Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Rural Electrification ... vs M/S Capital Building & Furnishing ...
2011 Latest Caselaw 5953 Del

Citation : 2011 Latest Caselaw 5953 Del
Judgement Date : 7 December, 2011

Delhi High Court
Rural Electrification ... vs M/S Capital Building & Furnishing ... on 7 December, 2011
Author: S. Muralidhar
       IN THE HIGH COURT OF DELHI AT NEW DELHI

                                  O.M.P. 467/2010

                                             Reserved on: November 21, 2011
                                             Decision on: December 7, 2011

       RURAL ELECTRIFICATION CORPORATION LTD.
                                                ..... Petitioner
                    Through: Mr. R.K. Joshi with
                             Mr. Jyotindra Kumar, Advocates.

                         versus

       M/S CAPITAL BUILDING & FURNISHING CO. ..... Respondent
                     Through: Mr. Abhijat with
                              Ms. Princy Ponnan, Advocates.

       CORAM: JUSTICE S. MURALIDHAR

                                   JUDGMENT

7.12.2011

1. Rural Electrification Corporation Ltd. challenges an Award dated 12th

April 2010 passed by the Arbitral Tribunal allowing Claim Nos. 1, 2, 3 and

4 of the Respondent Capital Building and Furnishing Co., together with

interest and costs while rejecting the counter-claims of the Petitioner.

2. In May 1994, the Petitioner invited tenders for interior and allied works

at its registered office building comprising four floors. The tender was an

item rate tender and work was to be completed in four months. On 15th

July 1994 the Petitioner split the tender into two packages. The first

package comprised of second and third floors and the second package

comprised of ground, first and fourth floors. This was on the premise that a

single contractor might not be able to complete the entire work within four

months.

3. The tender of the Respondent for the first package was accepted by the

Petitioner. The Respondent gave a rebate of 3.01% on the amount quoted

by it. The value of the contract, after discount, was approximately Rs.

89,34,593/-.

4. On 19th January 1995 the Petitioner issued a work order amounting to

Rs. 89,34,109/-. The site was also handed over on that date along with a

set of 85 drawings. According to the Petitioner, the Respondent did not

agree to the inclusion of the term concerning escalation as proposed by the

Respondent based on Clause 10CC of the CPWD Standard Terms and

Conditions. The Petitioner on 25th January 1995 informed the Respondent

that M/s. Dutt Designs had been appointed as Architects and Consultant

for the works.

5. A formal contract was entered into between the parties on 13th March

1995. Under Clause 23.0 it was provided that the contractor, i.e., the

Respondent shall from time to time be entitled to receive payment on the

basis of the actual work executed, approved and certified by the Architect

subject to the deductions mentioned in the said clause. From every

intermediate bill a sum of ten percent (10%) of the value of the work done

subject to the maximum amount of retention as stipulated in the Appendix,

shall be retained until the expiry of the defects liability period. No interest

was to be due to the contractor for the sums retained by the Petitioner. All

intermediate payments were regarded as payments by way of advance

against final payment only and not as payment for the work actually done

and completed. The final bill was to be submitted by the Respondent

within two months of the date of virtual completion of work failing which

the measurements of work taken by the Architect after due notice would be

considered as final and binding on all parties unless objected to within one

month of their being recorded in the measurement books. Under Clause

28.0 there were to be deductions for incorrect work. For the contract price,

the decision of the Petitioner/Architect in that respect was to be final.

Clause 40.0 dealt with the status of the Architect. The Architect was in

consultation and approval with the Petitioner to make decisions on all

claims of the Respondent and "...on all other matters relating to the

execution and progress of the work or the interpretation of the Contract

Documents." Further, "the decision, opinion, direction of the

Owner/Architect, with respect to all or any of the matters mentioned in

Clauses (a) to (l) of Clause 40.0 was to be binding."

6. According to the Petitioner, the Respondent delayed the execution of the

work and deviated from various terms of the contract, using sub-standard

material and failed to employ efficient manpower in sufficient numbers for

timely completion of the work. It is submitted that the Respondent

virtually suspended the work in October 1995 and adopted pressurizing

tactics to force the Petitioner to agree with the terms favourable to it as

condition precedent to resumption and completion of work. The last

extension of time was made on 15th May 1996. The Respondent ultimately

handed over possession of the premises to the Petitioner on 16th July 1996

without completing the works.

7. The Petitioner states that it received a total of eleven bills from the

Respondent including the one final bill. It paid the Respondent a sum of

Rs.79,04,596/- against the ten running bills after deducting Rs. 1,81,806/-

towards tax deducted at source ('TDS') and a sum of Rs. 4 lakhs towards

the security deposit. The Respondent was paid the balance amount of Rs.

73,22,790/- in stages.

8. The premises were inspected by the interior supervising committee of

the Petitioner and also by the Chief Technical Examiner ('CTE') of the

Central Vigilance Commission ('CVC'). The defects noted by the

aforementioned authorities were communicated to the Respondent with

request to remove the same. According to the Petitioner, the Respondent

failed to do so.

