Citation : 2009 Latest Caselaw 3627 Del
Judgement Date : 8 September, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: August 19, 2009
Date of Order: September 08, 2009
+OMP 330/2009
% 08.09.2009
M/s Jialall Kishorilall Pvt. Ltd. ...Petitioner
Through: Mr. D. Moitra, Advocate
Versus
Municipal Corporation of Delhi ...Respondent
Through: Ms. Mini Pushkarna, Advocate
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
1. The petitioner approached this Court on receipt of letter dated 28 th
May, 2009 from respondent rescinding the contract between petitioner and
respondent for construction of commercial Nalla at Gautam Nagar behind
Indian Oil Building with a prayer that the Court should stay the operation of
the letter and permit the petitioner to complete the work by August, 2009.
2. When notice of petition was served upon respondent, respondent took
a plea that there was no arbitration agreement between the parties and the
petition was not maintainable while petitioner took the stand that there exists
an arbitration agreement inter se parties. Both parties were asked to file their
respective affidavits with supporting documents.
3. A perusal of documents would show that the standard contract
Performa, which is supplied to all the contractors, contained an arbitration
OMP No.330 of 2009 M/s Jialall Kishorilall Pvt. Ltd. vs. MCD Page 1 Of 3 clause. However, this arbitration clause was scored off in the original contract
available with the respondent. The petitioner contended that this scoring off
was done later on. The petitioner had signed on each page of the contract at
the bottom and there were no specific signature of the petitioner at the
arbitration clause having been scored off. Respondent argued that the
Commissioner of MCD vide its office order dated 11th December 2006 had
ordered that the arbitration clause in various contracts forms being adopted
by MCD should be deleted with immediate effect. Pursuant to this office
order, the arbitration clause of this agreement between the parties dated 12th
December 2007 was also deleted and the contractor was very well aware of
this fact. The affidavit of Superintending Engineer filed on behalf of
respondent stated that at the time when tenders were opened he was present
and when the work was awarded in favour of contractor, the agreement was
signed in his office and the arbitration clause was specifically scored off and
the signatures of the contractor at the bottom of scored off clause were
obtained in token of its scoring. However, the counter affidavit filed by the
contractor (the petitioner herein) is contrary to the assertions made by the
Superintending Engineer and it is asserted that the signatures of petitioner
were affixed on the contract prior to the deletion of the arbitration clause and
the clause was deleted later on.
4. In my view, this controversy is unnecessary for disposal of this petition.
Even if it is presumed that there was an arbitration clause, the relief sought
by the petitioner by way of present petition cannot be granted. The petitioner
has sought cancellation of the contract done by respondent be stayed under
Section 9 of Arbitration & Conciliation Act, 1996.
5. This Court in Lt. Col. (retd). K.S. Ahluwalia v. Indraprastha Gat Ltd. 2009
OMP No.330 of 2009 M/s Jialall Kishorilall Pvt. Ltd. vs. MCD Page 2 Of 3 3 Arbitration Law Reporter 186(Delhi) observed that where a contract
between the parties stands terminated, the same cannot be kept alive by
virtue of Section 9 of Arbitration & Conciliation Act, 1996. It was not within the
jurisdiction of the Court to renew a contract between the parties or to extend
the contract between the parties. If a contract was a terminable contract and
has been terminated by a party, the opposite party has a claim to the
damages suffered by it and the same can be considered by the arbitrator
only. This Court in M/s Excel Generators Pvt. Ltd. v. IJM Corporation Berhad
OMP 241 of 2009 decided on 13th May 2009 had also observed that where a
contract is terminated or foreclosed interim relief under Section 9 cannot be
granted for specific performance of such a contract. In all those cases where
monetary damages can compensate the breach of the contract, the Court
cannot insist upon a party that the contract should be specifically performed.
Termination of a contract is one of the facets of commercial law and if a party
is agitated that the contract was wrongly terminated, the remedy lies in
claiming damages. The party cannot insist upon that the contract should be
specifically performed.
6. In view of my foregoing discussion, I find that the present
application/petition made by petitioner seeking a relief to the effect that
termination of the contract should be stayed and he be permitted to
specifically perform the contract, is not maintainable and is liable to be
dismissed. The petition is hereby dismissed. However, the order passed by
this Court is without prejudice to the rights and contentions of MCD about non
existence of the arbitration clause.
September 08, 2009 SHIV NARAYAN DHINGRA J. rd OMP No.330 of 2009 M/s Jialall Kishorilall Pvt. Ltd. vs. MCD Page 3 Of 3
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!