Citation : 2011 Latest Caselaw 3790 Del
Judgement Date : 8 August, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment reserved on: 25.07.2011
% Judgment delivered on: 08.08.2011
+ O.M.P. 108/2008 & I.A. No. 11533/2011
M S T C LIMITED ..... Petitioner
Through: Ms. Sonia Arora, Advocate.
versus
M/S JAIN TRADERS & ORS ..... Respondents
Through: Mr. Pradeep Misra & Mr. Daleep
Kumar Dhayani, Advocates for the
respondent No. 2.
AND
+ O.M.P. 363/2008
U.P. RAJYA VIDYUT UTPADAN NIGAM LTD. ..... Petitioner
Through: Mr. Pradeep Misra & Mr. Daleep
Kumar Dhayani, Advocates.
versus
M/S JAIN TRADERS & ORS AB+ ..... Respondents
Through: Ms. Sonia Arora, Advocate for the
respondent No. 2.
CORAM:
HON'BLE MR. JUSTICE VIPIN SANGHI
1. Whether the Reporters of local papers may
be allowed to see the judgment? : No
2. To be referred to the Reporters or not? : Yes
3. Whether the judgment should be reported
in the Digest? : Yes
O.M.P. Nos. 108/2008 & 363/2008 Page 1 of 22
JUDGMENT
VIPIN SANGHI, J.
1. The present petitions, filed under Section 34 of the Arbitration
and Conciliation Act, 1996 (the Act) assail the award dated 8th January,
2008 passed by the learned Sole Arbitrator Shri H.C. Gupta. O.M.P. No.
108/2008 has been filed by MSTC Ltd., whose services were engaged
by U.P. Rajya Vidyut Utpadan Nigam Ltd. - the owner of the scrap, to
sell the same. O.M.P. No. 363/2008 has been preferred by U.P. Rajya
Vidyut Utpadan Nigam Ltd. Both these petitioners were party
respondents in the arbitral proceedings. By the impugned award, the
ld. Arbitrator has partially allowed the claim of the respondent to the
tune of Rs.4,40,408/- and has granted pendente lite interest @ 12%
per annum from 10th March, 2006 till the date of the award and also
future interest @ 12% per annum till the payment.
2. The petitioner MSTC Ltd. (hereinafter MSTC) had floated tender
No. MSTC(D)/T-547/UPRVUNL/03-04 on behalf of U.P. Rajya Vidyut
Utpadan Nigam Ltd. The "lot" of the scrap which was the subject
matter of the tender was detailed in the tender as "125 MVA
transformer HT/LT damaged coil set, 11/242 KV copper wound,
Gross weight of each set of coil 13.5 tons (tentative) including
insulation". The "lot" was to be sold on "as is where is" basis. The
tender was to open on 19th March, 2004 and inspection was allowed
from 04.03.2004 to 18.03 2004. The tenderers were required to submit
a certificate along with their bid, declaring that the materials have
been inspected and they are satisfied with the materials' condition.
3. The respondent, in response to the tender, submitted its bid and
was declared the highest and successful bidder. In terms of the tender,
respondent deposited the first installment and pursuant to that they
collected the first coil from Aligarh on 19th August, 2004. The
respondent thereafter raised a dispute about the weight of the coil, by
claiming that the weight of the coil was 9.46 tonnes, as opposed to
13.5 tonnes stated in the tender. The respondent requested the
petitioner to reduce the price of the coil which had been delivered and
also to ensure that remaining coils were of the tentative weight. As the
petitioners did not agree with the respondent, the respondent invoked
the arbitration clause on 02.03.2005. Since the appointing authority
failed to appoint the Arbitrator, respondent moved this court under
Section 11 of the Act and same was allowed on 10.03.2006 with the
appointment of the Arbitrator.
4. The main contention of the respondent before the Arbitrator to
sustain its claim was that weight was an essential component in pricing
and the shortfall of almost 4.40 tonnes i.e. approx. 33% was quite
substantial. The bidder could not have ascertained the weight of such a
heavy coil, as there was no provision or facility provided for the same.
Respondent admitted that it had inspected the material but at the
same time it submitted that it was not possible to judge the exact or
approximate weight of the same with the naked eye.
5. The petitioners opposed the above contention and relied heavily
on Clause 5 of General Terms and Conditions of the tender to submit
that the goods were sold on "lot" basis and not on unit, number,
quantity basis; the weight is purely indicative, and; the owner was not
to be liable for any complaint from buyer for any deficiency in quantity,
quality, size etc.
6. The learned Arbitrator rejected the defense of the petitioners and
awarded the respondent's claim. The reasoning of the tribunal for
allowing the said claim reads as follows:
"May be as it is, it is extremely difficult for me to persuade myself to agree to the submissions made by the respondents that the actual weight, which is less by one- third of the tentative weight as mentioned in the tender document is not to be considered at all while deciding the issue. Had the difference between the tentative weight mentioned in the tender notice and the actual weight of the coil been marginal, say +10%, things would have been different. However, the actual weight is almost 33% less than the tentative weight. In this view of the matter, the weight of the coil assumes significance and would be a relevant factor. The coil is sold as the scrap and the claimant, who is the scrap dealer, has to dispose of the same as scrap. Clause 5.3 has to be given a reasonable interpretation and the claim regarding deficiency in the quantity would only mean that the bidder shall have no claim if the quantity is little more or less than the tentative quantity. But it does not mean that even when the coil turns out to be far below the tentative weight, the petitioner shall have no claim. In view of above I hold that the respondents have breached the terms and conditions of the contract by supplying the coils which were deficient in weight to the extent of 33%."
7. The submission of the petitioner MSTC is that the award made by
the ld. Arbitrator is patently illegal, as the same is contrary to the
express contractual terms. By acting contrary to the contractual
terms, the learned Arbitrator has acted beyond his jurisdiction and
misconducted himself. It submits that it was the accepted position that
scrap was sold by way of "lot" on "as is where is" basis. And the
Arbitrator has also found the same. Even after holding that the sale
was on "lot" basis, the Arbitrator held that the tentative weight
mentioned in the tender document was an essential condition of
contract, and petitioners have breached the contractual conditions as
the actual weight was less by 33%. This, according to the petitioners is
contrary to the express conditions of contract.
8. Clause 5 of the General Terms and Conditions of tender, on
which reliance is placed, reads as under:
"5. QUALITY, QUANTITY AND SECURITY OF SOLD MATERIAL.
5.1. The goods will be sold on "As is where is" basis in so far as the physical condition of the same is concerned. That is to say, the tenderer(s) will be deemed to have made themselves aware of the physical conditions, dimensions, size, weight, working conditions etc. by inspecting the material before submitting their tender and no complaint/claim in this regard will be entertained by MSTC after the submission of the tender.
5.2 Tenderers may quote for all or any of the lots mentioned in the schedule of Rate(s) but no quotation for part quantity of material in any particular lots will be accepted. Separate Earnest Money shall be payable for each of the lot quoted for.
5.3 Where goods are sold on "lot" basis and not by unit weight/number basis, the entire material lying in the lot will have to be lifted by the buyer(s) so as to clear the entire lot. The quantity, if indicated in such cases against the respective lots, are purely indicative and MSTC/Owner shall not entertain any claim/complaint from the buyer(s) for any deficiency in quantity/quality/size/dimension or for refund of the whole or any part of the purchase money or loss of profit or interest/damages or otherwise.
5.4 Where the goods are sold by unit i.e. weight or number and not on the basis of "lot", the quantity indicated in such cases against the respective lots are purely indicative which in actual may turn out, to be more or less than the indicated quantity after duly completion of the lifting by the buyer(s), the buyer(s) shall not be entitled to claim any damages, loss of interest of compensation or any other account, but shall be entitled to proportionate refund only.
5.5 Where there are items or more than one classification of any form in any lot & the tenderer quoted in lump sum of the entire lot instead of quoting in units per item, then no refund of any kind shall be entertained by MSTC/Owners, if the quantity, whatever mentioned in the tender, turns out to be less at the time of delivery. However, if the quantity turns out to be more than the tendered quantity then the delivery of materials shall be limited to tendered quantity only.
5.6 MSTC reserves the right to accept or withdraw from sale the materials offered for sale in full or part thereof prior to or after acceptance of the tender without assigning any reason whatsoever. In such an event the payment, if any, deposited by tenderer/purchaser shall be refunded by MSTC/Owner in due course of time without interest, and thereafter no liability/complaint, whatsoever shall be entertained by MSTC/Owner.
MSTC reserves the right to accept or reject the highest tender without assigning any reason and the contract of any or all the lots may be allotted by MSTC to one or more than one tenderer as MSTC may deem fit and no claim/complaint in this regard will be entertained by MSTC/Owner."
9. Counsel for U.P.R.V. Utpadan Nigam Ltd. (petitioner in O.M.P. No.
363/2008) submits that Arbitrator has failed to take into account the
counter claims raised by the petitioner and has disallowed the same on
the basis of non furnishing of the substantial evidence.
10. Respondent submits that the award in question does not suffer
from any illegality and the interpretation given to clause 5 by the
Arbitrator is the plausible interpretation. In support of this submission,
learned counsel places reliance on the order passed in Arb. P. No.
263/2005 on 10.03.2006 by Hon'ble Mr. Justice A.K. Sikri, whereby the
ld. Arbitrator was appointed on the respondent's application preferred
under Section 11(6) of the Act.
11. It is submitted that clause 5.3 of the standard terms states that
where sale is by "lot" there will be no complaint regarding weight of
the goods sold. At the same time, the tender specified the weight as
13.5 tons tentatively. Arbitrator has harmonized the two terms so as
not to render any term otiose. It is further submitted that the indication
of the tentative weight as 13.5 tons constitutes a special term of the
contract, and that should prevail over the general terms as provided
under General Terms and Conditions. Reliance is placed on M.K.
Abraham & Co. v. State of Kerala, (2009) 7 SCC 636; and M/s
Phoenix Cotton Tape Factory v. Union of India, ILR 1974 DEL 479.
12. It is submitted by the respondent that contract being one for
scrap, weight was an essential term and deviation amounting to 33% is
substantial. Weight of the coil was an essential factor to be considered
while making the bid. Petitioners being government organizations
should have acted honestly and true disclosure of the quantity of coil
should have been made. It is further submitted that petitioners had
opposed the inspection of the other two coils even during the
pendency of the arbitral proceedings. Petitioners have not produced
any document to show on what basis it had been claimed in the tender
document that the weight of the coil was around 13.50 tons.
13. The issues that arise for consideration are whether the ld.
Arbitrator has acted contrary to the contractual terms, and; whether
the view of the Arbitrator is a plausible view in the facts of this case.
14. The reasons of the tribunal for making its award on the merits of
the claim have been set out hereinabove. The fundamental premise on
which the award is founded is that the weight of the coil was an
essential term and although variation upto 10% of tentative weight
would have been acceptable, but deficiency of 33% would amount to
breach of the contract by the petitioners.
15. The aforesaid fundamental premise of the tribunal is completely
flawed and patently incorrect. It is not in dispute that the tender
stipulated the weight of coils as "tentative", and that the coils were
sold in a "lot" on "as is where is" basis. The tender specifically
stipulates that "..... .... ..... ..... the tenderer(s) will be deemed to have
made themselves aware of the physical conditions, dimensions, size,
weight, working conditions etc. by inspecting the material before
submitting their tender and no complaints/claim in this regard will
be entertained by the MSTC after the submission of the
tender." (emphasis supplied)
16. Clause 5 of the General Terms & Conditions shows that all sales
of goods made by MSTC are on "as is where is" basis in so far as
physical conditions are concerned. This is to say that the tenderers
are deemed to have made themselves aware of the physical conditions
namely the dimensions, size, weight, working conditions, etc. by
inspecting the material before submitting their tender. No
complaint/claim in this regard is entertained by MSTC after the
submission of the tender.
17. Clauses 5.3 & 5.4 deal with different kinds of sale. Whereas
Clause 5.3 deals with sale made on "lot" basis and not by
unit/weight/number basis, Clause 5.4 deals with goods sale on unit,
i.e., weight or number, and not on the basis of "lot". When the goods
are sold on "lot" basis the entire material lying in the lot has to be
lifted by the buyer so as to clear the entire "lot". This means that the
buyer cannot pick & choose some items constituting the "lot" and
leave the rest. Clause 5.3 specifically provides that "the quantity, if
indicated in such cases against the respective lots, are purely
indicative and MSTC/owner shall not entertain any claim/complaint
from the buyer(s) for any deficiency in quantity/quality/size/dimension
or for refund of the whole or any part of the purchase money or loss of
profit or interest/damages or otherwise". Therefore, it emerges that
firstly, the quantity indicated in a sale on "lot" basis is purely
"indicative" and, secondly, the buyer is put to prior notice that no
claim on account of deficiency, inter alia, in quantity shall be
entertained and no claim for refund on account of loss of
profit/damages will be entertained. In contradistinction to this, when
the goods are sold by unit, i.e., by weight or number and not on the
basis of "lot", the situation is remarkably different. In that situation, if
the quantity is found to be less, the buyer is not entitled to claim any
damages, loss of interest or compensation, "but he shall be entitled to
proportionate refund only". Therefore, the concept of proportionate
refund is contained in Clause 5.4, i.e., when the goods are sold on unit
basis, i.e., by weight or by number, and is specifically excluded in the
case of sale on "lot" basis.
18. This distinction has been completely ignored by the learned
Arbitrator and he has, on the basis of equitable considerations and his
notions of fairness, superimposed the concept of proportionate refund
in Clause 5.3, even though the same is specifically excluded from
Clause 5.3.
19. The Arbitrator is bound to implement the contractual clauses and
cannot go contrary to them. He cannot decide on the basis of his
notions of equity and fairness, particularly in such a manner that it
goes contrary to the specific contractual terms. Section 28(2) of the
Act provides that "The arbitral tribunal shall decide ex aequo et bono
or as amiable compositeur only if the parties have expressly
authorized it to do so". (emphasis supplied). The phrase "ex aecquo et
bono" means "according to equity and conscience" (see Black's Law
Dictionary 6th edition). In relation to the expression "Amiables
compositeurs" the Black's Law Dictionary refers to "Amicable
compounders" and states that "amicable compounders are arbitrators
authorized to abate something of the strictness of the law in favour of
natural equity". The parties in this case have not agreed that the
Arbitrator may decide as an amiable compositeur or on the basis of
"justice and fairness". Therefore, the learned Arbitrator could not have
disregarded the plain and grammatical meaning of Clauses 5.3 and 5.4
of the General Conditions of Contract to give way to his own sense of
equity, fairness or justice. Reference in this regard may also be made
to the decision in Food Corporation of India Vs. Chandu
Construction & Another, (2007) 4 SCC 697. The Supreme Court in
this decision held as follows:
"11. It is trite to say that the arbitrator being a creature of the agreement between the parties, he has to operate within the four corners of the agreement and if he ignores the specific terms of the contract, it would be a question of jurisdictional error on the face of the award, falling within the ambit of legal misconduct which could be corrected by the court. We may, however, hasten to add that if the arbitrator commits an error in the construction of contract, that is an error within his jurisdiction. But, if he wanders
outside the contract and deals with matters not allotted to him, he commits a jurisdictional error (see Associated Engg. Co. v. Govt. of A.P., (1991) 4 SCC 93; and Rajasthan State Mines & Minerals Ltd. v. Eastern Engg. Enterprises, (1999) 9 SCC 283).
12. In this context, a reference can usefully be made to the observations of this Court in Alopi Parshad & Sons Ltd. v. Union of India, AIR 1960 SC 588, wherein it was observed that the Contract Act does not enable a party to a contract to ignore the express covenants thereof, and to claim payment of consideration for performance of the contract at rates different from the stipulated rates, on some vague plea of equity. The Court went on to say that in India, in the codified law of contracts, there is nothing which justifies the view that a change of circumstances, "completely outside the contemplation of parties" at the time when the contract was entered into will justify a court, while holding the parties bound by the contract, in departing from the express terms thereof. Similarly, in Naihati Jute Mills Ltd. v. Khyaliram Jagannath, AIR 1968 SC 522, this Court had observed that where there is an express term, the court cannot find, on construction of the contract, an implied term inconsistent with such express term.
13. In Continental Construction Co. Ltd. v. State of M.P., (1988) 3 SCC 82, it was emphasised that not being a conciliator, an arbitrator cannot ignore the law or misapply it in order to do what he thinks is just and reasonable. He is a tribunal selected by the parties to decide their disputes according to law and so is bound to follow and apply the law, and if he does not, he can be set right by the court provided his error appears on the face of the award.
14. In Bharat Coking Coal Ltd. v. Annapurna Construction, (2003) 8 SCC 154, while inter alia, observing that the arbitrator cannot act arbitrarily, irrationally, capriciously or independent of the contract, it was observed, thus: (SCC pp. 161-62, para 22) "22. There lies a clear distinction between an error within the jurisdiction and error in excess of jurisdiction. Thus, the role of the arbitrator is to arbitrate within the terms of the contract. He has no power apart from what the parties have given him under the contract. If he has travelled beyond the contract, he would be acting without jurisdiction, whereas if he has remained inside the parameters of the contract, his award cannot be questioned on the ground that it contains an error apparent on the face of the record."
15. Therefore, it needs little emphasis that an arbitrator derives his authority from the contract and if he acts in disregard of the contract, he acts without jurisdiction. A deliberate departure from contract amounts to not only manifest disregard of his authority or a misconduct on his part, but it may tantamount to a mala fide action (also see Associated Engg. Co. v. Govt. of A.P., (1991) 4 SCC 93)."
20. After examining the contractual terms, the Supreme Court
further observed as follows:
"19. ..... ..... ..... It is, thus, clear that the claim awarded by the arbitrator is contrary to the unambiguous terms of the contract. We are of the view that the arbitrator was not justified in ignoring the express terms of the contract merely on the ground that in another contract for a similar work, extra payment for material was provided for. It was not open to the arbitrator to travel beyond the terms of the contract even if he was convinced that the rate quoted by the claimants was low and another contractor, namely, M/s Gupta and Company had been separately paid for the material. Claimants' claim had to be adjudicated by the specific terms of their agreement with the FCI and no other.
20. Therefore, in our view, by awarding extra payment for supply of sand the arbitrator has out-stepped confines of the contract. This error on his part cannot be said to be on account of misconstruing of the terms of the contract but it was by way of disregarding the contract, manifestly ignoring the clear stipulation in the contract. In our opinion, by doing so, the arbitrator misdirected and misconducted himself. Hence, the award made by the arbitration in respect of claim No. 9, on the face of it, is beyond his jurisdiction; is illegal and needs being set aside."
21. If the reasoning of the learned Arbitrator were to be accepted,
there would be no sacrosance remaining in the specific and express
contractual provisions, inter alia, contained in Clause 5.1 and 5.3 of the
General Terms & Conditions.
22. The submission of the respondent that in the tender document
the tentative weight of the "lot" had been mentioned and that the
same constituted the special condition, is completely without
substance. Clause 5.3, which deals with the sale of goods on "lot"
basis, itself provides that the mention of the weight would be only
indicative and that, by itself, would not entitle the buyer to either claim
refund or damages even if the goods turn out to be deficient in
quantity/quality/size/dimension. Therefore, the indication of the
tentative weight does not take the case out of Clause 5.3 of the
General Terms & Conditions, and it cannot be said that the indication
of weight in the tender is a special condition. Clause 5.3 itself
postulates the inclusion of the tentative weight in the tender for sale
by "lot". The two decisions relied upon by the respondent are not
applicable in this case for this reason.
23. The mention of the gross weight of each set of coil including
insulation as 13.5 tonnes was only tentative and indicative and not
much could have been read into it. These sales of scrap, which are
conducted by MSTC, do not attract laymen from the street. The
bidders invariably are experienced scrap dealers well-versed in their
trade who have the expertise to assess the worth of the "lot" that they
bid for. Even if, eventually a particular "lot" turns out to be a losing
proposition on account of deficiency of quantity/quality/size/dimension,
that is no ground to permit the raising of a claim contrary to the
contractual terms, as the bidders participate and bid in the tender
process with open eyes. The petitioners do not guarantee to the
successful bidder that the "lot" awarded to him would always be a
profitable proposition and the losses, if any, would be to the petitioners
account. The view taken by the learned Arbitrator if allowed to prevail
would completely undermine all sales undertaken by the petitioner-
MSTC on "lot" basis.
24. There is yet another aspect which has not been considered by
the learned Arbitrator. The sale was made on "lot" basis of 3 sets of
125 MVA Transformers HT/LT Damaged Coil Sets, 11/242 KV Copper
Bound. The respondent was obliged to pay for and remove all the
three sets and could not have picked & chosen one set and raised the
claim. Who knows, if the respondent had taken the entire "lot" as per
his contract, he may have been compensated for the alleged loss
suffered in the set collected by him, by the weight of the coil in the
other two sets. In fact, by not lifting the entire "lot" consisting of three
sets it is the respondent who breached the agreement, and not the
petitioners.
25. The respondent was made aware of all the conditions and they
being prudent businessmen entered into the contract with open eyes.
Respondent could not at a later stage plead that they were not aware
of the actual weight of the "lot".
26. The learned Arbitrator has completely overlooked and ignored
the well-settled principle of Caveat Emptor which was squarely
applicable to the transaction in question. The respondent was told that
the material is being offered on "as is where is" basis and he was also
required to submit a certificate along with his bid declaring that the
material has been inspected and that he is satisfied with the materials
condition. He was also aware of Clause 5 and, in particular, Clause 5.3
of the General Terms & Conditions of tender. The petitioners were
shouting from the roof top to tell all bidders that they must bid with
open eyes and after satisfying themselves about the
quantity/quality/size/dimension of the goods constituting the "lot", and
that no claim of any kind due to deficiency in
quantity/quality/size/dimension shall be entertained later for raising a
claim of refund or damages.
27. "Caveat Emptor qui ignorare debuit quod jus alienum emit"
means "let the purchaser beware who ought not to be ignorant that he
is purchasing the rights of another." The purchaser is generally bound
to view the land and to enquire after and inspect the title deeds; at his
peril if he does not. It is one of the settled maxims, applying to a
purchaser who is bound by actual as well as constructive knowledge of
any defect in the thing purchased, which is obvious, or which might
have been known by proper diligence. Caveat emptor does not mean
either in law, or in Latin, that the buyer must take chances. It means
that the buyer must take care." "Caveat emptor" is the ordinary rule in
contract. A vendor is under no duty to communicate the existence,
even of latent defects in his wares unless by act or implication he
represents such defects not to exist." [See William R. Anson, Principles
of the Law of Contract 245 (Arthur L. Corbin Ed.3d. Am. ed.1919)].
Upon a sale of goods the general rule with regard to the nature or
quality of goods is caveat emptor, so that in the absence of fraud, the
buyer has no remedy against the seller for any defect in the goods not
covered by some condition or warranty, expressed or implied. It is
beyond all doubt that, by the general rules of law there is no warranty
of quality arising from the bare contract of sale of goods, and that
where there has been no fraud, a buyer who has not obtained an
express warranty, takes all risk of defect in the goods, unless there are
circumstances beyond the mere fact of sale from which a warranty
may be implied. No one ought in ignorance to buy that which is the
right of another. The buyer according to the maxim has to be cautious,
as the risk is his and not that of the seller. (See Commr. of Customs
(Preventive) Vs. Aafloat Textiles (I) Pvt. Ltd. and Ors., (2009) 11
SCC 18)
28. In the present case, the respondent buyer was given an
opportunity to inspect the goods. They being prudent and experienced
men of trade, should have taken all due care to inspect the same and
to find any defect whatsoever. Seller MSTC did not provide any
warranty as to weight since quoted weight was only tentative and
contract specifically stipulated that no future claims would be
entertained as to weight of the goods. In such circumstances, the
respondent cannot plead breach of the contract by the petitioners.
29. The second issue that requires consideration is whether the view
of the learned Arbitrator is a plausible view, as it is contended by the
respondent that if two views are possible, and the Arbitrator has taken
one of those two views, the court has no jurisdiction to interfere with
the award. It is argued that when the order under Section 11(6) of the
Act was passed in Arbitration Petition No. 263/2005 and OMP
No.443/2005 on 10.03.2006 by Hon'ble Mr. Justice A.K. Sikri, in his
order he had himself indicated the same view, as has been eventually
adopted by the learned Arbitrator, as a plausible view. It is argued
that the petition under Section 11 preferred by the respondent had
been opposed by the petitioners on the ground that the contractual
terms are clear and do not admit of any ambiguity. Therefore, there is
no claim or dispute that the respondent could raise. The court, in the
light of the Supreme Court decision in M/s SBP Co. Ltd. Vs. M/s
Patel Engineering Ltd., JT 2005 (9) SC 291 went into the question
whether a dispute existed between the parties or not. The court
accepted the respondent's submission that a dispute existed. In doing
so, the court appreciated the respondent's submission that thought the
weight was stated to be "tentative", variation could not be to the
extent of 33% as the parties were expected to act honestly and the
petitioners, who are public undertakings, could not mention such a
weight which was much below the actual weight. After extracting from
the decision of the Supreme Court in SBP & Co. (supra), Hon'ble Mr.
Justice A.K. Sikri on the aforesaid order observed as follows:
"12. In view of the aforesaid observations of the Supreme Court, in these proceedings it is necessary to decide the jurisdictional aspects. It is not in dispute that there is a valid and existing arbitration agreement between the parties. What is disputed is that there are no "live and subsisting disputes" and nothing to be arbitrated upon. I proceed to examine this aspect.
13. No doubt, the petitioner had admitted that it had inspected the material before submitting the bid. It is also not in doubt that the gross weight of each set of coil, which is mentioned as 13.5 tons, is tentative. It is also an admitted position that the material was offered on "as and where" basis. At the same time it cannot be disputed that inspection of the material with naked eyes would not enable the bidder to weigh a particular coil of this magnitude.
14. Had the difference between the tentative weight mentioned in the tender notice and the actual weight of the coil been marginal, say even 10% ±, things would have been different. However, the actual weight found is almost 33% less than the tentative weight. It is also to be borne in mind that the coil is sold as a scrap and the petitioner who is a scrap dealer has to dispose of the same as scrap.
Therefore, weight of the coil assumes importance and would be a relevant factor.
15. In the aforesaid perspective, contention of the petitioner is that even the petitioner was allowed inspection; weight mentioned is tentative and the scrap is sold as "as and where" basis, there is a dispute, as according to the petitioner, the actual weight cannot be wide off the mark. The contention of the respondents, on the other hand, is that once the coils are sold on "as is where is" basis and the weight mentioned was only tentative and further since general terms and conditions of the tender clearly provided that no claim on the basis of weight would be entertained, the dispute raised by the petitioner has no merit. However, that would be an aspect which will be considered by the arbitrator ultimately. The respondent No. 1 has itself, on an earlier occasion, accepted the existence of the dispute. It is clear from the reply dated 8th June 2005 of the respondent No. 1 sent through its counsel to the petitioner's legal notice. This reply is filed with the petition as Annexure-15 and paras 2 and 4 of the said reply are as under:-
"2. That the contention of your client regarding less weight of scrap material is baseless and illegal my client had already explained every thing in this regard in detail in earlier communication. However, my client is well ready to co-operate the Arbitration proceedings to be held before the sole Arbitrator i.e. Chief Managing Director of U.P.R.V.U. Nigam Ltd.
3. xxxxxx
4. That it is also mentioned here that the venue for the Arbitration shall be decided by the sole Arbitration hence contention or your client that for Arbitration shall be at Delhi is wrong and baseless."
16. While maintaining its stand the respondent No. 1 at that stage showed its willingness to cooperate the arbitration proceedings to be held before the sole arbitrator, i.e. the Chief Managing Director of the respondent No. 1. Thereafter notice dated 13th June 2005
requesting him to enter upon reference and issue necessary directions to the parties.
17. Thus, it cannot be said that there are no disputes between the parties. The contention of the petitioner that the actual weight found is quite off the mark and almost
1/3rd less than the tentative weight needs to be considered. Case of the petitioner is that clause 5.3 has to be given reasonable interpretation and the claim regarding deficiency in quantity would only mean that if quantity is little more or less than the tentative quantity, the bidder shall have no claim. But it would not mean that even when the coil turns out to be far below the tentative weight, the petitioner shall have no claim. Whether the petitioner is right in his submission or not is for the arbitrator to decide by giving appropriate interpretation to clause 5 having regard to the facts of the case. In so far as this Court is concerned, it is clear that there are disputes between the parties which are subsisting."
30. In the impugned award, the learned Arbitrator has verbatim lifted
para 14 of the order passed by Hon'ble Mr. Justice A.K. Sikri. The
question is - can it be said that the observations made by Hon'ble Mr.
Justice A.K. Sikri contains a plausible view? To my understanding, the
answer has to be a plain "No".
31. It is settled position in law that the learned Judge while deciding
a petition under Section 11 of the Act sits as a designate of Chief
Justice. The scope of the proceedings before the Chief Justice or his
designate is limited, and issues that can be adjudicated by him are
also limited, as laid down by supreme court in National Insurance
Co. Ltd. v. Boghara Polyfab (P) Ltd., (2009) 1 SCC 267, in the
following manner.
"22. Where the intervention of the court is sought for appointment of an Arbitral Tribunal under Section 11, the duty of the Chief Justice or his designate is defined in SBP & Co. This Court identified and segregated the preliminary issues that may arise for consideration in an application under Section 11 of the Act into three categories, that is, (i) issues which the Chief Justice or his designate is bound to decide; (ii) issues which he can also decide, that is, issues which he may choose to decide; and (iii) issues which should be left to the Arbitral Tribunal to decide.
22.1. The issues (first category) which the Chief Justice/his designate will have to decide are:
(a) Whether the party making the application has approached the appropriate High Court.
(b) Whether there is an arbitration agreement and whether the party who has applied under Section 11 of the Act, is a party to such an agreement.
22.2. The issues (second category) which the Chief Justice/his designate may choose to decide (or leave them to the decision of the Arbitral Tribunal) are:
(a) Whether the claim is a dead (long-barred) claim or a live claim.
(b) Whether the parties have concluded the contract/transaction by recording satisfaction of their mutual rights and obligation or by receiving the final payment without objection.
22.3. The issues (third category) which the Chief Justice/his designate should leave exclusively to the Arbitral Tribunal are:
(i) Whether a claim made falls within the arbitration clause (as for example, a matter which is reserved for final decision of a departmental authority and excepted or excluded from arbitration).
(ii) Merits or any claim involved in the arbitration.
23. It is clear from the scheme of the Act as explained by this Court in SBP & Co. that in regard to issues falling under the second category, if raised in any application under Section 11 of the Act, the Chief Justice/his designate may decide them, if necessary, by taking evidence. Alternatively, he may leave those issues open with a direction to the Arbitral Tribunal to decide the same. If the Chief Justice or his designate chooses to examine the issue and decides it, the Arbitral Tribunal cannot re-examine the same issue. The Chief Justice/his designate will, in choosing whether he will decide such issue or leave it to the Arbitral Tribunal, be guided by the object of the Act (that is expediting the arbitration process with minimum judicial intervention). Where allegations of forgery/fabrication are made in regard to the document recording discharge of contract by full and final settlement, it would be appropriate if the Chief Justice/his designate decides the issue."
32. The observations of Hon'ble Mr. Justice A.K. Sikri, as quoted
above, have to be read and understood in the light of the aforesaid
judgment of the Supreme Court in Boghara Polyfab (supra). A
perusal of para 15 from the extract of the order of Hon'ble Mr. Justice
A.K. Sikri shows that what had been recorded in paras 13 & 14 was a
mere elaboration of the respondent's submission that a dispute under
the agreement exists, as according to the petitioner, the actual weight
could not be wide of the mark. After recording the submissions of both
the parties, Hon'ble Mr. Justice A.K. Sikri held that these aspects will
have to be considered by the Arbitrator ultimately. In para 17, the
learned Judge observed "Thus, it cannot be said that there are no
disputes between the parties. The contention of the petitioner that the
actual weight found is quite off the mark and almost 1/3 rd less than the
tentative weight needs to be considered. ..... ..... ... Whether the
petitioner is right in his submission or not is for the arbitrator to decide
by giving appropriate interpretation to clause 5 having regard to the
facts of the case". In so far as this Court is concerned, it is clear that
there are disputes between the parties which are subsisting.
33. Even if the submission of the learned counsel for the respondent
were to be accepted that the order passed by Hon'ble Mr. Justice A.K.
Sikri contain his view, the said view cannot be said to be a plausible
view as, while rendering the said view, the distinction between clauses
5.3 & 5.4 have not been analysed and appreciated. The scope of the
present proceedings under Section 34 of the Act is far wider when
compared to the proceedings under Section 11. The aspect of
interpretation of the contractual terms, which impinge on the merits of
the claim involved in arbitration, certainly cannot constitute an aspect
which can finally be determined in proceedings under Section 11 of the
Act and would, necessarily, be have to be left to be determined by the
Arbitral Tribunal as held by the Supreme Court in Boghara Polyfab
(supra). I am, therefore, of the view that the decision of Hon'ble Mr.
Justice A.K. Sikri in Arbitration Petition No. 263/2005 is of no avail to
the respondent.
34. For all the aforesaid reasons, I am of the view that the award
suffers from patent illegality as the learned Arbitrator has acted
contrary to the contractual terms and thereby acted without
jurisdiction. Accordingly, the impugned award insofar as it allows the
respondents claims and awards costs and interest is set aside. OMP
No.108/2008 is allowed.
35. So far as the objections of the petitioner - U.P. Rajya Vidyut
Utpadan Nigam Ltd. with regard to the dismissal of its counter-claim is
concerned, I find no merit in the objections. The learned Arbitrator has
rejected the said counter-claims on the basis that the petitioner - U.P.
Rajya Vidyut Utpadan Nigam Ltd. did not lead any evidence to support
their claim. Even before me, the learned counsel for U.P. Rajya Vidyut
Utpadan Nigam Ltd. has candidly admitted that no evidence was led in
support of the said counter-claim. This being the position, in my view,
there is no merit in the objection raised by U.P. Rajya Vidyut Utpadan
Nigam Ltd. with regard to the dismissal of its counter-claim.
36. In view of the aforesaid position, the impugned award, insofar as
it allows the respondent's claim stands set aside, leaving the parties to
bear their own costs.
(VIPIN SANGHI) JUDGE
AUGUST 08, 2011 'BSR'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!