Thursday, 30, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Vardhman Properties Ltd. vs North Delhi Power Ltd.
2009 Latest Caselaw 4003 Del

Citation : 2009 Latest Caselaw 4003 Del
Judgement Date : 6 October, 2009

Delhi High Court
Vardhman Properties Ltd. vs North Delhi Power Ltd. on 6 October, 2009
Author: Manmohan Singh
*          HIGH COURT OF DELHI : NEW DELHI

+          CS (OS) No. 1305/2005

                                 Reserved on: 7th September, 2009

%                                Decided on:         6th October, 2009

Vardhman Properties Ltd.                                ...Plaintiff
                    Through : Mr. Sanjay Goswami with Mr. H.K.
                              Balajee, Advs.

                                 Versus

North Delhi Power Ltd.                                   ...Defendant
                    Through : Mr. Sudhir Nandrajog, Sr. Adv. with
                              Mr. Vikram Nandrajog and Ms.
                              Himani Jadoun, Advs.

Coram:

HON'BLE MR. JUSTICE MANMOHAN SINGH

1. Whether the Reporters of local papers may
   be allowed to see the judgment?                                 No

2. To be referred to Reporter or not?                              No

3. Whether the judgment should be reported                         No
   in the Digest?

MANMOHAN SINGH, J.

1. The plaintiff has filed the present suit for recovery of a sum

of Rs. 21,07,930/- along with pendente lite and future interest @ 18%

p.a. The plaintiff is a limited company duly incorporated under the

Companies Act, 1956 and carries out construction of commercial

properties on duly allotted land. The defendant is a licensee under the

Electricity Supply Act, 1948 and is a distributor of electricity in North

Delhi. The predecessor of the defendant is DVB, with which the plaintiff

had the present arrangement, which forms the crux of the matter.

BRIEF FACTS

2. The plaintiff was allotted plot no. 7, District Centre,

Manglam Place, Sector 3, Rohini, Delhi (hereinafter referred to as „suit

building‟) by way of an auction conducted by the DDA. After

sanctioning of the building plan, the plaintiff approached the then

licensee (DVB) to frame the electrification scheme of the building, for

which the plaintiff and the licensee were to deposit 50% share each as

part of the electrification charges.

3. On 31 August, 2001 the plaintiff gave an area of 30 x 31 feet

to DVB to install the proposed sub-station. The total cost of electrifying

the suit building was Rs. 84,65,700/- out of which the plaintiff paid Rs.

44,55,100/- on 19 August, 2002. These charges were the estimated

charges subject to change upon actual cost realized after completion of

the work.

4. After much delay and subsequent to this court‟s order in Civil

Writ Petition No. 1496/2003 directing DVB to expedite the

electrification, the same was done and the defendant sent letter dated 10

November, 2003 to the plaintiff stating therein that the suit building had

been energized on 5 November, 2003.

PLAINTIFF'S CASE

5. The plaintiff‟s submission is that during the process of

electrification of the suit building certain changes were made to the

frame of the electrification scheme which resulted in the use of

substantially less money than the figure of cost arrived at previously, as

instead of three 630 KVA transformers as proposed, only two were

required as against the three in the proposal, and hence used. As a result

of this change, the cost of the remnant transformer as well as of the

corresponding material, transportation, cable and workmanship was

saved and approximately Rs. 13,68,786.55/- were the said savings falling

to the plaintiff‟s share.

6. The plaintiff claimed refund of the above-mentioned amount

from the defendant, in lieu of the deposit of Rs. 44,55,100/- made by it

on 19 August, 2002 by its letter dated 26 December, 2003. The plaintiff

also claimed the prevalent market interest on the same. The defendant

received the said letter but refused to refund the plaintiff, thereby

violating the provisions of the Delhi Electricity Regulatory Commission

(hereinafter referred to a „DERC‟) (Performance Standards) Metering

and Billing Regulations, 2002 and the Schedule of Miscellaneous

Charges and Completion of Handling Procedures Relating to

Distribution and Retail Supply.

7. The plaintiff filed a representation dated 27 January, 2004

under the DERC against the defendant, but received no relief and has

been running for the same from pillar to post. The defendant has been

enjoying the excessive amount deposited by the plaintiff since

November 2003, when the electrification work in the suit building was

completed. Thus, the present suit has been filed for recovery of Rs.

13,68,786.55/- with interest @ 18% p.a. from the date of deposit of Rs.

44,55,100/- till the filing of the instant suit, totaling an amount of Rs.

21,07,930/-.

DEFENDANT'S CASE

8. The defendant‟s submissions depict a completely different

version of events altogether. As per the defendant, the plaintiff is guilty

of approaching this court with unclean hands and of concealing material

information. The defendant‟s entire case relies upon two points of fact.

