Wednesday, 29, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Dr. Abdul Khalique vs Ministry Of Transport & Power
2010 Latest Caselaw 1205 Del

Citation : 2010 Latest Caselaw 1205 Del
Judgement Date : 3 March, 2010

Delhi High Court
Dr. Abdul Khalique vs Ministry Of Transport & Power on 3 March, 2010
Author: Sanjiv Khanna
*     IN THE HIGH COURT OF DELHI AT NEW DELHI

+     W.P.(C) 10272/2006          Date of decision: 3rd March, 2010.

      DR.ABDUL KHALIQUE                         ..... Petitioner
                      Through            Mr. M. Taiyab Khan, Advocate.

                    versus

      MINISTRY OF TRANSPORT & POWER        .... Respondent
                       Through     Mr. Ramesh Pd. Yadav,
                                   Advocate for BSES.
      CORAM:
      HON'BLE MR. JUSTICE SANJIV KHANNA

                             ORDER

%

1. The electricity connection in question is installed in a Nursing

Home at Yamuna Vihar Shahdara, Delhi. Electricity bills as per the

actual consumption were raised and paid by the petitioner up to

October, 2004. Thereafter, the respondent, discom raised provisional

bills without taking actual meter reading, though this is contrary to

Regulation 21 of the Delhi Electricity Supply Code and Performance

Standards Regulations. The petitioner made payment of the provisional

bills amounting to Rs. 1,50,000/- as raised by the respondent, discom

for the period October, 2004 till 31st March, 2006.

2. The petitioner in May, 2006 received a bill of Rs. 80,80,576.72/-

towards electricity consumption. The said bill was subsequently revised

W.P.(C) No.10272/2008 Page 1 to Rs. 6,76,200.29/- vide bill dated 31st May, 2006. The petitioner by

way of the present writ petition has challenged the said bill.

3. The respondent, discom in their counter affidavit have admitted

that incorrect bill for Rs. 80,80,576.72/- was raised. It is stated that this

was on account of the fact that the meter had recorded very high and

unusual consumption of 13,92,617 units as on 1st May, 2006. Thus, the

respondent, discom have admitted that the meter was defective and,

therefore, had recorded very high and unusual consumption of

electricity. The contention of the respondent, discom is that the meter

was not faulty up to 1st April, 2006 as the same was recording normal

actual consumption till the said date. It is stated that on the basis of

meter readings up to 1st April, 2006, the respondent, discom has raised

a bill for Rs. 6,76,200.29/- for consumption of 78196 units from 11th

September, 2004 to 8th August, 2005. It is stated that during this period

the meter had recorded consumption of about 7100 units per month

and the provisional bills were raised @ 2000 units per month,

therefore, the demand of Rs. 6,76,200.29/- is correct and justified.

4. The contention of the petitioner is that the meter was defective

throughout the said period and even before 1st April, 2006.

5. On 13th September, 2005, the petitioner had made a

W.P.(C) No.10272/2008 Page 2 representation to the respondent, discom stating that the meter was

defective and should be replaced as it was recording very high

consumption. The petitioner has placed on record copy of the meter

testing report dated 19th October, 2005. As per the said report, the

meter was faulty. Thus, the respondent themselves on the basis of the

report, came to the conclusion that the meter was faulty as on 19th

October, 2005. Once a meter is found to be defective, the respondent,

discom are duty bound to carry out assessment and raise bills in terms

of the Regulation 21 of the Delhi Electricity Supply Code and

Performance Standards Regulations for the past period as specified.

The respondent, discom has failed to calculate the payment due and

payable in terms of the said regulation. Full play and effect to the

regulation has to be given. After the new meter was installed on 22nd

May, 2006, the consumption of the petitioner has been between 2500

units to 786 units per month. Average consumption has been less than

1500 units per month. Therefore, the bill raised by the respondent,

discom on the basis that the petitioner was consuming 7100 units per

month as per the installed meter is clearly wrong. The meter was

defective as accepted in the inspection report. The respondent, discom

has also failed to download and examine CMRI data. The impugned bill

W.P.(C) No.10272/2008 Page 3 is accordingly quashed. However, it is left open to the respondent,

discom to calculate the user charges in terms of the Regulation 21 of

the Delhi Electricity Supply Code and Performance Standards

Regulations after giving notice and hearing the petitioner. The

petitioner has already deposited Rs. 3,00,000/- pursuant to inter order

passed by the Court. Credit of the said amount will be given to the

petitioner. In case, an adverse order is passed by the respondent,

discom, the petitioner is at liberty to redress his grievance in

accordance with law.

The writ petition is disposed of. No costs.

SANJIV KHANNA, J.

      MARCH 03, 2010
      NA




W.P.(C) No.10272/2008                                            Page 4
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter