Citation : 2009 Latest Caselaw 4684 Del
Judgement Date : 18 November, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELH
+ CS(OS) No.1581A/1998
18th November, 2009.
SH. S. KUMAR
...Petitioner
Through: Mr. S.K. Jain, Advocate.
VERSUS
DELHI DEVELOPMENT AUTHORITY ....Respondent.
Through: Ms. Anusuya Salwan, Advocate.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see
the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
% JUDGMENT (ORAL)
VALIMIKI J. MEHTA, J.
I.A.No.5256/1999 in CS(OS) No.1581A/1998
1. These are objections filed under Sections 30 and 33 of the
Arbitration Act, 1940 against the Award dated 13.7.1998 passed by the sole
Arbitrator. Ms. Salwan, on behalf of the objector, has pressed her challenge
only to claim Nos. 2,3,4,5,7,13,14 and 16 as awarded by the Arbitrator.
CS(OS) 1581A/1998 Page 1 2. Claim No.2 is on account of work done but not paid. The
Arbitrator has given detailed reasons as to how the contractor wrote various
letters showing extra work done and which were not responded to by the
objector. The only objection of the respondent was that the letters were not
received by the proper officer and were obtained by the Assistant Engineer
only. Not accepting this stand the Arbitrator has therefore held that the
contractor is entitled to the amount of the work done. I do not find any fault
with this reasoning of the Arbitrator. Even if I was of a different view since the
view taken by the Arbitrator is not a view which is a perverse view, sitting and
hearing objections under Sections 30 and 33 I would not like to interfere with
the findings in the Award.
3. Claim No.3 was on account of claim for escalation for higher
payment for work done during the extended period of work. It is not disputed
that the work period was in fact extended and the Arbitrator has relied upon the
notifications showing the enhanced charges payable to the labour. Accordingly,
the reasons of the Arbitrator are sound and this Court cannot go into the
reasonableness of the reasons as given by the Arbitrator.
4. Claim No.4 before the Arbitrator pertains to claim on account of
damages and loss of profitability. I find that the objection in this regard of the
CS(OS) 1581A/1998 Page 2 objector is justified because this claim is towards enhanced charges and for the
same subject and for the same period, escalation has already been paid to the
contractor under clause 10C. Therefore, payment under this head amounts to
duplication of payment which is impermissible in law. The Arbitrator, I note,
has not given any sufficient legal reasons for allowing this claim. In fact, the
Arbitrator notes under this head that the claim on account of damages and loss
of profitability was not established. Once the Arbitrator so holds that the said
claim is not established there cannot arise any reason for allowing of the same
claim by the Arbitrator. Objection in this regard is therefore justified and the
Award of the Arbitrator with respect to claim No.4 is set aside.
5. The claim No.5 before the Arbitrator pertained to increase in rates
beyond the stipulated date of completion beyond what has already been allowed
under clause 10C. The Arbitrator has arrived at a finding of fact that there was
a breach committed by the respondent. Such a finding of fact is final and it
cannot be challenged by the objector, more so because the same has not been
shown to be perverse. The claim for escalation therefore allowed by the
Arbitrator once it is found that the objector was guilty of breach is justified and
no fault therefore can be found with this part of the Award.
6. Claim No.7 of the contractor was its claim for payment because a
lesser amount was paid for the extra items. The condition in the contract was
CS(OS) 1581A/1998 Page 3 that if the extra items were sanctioned within a period of three months then the
respondent shall be entitled to a rebate of 1% of gross amount of all
extra/substituted items. However, it is an admitted fact that the sanction of
extra items was beyond the period of three months and therefore, the objector
was not entitled to rebate. Therefore, no objection can validly be sustained with
respect to claim no.7.