9. The Respondent submitted a final bill for Rs. 1,03,91,802/- on 4th

December 1996 which was increased to Rs. 1,04,58,118/-. The Respondent

claimed a sum of Rs. 20,78,360/- towards escalation and for refund of

security deposit that was deducted by the Petitioner. As against the final

bill submitted by the Respondent, the Architect certified and recommended

payment of Rs. 6,41,000/- whereas the interior committee of the Petitioner

found that no amount was due and payable. On the other hand, the

Petitioner found that a sum of Rs. 4,76,337/- was recoverable from the

Respondent after making various deductions and imposing liquidity

damages ('LD') on account of delay in completion of the works.

10. The Respondent invoked the arbitration clause and the disputes were

referred to the Arbitral Tribunal which passed the impugned Award on 12th

April 2010.

11. This Court has heard Mr. R.K. Joshi, learned counsel for the Petitioner

and Mr. Abhijat, learned counsel for the Respondent.

12. Claim No. 1 by the Respondent arose from the final bill submitted by it

to the Petitioner and was made under four different heads - (A), (B), (C)

and (D). Before the Arbitral Tribunal, the Respondent gave up Claim 1

(D). Claim 1 (A) was for a sum of Rs. 17,20,923/-. As regards this claim,

the Arbitral Tribunal found that the Architect had scrutinized the final bill

submitted by the Petitioner on 9th April 1997 and certified payment for a

sum of Rs. 6,41,000/-. The Tribunal observed that the Petitioner had not

been able to show how the amount certified by the Architect is not payable

and consequently allowed the claim to the extent of Rs. 6,41,000/-.

13. It was contended by the learned counsel for the Petitioner that the

Arbitral Tribunal ought to have gone by the certificate of the Petitioner and

not of the Architect. Clause 40.0 of the contract does state that the opinion

of the Architect in respect of several items would be final. Consequently,

this decision of the Tribunal as regards Claim No. 1(A) does not call for

interference.

14. Claim No. 1(B) concerned the amounts deducted from the final bill by

the Petitioner. The Petitioner herein sought to justify the deduction of Rs.

3,73,382/- on the ground that the materials used by the Respondent in

respect of certain items was of low quality. In fact, the Petitioner deducted

a sum more than what the Architect had certified. This, the Arbitral

Tribunal found to be unjustified and allowed the claim to the extent of Rs.

42,640/-. The deduction towards electricity and telephone charges in the

sum of Rs. 1,71,430/- was also found to be unjustified. Against the said

deduction, the deduction of Rs. 1,71,000/- was found to be unjustified.

Since the Respondent claimed only a sum of Rs. 1,66,144/-, the Tribunal

awarded that sum to the Respondent. The deduction towards water charges

in the sum of Rs. 7,285/- and a further sum of Rs. 28,284/- deducted on

account of the Respondent having used rubber wood instead of cedar wood

was also held to be unjustified. The deductions of Rs. 25,000/- and Rs.

11,628/- for items of block board and granite cladding were held to be

unsustainable in the absence of any supporting evidence or the certificate

of the Architect. The deduction of Rs. 1,25,000/- on the basis of the report

of the CVC was also held to be unjustified since the Petitioner did not

prove the same by producing evidence. Consequently, against Claim No. 1

(B), the Tribunal awarded the Respondent a sum of Rs. 3,97,886/- which it

held to have been arbitrarily deducted from the final bill by the Petitioner.

Claim No. (1)(C) was in respect of extra items. Again, the Arbitral

Tribunal appears to have gone by the certificate of the Architect who had

approved an amount of Rs. 3,05,491/-. Consequently, against Claim No. 1,

the Tribunal held that the Respondent was entitled to receive Rs.

13,57,277/-. The findings of the Arbitral Tribunal are factual, based on the

evidence before it. Counsel for the Petitioner has not been able to persuade

this Court to hold that the above conclusion of the Arbitral Tribunal is

patently illegal, contrary to any provision of law or of any clause of the

contract.

15. It was submitted by the learned counsel for the Petitioner that in terms

of Clause 23.1 of the General Conditions of the Contract, the payment in

relation to the final bill had to be on the basis of the actual work executed,

proved and certified by the Architect. This Court finds that the said clause

has in fact been correctly applied by the Tribunal. Consequently, the award

of interest at Rs. 58,000/- under Claim No. (3) by the Tribunal in favour of

the Respondent also does not call for interference.

16. Claim No. (4) was in respect of delayed payment of the final bill. The

Respondent had confined the claim to Rs. 24,92,836/-. The Tribunal found

factually that the final bill was not paid within a reasonable time. The

Tribunal nevertheless allowed interest on Rs. 13,57,277/- and not Rs.

24,92,836/- as claimed by the Respondent. Interest was also awarded at

the rate of 12% per annum from 22nd November 1997 till 3rd June 2002.

The other item was interest on security deposit (Claim No. 5). The claim of

the Respondent for escalation (Claim No. 6) was rejected. The

Respondent's claim for compensation for the delay was also not accepted.

The Petitioner's counter-claim in the sum of Rs. 20,26,276/- was rejected.

Learned counsel for the Petitioner was unable to persuade this Court to

reappreciate the evidence and come to a conclusion contrary to what was

reached by the Arbitral Tribunal in respect of the aforementioned claims

and counter-claim.

17. There is no merit in this petition and it is dismissed as such with costs

of Rs. 10,000/- which will be paid by the Petitioner to the Respondent

within four weeks.

S. MURALIDHAR, J DECEMBER 7, 2011 akg

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter