Citation : 2009 Latest Caselaw 3706 Del
Judgement Date : 11 September, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: July 23, 2009
Date of Order: September 11, 2009
+ CS(OS) No.849/1992
% 11.09.2009
G.D. BHUTANI & CO. .... Plaintiff
Through : Mr. Raman Kapoor, Adv.
Versus
DDA & ORS. .... Defendant
Through: Mr. D.S.Mahendru with
Ms. Alpana PAndey Advs.
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the
judgment? Yes.
2. To be referred to the reporter or not? Yes.
3. Whether judgment should be reported in Digest? Yes.
JUDGMENT
1. By this order I shall dispose of objections filed by the
respondent/DDA against the award under Section 30 & 33 of the Arbitration
and Conciliation Act, 1940. In the objection petition, the respondent has
stated that the respondent only assails the award in respect of claims no. 3, 5,
6 and 8 and the respondent/DDA is not objecting to award in respect of claims
no. 1, 2, 4 and 7.
Claim No.3
2. Claim no.3 was made by the claimant on account of recovery of
Rs.52,600/- because of consumption of the cement shown by the contractor
beyond the theoretical calculations with deviations. The contractor had stated
that this recovery for excess consumption at double the rate was illegal since
no notice as per provisions of the agreement was served. DDA before the
Arbitrator contended that the recovery was in terms of the clause 33 and 42 of
the agreement. The learned Arbitrator observed that no notice from the
respondent (DDA) was served upon the contractor nor there was any loss
sustained by DDA or evidence of the misuse of the cement except the case of
pilferage of one truck of cement dealt separately under claim no. 7. Therefore
recovery at twice the misuse of the stipulated rate was not justified.
3. It is argued by DDA that the award of this claim was contrary to
the terms and conditions of the contract. The Arbitrator mis-conducted by
exceeding his authority and travelled beyond the terms of contract. The
contractor on the other hand relied upon Salwan Construction Co. vs.
Union of India 474 DLT 1990.
4. It is settled law that an Arbitrator is not a judge in equity as he is
supposed to adjudicate the claim made by the parties in accordance with the
terms of the contract. The Arbitrator is as much bound by the terms of the
contract as the parties themselves. The Arbitrator cannot write a new contract
between the parties nor has authority to change the terms and conditions of
the contract nor has authority to hold that any clause of the contract was not
enforceable. Clause 42 of the contract is in respect of consumption of cement
and provides that cement used for the work had to be calculated on the basis
of statement showing theoretical consumption of the cement in the work.
Thus, the quantity of cement used in different items of work has to be
calculated as provided in Delhi Schedule of Rates, 1981 printed by CPWD
and over this theoretical quantity of cement a variation upto ± 3% is permitted
where the total cost is not more than Rs.5 lakhs and ± 2% is allowed where
the cost was more than Rs. 5 lakhs. Clause specifically provides that in the
event of difference in the quantity of cement issued and theoretical quantity
inclusive of variation the remaining cement shall be returned. In case of non-
return of this excess quantity of cement, DDA shall be authorized to charge
double the rate. When this clause was made a part of the contract, the
cement was a controlled item and was issued to the consumers only on the
basis of permit. There was no open market of the cement and the rate of
cement in black market was more than double the controlled rate and for this
reason this clause was provided in the contract so as to stop the pilferage and
misuse of the cement by the contractor. Theoretical quantities are provided in
Delhi Schedule of Rates on technically sound basis. The contractor, if was
not agreeable to the clause, had liberty not to sign the contract, but once the
contract is there with this specific provision, the Arbitrator‟s observation that
DDA had failed to establish the loss suffered by it, is contrary to the contract.
DDA was not supposed to establish the loss by any evidence. It is well
settled law that the parties can enter into a contract whereby damages are
provided for any particular item without actual proving of loss. The contractor
in this case had agreed to Clause 42 with open eyes. There was no
requirement of the contract or of law for DDA to show that DDA has suffered a
loss because of supply of cement to the contractor in excess than the
theoretical quantity. The loss was built in. The contractor was at liberty to
insist upon the clause based on actual use of cement instead of theoretical
quantities.
5. Even in normal practice it is not practically possible to measure
and check the actual quantity of the cement used that is the reason that this
clause no. 42 is provided in contracts of DDA to calculate the quantity of
cement used. The Arbitrator was not at liberty to write a new contract
between the parties and observe that the loss was required to be proved by
DDA. Also there is no requirement under Clause 42 for serving a notice by
the DDA on contractor. In fact it is only at the time of final bill that the
theoretical quantities and the actual quantities are calculated and in case of
excess cement than the theoretical quantity is found to have been supplied
and not returned, the penalty ensues. Had the cement been available in the
open market at the same rate, every contractor would have returned the
excess cement supplied, by purchasing it from the market. It is only because
the cement during those days was a black market item that this clause was
provided in order to prevent the pilferage.
6. It is surprising that despite the fact that in this case, the
contractor was caught red handed with one truck full of cement being pilfered
from the spot the learned Arbitrator still allowed this claim of the contractor.
Claim No. 7 under which the Arbitrator dealt with was a claim of the contractor
about recovery of double the cost of cement in respect of one truck load of
cement pilfered from the spot and caught red handed by the police from the
contractor. In view of this glaring evidence that the contractor did indulge in
pilferage of the cement there was no reason for the Arbitrator to record that
DDA failed to produce the evidence of pilferage. If theft of cement was shown
once, it was sufficient evidence of pilferage of cement got issued by contractor
in excess. The Arbitrator in this case gave an award contrary to terms of the
contract and exceeded his jurisdiction and mis-conducted himself. I consider
the award under claim no. 3 is liable to be set aside.
Claim No.5
7. Under this claim claimant has asked for an amount of
Rs.27,777/- on account of unlawful reduction/deduction for items of work from
the payment of final bill. The claimant had submitted before the Arbitrator that
this deduction was made arbitrarily in the rates in respect of certain items
without any notice as prescribed under Clause 14 of any defects or giving any
opportunity to the claimant for rectifying the defects. The respondent had
contended that reduction in rates was done due to work not having been done
or the same not having been done as per specifications and relied on letter
dated 27/11/1984 vide which DDA had pointed out the defects/items not
executed by the petitioner. The learned Arbitrator observed that as per
agreement maintenance period was 6 months and the contractor was bound
to rectify the defects pointed out during this period in terms of Clause 14. The
respondent did not act as per Clause 14. The letters dated 27/11/1984 and
13/2/1985 were written by the respondent much after the expiry of the
stipulated period of 6 months. Moreover, the letters were not issued by
Engineer-in-Charge. He therefore rejected the evidence of the respondent.
He also observed that none of the exhibits mentioned about the defects for
which the rates have been reduced rather the Superintendent Engineer after
inspecting the work had issued a completion certificate dated 30/3/1988 which
mentioned about the lines and levels, seepage, pealing of plaster etc. but
nothing about the defects on account of which deductions were made.
8. It is submitted by the objector (DDA) that the Arbitrator has not
gone into the question whether the deductions or recoveries made in the final
bill were correct or not. He simply referred to letters and awarded the amount.
The Arbitrator has also not taken into account the completion certificate, ex.R-
30 and passed the award contrary to the evidence. In fact, the claimant had
not raised a dispute at any stage regarding the defects mentioned in the
conditional completion certificate. The completion of the project could only be
considered when the defects in the work executed by the claimant were
rectified or removed. As the defects had not been rectified and unexecuted,
items had not been provided by the contractor, it could not be said that the
project was completed. It was specifically mentioned in ex.R-30 that the
completion was provisional subject to rectification of the defects and these
defects were to be removed by the contractor. Since he did not remove the
defects and did not execute the job, the amount was deducted from the bill for
those items. The deduction could be made only in final bill whether the final
bill is prepared within 6 months or after 6 months. The Arbitrator came to
conclusion that since the deduction was made after 6 years therefore they
were not valid deductions and contrary to the contract. Since the claimant
had never denied that they had not removed the defects and completion was
subject to condition, the Arbitrator could not have awarded this amount.
9. Challenge to this claim is made on merits. This Court cannot act
as a Court of appeal and reconsider the evidence. Even otherwise a perusal
of record would show that the deductions were made in respect of items
which did not form part of the defect list. I find no reason to interfere with the
award of the learned Arbitrator on this count.
Claim No.6
10. Under this claim, the claimant had claimed a sum of Rs.56,985/-
on account of recovery made by DDA due to work done at risk and cost of
contractor. Against this claim, the learned Arbitrator allowed a sum of
Rs.5,332/- in respect of recoveries made by DDA for not fixing brass valves in
RCC water tanks by contractor. The Arbitrator came to conclusion that this
item was not provided under the contract so the contractor was not obliged to
provide brass valves and no deduction could be made on this count.
11. The award is challenged by the petitioner on the ground that the
Arbitrator did not go into the fact that the DDA had wither to rectify the defects
itself or to pay for rectification of these defects and therefore DDA was entitled
to recover the amount. The objector has not addressed the issues of brass
valves not being a part of the contract. I consider that practically there is no
challenge to this claim. The objection in respect of this claim is therefore
turned down.
Claim No.8
12. Under claim no. 8 the contractor claimed a sum of Rs.1,20,000/-
on account of damages due to idle labour, T & P, establishment etc. Against
this claim, the learned Arbitrator has awarded an amount of Rs. 46,350/-.
Accepting the plea of the claimant that the delay in completion of work was
due to non-availability of site, cement, delay in supplying of drawings and
details, non-availability of shutters, delay in electrical work etc. The Arbitrator
came to conclusion that since the time for executing contract was extended
without levy of penalty, the claimant was justified in claiming the amount for
deployment of extended establishment, machinery, T & P remained unutilized
to the prolongation period.
13. The award is objected by DDA on the ground that the award
was contrary to contract and no damages or compensation could have been
awarded to the contractor because of delay in handing over of site or material
or drawings. The other ground taken by the petitioner is that the Arbitrator
has not stated as to how the amount of Rs.46,350/- was calculated by him. It
is stated that it was a condition of the agreement between the parties that
upon completion of contract, the contractor will have responsibility of
maintenance of the building for six months. The Arbitrator could not have
granted claim for the period when building was under maintenance of the
contractor. The petitioner also stated that the judgment of Justice P.K.Bahari
in Suit no.1389/89 titled as M.M. Associates vs. DDA was cited and proved
as R-39 and in this judgment the High Court has observed that the Arbitrator
should not be awarded any amount on account of losses/damages claimed by
him. The Arbitrator mis-conducted himself by ignoring the judgment.
14. In the tendered documents under "Specification and Conditions"
it was specifically provided:
"1. The contractor must get acquainted with the proposed site for the works and study specifications and conditions carefully before tendering. The work shall be executed as per programme approved by the Engineer-in-Charge. If part of site is not available for any reason or there is some un- avoidable delay in supply of materials stipulated by the Department, the programme of construction shall be modified accordingly and the contractor shall have no claim for any extras of compensation on this account"
15. The plea of claimant before the Arbitrator was that the site was
not available. There were jhuggis on the site. The above clause specifically
provides that the contractor has to inspect the site before filing tenders and it
also provides that if a part of the site was not available for any reasons or
there was some non-availability, delay in supply of material supplied by the
department, programme of construction has to be modified accordingly. The
clause provides that the contractor shall have no claim for any extras or
compensation on this account. The contract used words „for any reason‟
which only means „for any reason whatsoever‟. It is clear from the above
clause that in case the work got prolonged due to non-availability of site or
due to any other reason, the work of construction was to be re-programmed,
modified (by extension of time for completing the work) and no claim for any
extra amount or compensation could be made by the contractor. In the
present case, circumstances had been rather created by the contractor for
delay in material. The cement supplied by DDA was in fact pilfered from the
spot and a truck load (250 bags of cement) was apprehended by Food and
Supply Department being removed from the site by the contractor. Thus the
ground of delay in supply of cement could not have been entertained in view
of the fact that the contractor had pilfered the material from the site. However,
the learned Arbitrator without giving any reason as to how the contractor was
entitled to compensation despite his having indulged in pilferage of material
has allowed the claim of the contractor. This Court in Sunder Lal Kharti &
Sons vs. DDA in CS(OS) 2404A/1995 observed as under:
"19. A perusal of award in respect of claim no.7 would show that learned arbitrator observed that the general conditions and specifications as relied upon by the respondent DDA would not come to the rescue of DDA because it was not a case of non supply of material but the delay was on account of non supply of drawings and decision. However, this observation of the learned arbitrator is contradictory to the contentions in claim and the observations made by learned
arbitrator at page 13 of award. The claimant had contended before the arbitrator that there was delay due to non issuance of drawings, non supply of cement, non availability of site, delay in taking decisions and non-payment of dues in time. Non issuance of drawings and decision was only one of the factors enumerated. The other factors for delay as enumerated by the claimant/ contractor were non availability of site due to presence of barracks, non issuance of cement, non-payment of dues etc. The aforesaid clauses of the contract specifically take care of the non issuance of cement, steel and other material and non availability of site. It is specifically provided that in case of any delay in providing site or material, the programme of construction has to be re- scheduled and the contractor would not be entitled for any damages. The damages have been awarded to the contractor considering the idleness of his machinery, engineer, supervisor and deployment of labour, chowkidar etc on the presumption that the contractor was having no other work and he was having one sole contract at that time. It is never a case that one contractor does one work at a time and till the work is over, he does not engage his employees, labour, machinery, engineer, supervisor at other sites. Whenever a contractor claims loss on account of prolongation of contract on the ground that he has not been able to fruitfully utilized his machines and men, the arbitrator cannot presume that the contractor was having only one contract and he had no other site of work where he could deploy his engineer and labour. It is also a known fact that the civil contractors do not employ labour, chowkidars and other workforce as their permanent workforce. The workforce is employed by the civil contractors for a specific work and for specific period when the work is going on. It is for this reason that the contract provides for maintenance of wage register so that the record is there that the contractor had been employing the workforce all along for which the contractor makes claim. In absence of any wage register, no presumption can be drawn that the contractor had really paid wages to the workforce as claimed or this workforce was being employed at site. No claim could have been allowed by the arbitrator in absence of record of employment of engineer, supervisor, chowkidar, etc. record more so when the contract specifically provides that the contractor would not be entitled for any damages in case the contract gets prolonged due to non supply of material or non availability of site. The arbitrators allowing 25% or 50% of the claimed amount, without giving reason for arriving at such percentage amounts to arbitrariness. In Bharat Coking Coal Ltd. v L.K. Ahuja 2004(5) SCC 109, the Supreme Court observed as under:
"Para 23. Claim No. 8 has been rejected by the arbitrator. Now we proceed to consider claim No. 9 for
loss arising out of turnover due to prolongation of work. The claim made under this head is in a sum of Rs.10 lakhs. The arbitrator rightly held that on account of escalation in wage and prices of materials compensation was obtained and, therefore, there is not much justification in asking compensation for loss of profits on account of prolongation of works. However, he came to the conclusion that a sum of Rs.6,00,000/- would be appropriate compensation in a matter of this nature being 15% of the total profit over the amount that has been agreed to be paid. While a sum of Rs.12,00,000/- would be the appropriate entitlement, he held that a sum of Rs.6,00,000/- would be appropriate. He also awarded interest on the amounts payable at 15% per annum.
Para 24. Here when claim for escalation of wage bills and price for material s compensation has been paid and compensation for delay in the payment of the amount payable under the contract or for other extra works is to be paid with interest thereon, it is rather difficult for us to accept the proposition that in addition 15% of the total profit should be computed under the heading "Loss or Profit". It is not unusual for the contractors to claim loss of profit arising out of diminution in turnover on account of delay in the matter of completion of the work. What he should establish in such a situation is that had he received the amount due under the contract, he could have utilized the same for some other business in which he could have earned profit. Unless such a plea is raised and established, claim for loss of profits could not have been granted. In this case, no such material is available on record. In the absence of any evidence, the arbitrator could not have awarded the same. This aspect was very well settled in Sunley (B) & Co. Ltd. v. Cunard White Star Ltd. (1940) 1 KB 740 by the Court of Appeal in England. Therefore, we have no hesitation in deleting sum of Rs.6,00,000/- awarded to the claimant."
16. I therefore hold that the award of this amount by the Arbitrator
was contrary to the contract and uphold the objections of the objection/DDA
on this count.
17. In view of my above discussion, the objections of the
respondent/DDA in respect of claims no.3 and 8 are upheld and the
objections in respect of claims no. 5 & 6 are dismissed. The award, except in
respect of claims no. 3 and 8, is made a rule of the Court.
September 11, 2009 SHIV NARAYAN DHINGRA J. ak
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!