Citation : 2011 Latest Caselaw 5953 Del
Judgement Date : 7 December, 2011
IN THE HIGH COURT OF DELHI AT NEW DELHI
O.M.P. 467/2010
Reserved on: November 21, 2011
Decision on: December 7, 2011
RURAL ELECTRIFICATION CORPORATION LTD.
..... Petitioner
Through: Mr. R.K. Joshi with
Mr. Jyotindra Kumar, Advocates.
versus
M/S CAPITAL BUILDING & FURNISHING CO. ..... Respondent
Through: Mr. Abhijat with
Ms. Princy Ponnan, Advocates.
CORAM: JUSTICE S. MURALIDHAR
JUDGMENT
7.12.2011
1. Rural Electrification Corporation Ltd. challenges an Award dated 12th
April 2010 passed by the Arbitral Tribunal allowing Claim Nos. 1, 2, 3 and
4 of the Respondent Capital Building and Furnishing Co., together with
interest and costs while rejecting the counter-claims of the Petitioner.
2. In May 1994, the Petitioner invited tenders for interior and allied works
at its registered office building comprising four floors. The tender was an
item rate tender and work was to be completed in four months. On 15th
July 1994 the Petitioner split the tender into two packages. The first
package comprised of second and third floors and the second package
comprised of ground, first and fourth floors. This was on the premise that a
single contractor might not be able to complete the entire work within four
months.
3. The tender of the Respondent for the first package was accepted by the
Petitioner. The Respondent gave a rebate of 3.01% on the amount quoted
by it. The value of the contract, after discount, was approximately Rs.
89,34,593/-.
4. On 19th January 1995 the Petitioner issued a work order amounting to
Rs. 89,34,109/-. The site was also handed over on that date along with a
set of 85 drawings. According to the Petitioner, the Respondent did not
agree to the inclusion of the term concerning escalation as proposed by the
Respondent based on Clause 10CC of the CPWD Standard Terms and
Conditions. The Petitioner on 25th January 1995 informed the Respondent
that M/s. Dutt Designs had been appointed as Architects and Consultant
for the works.
5. A formal contract was entered into between the parties on 13th March
1995. Under Clause 23.0 it was provided that the contractor, i.e., the
Respondent shall from time to time be entitled to receive payment on the
basis of the actual work executed, approved and certified by the Architect
subject to the deductions mentioned in the said clause. From every
intermediate bill a sum of ten percent (10%) of the value of the work done
subject to the maximum amount of retention as stipulated in the Appendix,
shall be retained until the expiry of the defects liability period. No interest
was to be due to the contractor for the sums retained by the Petitioner. All
intermediate payments were regarded as payments by way of advance
against final payment only and not as payment for the work actually done
and completed. The final bill was to be submitted by the Respondent
within two months of the date of virtual completion of work failing which
the measurements of work taken by the Architect after due notice would be
considered as final and binding on all parties unless objected to within one
month of their being recorded in the measurement books. Under Clause
28.0 there were to be deductions for incorrect work. For the contract price,
the decision of the Petitioner/Architect in that respect was to be final.
Clause 40.0 dealt with the status of the Architect. The Architect was in
consultation and approval with the Petitioner to make decisions on all
claims of the Respondent and "...on all other matters relating to the
execution and progress of the work or the interpretation of the Contract
Documents." Further, "the decision, opinion, direction of the
Owner/Architect, with respect to all or any of the matters mentioned in
Clauses (a) to (l) of Clause 40.0 was to be binding."
6. According to the Petitioner, the Respondent delayed the execution of the
work and deviated from various terms of the contract, using sub-standard
material and failed to employ efficient manpower in sufficient numbers for
timely completion of the work. It is submitted that the Respondent
virtually suspended the work in October 1995 and adopted pressurizing
tactics to force the Petitioner to agree with the terms favourable to it as
condition precedent to resumption and completion of work. The last
extension of time was made on 15th May 1996. The Respondent ultimately
handed over possession of the premises to the Petitioner on 16th July 1996
without completing the works.
7. The Petitioner states that it received a total of eleven bills from the
Respondent including the one final bill. It paid the Respondent a sum of
Rs.79,04,596/- against the ten running bills after deducting Rs. 1,81,806/-
towards tax deducted at source ('TDS') and a sum of Rs. 4 lakhs towards
the security deposit. The Respondent was paid the balance amount of Rs.
73,22,790/- in stages.
8. The premises were inspected by the interior supervising committee of
the Petitioner and also by the Chief Technical Examiner ('CTE') of the
Central Vigilance Commission ('CVC'). The defects noted by the
aforementioned authorities were communicated to the Respondent with
request to remove the same. According to the Petitioner, the Respondent
failed to do so.
9. The Respondent submitted a final bill for Rs. 1,03,91,802/- on 4th
December 1996 which was increased to Rs. 1,04,58,118/-. The Respondent
claimed a sum of Rs. 20,78,360/- towards escalation and for refund of
security deposit that was deducted by the Petitioner. As against the final
bill submitted by the Respondent, the Architect certified and recommended
payment of Rs. 6,41,000/- whereas the interior committee of the Petitioner
found that no amount was due and payable. On the other hand, the
Petitioner found that a sum of Rs. 4,76,337/- was recoverable from the
Respondent after making various deductions and imposing liquidity
damages ('LD') on account of delay in completion of the works.
10. The Respondent invoked the arbitration clause and the disputes were
referred to the Arbitral Tribunal which passed the impugned Award on 12th
April 2010.
11. This Court has heard Mr. R.K. Joshi, learned counsel for the Petitioner
and Mr. Abhijat, learned counsel for the Respondent.
12. Claim No. 1 by the Respondent arose from the final bill submitted by it
to the Petitioner and was made under four different heads - (A), (B), (C)
and (D). Before the Arbitral Tribunal, the Respondent gave up Claim 1
(D). Claim 1 (A) was for a sum of Rs. 17,20,923/-. As regards this claim,
the Arbitral Tribunal found that the Architect had scrutinized the final bill
submitted by the Petitioner on 9th April 1997 and certified payment for a
sum of Rs. 6,41,000/-. The Tribunal observed that the Petitioner had not
been able to show how the amount certified by the Architect is not payable
and consequently allowed the claim to the extent of Rs. 6,41,000/-.
13. It was contended by the learned counsel for the Petitioner that the
Arbitral Tribunal ought to have gone by the certificate of the Petitioner and
not of the Architect. Clause 40.0 of the contract does state that the opinion
of the Architect in respect of several items would be final. Consequently,
this decision of the Tribunal as regards Claim No. 1(A) does not call for
interference.
14. Claim No. 1(B) concerned the amounts deducted from the final bill by
the Petitioner. The Petitioner herein sought to justify the deduction of Rs.
3,73,382/- on the ground that the materials used by the Respondent in
respect of certain items was of low quality. In fact, the Petitioner deducted
a sum more than what the Architect had certified. This, the Arbitral
Tribunal found to be unjustified and allowed the claim to the extent of Rs.
42,640/-. The deduction towards electricity and telephone charges in the
sum of Rs. 1,71,430/- was also found to be unjustified. Against the said
deduction, the deduction of Rs. 1,71,000/- was found to be unjustified.
Since the Respondent claimed only a sum of Rs. 1,66,144/-, the Tribunal
awarded that sum to the Respondent. The deduction towards water charges
in the sum of Rs. 7,285/- and a further sum of Rs. 28,284/- deducted on
account of the Respondent having used rubber wood instead of cedar wood
was also held to be unjustified. The deductions of Rs. 25,000/- and Rs.
11,628/- for items of block board and granite cladding were held to be
unsustainable in the absence of any supporting evidence or the certificate
of the Architect. The deduction of Rs. 1,25,000/- on the basis of the report
of the CVC was also held to be unjustified since the Petitioner did not
prove the same by producing evidence. Consequently, against Claim No. 1
(B), the Tribunal awarded the Respondent a sum of Rs. 3,97,886/- which it
held to have been arbitrarily deducted from the final bill by the Petitioner.
Claim No. (1)(C) was in respect of extra items. Again, the Arbitral
Tribunal appears to have gone by the certificate of the Architect who had
approved an amount of Rs. 3,05,491/-. Consequently, against Claim No. 1,
the Tribunal held that the Respondent was entitled to receive Rs.
13,57,277/-. The findings of the Arbitral Tribunal are factual, based on the
evidence before it. Counsel for the Petitioner has not been able to persuade
this Court to hold that the above conclusion of the Arbitral Tribunal is
patently illegal, contrary to any provision of law or of any clause of the
contract.
15. It was submitted by the learned counsel for the Petitioner that in terms
of Clause 23.1 of the General Conditions of the Contract, the payment in
relation to the final bill had to be on the basis of the actual work executed,
proved and certified by the Architect. This Court finds that the said clause
has in fact been correctly applied by the Tribunal. Consequently, the award
of interest at Rs. 58,000/- under Claim No. (3) by the Tribunal in favour of
the Respondent also does not call for interference.
16. Claim No. (4) was in respect of delayed payment of the final bill. The
Respondent had confined the claim to Rs. 24,92,836/-. The Tribunal found
factually that the final bill was not paid within a reasonable time. The
Tribunal nevertheless allowed interest on Rs. 13,57,277/- and not Rs.
24,92,836/- as claimed by the Respondent. Interest was also awarded at
the rate of 12% per annum from 22nd November 1997 till 3rd June 2002.
The other item was interest on security deposit (Claim No. 5). The claim of
the Respondent for escalation (Claim No. 6) was rejected. The
Respondent's claim for compensation for the delay was also not accepted.
The Petitioner's counter-claim in the sum of Rs. 20,26,276/- was rejected.
Learned counsel for the Petitioner was unable to persuade this Court to
reappreciate the evidence and come to a conclusion contrary to what was
reached by the Arbitral Tribunal in respect of the aforementioned claims
and counter-claim.
17. There is no merit in this petition and it is dismissed as such with costs
of Rs. 10,000/- which will be paid by the Petitioner to the Respondent
within four weeks.
S. MURALIDHAR, J DECEMBER 7, 2011 akg
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!