Thursday, 30, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Humboldt Wedag Gmbh vs Dalmia Cement Ventures Ltd. & Ors.
2010 Latest Caselaw 1226 Del

Citation : 2010 Latest Caselaw 1226 Del
Judgement Date : 4 March, 2010

Delhi High Court
Humboldt Wedag Gmbh vs Dalmia Cement Ventures Ltd. & Ors. on 4 March, 2010
Author: Valmiki J. Mehta
*             IN THE HIGH COURT OF DELHI AT NEW DELHI

+                          O.M.P. No.548/2009


                                                   4th March, 2010


HUMBOLDT WEDAG GMBH                                              ...Petitioner

                           Through:     Mr. Neeraj Kishan Kaul, Senior
                                        Advocate with Ms. Anuradha Lal,
                                        Advocate and Mr. Om Parkash,
                                        Advocate for the petitioner.

              VERSUS


DALMIA CEMENT VENTURES LTD. & ORS.                        ....Respondents.

Through: Mr. Jayant Bhushan, Senior Advocate with Mr. Mihir Kumar, Advocate and Mr. Gautam Talukdar, Advocate for the respondent no.1.

Mr. Abhishek Kumar, Advocate for respondent no.2.

CORAM:

HON'BLE MR. JUSTICE VALMIKI J.MEHTA

1. Whether the Reporters of local papers may be allowed to see the judgment?

     2. To be referred to the Reporter or not?     Yes

     3. Whether the judgment should be reported in the Digest?          Yes

    %                            JUDGMENT (ORAL)

VALMIKI J.MEHTA, J

1. This is the petition under Section 9 of the Arbitration and

Conciliation Act, 1996 whereby the petitioner seeks an injunction to restrain

OMP 548/09 Page 1 the respondent No.1 (hereinafter „the respondent‟) from invoking the Bank

Guarantee for Euro 2,835,000 and which Bank Guarantee was given to

secure the advance payment given by the respondent to the petitioner. The

petitioner as the contractor and the respondent as an owner entered into a

contract by virtue of the Letter of Intents dated 20.2.2008 whereby the

petitioner was to design, engineer, manufacture, supply and sell the cement

plants to the respondents for its sites at Belgaum; Karnataka, Gulbarga-I;

Karnataka, Gulbarga-II; Karnataka and Meghalaya. The subject contract is

dated 17.3.08.

2. In terms of the contract, the respondent gave an advance

payment and which advance payment was secured by the petitioner by

giving to the respondent the subject Bank Guarantee. The original contract

contained a Clause called as Section 26.2 which reads as under:

"26.2 Consequences If the Contract is terminated as per Section 26-Termination for Convenience, the Seller shall determine:

(i) the cost of material and goods ordered for the purposes of the Contract or for use in connection with supply of the Equipment which have been delivered to the Seller or for which the Seller is legally liable to pay or accept delivery. Such materials and goods shall become the property of and be at the risk of the Buyer when paid for by the Buyer and the Seller shall place the same at the Buyer‟s disposal; and

(ii) the amount of any other reasonable expenditure incurred by the Seller in the expectation of completing the whole of the supply of the Equipment as well as cancellation charges as applicable on submission of proofs; and

OMP 548/09 Page 2

(iii) the costs for removal of Equipment from the Site and the return of these items to the Seller‟s and/or Subcontractors‟ workshops as well as the costs of repatriation of the Seller‟s and/or Subcontractors personnel; and

(iv) a reasonable amount in respect of loss of profit not exceeding 10% of the total amount due under the Contract to the extent that such profit has not already been paid to the Seller in sums already invoiced;

And shall issue an accumulated invoice certified by the auditor of the Seller payable by means of the Letter of Credit as specified in Annex 11(Forms of Securities).

