Citation : 2011 Latest Caselaw 3671 Del
Judgement Date : 2 August, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Bail Application No.882/2011
% Reserved on: 27th July, 2011
Decided on: 2nd August, 2011
Anil Kumar Madan ..... Petitioner
Through: Mr. N. Hari Haran, Adv.
versus
Central Bureau of Investigation ..... Respondent
Through: Mr. Dayan Krishnan with
Mr. Gautam Narayan, Advs.
Coram:
HON'BLE MS. JUSTICE MUKTA GUPTA
1. Whether the Reporters of local papers may Not Necessary
be allowed to see the judgment?
2. To be referred to Reporter or not? Yes
3. Whether the judgment should be reported Yes
in the Digest?
MUKTA GUPTA, J.
1. By this application, the Petitioner seeks anticipatory bail in case RC-
DAI-2010-A-0044 for offences under Section 120B read with Sections
420/467/468/471 IPC and Section 13(2) read with Section 13(1)(d) of the
Prevention of Corruption Act, 1988.
2. Learned counsel for the Petitioner contends that the allegation of the
CBI that the Petitioner in conspiracy with M/s Swiss Timing Ltd., Switzerland
(in short „STL‟) and M/s AKR Construction Ltd. (hereinafter referred to as
„AKR‟) entered into fraudulent contract thereby embezzling Government
money is totally unfounded. The Petitioner had no contract whatsoever with
either the Organizing Committee (OC) of the Common Wealth Games nor
was involved in the Expression of Interest (EOI) or Request for Proposal
(RPF). The Petitioner was engaged by STL as a sub-contractor subsequent to
an agreement entered into with OC for Timing Scoring Mechanism (TSM).
As a matter of fact, there was no conspiracy even between the STL and the
two accused named in the FIR as the bid was not finalized by the members of
OC named in the FIR but by various Committees. The bid was first
shortlisted by a four member Committee at a pre-qualification bid stage.
Since the conditions were very stringent and all venues were to be covered
simultaneously, only two companies had applied. Thereafter financial bid
was approved by the Finance Sub-Committee, which consisted of 12 persons
out of which 8 persons were serving IAS officers. None of the members of
the Committee have been made as accused. In the contract entered into
between the OC and the STL, there is no bar that sub-contractors cannot be
engaged for the work. The Petitioner‟s firm M/s Gem International is a sub-
contractor, whose contract was entered into much later than the contract
between STL and OC. Since the work was enormous, the Petitioner Company
further entered into a sub-contract with AKR for civil work of laying the
cables. The Petitioner‟s Company raised invoices and STL paid the amount in
accordance with the invoices. The Petitioner had received payment only in
August, 2010 while the works were going on. Learned counsel points out
that despite that fact that it had entered into a sub-contract with AKR for
laying the cables, however, still there was enormous work, which was
technical in nature like presentation, field outlay, precision timing, conducting
test events, operation of all installations, transportation of installations from
Government warehouses to the venues and thereafter repacking and sending
them back, maintaining safety conditions and score board operation plan etc.
3. Reliance is placed on Bodhraj v. State of J&K, (2002) 8 SCC 45 to
contend that principles applicable in a case of conspiracy are not made out in
the present case. Reliance is also placed on Sureshchandra Ramanlal v. State
of Gujarat and another, (2008) 7 SCC 591 to contend that the Petitioner‟s
case is similar as that was before the Hon‟ble Supreme Court and thus, he is
entitled to anticipatory bail.
4. Learned Special Public Prosecution on the other hand contends that the
case of the prosecution demonstrates a conspiracy being hatched pursuant to
which initially an attempt was made to award the contract to M/s STL by
nomination, and thereafter the contract was awarded to STL on the basis of
tailor made conditions so as to oust all other competitors at the pre-qualifying
stage. It is stated that EOI was issued without any inputs from the concerned
division i.e. Technology Functional Area, mentioning that "only Swiss
Timing-Omega meets out above all criteria". Thereafter, RFP was issued on
1st October, 2009 and the conditions framed thereunder were so as to further
restrict competition in favour of STL. In order to preclude any other company
except STL from clearing the pre-qualification stage, the RPF conditions were
altered in a non-transparent manner on 4th October, 2009 on the written
directions of Mr. V.K. Verma through his note dated 3rd October, 2009. In
response to the RFP, 2 bids were received, one from STL and the other from
M/s MSL, Spain (MSL). In a pre-meditated manner MSL was wrongfully
eliminated at the pre-qualification stage, thus, making the process virtually a
single tender. STL was awarded the contract at exorbitant rate of `107 crores
causing huge undue loss to the Government of India.
5. The ground taken for ill health of the Petitioner is totally unfounded as
the documents enclosed show otherwise. As regards the operation of Retina
conducted at Switzerland, the doctor in the email addressed to the Petitioner
himself has stated that there was no urgency and surgery could be planned
according to the professional agenda during the period when the Petitioner
was a bit less busy. As regards the ailment that the Petitioner is suffering
from Ankylosing Spondylosis, reference is made to the discharge summary of
Fortis Escorts dated 23rd January, 2011 which shows that no treatment of
Ankylosing Spondylosis was done and the Petitioner‟s complaint at the time
was only of snoring chirring sleep, disturbed sleep, recurrent awakening
during sleep and choking sensation at night. After examination, the condition
of the Petitioner was found to be stable.
6. It is also contended by learned Special Prosecutor that during
investigation it has been revealed that M/s Gem International, whose partners
are Anil Kumar Madan and P.D. Arya, was acting as some sort of
agents/associates of M/s STL in the matter of dealing with the Organizing
Committee and huge amounts were transferred by M/s STL to M/s Gem
International on the pretext of its carrying out some sub-contractual work
relating to provision of TSR solution for CWG D2010. M/s Gen International
received at least `23 crores from STL on the basis of generic, vague, lump
sum and incorrect invoices, which do not contain rates, quantities or details of
works carried out by them. It has further been revealed that the invoices are
false and are not based on genuine commercial transactions.
7. I have heard learned counsel for the parties. The first and foremost
contention of the Petitioner regarding his health being one of the grounds for
grant of bail deserves to be rejected. The email of Prof. Wolfensberger
Thomas sent to the Petitioner on 19th April, 2011 regarding retina detachment
of the Petitioner due to PVR (proliferative vitreoretinopathy) shows that
though the retinal detachment was very advanced and longstanding with PVR
and cicatricial reaction had taken place after the successful surgery. The
Petitioner had been advised the second surgery. It is further stated that
nevertheless the situation did not look extremely urgent to the doctor and
according to him, surgery could be planned according to the professional
agenda during a period when the Petitioner was a bit less busy. Thus, there
was no urgency shown to get the second operation of retinal detachment to be
conducted.
8. As regards the ailment of Ankylosing Spondylosis, a perusal of the
discharge summary from Fortis Escorts shows that the Petitioner was admitted
on 22nd January, 2011 and discharged on 23rd January, 2011with complaint of
snoring chirring sleep, disturbed sleep, recurrent awakening during sleep and
choking sensation at night. After all the tests conducted, the patient was
found to be stable. No document has been annexed to show that the Petitioner
is immobilized because of the ailment of Ankylosing Spondylosis. A few
photographs of the Petitioner in various postures are annexed, however, they
also do not show that the Petitioner is not in a position to stand or walk
without an attendant. As a matter of fact, the evidence shows otherwise. The
Petitioner not only went to Switzerland for his treatment but also travelled to
Jharkhand when games were organized over there. The reliance of the
Petitioner on Sureshchandra Ramanlal (supra) is misconceived because in the
said case the Appellant before the Hon‟ble Supreme Court was bedridden and
could not even stand without two attendants. A perusal of the photographs of
the Petitioner and the activities he is performing do not show that he is
bedridden.
9. The Petitioner initially responded to the notices, i.e., when search were
conducted, he was present and was interrogated. The Petitioner was getting
treatment from „Centre for Sight‟ at Delhi in January, 2011, however, after the
searches conducted at his residence in February, 2011, he went to Switzerland
to get himself treated. Even after coming back from Switzerland, he has
avoided investigation. The Petitioner did not appear pursuant to a notice
issued on 4th April, 2011 ostensibly on the ground that he had gone for
treatment to Switzerland. However, as per the objections filed to the order of
proclamation, the Petitioner had returned to India on the 4 th April, 2011.
Further for a notice for appearance on the 27 th April, 2011, it was replied that
the Petitioner is not in Delhi. Learned counsel for the CBI has pointed out an
affidavit of the Petitioner filed in WP(Crl.) No.596/2011, which was sworn in
on 27th April, 2011 demonstrating that the Petitioner was, thus, in Delhi.
10. The Petitioner and co-accused P.D. Arya were authorized representative
of M/s STL and thus, it cannot be said that the Petitioner‟s firm was merely a
sub-contractor and had no role to play in the initial transaction. A perusal of
the statement of witnesses i.e. PW1, PW2 and PW3 shows that the Petitioner
along with co-accused P.D. Arya and other officers of STL visited the stadia
even in 2009 along with the officers of Organizing Committee. The pre-bid
conference in respect of TSR was attended by the Petitioner on behalf of M/s
STL. In fact, the bid was also submitted by Mr. A.K. Madan. As regards
awarding of sub-contract to AKR though learned counsel for the Petitioner
has strenuously argued that the invoices were raised, however, they were
found to be bogus as invoices had been raised even in respect of game of
shooting though the contract of laying of cables in respect of shooting was not
awarded by the Committee but by the Sports Authority of India. The
Petitioner being a partner of M/s Gem International contends that there was no
bar to a sub-contract, however, the contract entered between the OC and M/s
STL clearly stated that before entering into a sub-contract, the party will take
prior approval/intimation to the Committee. The initial attempt of the
OC was to award the contract to M/s STL by nomination. However, when a
number of complaints were received from persons like Smt. Sunita Goyal, the
tender conditions were prepared in a clandestine manner so as to exclude all
other companies. Even after the request for proposal (RFP) was published,
amendments were made therein fraudulently. As per the statement of
witnesses, the Petitioner and his co-accused P.D. Arya were frequenting the
office of OC even in 2009 prior to the initiation of the procurement process
for the system.
11. The Petitioner has not cooperated in the investigation. Though charge
sheet has been filed, however, on the basis of additional evidence required to
be collected from the Petitioners, supplementary charge sheet may be required
to be filed. Reliance of the Petitioner on the decision rendered in Bodhraj
(supra) is misconceived as on the basis of evidence collected at this stage it
cannot be said that no case for conspiracy is made out.
12. In view of these facts, I do not find it to be a fit case to grant
anticipatory bail to the Petitioner. The application is dismissed.
(MUKTA GUPTA) JUDGE AUGUST 02, 2011 vkm
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!