One, that the plaintiff failed to comply with a term of allotment of the

suit building which provided that the plaintiff was to provide „adequate

space‟ for the construction of a sub-station and for installation of other

equipment in the said building. The defendant has alleged that the

plaintiff used the entire area available in the building for sale to

commercial users, and provided the former with limited space (30 x 31

feet), i.e. space enough only for two transformers and not three, the latter

being the number of transformers required to meet the estimated load

requirement.

9. The second fact stated by the defendant is that it has nowhere

stated that the electrification work at the suit building was „complete‟ as

the same is still pending. If a third transformer is not set up, the load on

the other two transformers will cause over-heating and possible

breakdown, resulting in danger to the occupants of the suit building as

well as the building itself. The defendant has submitted that it is willing

to install the third transformer provided the plaintiff provides it with the

requisite space that it had promised.

10. The defendant has averred that the plaintiff did not get the

building plans approved by the electricity provider in accordance with

the allotment, as it was in a hurry to sell the area for commercial gain.

Further, as per the defendant the delay in the implementation of the

electrification scheme occurred wholly due to the plaintiff‟s failure to

provide the requisite space for the same. Further still, the plaintiff is not

entitled to any refund as according to the defendant, the question of any

excess amount etc. can only be determined once the electrification

process is completed. The said process can only be completed once the

plaintiff provides space for another transformer, so that electricity can be

provided keeping in mind the full load of the suit building.

EVIDENCE

11. The plaintiffs have exhibited several documents as evidence.

Amongst other documents, the plaintiff has exhibited DVB‟s letter dated

15 March, 2001 (Ex P-3) stating that sub-station space measuring 25" x

32" must be earmarked on an approved copy of the layout plan for

taking the electrification scheme further. By its letter dated 28 July, 2001

(Ex. P-4) the plaintiff has replied to the defendant‟s afore-mentioned

letter stating that area measuring 30" x 31" is marked at stilt level for

installation of the sub-station. Another letter dated 21 August, 2001 (Ex.

PW1/5) from the defendant to the plaintiff states that "...the competent

authority of D.V.B. has accepted the built up S/Stn space measuring 31"

x 31" in the stilt above the basement in..."

12. The clinching evidence is DVB‟s letter dated 4 March, 2002

(Ex. PW1/6) to the plaintiff which discusses the load required and

calculation of various costs expected in the electrification scheme etc.

On page 15 of the evidence documents, internal page 2 of the instant

document mentioned, para 3 mentions that the construction of the suit

building is in its final stages and it is not feasible for the promoter to part

with any additional space. Having said that, the defendant goes on to

state the following :

"In view of the above CE (D) NW approved the installation of the new 630 KVA transformers in rge already handed over built-up s/stn space. Which is adequate to accommodate 3 new 630 KVA Trs. as the measurement of the Trs. body of 630 KVA rating Trs. is 2.1mt x 1.5 mt."(emphasis added) All the afore-mentioned documents have been admitted by the defendant

without any reservation or exception as to content or otherwise.

13. The defendant has filed, by way of evidence, an affidavit of

Mr. Shishir Singh who was examined, cross-examined and discharged

on 3 October, 2008. Amongst other things, the said witness has claimed

that it is incorrect to suggest that the two transformers installed in the

suit building are more than sufficient for the same. However, he goes on

to state in the next sentence itself that "it is correct that no need for the

installation of the third transformer has been felt in the last five years."

14. On 8 January, 2007 this court framed the Issues in this

matter. Having perused the rival contentions of both parties and the

evidence pertaining to the same, I shall now proceed to deal with the

Issues separately.

15. ISSUE NO.1

"Whether the plaint has been signed and verified and the suit instituted by an authorized person?"

The plaintiff has filed a copy of the minutes of the meeting of Board of

Directors held on 3 January, 2005 which is duly attested holding the

plaintiff capacitated for filing the present civil suit for recovery of dues

against the defendant. There is hardly any opposition to this issue.

Therefore, it is held that the suit has been properly signed, verified and

instituted by a duly authorised person.

16. ISSUE NO.2

"Whether the defendant while executing the electrification work made any changes/alterations to the scheme as it was originally proposed and thereby made certain reductions in expenditure and cost?"

The burden of this issue was put on the plaintiff. It is a matter of fact

that while executing the electrification work the defendant made no

changes/alterations to the Scheme as the electrification scheme/letter

dated 28 February, 2002 filed by the plaintiff is duly proved by Ex.PW-

1/7 as well as the copy of the scheme by Ex.PW-1/6, and both are

admitted by the defendant. The defendant has neither filed any other

scheme/letter which shows any changes/alterations to the scheme

originally proposed and filed by the plaintiff, nor made any reduction in

the expenditure and costs. Therefore, this issue is duly proved by the

plaintiff and is decided in favour of the plaintiff accordingly.

17. ISSUE NO.4

"Whether the defendant has notified the plaintiff of any deficiency enabling it to electrify the building?" As regards issue No.4, the burden of this issue is also on the plaintiff.

On 31 August, 2001 the plaintiff gave an area of 30 x 31 ft. to DVB to

install the proposed sub station. The plaintiff also paid Rs.44,55,100/- on

19 August, 2002. In the letter dated 15 March, 2001 (marked as Ex. P-1),

the defendant has asked the plaintiff to provide space measuring 25 x 32

in the open area with a road measuring six meters wide on two adjacent

sites earmarked on the approval copy of the layout plan etc. The plaintiff

wrote letter dated 28 July, 2001 to the defendant by which space for sub

station measuring 30 x 31 was provided to the defendant at stilt level as

well consent was given for installation of dry type transformer. By letter

dated 21 August, 2001 (marked as Ex. PW-1/5), there is a confirmation

by the defendant that the competent authority of DVB has accepted the

built up space measuring 30 x 31 at the stilt level in the building.

Physical possession of the said area was also taken by the defendant and

the same is acknowledged by the defendant vide letter dated 31 August,

2001 (marked as Ex.PW-1/3). Handing over of the possession and

taking over report which is duly signed by the parties and marked as

Ex.PW-1/4 has also been placed on record. The plan of built up space at

stilt level of the suit property is also placed on record and marked as

Ex.P-6. The scheme was also approved by DVB‟s competent authority

on the basis of the area provided by the plaintiff and the said approval in

this regard is also placed on record as Ex.PW-1/6.

18. There is no rebuttal on this regard by the defendant. There is

no letter written by the defendant of any kind nor has any evidence been

produced to notify/clarify that there was any deficiency hampering the

defendant‟s capacity to electrify the building. No evidence has been

produced by the defendant to the effect that the space provided by the

plaintiff is enough only for two transformers and not three, rather the

scheme approved by the defendant speaks otherwise. Thus in the

absence of any evidence as afore-mentioned, this issue is also decided in

favour of the plaintiff and against the defendant.

19. ISSUE NO.3

"Whether the plaintiff did not fulfil the requirements for electrification of the building no. 7, District Centre, Manglam Place, Sector 3, Rohini, Delhi as per the electrification scheme framed by the defendant?"

The burden of this issue lies on the defendant. I have already given my

finding on issue No.4. The plaintiff has exhibited several documents as

evidence. The plaintiff has produced evidence by way of affidavit

wherein it is specifically mentioned that possession was handed over to

the defendant and the defendant thereafter duly prepared the

electrification scheme of the Building No.7 District Centre, Mangalam

Place, Sector 3, Rohini on 2 December, 2001 vide the following

particulars:-

           No.                    Date       Drawing No.

XPCNW1/2001-02/Pig/34/622 7-12-01             XPCNW.1/2001-02/





20. By letter dated 4 March, 2002 the Commercial Officer III

DVB on the subject of electrification informed and gave the detailed

schedule prepared for the Planning Department of DVB/Licensing

amounting to Rs.84,65,700/- out of which Rs.44,55,100/- was deposited

as its share of the electrification charges. Copy of the two letters Ex.PW-

1/7 and PW-1/8 are duly marked. CWP No.1496/03 was decided on 25

February, 2003 by this court wherein a direction to complete the

electrification work within a certain time frame was issued. The plaintiff

was informed by letter dated 10 November, 2003 that the installation had

been energized on 5 November, 2003 and the electrification work was

completed. Copy of the said letter is attached as Ex.PW-1/10.

21. The contention of the plaintiff is that in the process of

execution of the said electrification scheme, there was substantial saving

of material and workmanship resulting in completion of electrification at

a cost comparatively less than the original estimate. Therefore, on

account of the reduction in use of equipment, cable, labour and

transportation etc. an estimated saving of approximately Rs.13,68,786.55

was made against the share of the plaintiff which amounted to

Rs.44,55,100/- which was deposited by the plaintiff with the licensing

authority on 19 August, 2002. The details of the savings on account of

reduction in use of material, labour and transportation which were

worked out in detail by the plaintiff and sent to the defendant is marked

as Ex.PW-1/11.

22. It is further contended by the plaintiff that as per letter of the

licencee dated 4 March, 2002 calling upon the plaintiff to deposit its

share, the electrification charges payable by the plaintiff were only

estimated and tentative, subject to final adjustment as per actual cost

worked out and accounts finalized by the Accounts Department of the

licensee after completion of the work. In view of this the plaintiff

submits that he is entitled to refund of Rs.13,68,786.55 on account of the

savings in its share towards the total electrification charges. The plaintiff

also sent notice dated 16 December, 2003 to the defendant for refund of

the said amount. A copy of the notice and postal receipts are filed as

Ex.PW-1/12 and Ex.PW-1/13. The plaintiff made a representation and

replied to the defendant, both of which are marked as Ex.PW-1/14 and

Ex.PW-1/15 respectively. Since the defendant did not refund the said

amount the plaintiff filed the present suit.

23. Learned counsel for the defendant has referred to the cross

examination of the plaintiff Sh. Sushil Kumar Jain wherein it was

deposed by the plaintiff that the approval of the DVB was not obtained

before commencement of construction. It is also admitted by the plaintiff

that there was a provision in the lease deed for the area of construction

of electric sub station and in the sanctioned plan no specified area for the

same was mentioned. It appears from the said cross examination that the

said admission of the plaintiff does not help the case of the defendant in

the light of the correspondence exchanged between the parties from 28

April, 2002 up to the date of electrification scheme/letter dated 10

November, 2003 from the defendant whereby the defendant has stated

that the suit building has been energized. Further, there is no contrary

evidence which has been produced by the defendant to demolish the case

of the plaintiff in this regard. Further still, no issue has been framed in

this respect.

24. As regards the evidence of the defendant, the same was filed

by way of an affidavit of Sh. Shishir Singh who has deposed that he was

not working with the DVB when the electrification scheme in this case

was framed. He deposed that his knowledge is based upon the study of

the scheme and the site visit. According to him the electrification

scheme of the building was complete in the year 2003, though he

volunteered that it is still pending. He has also admitted letter Ex.P-13

having been issued by the defendant. In his cross examination he has

admitted that no need of installation of three transformers has been felt

in the last 5 years. He has also admitted that as per the electrification

scheme the electrification cost which was estimated was only

approximate and was dependent upon the completion of the scheme. He

has also deposed that he could not say that in a particular building after

2003 the defendant had any requirement for carrying out load

enhancement.

25. Learned counsel for the defendant has argued that the

defendant is ready to install one more transformer as the defendant feels

that two transformers are not sufficient for the building as such burden

would cause over-heating and possible breakdown, resulting in danger to

the occupants. On the contrary the learned counsel for the plaintiff has

argued that the defendant has failed to produce any evidence in this

regard and if ever the need arises, the plaintiff will again apply for a

third transformer and shall deposit the present charges as per current

charges. As of now, however, the plaintiff submits that it is entitled to

refund as prayed. This issue is also decided in favour of the plaintiff and

against the defendant as the Department has failed to discharge its

burden in issue No.3.

"5) Whether the plaintiff is entitled to recover any amount from the defendants? If so, then what amount?

6) Whether the plaintiff is entitled to recover any interest on the amounts due to it from the defendant? If yes, then at what rate?"

As regards issue No.5 and 6, the plaintiff has sent an estimate of the

refund vide its letter dated 16 December, 2003 which is marked as

Ex.PW-1/11 and estimate of Rs.13,68,786.55. The defendant has filed no

other evidence nor made any statement to the effect that the estimation

of Rs. 13 lac (approximately) given by the plaintiff is too high or that it

should have been any less. In this regard, the plaintiff has referred to

Section 114 (1) (g) of the Evidence Act, 1872 and submitted the

following decisions in that regard. The relevant portions of both these

decisions are produced hereinbelow :

(I) Union of India v. Mohan Behari Jasod Kumari, 2004 (114) DLT

"27. It is a settled principle of law that irrespective of the burden of proof, the party in possession of the best evidence is bound to produce the same. In this behalf regard be made to the judgment of the Supreme Court of India reported at AIR 1968 SC 1413. The forwarding note was in the power and possession of the defendant no. 1. It is not disputed that the same was material contemporaneous documentary evidence which was not produced. Adverse inference is, therefore, to be drawn against the defendant no. 1 for failure to produce the documents."

(II) Gopal Krishnaji Ketkar v. Mahomed Haji Latif & Ors., (1968) 3

SCR 862 (at page 866)

"Even if the burden of proof does not lie on a party the Court may draw an adverse inference if he withholds important documents in his possession which can throw light on the facts at issue. It is not, in our opinion, a sound practice for those desiring to rely upon a certain state of facts to withhold from the Court the best evidence which is in their possession which could throw light upon the issues in controversy and to rely upon the issues in controversy and to rely upon the abstract doctrine of onus of proof."

27. In view of the above-stated, the suit of the plaintiff for

recovery of Rs.21,07,930/- is decreed as in my opinion the plaintiff is

entitled to the said amount. As far as pendente lite and future interest is

concerned, I feel that the claim of 18% p.a. is on the higher side. In the

interest of justice and equity the plaintiff is entitled to pendente lite and

future interest @ 8% p.a. from the date of filing of the suit till the date of

realization of the said amount. The decree be drawn accordingly in

favour of the plaintiff and against the defendant. The plaintiff is also

entitled to costs of the suit.

MANMOHAN SINGH, J.

OCTOBER 6, 2009 nn

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter