Citation : 2009 Latest Caselaw 4124 Del
Judgement Date : 13 October, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS)2143/2002 & OMP 21/2004
% Date of decision: 13th October, 2009
M/S KARAM CHAND THAPAR ....Petitioner
& BROS(CS) LTD
Through: Mr. P. Mishra, Sr Advocate with Mr
Sandeep Sharma, Advocate
Versus
NATIONAL HYDROELECTRIC POWER CORP...Respondent
& ANOTHER
Through: Mr. S.K. Taneja, Sr Advocate with Mr
Sachin Datta and Ms Shaila Arora, Advocates.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? No
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported
in the Digest? No
RAJIV SAHAI ENDLAW, J.
1. CS(OS) 2143A/2002 was registered on the filing of a petition
under section 14 of the Arbitration Act 1940 for directing the
arbitrator to file the original interim award dated 22nd November,
2002 in this court alongwith the entire arbitration
proceedings/record. Vide order dated 3rd January, 2003 the
arbitrator was directed to file the award and proceedings in this
court. The petitioner even without awaiting the filing of the award by
the arbitrator in this court filed IA.No. 5933/2003 under Sections 30
and 33 of the 1940 Act for setting aside the interim award dated 22 nd
November, 2002. The pleadings in the said application have been
completed. OMP 21/2004 was filed under Sections 5,11 and 12 of
the 1940 Act for revoking the authority of the arbitrator, so as to
prevent him from proceeding further with the arbitration
proceedings after the interim award aforesaid and for appointment
of an arbitrator in his place. Vide order dated 23rd January, 2004 in
the OMP though further proceedings before the arbitrator were
allowed to be continued, it was ordered that the arbitrator shall not
pass the final award. The said order has remained in force. The
counsels have informed that though the arbitrator has concluded the
proceedings and even heard arguments, however, the award has not
been published owing to the order aforesaid in these proceedings. It
was further informed that the arbitrator who is a retired judge of the
Allahabad High Court is over 83 years of age.
2. The senior counsel for the petitioner contended that if this
court were to allow the OMP, the ground for revocation of authority
wherein is the bias of the arbitrator in favour of the respondent, the
interim award against which objections have been filed in CS(OS)
2143A/2002 would also become liable to be set aside.
3. In the OMP the grounds taken for revocation of authority of
the arbitrator are, the arbitrator acting in a high handed fashion in
the matter of hearings preceding the interim award and pronouncing
the interim award. It is pleaded that the interim award given by the
arbitrator has shaken the faith of the petitioner in the conduct of the
arbitration proceedings by the arbitrator; a letter dated 30 th
December, 2002 is also stated to have been written by the petitioner
to the arbitrator in this regard expressing their loss of faith in the
arbitrator. The interim award subject matter of challenge in CS(OS)
2143A/2002 is on the arbitrability of the claims of the petitioner
against the respondent. The arbitrator has held some of the claims
of the petitioner to be not arbitrable. The said interim award is inter
alia challenged and it is also a ground in the OMP that the arbitrator
rushed into pronouncing on the arbitrability of the claims though the
contention of the petitioner before the arbitrator was that the said
arbitrability could not be gone into without adducing evidence; the
arbitrator is alleged to have disregarded the said submission of the
petitioner and rushed into making the interim award. It is also
pleaded in the OMP that subsequent claims of the petitioner against
the respondent with respect to the same contract were referred to
the arbitration of Justice H.C. Goel (Retd) of this court vide order
dated 10th April 2003 in Arbitration Application 299/2000 and it is
prayed that after revoking the authority of the arbitrator in this case,
the disputes subject matter of these cases be also referred to Justice
H.C. Goel. During the hearing it was informed that Justice H.C. Goel
has since recused himself and petition is pending in this court for
appointing a substitute arbitrator.
4. The petitioner has also filed I.A.No. 3193/2004 in the OMP
stating that it has come to know that the arbitrator whose authority
is sought to be revoked is the panel arbitrator of the respondent and
has been doing a number of arbitrations for the respondent and has
in all arbitrations to which the respondent is a party given an award
in favour of the respondent; it is further alleged in this application
that to the knowledge of the petitioner the arbitrator is paid a
monthly salary as fee by the respondent for doing the arbitration
matters; information was sought from the respondent in this regard;
the petitioner also filed copies of arbitral awards in other arbitration
proceedings in which the respondent was party and in which the
awards were published in favour of the respondent by the same
arbitrator.
5. The respondent in pursuance to the directions of this court on
25th August, 2004 in the OMP filed an affidavit verified on 9th
October, 2004 of its Deputy Manager (Civil) and in which it is stated
that the arbitrator is on the panel of arbitrators of the respondent;
that the arbitration with the petitioner is the only ongoing arbitration
of the respondent before the same arbitrator; that the other
arbitration proceedings of the respondent were before other
arbitrators; that the same arbitrator has acted as the arbitrator in
only ten arbitrations of the respondent; that the awards passed by
the same arbitrator in none of those arbitrations has been set aside
by any court; it was denied that any monthly salary / fee was paid by
the respondent to the arbitrator and it was stated that the
arbitrator's fee was shared by both parties to the arbitration in all
the cases and no extra remuneration had at any time been given by
the respondent to the said arbitrator. In fact, allegations of abuse of
process of this court are made against the petitioner. It is contended
that the petitioner surreptitiously, while seeking the order for filing
of interim award in this court also sought the order of calling for
arbitral record in this court and which resulted in scuttling the
further arbitration proceedings before the arbitrator, of stay whereof
there was no order also from this court.
6. To complete the narrative of facts, in the interim award dated
22nd November, 2002 under challenge, the arbitrator has held the
1940 Act to be applicable to the arbitration proceedings and negated
the contention of the petitioner of the applicability of the 1996 Act.
The senior counsel for the petitioner has not challenged the said part
of the interim award.
7. The arbitrator has by the interim award dated 22nd
November, 2002 adjudicated the plea of the respondent of the claims
of the petitioner being not arbitrable. The petitioner had made
seven claims against the respondent. The arbitrator has held claims
1, 3, 6 and 7 to be arbitrable and held claims 2, 4 and 5 to be not
arbitrable.
8. The arbitrator in deciding the arbitrability has relied upon
General Manager, Northern Railway Vs Sarvesh Chopra (2002)
4 SCC 45. According to the arbitrator, the Supreme Court in the
said judgment has carved out two exceptions to the arbitrability i.e.,
those claims which as per the terms and conditions of the contract
are simply not entertainable and secondly those which under the
terms and conditions of the contract are liable to be adjudicated
upon by an authority, in Sarvesh Chopra of the Railways and in the
present case of the respondent; whose decision the parties have
agreed to treat as final and binding and hence not arbitrable. The
arbitrator has held claims 2, 4 and 5 to be not entertainable, i.e.,
with respect whereto the contract provides that no claim shall be
entertained, even though no `in house' mechanism for settling such
claims is provided in the contract.
9. The senior counsel for the petitioner has contended that
when the same person is repeatedly appointed as the arbitrator by a
party, it creates an apprehension as to the impartiality of that
arbitrator. Reliance is placed on Nandyal Cooperative Spinning
Mills Vs K.V.Mohan Rao (1993) 2 SCC 654. He has further
contended that the plea of bias can never be conclusively
proved/made out and the court can act only on the basis of
circumstances. Reliance is placed on Amarchand Lalitkumar Vs
Shree Ambica Jute Mills Ltd AIR 1966 SC 1036 laying down the
criteria and the approach of the court in exercising the power to
revoke the authority of the arbitrator. It is contended that repeated
appointment by the respondent of the same arbitrator is a
disqualification and raises a justifiable doubt to the petitioner as to
why the respondent is relying upon one person only as the arbitrator.
Reference is made to Roshan Lal Sethi Vs The Chief Secretary
AIR 1971 J&K 91 to contend that authority of arbitrator can be
revoked on mere likelihood of bias. It is contended that the arbitrator
in the present case has prejudged the matter. The judgments in
International Airports Authority of india Vs K.D. Bali AIR 1988
SC 1099 and in Ranjit Thakur Vs Union of india AIR 1987 SC
2386 on, what is bias, have also been cited. It is urged that the
arbitrator sought to be removed is a "stock arbitrator" of the
respondent and the awards made by him in cases involving the
respondent, and in which other parties were large construction
companies, are under challenge. In response to another objection of
the respondent of the challenge to the order dated 22nd November,
2002 (interim award) being not maintainable at this stage, reliance is
placed on Satwant Singh Sodhi Vs State of Punjab (1999) 3 SCC
487 and National Thermal Power Corporation Vs Siemens
Atiengesellschaft 2005 2 ARBLR 172 Delhi to contend that where
the award is final and will have force without the delivery of the final
award, it is final for the objections to be preferred with respect
thereto and to draw a distinction between the interim award and a
final award.
10. The senior counsel for the petitioner while addressing on the
objections to the interim award drew attention to the arbitration
clause contained in clause 55.1 of the General Conditions of the
contract and which is as under:
"55.1. Except as otherwise provided, in clause 53 hereinbefore,
all questions, disputes or differences in respect of which the
decision has not been final and conclusive arising between
the contractor and the corporation, in relation to or in
connection with the contract shall be referred for
arbitration in manner provided as under : ..........."
Clause 53 is as under:
"Clause 53. Finality Clause
it shall be accepted as an inseparable part of the contract
that in matters regarding materials, workmanship, removal of
improper work, interpretation of the contract drawings and
contract specifications, mode of procedure and the carrying
out of the work as stipulated in the clause numbers 7, 8, 10,
13,17,18,21,23,24,29,32,34,37,38,40,41 and 44 the decision
of the Engineer-in-charge which shall be given in writing,
shall be final and binding on the contractor."
11. The claim No.2 of the petitioner which the arbitrator has held
to be not arbitrable was an account of use of higher size diameter of
steel in casting precast concrete lagging, than 6 mm diameter steel
bars as provided for in the drawings. It was inter alia the case of the
petitioner that the drawings in which the diameter of steel bars was
shown as 6 mm and on the basis whereof the costs had been
calculated by the respondent were supplied to the petitioner late but
even prior thereto the petitioner under supervision of / instruction of
the official of the respondent had been made to use the steel bars of
a higher diameter resulting in additional costs to the petitioner. The
arbitrator has held the said claim to be not arbitrable on the basis of
clause 21.2 of the agreement providing that the contractor shall not
be entitled to any additional payment over and above the unit price
contracted for various items of work, on account of variation in
dimension of structure, layout, design and details of work during the
execution of the work.
12. The arbitrator on an interpretation of Sarvesh Chopra
(supra) to the effect that the claims, which under the terms of the
contract were not entertainable or allowable were not arbitrable,
held the claim of the petitioner on account of use of higher diameter
steel bars not arbitrable.
13. The senior counsel for the petitioner has also contended that
the respondent, in its pleadings before the arbitrator did not
controvert that the drawings were given by the respondent to the
petitioner after the work using the aforesaid diameters steel bars
had been carried out; that the petitioner till the delivery of the said
drawings could not know the diameter of steel bar of which price
had been provided; that the officials of the respondent had for
geological reasons advised the petitioner to use the steel bars of a
higher diameter; that the bar in clause 21.2 (supra) is only of quoted
items and would not apply to the items which the petitioner during
the execution of the work is directed to use. It is argued that the 10
MM steel diameter of steel in claim No.1 is not provided in the
contract but only in the drawings. It is further contended that under
sub-clause (6) of the Arbitration clause 55, where the claims are of
over Rs 1 lac, the arbitrator is required to give reasons. It is
contended that the arbitrator has while holding claim No.2 to be not
arbitrable neither given any reason nor discussed the pleas of the
petitioner.
14. Claim No.4 of the petitioner was for extra expenses incurred
due to disproportionate increase in minimum wages not
compensated by the escalation formula. The arbitrator has held the
said claim also to be not arbitrable for the reason of clause 29.13 of
the contract prohibiting any claim on account of the contractor being
required to perform his obligation under the contract. Clause 29.5
provides for the contractor being liable to pay minimum wages.
15. The senior counsel for the petitioner has contended that
there was a delay of three years and three months and for which
period the contract time was extended by the respondent without
demur. Pleadings in OMP are relied on to demonstrate that the
delay was attributable to the respondent. It is further urged that the
respondent had allowed the petitioner to continue with the works
even after the expiry of the time and thus the clause 29.13 applicable
during the term of the contract would not come into play. Reliance
is placed on para 16 of Sarvesh Chopra (supra) to contend that
whether a particular matter is excepted or not is to be decided after
considering the relevant material - it is urged that the arbitrator in
the present case has decided without considering any material or
without giving any opportunity to the petitioner to lead evidence.
Reliance is also placed on the pleadings in the objections to the
award to contend that there is no express/specific denial by the
respondent to the factual pleas in the objections also. The senior
counsel for the petitioner also relies upon Paragon Constructions
(India) Pvt Ltd Vs UOI 2008 II AD (Delhi) 502 where a Single
Judge of this court has held that claims for prolongation of the
contract cannot be blocked by a no claim clause inasmuch as such
claims are by way of damages under Section 73 of the Contract Act.
I may however notice that in the said judgment the arbitrability was
not in question. Reliance is also placed on K.R. Raveendranathan
Vs State of Kerala (1998) 9 SCC 410. However, in that case the
Supreme Court only held that the court could not take upon itself the
burden of saying whether the claim was contrary to the contract or
not. The said two judgments are thus not found applicable. The
senior counsel for the petitioner next contended that the clause
29.13 aforesaid bars a claim only during the term of the contract but
not for a period beyond the terms of the contract.
16. Though no express arguments with respects to the claim No.
5 are addressed, the pleas in the objections with respect thereto are
the same as with respect to the claim No.4 aforesaid.
17. Per contra, the senior counsel for the respondent has
contended that the petitioner had in the present case instituted a
suit under Section 20 of the Arbitration Act, 1940 for appointment of
arbitrator being suit No. 1526A/1995; that the respondent had at
that stage only taken the plea of the claims of the petitioner being
not arbtirable; that the said suit was disposed of vide order dated
10th April, 2001 leaving the question of arbitrability also to be
decided by the arbitrator. It is further contended that it is not as if
the arbitrator is the nominee of the respondent; in the order dated
10th April, 2001 aforesaid it was provided that the respondent shall
send a panel of three names of retired judges of the High Court to
the petitioner and the petitioner out of the said panel will select one
to be appointed as the sole arbitrator in terms of the arbitration
agreement between the parties; it is contended that it is the
petitioner which has chosen the name of the arbitrator sought to be
removed, to be the sole arbitrator pursuant to the order aforesaid.
The respondent has also controverted the plea of the petitioner of
the arbitrator having not given appropriate opportunity to the
petitioner to address on arbitrability. It is contended that this court
in order dated 10th April, 2001, with the consent of the parties,
directed that the arbitrator will "first decide" the objection regarding
arbitrability of the disputes and thereafter proceed to decide the
disputes in accordance with law. It is thus contended that no bias,
irregularity or misconduct can be attributed to the arbitrator in first
deciding the aspect of the arbitrability. It is further urged that the
record of the arbitrator shows that the arbitrator heard the counsel
for the parties on five dates of which three were taken by the counsel
for the petitioner, qua arbitrability. It is also contended that in fact
it is the petitioner which after the interim award dated 22nd
November, 2002 aforesaid, on 5th December, 2002 took time to file
evidence but thereafter changed its advocate and then wrote letter
dated 30th December, 2002 for the first time alleging bias against the
arbitrator. It is contended that the order was surreptitiously
obtained from this court calling for the arbitral record also and not
merely the interim award and which resulted in further proceedings
before the arbitrator being held up. It is urged that the petitioner,
at the time of hearing on arbitrability before the arbitrator, did not
take a stand that the arbitrator should record the evidence first
before adjudicating on arbitrability. It is also argued that in fact
there is no interim award and only an order and objections at this
stage do not lie. On query as to what is the remedy of the petitioner,
being aggrieved by the interim award/order, the senior counsel for
the respondent contends that earlier there was a practice of
preferring petitions under Article 227 of the Constitution of India
before this court challenging the finding of the arbitrator on
arbitrability.
18. The senior counsel for the respondent has further urged that
the petitioner has not filed affidavit of its counsel who had appeared
before the arbitrator or of any other official of the petitioner
appearing before the arbitrator to the effect that any request was
made to the arbitrator for adjudicating the arbitrability after
recording evidence. The senior counsel for the respondent relies on
judgment of the Single Judge of this court in G Vijayaraghavan Vs
M.D., Central Warehousing Corporation 2003 (3) Arb LR 35 in
which Nandyal (supra) was also considered. Reference is also made
to M/s Setech Electronics Ltd Vs K.N. Memani 77 (1999) DLT
759 where another Single Judge of this court on the allegations in
that case, held no case of bias or revocation of authority of arbitrator
to be made out.
19. Reliance is placed on M/s Uttam Singh Duggal & Co. Pvt
Ltd Vs M/s Hindustan Steel Ltd AIR 1982 MP 206 where the
Division Bench held an order of the arbitrator on a preliminary issue
relating to jurisdiction to be not an interim award and no appeal
there against being maintainable. On the same aspect reliance is
also placed on Union of India Vs M/s East Coast Boat Builders &
Engineers AIR 1999 Delhi 44 though under the 1996 Act.
20. On the merits of the award, besides Sarvesh Chopra (supra)
forming the fulcrum of the interim award under challenge, reliance
is also placed also on Rajasthan State Mines and Minerals Ltd Vs
Eastern Engineering Enterprises (1999) 9 SCC 283 where also
the Supreme Court held that an award made by the arbitrator
disregarding the terms of the reference or the arbitration agreement
or the terms of the contract would suffer from a jurisdictional error;
that an arbitrator cannot award an amount which is ruled out or
prohibited by the terms of the agreement; because of a specific bar
stipulated by the parties in the agreement that claim could not be
raised - even if it is raised and referred to arbitration because of a
wider arbitration clause such claim amount cannot be awarded as
the agreement is binding on the arbitrator and the arbitrator has to
adjudicate as per the agreement.
21. On merits it is also urged that the Manager (Civil) of the
respondent who is stated to be the Engineer in Charge had vide
letter dated 27th June, 1992 held the claim No. 2 of the petitioner to
be untenable. Vis-à-vis the claims 4 and 5 it is stated that clause No.
29.13 is applicable not only during the term of the agreement only
but till the completion of the works and no claim for enhancement in
minimum wages even after the expiry of term of the contract can be
made in terms thereof also. The senior counsel for the respondent
contended that in the present case all the three claims held by the
arbitrator to be non-arbitrable were raised before the Engineer in
charge also and were negated after hearing; it is contended that the
same is borne out from the correspondence. However, the senior
counsel admits that the arbitrator has not dealt with the said aspect
in the award.
22. The senior counsel for the petitioner in rejoinder has urged
that the findings of the arbitrator on claim No.1 and on claims 4 and
5 are inconsistent. It is contended that claim No.1 has been held to
be arbitrable notwithstanding there being no basis therefor in the
agreement or for any in house determination for such a dispute. On
the contrary, in the same facts claims 4 and 5 are held to be not
arbitrable. It is further contended that the respondent had vide
letter dated 28th June, 1993 rejected the claim No.3 of the petitioner
also but the arbitrator has held the same to be maintainable. It is
denied that there is any decision of the Engineer-in-charge with
respect to the claims held to be not arbitrable. It is also contended
that this court should strike down any clause in the agreement even
if making a claim non-arbitrable as unconscionable inasmuch as the
petitioner cannot be deprived of a remedy. It is contended that the
parties having agreed on arbitration, there is no justification for
holding some claims to be arbitrable and others not. It is also urged
that the arbitrator has not even considered the entire clause 21.2 on
the basis whereof claim No.2 has been held to be non-arbitrable.
23. In the aforesaid state of affairs, three issues requiring
determination can be culled out:
A. what is the nature of the interim award / order dated 22 nd
November, 2002 and what remedy, if any, lies there against;
B. whether the authority of the arbitrator is liable to be revoked
and a new arbitrator is to be appointed and;
C. whether the interim award if objections there against are
permissible at this stage is liable to be set aside.
24. As far as the first of the aforesaid is concerned, the 1940 Act
unlike the 1996 Act did not provide for any appeal against the order
of the arbitrator holding a claim to be not arbitrable. In the absence
of any such provision, in my view the question posed does not really
arise for consideration. Upon the arbitrator holding the particular
claims to be not arbitrable, the only remedy there against can be by
way of proceedings under Sections 14, 30 and 33 of the Act. It is
nobody's case that the aggrieved party in such a situation is
remedyless or has no other recourse. The senior counsel for the
respondent had also suggested the recourse of Article 227 of the
Constitution of India. However, since the finding of the arbitrator
against arbitrability has an element of finality and of rejection of the
claim at least before the arbitrator, I do not see any reason as to why
the same could not be treated as interim award within the meaning
of Section 27 of the 1940 Act. As far as the claims which are held to
be not arbitrable, the arbitration proceedings would stand
terminated and no purpose would be served in requiring the
aggrieved party to wait till adjudication of the claims held to be
arbtirable to make a challenge to the finding of the arbitrator of
arbitrability then only. It has not been argued that the facts in this
case are so - as to render it impossible or inconvenient for this court
to return a finding on arbitrability at this stage or which will cause
prejudice to the adjudication of the other claims of the petitioner. If
that be so, in a particular case the court may defer the decision on
the objections qua the arbitrability till the decision on the claims
held arbitrable by the arbitrator. That being not the case, in my
view the present suit and the objections for setting aside of the
award are maintainable. I respectfully disagree with the Division
Bench of the Madhya Pradesh High Court in this regard.
25. The second question to be considered is of the revocation of
authority of the arbitrator. Such revocation was sought in the OMP
on the ground of misconduct in the proceedings leading to the
interim award. Subsequently as aforesaid the plea of the arbitrator
being the stock arbitrator of the respondent was also taken. The
appointment of the arbitrator at least in the present case was not as
the nominee of the respondent. The said appointment was pursuant
to the order dated 10th April, 2001 of this court in suit No.
1526A/1995. Thus, it is not as if the respondent imposed the
arbitrator on the petitioner. The respondent in accordance with the
order, furnished a panel of three names of retired judges of the High
Court to the petitioner including that of the said arbitrator and it is
the petitioner who selected the name of the arbitrator sought to be
removed out of the said panel. Of course, the senior counsel for the
petitioner has contended that the petitioner was then not aware of
the said arbitrator being the stock arbitrator of the respondent.
However, in my view the same would also be immaterial. The courts
have from time to time upheld the validity of arbitration clauses
enabling one of the parties only to appoint the arbitrator. Whenever
such authority / power is given to one of the contracting parties, that
contracting party would accordingly appoint someone in which faith
is reposed by that party. If that party is involved in a number of
arbitrations, the same person may be appointed as the arbitrator in
all the arbitrations. That alone in my view would not constitute a
ground for bias. Moreover, in the present case I find that no
objection whatsoever as to the procedure adopted by the arbitrator
was raised till the making of the interim award or in fact for more
than one year thereafter. The pleas of bias came to be made only
when the arbitrator decided against the petitioner on the matter of
arbitrability. An aggrieved party cannot be permitted to make such
allegation of bias for the reason of an unfavourable order. If the
same were to be permitted, it would prevent the people, not willing
to have their names dragged into controversy, from acting as
arbitrators.
26. In this regard another contention of the senior counsel for the
petitioner may also be noticed. It was suggested that the fact that
the arbitrator notwithstanding objection by the petitioner was
insisting upon continuing, speaks volumes of the bias of the
arbitrator. I am unwilling to accept the said proposition also. If the
same were to be upheld, it would give a handle to unscrupulous
litigants to unreasonably delay the arbitral proceedings by raising
allegations against the arbitrator. In Eckersley Vs Mersey Dock
and Harbor Board 1894 2 QB 667 quoted with approval in Indian
Oil Corporation Vs Raja Transport Pvt Ltd MANU/SC/1502/2009
it has been held that the rule which applies to a judge or other
person holding judicial office, namely, that he is not to hear cases in
which he might be suspected of bias in favour of one of the parties
does not apply to an arbitrator named in a contract to whom the
parties have agreed to refer disputes which may arise between them
under it. It was further held that in order to satisfy the court that
such an arbitrator is disqualified from acting, circumstances must be
shown to exist which establish at least the probability that he will in
fact be biased in favour of one of the parties in giving his decision.
In my view the same rule will apply even in the cases of appointment
of an arbitrator as in the present case or where the arbitrator is
stated to be the arbitrator in several of the arbitrations of the
respondent. Such arbitrators are not required to recuse themselves
merely because of allegation of bias being made against them.
27. None of the averments of the petitioner are found to be such
which even prima facie establish before this court that the arbitrator
has any bias against the petitioner or in favour of the respondent.
This court cannot go into the merits of the other awards stated to be
published by the arbitrator in other disputes concerning the
respondent. This court thus cannot comment on perusal of the
awards, copies of which have been filed in this case, that the
arbitrator has dismissed the claims of other contractors against the
respondent which otherwise were tenable. In fact I would go to the
extent of holding that even if this court were to set aside the interim
award of the arbitrator, in the absence of any mala fide being found,
that alone would also not be a ground for changing the arbitrator.
28. That brings me to the last leg of this case i.e., on the merits of
the interim award. The interim award as aforesaid is based on
Sarvesh Chopra (supra). Sarvesh Chopra (supra) undoubtedly
lays down that the claims which under the terms of the contract are
made, "not payable" are not entertainable or not arbitrable. The
arbitrator in the present case on an interpretation of the various
clauses of the agreement has held that the claims 2, 4 and 5 fall in
such category i.e., which were agreed by the parties to be not
payable. The same proposition was reiterated in Rajasthan State
Mines and Minerals Ltd (supra) with the addition that even if such
claims were referred, the same were not to be allowed by the
arbitrator inasmuch allowing the same would be in contravention of
the agreement.
29. The petitioner has not really pointed out anything wrong in
the finding of the arbitrator of the said claims being not maintainable
and/or barred by agreement of the parties. However, I may add that
even if this court on an interpretation of the clauses of the
agreement relied upon by the arbitrator to bar the said claims, were
to hold a different opinion, the same would still not entitle this court
to set aside the award. The arbitrator is a private court/forum
chosen by the parties and the parties are bound by his interpretation
of the contract. I even otherwise am of the same opinion as the
arbitrator as to the interpretation of the clauses of the agreement
relied upon to hold claims 2, 4 and 5 to be non-arbitrable. I may
notice that the arbitration clause under consideration in Sarvesh
Chopra (supra) was very widely worded and the only exception
thereto also was the matters whereunder the decision of the Railway
Authority was final. However, the Supreme Court held not only
those matters which were expressly excepted but even those matters
which were prohibited, to be not arbitrable. The position in the
present case is the same.
30. In the aforesaid background, the contention of the petitioner
of the drawings being given late or the work being executed before
thereto losses its significance. Once a claim is barred under the
agreement, the same would remain barred whatsoever may be the
circumstances leading thereto. I also do not find any merit in the
argument of any inconsistency in the award or of claim No.3 being
denied by the respondent and being held to be arbitrable by the
arbitrator. No clause in the agreement has been pointed out
whereunder the claim No.1 is barred. Merely because a provision is
not made for a claim does not tantamount to saying that it is barred.
In fact as noticed by the Single Judge of this court in Paragon
Construction India (supra), claims which are not barred can be
made under Section 73 of the Contract Act even though no remedy
thereof is provided in the contract. Similarly, it is not stated that any
clause of the agreement bars the claim No.3 held by the arbitrator to
be arbitrable. Merely because the arbitrator has not agreed with the
Engineer-in-charge / Manager of the respondent is no ground for
finding fault with the award. In fact it shows that the arbitrator has
not toed the line of the respondent. Again it is not as if the petitioner
is remedyless with the claims being held to be non-arbitrable. The
petitioner has the remedy of a civil suit available to it with respect
thereto, though it is a different matter whether the civil court also
would allow the said claim or not, if the parties had agreed to such
claim being not entertainable under the contract.
31. The petitioner has not been able to show that any of the
claims held to be not arbitrable do not fall within the clauses of the
agreement prohibiting such claims. Undoubtedly the courts have
allowed claims for escalation beyond the formulas agreed upon by
the parties, upon finding the contractor to have incurred escalation
for reasons attributable to the owner of the project. However, in
none of those cases was there any prohibition in the agreement to
such a claim. In the present case, the clause 29.13 prohibits the
petitioner from making the claims for the reason of complying with
his obligation under the contract, inter alia, of payment of minimum
wages. The wide of the said clause cannot be whittled down by
giving an interpretation that the compliance of obligation is to be
during the term of the agreement only. The parties had mutually
extended the term of the agreement and it is not shown that such
extension was on terms other than those earlier agreed between the
parties. The same is the position with respect to the claim No. 5 for
losses due to supply of electric power at low voltage. Clause 24.1
provides that the petitioner will not claim any damages or
compensation for non-supply of power as agreed.
32. The objections of the petitioner to the award, as well as the
OMP thus fail. The interim award dated 22nd November, 2002 is
made a rule of the court and decree is passed in terms thereof. The
petitioner is found to have held up the arbitral proceedings for a long
span of seven years. The petitioner is as such burdened with costs of
these proceedings of Rs 50,000/-
RAJIV SAHAI ENDLAW (JUDGE)
October 13, 2009 M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!