3. Pursuant to the fresh discussion and negotiations between the

parties, the contract was novated on 5.9.2008 and these novations are as

under:

" Amendment No.3 to Contract between Dalmia Cement Ventures Ltd. and Humboldt Wedag GmbH made on March 17,2008

Contract No.DV-MGH-DLH-PUO-002-00

-----------------------------------------------------------------------------------Following amendments have been agreed between DCVL &HWG for Plant no.3 (Gulbarga II) and Plant 4 (Meghalaya).

1) The contract value for plant No.3 and 4 remains EURO 10,253,500.00.

2) HW Germany confirms placing order of the following items.

         a)        12 Nos.                Roller Bearing Assemblies

         b)        3Nos.                  Oil Lubrication Systems

         C)        2 Nos.         Rollers Complete welded

         d)        4 Nos.         Rollers with complete studs

         e)        6 Nos.         Gear boxes



The contract value of these items amounts to Euro 7,900,000.00 and it has been agreed between DCVL & HWG as follows:

i) DCVL shall release an advance payment amounting to 10% of Euro 7,900,000.00 by September 15,2008 at the latest.

OMP 548/09 Page 3

ii) DCVL shall open a L/C of 90% of Euro 7,99,000.00 within 15 days from the date of advance payment, latest by September 15, 2008 whereas the confirmation of this L/C shall not be effective before Nov. 15, 2008.

After the advance payment is made and the L/C is opened in accordance with the contract stipulations, DCVL shall confirm one of the following options 1-3:

Option 1: DCVL TO CONTINUE THE CONTRACT ENTIRELY

In case DCVL confirm continuation of contract by 15 th Nov‟08, the pending portion of Euro 10,253,000.00 minus Euro 7,900,000.00= Net Euro 2,353,000.00 will be paid as follows:

1.1) the advance payment of 10% of Euro 2,353,000.00 shall be transferred th on 15 Nov‟08 and, 1.2) the L/C of 90% of Euro 2,353,000.00 shall be opened by 15th Nov‟08 In case that the above mentioned payment conditions have not been fully fulfilled until Nov. 15, 2008 the contract portion value Euro 2,353,000.00 has be to renegotiated.

In case that the before mentioned payment terms under (i), (ii), Option 1.1) and Option 1.2) are fulfilled, HWG has accepted the following delivery periods:

Amendment No.3 to Contract between Dalmia Cement Ventures Ltd. and Humboldt Wedag GmbH made on March 17,2008 CONTRACT No. DV-MGH-DLH-PUO-002-00

Items for Commencement Amendment to Contractual Agreed Last Plants No.3& Date Commencement Delivery Time Date of 4 Date Shipment

2 RP 16- Febr. 20,2008 +3.5 months 18 months Dec. 05, 2009

1RP7-170/90 Febr. 20,2008 +3.5 months 19 months Jan. 05, 2010 1RP 16-

Pyro Febr. 20, 2008 +3.5 months 12 months Jun. 05, 2009 Processing Plant 4

OMP 548/09 Page 4 Option 2: DCVL TO BUY SPARE PARTS AND TO TERMINATE THE SMALLER CONTRACT PORTION DCVL has the option to take

- 12 Nos. Roller Bearing Assemblies

- 3 Nos. Oil Lubrication Systems

- 2 Nos. Rollers Complete welded

- 4 Nos. Rollers with complete studs

- 6Nos. Gear boxes At Euro 7,900,000.00 Price. In such case, DCVL will terminate the contract portion of Plant Nos. 3 and 4 in the outstanding amount of EUR 2,353.000.00 by convenience before 15th Nov‟ 08.

Option 3: DCVL TO TERMINATE THE CONTRACT FOR PLANT

In case the DCVL terminates the contract portion of Plant Nos.3 and 4 entirely by convenience before 15th Nov‟08, then HWG will estimate the loss due to termination of the contract and will inform DCVL accordingly. The loss finally settled for the termination will not be more than 15% and not less than 10% of Euro 7,900,000.00. This amount shall be covered by advance payment to HW Germany as mentioned under (i) and through payment of the L/C mentioned under (ii). Advance Payment Bank Guarantee will be amended to cover the eventuality of release without refund of advance payment in the event of termination of contract. Likewise L/C terms will have to provide for claiming the loss in excess of 10% of the Euro 7,900,000.00."

4. We are concerned with Option No. 3 which was the novation

and amendment to the contract.

5. It is not disputed that by virtue of Section 26 of the Contract,

the respondents could have terminated the contract for its convenience i.e.

without any fault on the part of either of the parties. Such termination for

convenience had the consequences as specified in Section 26.2 of the

contract.

6. By virtue of the amendment dated 5.9.2008 made to the

contract, Section 26.2 was amended whereby the loss which was quantified

OMP 548/09 Page 5 at 10% of the total amount due under the contract was amended to not less

than 10% but not more than 15% of Euro 7,900,000. In this Option 3, it is

clear that the amount of this loss shall be covered by the advance payment

made to the petitioner and the advance payment Bank Guarantee will be

amended to cover the eventuality of release without refund of advance

payment in the event of termination of the contract.

7. The law with regard to interdicting of encashment of a Bank

Guarantee is now well-settled. Payment under an unconditional, on demand

without demur Bank Guarantee can be injuncted by the Court only in the

circumstances of there existing a clear cut case of an egregious fraud or in

circumstances called special equities or when the demand may not be in

accordance with the Bank Guarantee. I must, at this very stage, state that

disputes as to merits under the contract, do not become egregious fraud, and

which fraud alleged has to be so apparent and stark on the face of the record

that thereby the petitioner can seek restraint of encashment of the Bank

Guarantee. Keeping in view the aforesaid parameters of law, let us examine

the facts of the present case as to whether the injunction as prayed for by the

petitioner can or cannot be granted.

8. The facts narrated above show as under:

(i) Under the contract, which was entered into between the parties,

the petitioner did receive the advance payment.

OMP 548/09                                                              Page 6
       (ii)    This advance payment was secured by the subject Bank

Guarantee.

(iii) The original contract was amended by the amendment dated

5.9.2008 whereby the loss in terms of Section 26.2 of the contract was

amended to not less than 10% but not exceeding 15%, of Euro 7,900,000

and which would therefore be the figure of liquidated damages in case of no

fault termination of the contract.

(iv) The Option No.3 does not envisage the situation in Option No.2

whereby the respondent was to take spare parts and materials from the

petitioner.

9. Mr. Neeraj Kishan Kaul, Senior Advocate for the petitioner, has

vehemently contended that the injunction against the encashment of the

Bank Guarantee ought to be granted because the petitioner has huge claims

against the respondent and which have been duly notified to the respondent

by virtue of the letters at pages 38 to 42 of the rejoinder and which claims

the petitioner is entitled to by virtue of Section 26.2 of the contract. Mr.

Kaul further argued that in any case by virtue of the amendment, the Bank

Guarantee should necessarily be reduced by 15% of Euro 7,900,000 because

admittedly by the novation, the advance payment refund was to be adjusted

by the loss which would be incurred by the petitioner on account of no fault

termination by the respondents and which is upto 15% of Euro 7,900,000.

OMP 548/09 Page 7

10. In my opinion, the contentions as put forth by the petitioner

merit a limited acceptance. The limited entitlement for injunction with

respect to encashment of the subject Bank Guarantee, is with respect to the

second argument as advanced by Mr. Kaul. This argument is borne out and

substantiated from the amendment dated 5.9.08 which makes it clear that

advance payment refund shall be reduced by the figure of loss not less than

10% and not exceeding 15% of Euro 7,900,000 in case of no fault

termination of the contract. Admittedly, in this case, there is a no fault

termination of the contract, and therefore, by the admitted amendment

between the parties, the subject Bank Guarantee of Euro 2,835,000 shall

stand reduced by 15% of Euro 7,900,000. Meaning thereby the respondent

can encash the Bank Guarantee, however, encashment of this Bank

Guarantee will be for the amount of the Bank Guarantee less a sum of Euro

11,85,000 i.e. 15% of Euro 7,900,000.

11. That a Bank Guarantee need not to be encahsed for the entire

amount but it can be encashed for a limited amount has been held by the

Supreme Court in the judgment reported as Fenner (India) Ltd. Vs. Punjab

& Sind Bank 1997 (7) SCC 89.

12. So far as the other contention of Mr. Kaul is concerned that the

petitioner is entitled to restrain the respondent with respect to its claims of

losses by virtue of other parts of Section 26.2, in my opinion, this contention

is not worthy of acceptance. The position today, is that this is only a claim

OMP 548/09 Page 8 of the petitioner and not an adjudicated claim. It is not necessary that the

petitioner is bound to succeed in its claim, it may, but today it cannot be

said so. Disputes under the contract, cannot interdict the payment under the

Bank Guarantee. Therefore, simply because the petitioner has made claims

against the respondent, however well merited they may be, cannot entitle the

petitioner to seek restraint against encashment of an unconditional, on

demand and without demur Bank Guarantee as it has been repeatedly held

that the contract of Bank Guarantee is an independent contract and has to be

read as per its terms.

13. The last contention which was raised by Mr. Kaul in terms of

the language of the Bank Guarantee was that the Bank Guarantee was given

towards fulfilment of contractual obligations and in this case there does not

arise the issue of fulfilment of contractual obligations because the contract

has been terminated on account of no fault termination. Again I find that

this argument is of no help to the petitioner because surely the expression

"contractual obligations" would necessarily include the obligations of the

petitioner for refunding by it to the respondent, of amounts which the

petitioner is not entitled to retain. Refund of the advance payment and

which is secured by the Bank Guarantee will surely fall within the

expression "contractual obligations" of the petitioner. Mr. Jayant Bhushan,

Learned Senior Counsel for the respondent, has rightly argued that today,

there is no letter of invocation and when the letter of invocation would be

OMP 548/09 Page 9 made it would be made in terms of the Bank Guarantee and in which

invocation letter it will be necessarily stated that the contractual obligations

have not been performed by the petitioner entitling the respondents to

invoke and encash the Bank Guarantee. I may only note that the Court or

the bank does not go into the merits of the breach of the contractual

obligations and in case of an unconditional Bank Guarantee a demand made

by the beneficiary is treated as final with respect to existence of the

circumstances entitling the beneficiary to invoke and encash the Bank

Guarantee. The argument of Mr. Kaul, is therefore rejected, that the Bank

Guarantee in question does not envisage encashment in case of a no fault

termination.

14. In my opinion, therefore, the petitioner, neither has a prima

facie case nor has the balance of convenience in its favour or that it will be

caused any irreparable injury as required under the law with respect to

injunction against encashment of Bank Guarantee. The catena of judgments

of the Supreme Court and of this Court with respect to encashment of Bank

Guarantee, therefore, have to be followed by this Court and injunction as

prayed for by the petitioner cannot be granted.

15. The present petition is therefore only partly allowed whereby

the respondent is permitted to encash the Bank Guarantee of Euro 2,835,000

minus therefrom a sum of Euro 11,85,000.

OMP 548/09 Page 10

16. Since the petition is partly allowed and partly dismissed, I

would not impose the complete costs upon the petitioner. Ordinarily, I

would have imposed 100% of the costs of these proceedings upon the

petitioner by virtue of para 37 of the judgment of Supreme Court in the case

of Salem Advocate Bar Association Vs. Union of India (2005) 6 SCC 344,

because the petitioner has illegally sought injunction against encashment of

the entire amount of the Bank Guarantee, however, in the peculiar facts of

the case, I order that this petition stands disposed of in terms of the

directions given above subject to payment of costs of Rs.50,000/- by the

petitioner to the respondent.

17. With the aforesaid observations, the petition stands disposed of.




                                             VALMIKI J.MEHTA, J


March 04, 2010
Ne




OMP 548/09                                                             Page 11
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter