Citation : 2009 Latest Caselaw 4166 Del
Judgement Date : 15 October, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO(OS) No.21/2008 & CM Nos.606-607/2008
AIRPORT AUTHORITY OF INDIA.....Appellant through
Mr. Amarendra Sharan,
Sr. Adv. with Mr. P.R.
Tiwary & Mr. Amit Anand
Tiwari, Advs.
versus
HINDUSTAN STEEL WORKS ......Respondent through
CONSTRUCTION LTD. Mr. C.M. Oberoi with
Ms. Surekha Raman, Advs.
% Date of Hearing : August 21, 2009
Date of Decision : October 15, 2009
CORAM:
* HON'BLE MR. JUSTICE VIKRAMAJIT SEN
HON'BLE MR. JUSTICE RAJIV SHAKDHER
1. Whether reporters of local papers may be
allowed to see the Judgment? Yes
2. To be referred to the Reporter or not? Yes
3. Whether the Judgment should be reported
in the Digest? Yes
VIKRAMAJIT SEN, J.
1. This Appeal assails the Order of the learned Single
Judge dated 1.8.2007 referring the disputes and claims made
by the Plaintiff, namely, Hindustan Steel Works Construction
Limited, who is the Respondent before us, to the Permanent
Machinery of Arbitrators (PMA). It is noteworthy that both
the parties are „public sector enterprises‟ and hence ought to
have respected and implemented the legal regime set-down
by the Supreme Court in ONGC -vs- Collector of Central
Excise, 1992 Supp (2) SCC 432. It is indeed a matter of
regret that the Appellant, who is the Defendant in the Suit,
had elected not to do so and apart from spending large sums
of monies in frivolous and needless litigation, has exhausted a
large chunk of time available to the Courts, which we feel
could have been better utilized.
2. In the impugned Order, the learned Single Judge has
recorded the existence of an Arbitration Clause in the
General Conditions of Contract (GCC) which empowers the
Chairman, National Airport Authority (NAA) or the
Administrative Head of the NAA to appoint the Sole
Arbitrator. It appears that before the filing of the Suit, the
Plaintiff had made repeated efforts to have the disputes
referred to Arbitration, all of which met with no fruition due
to the obduracy on the part of NAA. In the first instance, the
Appellant/Defendant had called upon the Plaintiff to make
specific claims and when this was done, the request for
arbitration was declined on the ground that since more than
ninety days had elapsed, the request for arbitration contained
in Clause 25 of GCC has been rendered ineffectual. At this
juncture, the Plaintiff addressed a communication dated
10.2.2005 to the Secretary, Department of Public Enterprises,
requesting for a Reference of the claims to the PMA which
declined to intervene on the specious ground that the
Arbitration Clause did not contemplate a Reference of
disputes to the PMA. If ONGC is properly and
comprehensively understood, NAA should have welcomed the
PMA as the forum for a resolution of its disputes as an alter
ego, as it were, to the Cabinet Committee of Disputes. We
have been informed that the PMA has, in the interregnum
thereafter, issued notice to the parties hereto for entering
and completing the arbitration process. A suggestion,
however, was made by the PMA that the parties may agree to
fresh Arbitration Clause empowering the PMA to enter upon
the Reference. The Plaintiff‟s request to this effect was
declined by the Appellant/Defendant, leaving the former with
no alternative but to file a suit for the recovery of Rupees
2,95,75,162/-.
3. In response to the Plaint, the Appellant made a
complete turn around and has raised a Preliminary Objection
pertaining to the alleged non-maintainability of the suit in
view of the existence of the Arbitration Clause. The
submission made before the learned Single Judge was that it
was open to the Plaintiff/Respondent to invoke the provisions
of Section 11(b) of the Arbitration Act, 1996 (for short „A&C
Act‟) for the purposes of appointment of an arbitrator. In the
impugned Order it has been opined that once a Defendant
has repudiated the arbitration agreement, the Plaintiff could
pursue either of the two options - firstly, to file a suit for
recovery and secondly, to invoke Section 11 of the A&C Act.
The learned Single Judge has applied the decisions of the
Supreme Court in Datar Switchgears Ltd. -vs- Tata Finance
Ltd., (2000) 8 SCC 151 and S.B.P. & Co. -vs- Patel
Engineering Ltd., (2005) 8 SCC 618 to arrive at the
conclusion that the appointment in terms of Section 25 of the
GCC had been deliberately delayed, leaving it to the Court to
adopt the option of appointing an arbitrator itself.
Implementing the dicta in P. Anand Gajapathi Raju -vs- P.V.G
Raju, (2000) 4 SCC 539, the learned Single Judge has
referred the parties to arbitration in respect of all the claims
of the Plaintiff/Respondent under the aegis of the PMA.
4. Even in respect of this decision the Appellant has
decided to file the present vexatious and indubitably time-
barred Appeal. The gravamen of the ONGC, that disputes
between public sector enterprises should not be brought to
Court as a last resort, has accordingly been willfully
challenged at every conceivable stage by the Appellant,
thereby wasting scarce government resources and Court
time. It would indeed be significant to make an inquiry of the
legal costs incurred by the Appellant/Defendant in the course
of this litigation. We have touched upon the merits of the case
because we are, in the first instance, called upon to decide
the Appellant‟s Application for condonation of delay in filing
the Appeal.
5. The Application filed by the Appellant seeking
condonation of delay is carelessly cryptic and blissfully devoid
of necessary details. The non-exercise of mind is palpably
clear from the statement made in paragraph 4 of the
Application which is to the effect that - "The Petitioner most
humbly pray that the delay in filing Special leave petition
may be condoned in the interest of Justice." The narration of
facts, which may be germane for the Court to reach a
decision whether or not to condone the delay in filing the
Appeal, are as follows:-
2.(a) The Hon‟ble High Court delivered its judgment on 1.8.2007. It is submitted that the application for certified copy of the impugned order was moved on 3.8.2007and the certified copy was made ready on
18.9.2007. The Advocate sent the copy to department of law, Airport Authority of India and thereafter the Department of Law sent the copy to Directorate of Engineering Southern Region. On 18.10.2007 General Manager (Engg.) informed to the General Manager Airports Authority of India. Since the present matter is purely a legal issue, therefore only legal wing can take final decision.
(b) It is after that file has been sent to Chairman Airport Authority of India to take final decision.
(c) Thereafter the Airport Authority sent the papers to advocate for drafting the FAO(OS). The drafting counsel after preparing FAO(OS) returned the file to Airport Authority of India.
(d) After receiving the reasons for day to day delay the Airport Authority of India sent the file to the drafting counsel on 23.11.2007 on the drafting counsel after preparing the applicant sent the same to the Airport Authority of India. ....
(3) That the above is sole cause of delay. There is sufficient cause which has prevented not to file present LPA within a period of 30 days. The delay was not intentional but due to aforesaid circumstances.
6. The Appellant has not considered it necessary to
disclose to the Court the "reasons for the day to day delay"
stated in paragraph 2(d) of the Application. In fact, the
reasons for delay have not been spelt out at all. Since no
reasons have been presented in the Application, referring to
the circumstances in which their Lordships had condoned the
delay in several cases, including State of Bihar -vs-
Kameshwar Prasad Singh, (2000) 9 SCC 94, can be of no avail
to the Appellant. In any event, what ought not to be lost sight
of is the fact that the learned Single Judge had referred the
parties to the arbitration of the PMA, which, in the tenor of
the ONGC decision, is best and ideally suited to resolve the
disputes between the public sector enterprises. Furthermore,
on the failure of the Appellant to appoint an arbitrator and in
light of its reliance on the Arbitration Clause in defence to the
suit for recovery filed by the Respondent, the learned Single
Judge was fully empowered to appoint an arbitrator, which is
precisely what it has done in the present case.
7. Shree Subhlaxmi Fabrics(P) Ltd. -vs- Chand Mal
Baradia, (2005) 10 SCC 704, a Two Judge Bench has held in
paragraph 14 that the question whether an Arbitration Clause
in fact existed should properly be decided by the Arbitral
Tribunal. In India Household and Healthcare Ltd. -vs- LG
Household and Healthcare Ltd., (2007) 5 SCC 510 the
learned Single Judge has observed that "as and when a
question in regard to the validity or otherwise of the
arbitration agreement arises, a judicial authority would have
the jurisdiction under certain circumstances to go into the
said question". The definitive opinion on this legal labyrinth is
available in paragraph 19 of the Seven Judge Bench decision
in Patel Engineering Ltd. which reads thus:-
19. It is also not possible to accept the argument that there is an exclusive conferment of jurisdiction on the Arbitral Tribunal, to decide on the existence or validity of the arbitration agreement. Section 8 of the Act contemplates a judicial authority before which an action is brought in a matter which is the subject of an arbitration agreement, on the terms specified therein, to refer the dispute to arbitration. A judicial authority as such is not defined in the Act. It would certainly include the court as defined in Section 2(e) of the Act and would also, in our opinion, include other courts and may even include a special tribunal like the Consumer Forum (see Fair Air Engineers (P) Ltd. v. N.K. Modi (1996) 6 SCC 385). When the defendant to an action before a judicial authority raises the plea that there is an arbitration agreement and the subject-matter of the claim is covered by the agreement and the plaintiff or the person who has approached the judicial authority for relief, disputes the same, the judicial authority, in the absence of any restriction in the Act, has necessarily to decide whether, in fact, there is in existence a valid
arbitration agreement and whether the dispute that is sought to be raised before it, is covered by the arbitration clause. It is difficult to contemplate that the judicial authority has also to act mechanically or has merely to see the original arbitration agreement produced before it, and mechanically refer the parties to an arbitration. Similarly, Section 9 enables a court, obviously, as defined in the Act, when approached by a party before the commencement of an arbitral proceeding, to grant interim relief as contemplated by the section. When a party seeks an interim relief asserting that there was a dispute liable to be arbitrated upon in terms of the Act, and the opposite party disputes the existence of an arbitration agreement as defined in the Act or raises a plea that the dispute involved was not covered by the arbitration clause, or that the court which was approached had no jurisdiction to pass any order in terms of Section 9 of the Act, that court has necessarily to decide whether it has jurisdiction, whether there is an arbitration agreement which is valid in law and whether the dispute sought to be raised is covered by that agreement. There is no indication in the Act that the powers of the court are curtailed on these aspects. On the other hand, Section 9 insists that once approached in that behalf, "the court shall have the same power for making orders as it has for the purpose of and in relation to any proceeding before it". Surely, when a matter is entrusted to a civil court in the ordinary hierarchy of
courts without anything more, the procedure of that court would govern the adjudication (see R.M.A.R.A. Adaikappa Chettiar v. R. Chandrasekhara Thevar, AIR 1948 PC 12.)
8. The following observations in K.V. Aerner Cementation
India Ltd. -vs- Bajranglal Agarwal, IV(2001) SLT 535 = 2001
(6) Supreme 265 are noteworthy even though it needs to be
clarified that when a Civil Court is called upon to pass an
injunction order under Section 9 of the A&C Act, it must be
satisfied that it enjoys jurisdiction under that Act:-
....the petitioner contends that the jurisdiction of the civil Court need not be inferentially held to be ousted unless any statute on the face of it excludes the same and judged from that angle when a party assails the existence of an arbitration agreement, which would confer jurisdiction on an arbitral Tribunal, the Court committed error in not granting an order of injunction. There cannot be any dispute that in the absence of any arbitration clause in the agreement, no dispute could be referred for arbitration to an arbitral Tribunal. But, bearing in mind the very object with which the Arbitration and conciliation Act, 1996 has been enacted and the provisions thereof contained in Section 16 conferring the power
on the arbitral Tribunal to rule on its own jurisdiction including ruling on any objection with respect to existence or validity of the arbitration agreement, we have no doubt in our mind that the Civil Court cannot have jurisdiction to go into that question. A bare reading of Section 16 makes it explicitly clear that the arbitral Tribunal has the power to rule on its own jurisdiction even when any objection with respect to existence or validity of the arbitration agreement is raised and a conjoint reading of sub-sections(2), (4) and (6) of Section 16 would make it clear that such a decision would be amenable to be assailed within the ambit of Section 34 of the Act. In this view of the matter, we see no infirmity with the impugned order so as to be interfered with by this Court. The petitioner who is a party to the arbitral proceedings may raise the question of jurisdiction of the Arbitrator as well as the objection on the ground of non-existence of any arbitration agreement in the so- called dispute in question and such an objection being raised, the Arbitrator would do well in disposing of the same as a preliminary issue so that it may not be necessary to go into the entire gamut of arbitration proceedings.
9. In Patel Engineering Ltd. the Court had itself
formulated the question that had been posed before it to be
what is the nature of the function of the Chief Justice or his
designate under Section 11 of the A&C Act. Their Lordships
returned twelve conclusions, of which the fourth is pertinent
to the conundrum before us, viz. - "The Chief Justice or the
designated Judge will have the right to decide the preliminary
aspects as indicated in the earlier part of this judgment.
These will be his own jurisdiction to entertain the request,
the existence of a valid arbitration agreement, the existence
or otherwise of a live claim, the existence of the condition for
the exercise of his power and on the qualifications of the
arbitrator or arbitrators. The Chief Justice or the designated
Judge would be entitled to seek the opinion of an institution
in the matter of nominating an arbitrator qualified in terms of
Section 11(8) of the Act if the need arises but the order
appointing the arbitrator could only be that of the Chief
Justice or the designated Judge". The neat and vexed
question which arises is whether such a decision is final or
prima facie in nature, especially in view of Section 16 of the
A&C Act which imparts to the Arbitral Tribunal the power to
rule on its own jurisdiction, including ruling on any objection
with respect to the existence or validity of the arbitration
agreement. In paragraph 19 their Lordships in Patel
Engineering Ltd. (reproduced above) have opined that
before passing an interim order under Section 9 of the A&C
Act it is necessary for it to decide whether it has jurisdiction
and/or whether there is a valid arbitration agreement and/or
whether the dispute is covered by that Agreement. It appears
to us that the conclusion arrived at by the Court in such
circumstances would be binding on the Arbitral Tribunal
since the Court would not grant interim relief unless it was
positively satisfied that it possessed and could exercise
jurisdiction under the A&C Act. It appears to us that the
situation is different when the Chief Justice or his designate
discharges the functions, albeit judicial, postulated under
Section 11(6) of the A&C Act. While doing so, it may direct
parties in the direction of the Arbitral Tribunal, leaving it
open to the Arbitral Tribunal to rule on its own jurisdiction,
including ruling on any objection with respect to the
existence or validity of an arbitration agreement. This is
despite the fact that it is now well-settled that it is a judicial
function that is performed under Section 11(6) of the A&C
Act. We are of the opinion that the judge exercising powers
under Section 11(6) should clearly indicate whether it has a
prima facie or final ruling on the existence or validity of the
arbitration agreement.
10. We cannot lose sight of the fact that an appointment
made under Section 11(6) of the A&C Act is not appealable,
as would be evident from a reading of Section 37 of the said
Act. In this context, we think it necessary to briefly discuss
Ludhiana Improvement Trust -vs- Today Homes and
Infrastructure Pvt. Ltd., (2008) 10 SCC 715 to dispel any
discussion on this very interesting aspect of the law. Their
Lordships had clarified that all appointments made under
Section 11(6) of the A&C Act prior to Patel Engineering
Ltd. would be valid, leaving it to the parties to raise
objections to the existence or validity of an arbitration
agreement before the Arbitral Tribunal. Their Lordships have
not stated that post Patel Engineering Ltd. the statutory
provisions of Section 16 have been rendered otiose. A
harmonious construction of both provisions convinces us to
conclude that while exercising its judicial functions under
Section 11(6), the Judge may give either a prima facie or a
final finding on that point. To this, we add that as presently
advised, we will lean towards a prima facie character of the
opinion, leaving it to the Arbitral Tribunal to give a detailed
final finding. The enunciation in Shin-Etsu Chemical Ltd. -vs-
Aksh Optfiber Ltd., AIR 2005 SC 3766 : (2005) 7 SCC 234
should be noted here even though it was in the context of
Section 45 of the A&C Act. Firstly, their Lordships opined
that the ratio of General Electric Company -vs- Renusagar
Power Company, (1984) 4 SCC 679 could not be extrapolated
into cases post A&C Act because the avowed intention of the
Legislature was to minimize curial interference in
arbitrations since it would invariably cause delays in the final
adjudication of disputes. Secondly, if the decision to refer
parties to the Arbitral Tribunal was not prima facie but final,
the challenge to the Award on this ground would be
foreclosed because of res judicata. This would work injustice
for the reason that a final finding would have been given on
insufficient material and not after a full-fledged adjudication.
We think it proper to reiterate that Patel Engineering Ltd.
prescribes that before granting relief under Section 9 of the
A&C Act the Court must be fully satisfied with regard to the
existence of an arbitration clause (see paragraph 19). Their
Lordships did not opine that this finality should be present in
other decisions under the A&C Act. This position commends
itself to us also, Firstly for the reason that by virtue of Section
34(2)(a)(ii) as well as Section 48(1) of the A&C Act an
arbitral award may be set aside by the Court if the arbitration
agreement is not valid under the applicable law; Secondly,
for the reason that Section 16 of the A&C Act, which extends
the legislative intent of minimal curial interference by
enabling the Arbitral Tribunal to rule on any objections with
respect to existence or validity of the arbitration agreement
or even on its own jurisdiction etc., would become otiose.
Finally, the avenue to assail the conclusion of the Arbitral
Tribunal on this point either under Section 34 or Section 48
of the A&C Act should not be rendered untraversable. In
these circumstances, it is built into the statutory framework
that a Court will have a final say on the important aspect of
the existence or validity of an arbitration agreement.
11. As no grounds or facts whatsoever have been disclosed
which we may have seen as sufficient for condoning the delay
in preferring the present Appeal, it is liable for dismissal on
this short ground. However, assuming that delay stands
condoned, we are of the view that the Appeal is not
maintainable, leaving it to the parties to raise all issues
available to them in law before the Arbitral Tribunal. It is
ordered accordingly. Pending applications also stand
dismissed. Furthermore, since both the parties are public
sector enterprises, we are convinced that they cannot have
any cavil to the resolution of their disputes by the PMA, of the
Bureau of Public Enterprises, which functions under the
Central Government.
12. Since the adversaries are public sector enterprises, we
would not like to compound the immense wastage of finances
by imposing costs.
13. A copy of this Order be dispatched to the PMA for
further requisite action on expeditious speed.
( VIKRAMAJIT SEN )
JUDGE
( RAJIV SHAKDHER )
October 15, 2009 JUDGE
tp
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!