be drawn accordingly.
(V.K. JAIN) JUDGE DECEMBER 08, 2011 KA
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!