7. Claim No.13 though is of small amount of Rs.3556/-, I find that the
same is not justified. This amount of Rs.3556/- was recovered by the objector
because the contractor had to do certain painting works and such work was
found not to have been done. The Arbitrator has simply awarded the amount
merely because the objector had not issued any notice during the period of the
contract. I do not think that this is a justified reason because this is a claim for
work done and if work is not done then no payment can be claimed. Since the
work has not been done and the reasons of the Arbitrator are not justified, this
amount awarded under this claim, though of a small amount of Rs.3556/- , the
same is set aside and this claim of the contractor is rejected.
8. Claim No.14 is the claim of the contractor towards interest for
delayed payment. The Arbitrator has found as a matter of fact that there is a
delay in the payment of the amounts to the contractor. Since there is a delay in
the payment, the claimant is entitled to interest. It has been held by the
CS(OS) 1581A/1998 Page 4 Supreme Court in the case of South Eastern Coalfields Ltd. Vs. State of M.P.
(2003) 8SCC 648 that in certain cases interest can be granted in equity though
not provided for either in the agreement or in custom. Interest is therefore
basically compensation for the amount of monies illegally retained by a person
who ought to have made payment in time. I do not therefore find any merit
with the objection with regard to claim no.14.
9. That takes me to the last claim being claim No.16 with respect to
the interest granted by the Arbitrator. I note that the Arbitrator has awarded
interest at the rate of 18% per annum. The Supreme Court in the recent line of
judgments reported as Rajendra Construction Co. Vs. Maharashtra Housing
& Area Development Authority & ors.2005 (6) 678, McDermott International
Inc. Vs. Burn Standard Co. Ltd.& ors 2006 (11) SCC 181, Rajasthan State
Road Transport Corpn. Vs. Indag Rubber Ltd. (2006) 7 SCC 700 and Krishna
Bhagya Jala Nigam Ltd. Vs. G.Harischandra, 2007 (2) SCC 720 and State of
Rajasthan Vs. Ferro Concrete Construction Pvt. Ltd (2009) 3 Arb. LR 140
(SC) has held that on account of consistent fall in the rate of interest the courts
must reduce the rate of interest as granted by the Arbitrator, more so when the
Arbitration proceedings are of a long period. I note in this case, the Award is
more than 11 years old having been passed on 13.7.98. Therefore, in
accordance with the mandate in the aforesaid Supreme Court judgments in the
CS(OS) 1581A/1998 Page 5 facts and circumstances of the case, I feel interest at the rate of 9% per annum
simple ought to be awarded to the contractor. The counsel for the non-objector
has very strenuously relied upon the decision of the Supreme Court in the case
of Sayeed Ahmed Vs.State of UP (2009) 3 ARb. L.R 29. I find that the said
judgment will not apply in the facts and circumstances of the present case
because in that case, the Supreme Court found that the High Court did not
assign any reasons for reducing rate of interest. As already stated above, this
court is giving reasons in law inasmuch as the Supreme Court itself in the chain
of judgments reproduced above has specifically brought to the notice of the
courts that they should be alive to the changed economic scenario and grant a
lower rate of interest accordingly, I am therefore unable to agree with the
contention of the non-objector in this regard. Accordingly, objection petition is
partly allowed to the extent that the claims which are awarded under claimNo.4
and 13 as awarded by the Arbitrator are set aside. Further there is a
modification with respect to claim No.16 for the rate of interest to be 9% per
annum simple meaning thereby where the Arbitrator has awarded interest @
18% per annum or otherwise the rate of interest shall be read as 9% per annum
simple.
10. With the aforesaid modification, the objection petition and the suit
stands disposed of. The Award is made rule of the Court subject to the
CS(OS) 1581A/1998 Page 6 modifications. In case the objector makes the payment of the amount as per this
judgment within 90 days from today then the rate of interest from the date of the
today's judgment till the date of payment shall be 9%. However, in case of
payment after 90 days the rate of interest from the date of this judgment till
payment shall be 11% in terms of Section 29 of the Arbitration Act, 1940. No
order as to costs.
November 18, 2009 VALMIKI J.MEHTA, J Ne/ib CS(OS) 1581A/1998 Page 7
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!