Thursday, 30, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Pcp International Ltd. And Anr. vs Gas Authority Of India
2010 Latest Caselaw 1243 Del

Citation : 2010 Latest Caselaw 1243 Del
Judgement Date : 5 March, 2010

Delhi High Court
Pcp International Ltd. And Anr. vs Gas Authority Of India on 5 March, 2010
Author: Manmohan
                                             #F-18-19
*      IN THE HIGH COURT OF DELHI AT NEW DELHI

18
+      O.M.P. 208/2001

       GAS AUTHORITY OF INDIA                      ..... Petitioner
                    Through                        Mr. Rajiv Bansal, Advocate

                      versus


       PCP INTERNATIONAL LTD.
       AND ANR.                                    ..... Respondents
                    Through                        Mr. N.B. Joshi with
                                                   Mr. Kaushik Dey, Advocates

                                          AND
19
+      O.M.P. 217/2001

       PCP INTERNATIONAL LTD.
       AND ANR.                                    ..... Petitioners
                    Through                        Mr. N.B. Joshi with
                                                   Mr. Kaushik Dey, Advocates
                      versus


       GAS AUTHORITY OF INDIA                      ..... Respondent
                    Through                        Mr. Rajiv Bansal, Advocate

       %                                  Date of Decision : March 5, 2010

       CORAM:
       HON'BLE MR. JUSTICE MANMOHAN

       1. Whether the Reporters of local papers may be allowed to see the judgment?      No.
       2. To be referred to the Reporter or not?                                         No.
       3. Whether the judgment should be reported in the Digest?                         No.


                                      JUDGMENT

MANMOHAN, J (ORAL)

1. By way of present petitions both Gas Authority of India (in

short "GAIL) and PCP International Ltd. (in short "PCP") have filed

objections under Section 34 of Arbitration and Conciliation Act, 1996

(hereinafter referred to as "Act, 1996") challenging the Award dated

8th January, 2001 passed by the Sole Arbitrator, Mr. Justice (Retd.)

M.S. Gujral. While OMP No. 208/2001 has been filed by GAIL,

OMP No. 217/2001 has been filed by PCP.

2. The controversy pertains to a contract between the parties

executed on 24th October, 1994 for construction of certain buildings

etc. at the site of GAIL in Uttar Pradesh. Suffice it to say that

disputes arose between the parties which led to arbitration clause

being invoked in respect of the disputes. PCP filed its statement of

claims to which GAIL filed its written statement/objections and raised

certain counter claims. The arbitral proceedings culminated in the

Award dated 8th January, 2001.

3. After the passing of the Award, both GAIL and PCP filed

applications under Section 33 of Act, 1996 before the Arbitrator.

Both the applications were disposed of by the Arbitrator vide order

dated 3rd March, 2001. The Arbitrator made a minor correction in the

Award which was in the nature of correcting typographical error and

other than that correction, the Arbitrator dismissed both these

applications.

4. Both the parties before the Arbitrator approached this Court by

way of their OMPs. As both the parties had impugned the Award as

well as the order of the Arbitrator dismissing their applications under

Section 33 of Act, 1996, there was no question of executing the

Award. Pleadings being complete in the two OMPs and the arbitral

record having been summoned, both the parties were heard at length.

5. During the course of arguments, Mr. N.B. Joshi, learned

counsel for PCP argued that the Arbitrator has not considered the

evidence and has made the Award without taking into account the

documentary evidence on record, even though the Arbitrator has

stated in the Award that the questions would be decided on the basis

of documentary evidence.

6. Similarly, Mr. Rajiv Bansal, learned counsel for GAIL has

argued that the Arbitrator has not decided the controversy with respect

to liquidated damages. Both the learned counsel have in effect argued

that the determination of facts made by the Arbitrator is faulty and

that such determination is perverse.

7. Mr. Joshi has further argued that assuming that the findings of

the Arbitrator are not to be interfered with, the Arbitrator has made

grave errors of arithmetical calculation and has worked out a final

figure of Rs.49,29,,824 as the principal sum payable by PCP to GAIL

under the Award. Mr. Joshi contended that while arriving at such a

figure, the Arbitrator has not taken into account the amounts already

received by GAIL by way of encashment of bank guarantees and that

the Arbitrator has not given PCP the credit of the final bill. According

to Mr. Joshi, even if impugned Award is allowed to stand, it is only a

sum of Rs.16,64,453/- which can be said to be payable by PCP to

GAIL.

8. In a similar vein, Mr. Bansal argued that it is on account of an

arithmetical error/calculation mistake that the learned Arbitrator has

left out the amount of Rs. 5,94,617, being the interest accrued on the

sum of Rs. 35 lakhs disbursed by GAIL to PCP as Special Advance

for the period commencing from the date of release till 4th October,

1996. His submission therefore is, that this amount of Rs. 5,94,617/-

should have been awarded to GAIL.

9. The substantive challenge to the Award by both the parties in

effect requires this Court to appreciate the evidence afresh and come

to a finding of fact different from the finding arrived at by the

Arbitrator. The scope of Section 34 of the Act, 1996 is very limited.

Section 34 does not permit this Court to re-appreciate evidence. This

Court does not exercise appellate jurisdiction over the award passed

by the Arbitrator. The grounds on which this Court can interfere with

the Award have been enumerated in section 34(2) of the Act, 1996. I

find no such infirmity in the impugned Award.

10. It was urged by Mr. Bansal that the claim of GAIL with respect

to liquidated damages was not adjudicated by the Arbitrator as should

have been done. Having gone through the Award and having

examined the contract between the parties, I find that Clause 27 of the

contract specifically states that on this aspect, it is the decision of the

Engineer-in-charge which would be binding on the parties. Thus, I

find no infirmity in the Award. The Arbitrator could well not have

given any finding on GAIL's claim of liquidated damages, as it was

beyond the purview of the arbitration and did not form the subject

matter of an arbitral dispute. I, therefore, find no merit in the

objections of GAIL to the impugned Award. OMP No.208/2001

preferred by GAIL is, therefore, dismissed, subject however, to the

directions given hereunder.

11. I have no hesitation in dismissing OMP No.217/2001 on the

same grounds i.e. that this Court cannot go into the evidence and

come to a finding of fact different from the finding arrived at by the

Arbitrator.

12. Nevertheless, I find merit in the contention of Mr. Joshi that

the computation of the total amount payable by PCP to GAIL where

such a computation arises out of the Award itself requires

examination. For this, Mr. Joshi has placed reliance on an illustrative

Chart at Page 124 of the paper book in OMP No. 217/2001, which

appears to be based on figures culled out of the amount awarded with

credit being claimed by PCP from the bank guarantee amounts as well

as the final bill.

13. Consequently, I direct the General Manager (Law), GAIL to

appoint a Chartered Accountant within ten days from today.

Similarly, PCP will also appoint a Chartered Accountant within ten

days from today. Both the Chartered Accountants will meet as often

as may be required in the week commencing 15th March, 2010. They

will reconcile the amounts payable by PCP to GAIL with reference to

the Chart referred to hereinabove. They shall also verify whether it is

on account of an arithmetical error/calculation mistake that the

Arbitrator has left out the amount of Rs. 5,94,617, being the interest

accrued on the sum of Rs. 35 lakhs disbursed by GAIL to PCP as

Special Advance for the period commencing from the date of release

till 4th October,1996. The Chartered Accountants shall submit their

joint report to this Court not later than 5th April, 2010 with advance

copies to both the parties.

14. List this matter for directions in the category of short matters on

16th April, 2010.

15. Order Dasti to both the parties under the signature of the Court

Master.

MANMOHAN,J MARCH 05, 2010 rn

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter