Citation : 2009 Latest Caselaw 4003 Del
Judgement Date : 6 October, 2009
* HIGH COURT OF DELHI : NEW DELHI
+ CS (OS) No. 1305/2005
Reserved on: 7th September, 2009
% Decided on: 6th October, 2009
Vardhman Properties Ltd. ...Plaintiff
Through : Mr. Sanjay Goswami with Mr. H.K.
Balajee, Advs.
Versus
North Delhi Power Ltd. ...Defendant
Through : Mr. Sudhir Nandrajog, Sr. Adv. with
Mr. Vikram Nandrajog and Ms.
Himani Jadoun, Advs.
Coram:
HON'BLE MR. JUSTICE MANMOHAN SINGH
1. Whether the Reporters of local papers may
be allowed to see the judgment? No
2. To be referred to Reporter or not? No
3. Whether the judgment should be reported No
in the Digest?
MANMOHAN SINGH, J.
1. The plaintiff has filed the present suit for recovery of a sum
of Rs. 21,07,930/- along with pendente lite and future interest @ 18%
p.a. The plaintiff is a limited company duly incorporated under the
Companies Act, 1956 and carries out construction of commercial
properties on duly allotted land. The defendant is a licensee under the
Electricity Supply Act, 1948 and is a distributor of electricity in North
Delhi. The predecessor of the defendant is DVB, with which the plaintiff
had the present arrangement, which forms the crux of the matter.
BRIEF FACTS
2. The plaintiff was allotted plot no. 7, District Centre,
Manglam Place, Sector 3, Rohini, Delhi (hereinafter referred to as „suit
building‟) by way of an auction conducted by the DDA. After
sanctioning of the building plan, the plaintiff approached the then
licensee (DVB) to frame the electrification scheme of the building, for
which the plaintiff and the licensee were to deposit 50% share each as
part of the electrification charges.
3. On 31 August, 2001 the plaintiff gave an area of 30 x 31 feet
to DVB to install the proposed sub-station. The total cost of electrifying
the suit building was Rs. 84,65,700/- out of which the plaintiff paid Rs.
44,55,100/- on 19 August, 2002. These charges were the estimated
charges subject to change upon actual cost realized after completion of
the work.
4. After much delay and subsequent to this court‟s order in Civil
Writ Petition No. 1496/2003 directing DVB to expedite the
electrification, the same was done and the defendant sent letter dated 10
November, 2003 to the plaintiff stating therein that the suit building had
been energized on 5 November, 2003.
PLAINTIFF'S CASE
5. The plaintiff‟s submission is that during the process of
electrification of the suit building certain changes were made to the
frame of the electrification scheme which resulted in the use of
substantially less money than the figure of cost arrived at previously, as
instead of three 630 KVA transformers as proposed, only two were
required as against the three in the proposal, and hence used. As a result
of this change, the cost of the remnant transformer as well as of the
corresponding material, transportation, cable and workmanship was
saved and approximately Rs. 13,68,786.55/- were the said savings falling
to the plaintiff‟s share.
6. The plaintiff claimed refund of the above-mentioned amount
from the defendant, in lieu of the deposit of Rs. 44,55,100/- made by it
on 19 August, 2002 by its letter dated 26 December, 2003. The plaintiff
also claimed the prevalent market interest on the same. The defendant
received the said letter but refused to refund the plaintiff, thereby
violating the provisions of the Delhi Electricity Regulatory Commission
(hereinafter referred to a „DERC‟) (Performance Standards) Metering
and Billing Regulations, 2002 and the Schedule of Miscellaneous
Charges and Completion of Handling Procedures Relating to
Distribution and Retail Supply.
7. The plaintiff filed a representation dated 27 January, 2004
under the DERC against the defendant, but received no relief and has
been running for the same from pillar to post. The defendant has been
enjoying the excessive amount deposited by the plaintiff since
November 2003, when the electrification work in the suit building was
completed. Thus, the present suit has been filed for recovery of Rs.
13,68,786.55/- with interest @ 18% p.a. from the date of deposit of Rs.
44,55,100/- till the filing of the instant suit, totaling an amount of Rs.
21,07,930/-.
DEFENDANT'S CASE
8. The defendant‟s submissions depict a completely different
version of events altogether. As per the defendant, the plaintiff is guilty
of approaching this court with unclean hands and of concealing material
information. The defendant‟s entire case relies upon two points of fact.
One, that the plaintiff failed to comply with a term of allotment of the
suit building which provided that the plaintiff was to provide „adequate
space‟ for the construction of a sub-station and for installation of other
equipment in the said building. The defendant has alleged that the
plaintiff used the entire area available in the building for sale to
commercial users, and provided the former with limited space (30 x 31
feet), i.e. space enough only for two transformers and not three, the latter
being the number of transformers required to meet the estimated load
requirement.
9. The second fact stated by the defendant is that it has nowhere
stated that the electrification work at the suit building was „complete‟ as
the same is still pending. If a third transformer is not set up, the load on
the other two transformers will cause over-heating and possible
breakdown, resulting in danger to the occupants of the suit building as
well as the building itself. The defendant has submitted that it is willing
to install the third transformer provided the plaintiff provides it with the
requisite space that it had promised.
10. The defendant has averred that the plaintiff did not get the
building plans approved by the electricity provider in accordance with
the allotment, as it was in a hurry to sell the area for commercial gain.
Further, as per the defendant the delay in the implementation of the
electrification scheme occurred wholly due to the plaintiff‟s failure to
provide the requisite space for the same. Further still, the plaintiff is not
entitled to any refund as according to the defendant, the question of any
excess amount etc. can only be determined once the electrification
process is completed. The said process can only be completed once the
plaintiff provides space for another transformer, so that electricity can be
provided keeping in mind the full load of the suit building.
EVIDENCE
11. The plaintiffs have exhibited several documents as evidence.
Amongst other documents, the plaintiff has exhibited DVB‟s letter dated
15 March, 2001 (Ex P-3) stating that sub-station space measuring 25" x
32" must be earmarked on an approved copy of the layout plan for
taking the electrification scheme further. By its letter dated 28 July, 2001
(Ex. P-4) the plaintiff has replied to the defendant‟s afore-mentioned
letter stating that area measuring 30" x 31" is marked at stilt level for
installation of the sub-station. Another letter dated 21 August, 2001 (Ex.
PW1/5) from the defendant to the plaintiff states that "...the competent
authority of D.V.B. has accepted the built up S/Stn space measuring 31"
x 31" in the stilt above the basement in..."
12. The clinching evidence is DVB‟s letter dated 4 March, 2002
(Ex. PW1/6) to the plaintiff which discusses the load required and
calculation of various costs expected in the electrification scheme etc.
On page 15 of the evidence documents, internal page 2 of the instant
document mentioned, para 3 mentions that the construction of the suit
building is in its final stages and it is not feasible for the promoter to part
with any additional space. Having said that, the defendant goes on to
state the following :
"In view of the above CE (D) NW approved the installation of the new 630 KVA transformers in rge already handed over built-up s/stn space. Which is adequate to accommodate 3 new 630 KVA Trs. as the measurement of the Trs. body of 630 KVA rating Trs. is 2.1mt x 1.5 mt."(emphasis added) All the afore-mentioned documents have been admitted by the defendant
without any reservation or exception as to content or otherwise.
13. The defendant has filed, by way of evidence, an affidavit of
Mr. Shishir Singh who was examined, cross-examined and discharged
on 3 October, 2008. Amongst other things, the said witness has claimed
that it is incorrect to suggest that the two transformers installed in the
suit building are more than sufficient for the same. However, he goes on
to state in the next sentence itself that "it is correct that no need for the
installation of the third transformer has been felt in the last five years."
14. On 8 January, 2007 this court framed the Issues in this
matter. Having perused the rival contentions of both parties and the
evidence pertaining to the same, I shall now proceed to deal with the
Issues separately.
15. ISSUE NO.1
"Whether the plaint has been signed and verified and the suit instituted by an authorized person?"
The plaintiff has filed a copy of the minutes of the meeting of Board of
Directors held on 3 January, 2005 which is duly attested holding the
plaintiff capacitated for filing the present civil suit for recovery of dues
against the defendant. There is hardly any opposition to this issue.
Therefore, it is held that the suit has been properly signed, verified and
instituted by a duly authorised person.
16. ISSUE NO.2
"Whether the defendant while executing the electrification work made any changes/alterations to the scheme as it was originally proposed and thereby made certain reductions in expenditure and cost?"
The burden of this issue was put on the plaintiff. It is a matter of fact
that while executing the electrification work the defendant made no
changes/alterations to the Scheme as the electrification scheme/letter
dated 28 February, 2002 filed by the plaintiff is duly proved by Ex.PW-
1/7 as well as the copy of the scheme by Ex.PW-1/6, and both are
admitted by the defendant. The defendant has neither filed any other
scheme/letter which shows any changes/alterations to the scheme
originally proposed and filed by the plaintiff, nor made any reduction in
the expenditure and costs. Therefore, this issue is duly proved by the
plaintiff and is decided in favour of the plaintiff accordingly.
17. ISSUE NO.4
"Whether the defendant has notified the plaintiff of any deficiency enabling it to electrify the building?" As regards issue No.4, the burden of this issue is also on the plaintiff.
On 31 August, 2001 the plaintiff gave an area of 30 x 31 ft. to DVB to
install the proposed sub station. The plaintiff also paid Rs.44,55,100/- on
19 August, 2002. In the letter dated 15 March, 2001 (marked as Ex. P-1),
the defendant has asked the plaintiff to provide space measuring 25 x 32
in the open area with a road measuring six meters wide on two adjacent
sites earmarked on the approval copy of the layout plan etc. The plaintiff
wrote letter dated 28 July, 2001 to the defendant by which space for sub
station measuring 30 x 31 was provided to the defendant at stilt level as
well consent was given for installation of dry type transformer. By letter
dated 21 August, 2001 (marked as Ex. PW-1/5), there is a confirmation
by the defendant that the competent authority of DVB has accepted the
built up space measuring 30 x 31 at the stilt level in the building.
Physical possession of the said area was also taken by the defendant and
the same is acknowledged by the defendant vide letter dated 31 August,
2001 (marked as Ex.PW-1/3). Handing over of the possession and
taking over report which is duly signed by the parties and marked as
Ex.PW-1/4 has also been placed on record. The plan of built up space at
stilt level of the suit property is also placed on record and marked as
Ex.P-6. The scheme was also approved by DVB‟s competent authority
on the basis of the area provided by the plaintiff and the said approval in
this regard is also placed on record as Ex.PW-1/6.
18. There is no rebuttal on this regard by the defendant. There is
no letter written by the defendant of any kind nor has any evidence been
produced to notify/clarify that there was any deficiency hampering the
defendant‟s capacity to electrify the building. No evidence has been
produced by the defendant to the effect that the space provided by the
plaintiff is enough only for two transformers and not three, rather the
scheme approved by the defendant speaks otherwise. Thus in the
absence of any evidence as afore-mentioned, this issue is also decided in
favour of the plaintiff and against the defendant.
19. ISSUE NO.3
"Whether the plaintiff did not fulfil the requirements for electrification of the building no. 7, District Centre, Manglam Place, Sector 3, Rohini, Delhi as per the electrification scheme framed by the defendant?"
The burden of this issue lies on the defendant. I have already given my
finding on issue No.4. The plaintiff has exhibited several documents as
evidence. The plaintiff has produced evidence by way of affidavit
wherein it is specifically mentioned that possession was handed over to
the defendant and the defendant thereafter duly prepared the
electrification scheme of the Building No.7 District Centre, Mangalam
Place, Sector 3, Rohini on 2 December, 2001 vide the following
particulars:-
No. Date Drawing No. XPCNW1/2001-02/Pig/34/622 7-12-01 XPCNW.1/2001-02/
20. By letter dated 4 March, 2002 the Commercial Officer III
DVB on the subject of electrification informed and gave the detailed
schedule prepared for the Planning Department of DVB/Licensing
amounting to Rs.84,65,700/- out of which Rs.44,55,100/- was deposited
as its share of the electrification charges. Copy of the two letters Ex.PW-
1/7 and PW-1/8 are duly marked. CWP No.1496/03 was decided on 25
February, 2003 by this court wherein a direction to complete the
electrification work within a certain time frame was issued. The plaintiff
was informed by letter dated 10 November, 2003 that the installation had
been energized on 5 November, 2003 and the electrification work was
completed. Copy of the said letter is attached as Ex.PW-1/10.
21. The contention of the plaintiff is that in the process of
execution of the said electrification scheme, there was substantial saving
of material and workmanship resulting in completion of electrification at
a cost comparatively less than the original estimate. Therefore, on
account of the reduction in use of equipment, cable, labour and
transportation etc. an estimated saving of approximately Rs.13,68,786.55
was made against the share of the plaintiff which amounted to
Rs.44,55,100/- which was deposited by the plaintiff with the licensing
authority on 19 August, 2002. The details of the savings on account of
reduction in use of material, labour and transportation which were
worked out in detail by the plaintiff and sent to the defendant is marked
as Ex.PW-1/11.
22. It is further contended by the plaintiff that as per letter of the
licencee dated 4 March, 2002 calling upon the plaintiff to deposit its
share, the electrification charges payable by the plaintiff were only
estimated and tentative, subject to final adjustment as per actual cost
worked out and accounts finalized by the Accounts Department of the
licensee after completion of the work. In view of this the plaintiff
submits that he is entitled to refund of Rs.13,68,786.55 on account of the
savings in its share towards the total electrification charges. The plaintiff
also sent notice dated 16 December, 2003 to the defendant for refund of
the said amount. A copy of the notice and postal receipts are filed as
Ex.PW-1/12 and Ex.PW-1/13. The plaintiff made a representation and
replied to the defendant, both of which are marked as Ex.PW-1/14 and
Ex.PW-1/15 respectively. Since the defendant did not refund the said
amount the plaintiff filed the present suit.
23. Learned counsel for the defendant has referred to the cross
examination of the plaintiff Sh. Sushil Kumar Jain wherein it was
deposed by the plaintiff that the approval of the DVB was not obtained
before commencement of construction. It is also admitted by the plaintiff
that there was a provision in the lease deed for the area of construction
of electric sub station and in the sanctioned plan no specified area for the
same was mentioned. It appears from the said cross examination that the
said admission of the plaintiff does not help the case of the defendant in
the light of the correspondence exchanged between the parties from 28
April, 2002 up to the date of electrification scheme/letter dated 10
November, 2003 from the defendant whereby the defendant has stated
that the suit building has been energized. Further, there is no contrary
evidence which has been produced by the defendant to demolish the case
of the plaintiff in this regard. Further still, no issue has been framed in
this respect.
24. As regards the evidence of the defendant, the same was filed
by way of an affidavit of Sh. Shishir Singh who has deposed that he was
not working with the DVB when the electrification scheme in this case
was framed. He deposed that his knowledge is based upon the study of
the scheme and the site visit. According to him the electrification
scheme of the building was complete in the year 2003, though he
volunteered that it is still pending. He has also admitted letter Ex.P-13
having been issued by the defendant. In his cross examination he has
admitted that no need of installation of three transformers has been felt
in the last 5 years. He has also admitted that as per the electrification
scheme the electrification cost which was estimated was only
approximate and was dependent upon the completion of the scheme. He
has also deposed that he could not say that in a particular building after
2003 the defendant had any requirement for carrying out load
enhancement.
25. Learned counsel for the defendant has argued that the
defendant is ready to install one more transformer as the defendant feels
that two transformers are not sufficient for the building as such burden
would cause over-heating and possible breakdown, resulting in danger to
the occupants. On the contrary the learned counsel for the plaintiff has
argued that the defendant has failed to produce any evidence in this
regard and if ever the need arises, the plaintiff will again apply for a
third transformer and shall deposit the present charges as per current
charges. As of now, however, the plaintiff submits that it is entitled to
refund as prayed. This issue is also decided in favour of the plaintiff and
against the defendant as the Department has failed to discharge its
burden in issue No.3.
"5) Whether the plaintiff is entitled to recover any amount from the defendants? If so, then what amount?
6) Whether the plaintiff is entitled to recover any interest on the amounts due to it from the defendant? If yes, then at what rate?"
As regards issue No.5 and 6, the plaintiff has sent an estimate of the
refund vide its letter dated 16 December, 2003 which is marked as
Ex.PW-1/11 and estimate of Rs.13,68,786.55. The defendant has filed no
other evidence nor made any statement to the effect that the estimation
of Rs. 13 lac (approximately) given by the plaintiff is too high or that it
should have been any less. In this regard, the plaintiff has referred to
Section 114 (1) (g) of the Evidence Act, 1872 and submitted the
following decisions in that regard. The relevant portions of both these
decisions are produced hereinbelow :
(I) Union of India v. Mohan Behari Jasod Kumari, 2004 (114) DLT
"27. It is a settled principle of law that irrespective of the burden of proof, the party in possession of the best evidence is bound to produce the same. In this behalf regard be made to the judgment of the Supreme Court of India reported at AIR 1968 SC 1413. The forwarding note was in the power and possession of the defendant no. 1. It is not disputed that the same was material contemporaneous documentary evidence which was not produced. Adverse inference is, therefore, to be drawn against the defendant no. 1 for failure to produce the documents."
(II) Gopal Krishnaji Ketkar v. Mahomed Haji Latif & Ors., (1968) 3
SCR 862 (at page 866)
"Even if the burden of proof does not lie on a party the Court may draw an adverse inference if he withholds important documents in his possession which can throw light on the facts at issue. It is not, in our opinion, a sound practice for those desiring to rely upon a certain state of facts to withhold from the Court the best evidence which is in their possession which could throw light upon the issues in controversy and to rely upon the issues in controversy and to rely upon the abstract doctrine of onus of proof."
27. In view of the above-stated, the suit of the plaintiff for
recovery of Rs.21,07,930/- is decreed as in my opinion the plaintiff is
entitled to the said amount. As far as pendente lite and future interest is
concerned, I feel that the claim of 18% p.a. is on the higher side. In the
interest of justice and equity the plaintiff is entitled to pendente lite and
future interest @ 8% p.a. from the date of filing of the suit till the date of
realization of the said amount. The decree be drawn accordingly in
favour of the plaintiff and against the defendant. The plaintiff is also
entitled to costs of the suit.
MANMOHAN SINGH, J.
OCTOBER 6, 2009 nn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!