Citation : 2009 Latest Caselaw 3774 Del
Judgement Date : 15 September, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: September 07, 2009
Date of Order: September 15, 2009
+OMP 64/1996
% 15.09.2009
Punjab National Bank ...Petitioner
Through: Mr. Jagdeep Kishore, Advocate
Versus
M/s ML Anand & Co. ...Respondent
Through: Respondent in person
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
1. By this petition under Section 33 read with Sections 8, 11 and 12 of the
Indian Arbitration Act, 1940 ("the Act", for short) the petitioner has made a
prayer that this Court should decide the existence, validity and effect of the
arbitration agreement between the parties and declare that no arbitral
dispute exits inter se parties which could be referred to the arbitrator in view
of accord and satisfaction confirmed by respondents no.1 and 2.
2. Brief facts relevant for the purpose of deciding this petition are that the
petitioner Punjab National Bank (PNB) entered into a contract with
respondents for construction of a building at Sri Ganga Nagar, Rajasthan. The
contract between the parties contained an arbitration clause being Clause No.
5.44 which provided that the disputes between the parties should be referred
to and would be adjudicated through the means of arbitration and the
OMP 64 of 1996 PNB vs. M/s ML Anand & Co. Page 1 Of 7 procedure for appointment of the arbitrator was provided in the clause itself.
The respondent invoked the arbitration clause vide letter dated 14 th April,
1995 alleging that respondent was short-paid its final bill and had not been
paid the amount for deviated quantities. The amounts were wrongly deducted
from the final bill under defect liability and liquidated damages. The
respondent asked the bank for appointment of an arbitrator and for referring
the disputes for adjudication. In response to this letter, the bank informed the
respondent that respondent had already given a receipt in lieu of full and final
payment of all claims in respect of Sri Ganga Nagar Project and no dispute
existed for referring to the arbitrator. When the bank did not refer the dispute
to the arbitrator on above ground, respondent in terms of clause 5.44 sent a
panel of three names to the petitioner viz. Mr. V.D. Tiwari, Mr. B.G. Kora,
Justice Avadh Bihari Rohtagi (retired) and asked the petitioner to choose one
of the arbitrators. The petitioner still stuck to its stand that there was no
dispute to be referred to the arbitrator and did not choose out of the names
suggested by respondent. In terms of arbitration clause, in case of failure on
the part of petitioner to choose one of the arbitrators out of the penal
suggested by respondent, the respondents was at liberty to chose one of the
arbitrators, so the respondent appointed Mr. V.D. Tiwari, retired Chief
Engineer CPWD as the arbitrator and referred the disputes to him. It is after
appointment of Mr. V.D. Tiwari that the petitioner filed this petition with the
aforesaid prayer.
3. A perusal of petition filed by the petitioner would show that the only
stand of the petitioner is that the respondent had executed full and final
receipt on 24th January, 1995.
OMP 64 of 1996 PNB vs. M/s ML Anand & Co. Page 2 Of 7
4. It is submitted that the architect of the petitioner bank had issued a
certificate regarding final bill of respondent approving it for Rs.81,56,784.42,
after making certain deductions etc. The petitioner paid the remaining
outstanding amount of Rs.16,53,521.74 to the respondents on 23rd January,
1995. This payment was accepted by the respondent against the final bill as
full and final payment and as settlement of all his claims against petitioner in
respect of the contract. The respondent also confirmed this vide a receipt
dated 24th January, 1995 that no amount in respect of the work executed by
him was due from the bank. The copy of receipt executed by respondent is
placed on record.
5. The respondent in his reply took the stand that the total value of the
work executed by him was Rs.88 lac. The architect did not give a proper
certificate and did not reflect the true and correct picture. Respondent was
not bound by the certificate issued by the architect. The architect had earlier
given a certificate in favour of respondent certifying work of Rs.84 lac
approximately, however, later on, at the behest of the petitioner bank, he
reduced the same to about Rs.81 lac, making wholly unjustified deductions.
The petitioner had committed default in payment of the final bill of
respondent. The lumpsum payment made by petitioner bank was accepted by
respondent under protest and the respondent lodged his claim with the
petitioner bank about the loss of interest for delayed period also alongwith
other claims soon after the payment of Rs.16,53,521.74 on 24th January 1995.
It is stated that the respondents were forced to sign a pre-typed receipt while
handing over a cheque of Rs.16,53,523.74 and was told that the cheque
would be released only subject to signing of the said receipt. When
respondents refused to sign the said receipt, the petitioner refused to release
OMP 64 of 1996 PNB vs. M/s ML Anand & Co. Page 3 Of 7 the payment. Finding no alternative, respondent was made to sign the
receipt. However, after signing the receipts, respondents wrote a letter dated
27th January 1995 to the petitioner that the receipt was got signed from him
under duress and coercion and he challenged the action of the petitioner.
Respondent then gave a notice to the petitioner bank for payment of the
remaining amount as per the final bill prepared by respondent and also asked
petitioner to pay interest for the delayed period and other claims of the
respondent. When petitioner failed to make the payment despite writing
letters, respondent had no alternative but to invoke the arbitration clause.
Respondent in terms of the arbitration clause, asked the bank to appoint an
arbitrator. It is only when the bank did not appoint an arbitrator, the
respondent had a right to name a panel of arbitrators in terms of arbitration
clause. Respondent sent names of panel of arbitrators to the petitioner but
the petitioner refused to act and that is why respondent was compelled to
choose one of the arbitrators from the panel and referred the matter to him.
6. I have heard the counsel for petitioner as well as respondent (who
appeared in person and argued the matter) and perused the documents
placed on record. A perusal of receipt of full and final settlement would show
that the receipt was a pre-typed receipt prepared on 23rd January 1995 and
signed by the respondent on that date and it was again signed by respondent
on a revenue receipt on 24th January 1995 and it is only after signing this
receipt that the cheque dated 20th January, 1994 was handed over to
respondent. In fact, the contract itself contained a clause that the final bill
would be paid subject to the contractor (respondent herein) executing a full
and final payment receipt.
OMP 64 of 1996 PNB vs. M/s ML Anand & Co. Page 4 Of 7
7. The final bill as raised by the contractor was not paid by the petitioner.
The petitioner made various deductions out of this bill on alleged approval
from the architect. Respondents obviously received this amount under protest
as is clear from the letter dated 27th January 1995 and asked the petitioner to
give details of deductions time and again. The respondent has placed on
record the documents showing that the work was complete sometime in
February 1994 and final bill in respect of the work was prepared by Mr. R.K.
Beri, an engineer of petitioner bank who forwarded it to respondent along
with his letter dated 4th May, 1994. The architect of the bank wrote a letter
dated 4th July 1994 to the petitioner's Chief Architect (BNC of PNB) wherein
details of the work done by respondents have been specified. A perusal of this
letter dated 4th July 1994 would show that the gross value of the bill as
approved by the architect was Rs.83,61,604/-. This letter specifically
mentions that the work was completed on 2nd February 1994 and the building
was handed over to the petitioner bank on that day and the defect liability
period starts from 3rd February 1994 and will continue up to 2nd February
1995. It also specifies that the measurements mentioned in the final bill were
on the basis of measurements books and the work recorded in the
measurement books have been executed at the site satisfactorily as per the
tender drawings and conditions. The architect approved the gross amount of
Rs.83,61,604.27 and directed that the remaining payment be made to
respondents. Despite this letter of the architect written on 4th July 1994, the
payment was not released to the respondent and the respondent/contractor
kept on writing letters for releasing the payment. The architect had also given
another certificate in August, 1994 certifying that the construction was
satisfactorily completed by respondent on 2nd February 1994 for total bill
amount of Rs.83,61,000/-.
OMP 64 of 1996 PNB vs. M/s ML Anand & Co. Page 5 Of 7
8. As per the contract, the payment on account of final bill was to be
made within six months from the date of completion certificate issued by the
architect/ site engineer. As per architect's letter, the completion was made on
2nd February 1994 and the building was handed over. The six months' period
for clearing final bill expired on 2nd August 1994. It is apparent that the bank
(petitioner herein) deliberately withheld the payment of the respondent
contrary to the contract and the contractor (respondent) was being put to
unnecessary harassment. A perusal of letters of the contractor would show
that the contractor had been writing of its facing severe financial constraints.
It is not understood as to how subsequently the architect varied and reduced
the amount of final bill to Rs.81,56,784.42. The correspondence also shows
that the petitioner bank had withheld the security deposit and another
amount of Rs.38,000/- on account of defect liabilities and another Rs.32,500/-
towards liquidated damages. There is no reason given by the bank as to how
the liquidated damages were imposed when no notice for defects was given
to the respondents. No reason is given why the security deposit was not
refunded to the contractor. The petitioner, however, vide another letter dated
13th July 1995 told the respondent that only a balance of Rs.1,09,916/- was
payable to him and sent a cheque to the respondent. All this shows that the
account between the parties had not been finalized and the bank was
exerting coercion and pressure on the respondents to sign the final payment
receipt without which the payment was not being released. I consider that it
cannot be said that no dispute existed between the parties or accounts had
been finally settled and there was no dispute left for arbitration.
9. In view of my foregoing discussion, I find no merits in the petition. The
OMP 64 of 1996 PNB vs. M/s ML Anand & Co. Page 6 Of 7 petition is hereby dismissed with costs, cost is quantified as Rs.1 lac, with
directions that the arbitrator appointed by respondents shall continue with
arbitral proceedings. Since considerable time has already elapsed, the
arbitrator shall give his award within a period of six months from receipt of
this order.
September 15, 2009 SHIV NARAYAN DHINGRA J. rd OMP 64 of 1996 PNB vs. M/s ML Anand & Co. Page 7 Of 7
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!