Citation : 2009 Latest Caselaw 4521 Del
Judgement Date : 6 November, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ C.S. (OS) No. 674-A/1997
6th November, 2009.
M/S. PROMINENT ELECTRIC WORKS ..Petitioner
Through: Mr. Vivekanand, Advocate.
VERSUS
DELHI DEVELOPMENT AUTHORITY & ORS. ...Respondents
Through: Ms. Amita Singh, Advocate
CORAM:
HON‟BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see
the judgment?
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be reported in the Digest? Yes
%
JUDGMENT (ORAL)
I.A. No.252/1998 and CS(OS) No.674A/1997
1. These are the objections filed by the petitioner under
Sections 30 and 33 of the Arbitration Act, 1940 against the Award
dated 14.3.1997. The award arises on account of the disputes which
arose between the parties with respect to the work of construction of
C.S(OS)No.674A/1997 Page 1 410 Janta Houses for harijans and landless persons at Peera Garhi,
New Delhi.
2. The facts of this case are that the work was awarded to
the petitioner vide letter dated 14.9.1983 which prescribed the
stipulated date of completion as 24.9.1983. Since the work could not
be completed even well after 24.9.1983, the work in question was
broken up with respect to the balance work which was of the amount
of Rs.33,292/-. For this balance work of Rs.33,292/-, a
supplementary agreement dated 31.8.1988 was entered into between
the parties which prescribed the period for completion of work to be
nine months. The work was however completed on 20.3.1993.
3. The counsel for the objector/petitioner has challenged the
award whereby his claims filed in 1994 have been dismissed as being
time barred, because claims filed were with respect to the main
contract dated 14.9.1983 and which was already closed when the
supplementary agreement dated 31.8.1988 was entered into between
the parties. The counsel for the objector has referred to the
agreement dated 31.8.1988 which uses instead of word „closure‟, the
C.S(OS)No.674A/1997 Page 2 expression "provisional closure". The counsel for the objector
therefore contended that all the disputes under the original agreement
dated 14.9.1983 continued to survive right till the end when the
balance work under the supplementary agreement was ultimately
completed on 20.3.1993. The counsel for the objector/petitioner has
also very heavily relied upon the final bill dated 18.1.1994. The
counsel relying on this final bill has pointed out that this is a
consolidated bill for work done both as per the original agreement as
also the supplementary agreement. He has further referred to the fact
that in the supplementary agreement dated 31.8.1988 there is no date
mentioned for completion of work under the contract dated
14.9.1983. Per contra the counsel for the non-objector, however,
urges that two views are possible for this expression „provisional
closure‟ as used in the letter dated 31.8.1988. She has further urged
that one of the acceptable views can certainly be as held by the
Arbitrator that the original contract was closed whereby the claims
under the same ought to have been filed when the same was closed in
1988 and not in 1994 and only the balance work remained to be
performed by means of the fresh agreement titled as supplementary C.S(OS)No.674A/1997 Page 3 agreement thereby nothing remained to be done under the original
agreement, and this Court while hearing objections under Sections 30
and 33, has repeatedly held that it will not interfere with the Award if
two views are possible. Consequently, the Arbitrator having taken one
view which shows that the first contract was closed when the
supplementary agreement was signed on 31.8.1988, claims had to be
filed within three years from that date so far as the claims under the
first contract and which admittedly was not done. It was, therefore,
urged that the conclusion on the issue of limitation as held by the
Arbitrator, therefore, is clearly justified.
4. I feel that the contention of the objector is correct and
merits acceptance. In the final bill dated 18.1.1994, there is a specific
mention of the actual date of completion of work, which was not
mentioned in the Supplementary Agreement dated 31.8.1988, and,
which final bill is with reference not only to the original agreement of
1983 but also for the supplementary agreement dated 31.8.1988. This
final bill also while referring to both the contracts mentions the date
of closure not as the date of the supplementary agreement dated
C.S(OS)No.674A/1997 Page 4 31.8.1988 but 20.3.1993 which is inclusive of the work completed
after the supplementary agreement dated 31.8.1988. A reference to
the final bill and the entries contained therein does definitely show
that it was a consolidated bill for both the agreements and since it was
a consolidated bill for both the contracts, it refers to payments made
under the first contract also. Consequently the Arbitrator so far as
having determined the issue that the claims for the agreement which
began in 1983 are barred by limitation does not appear to be correct
considering the fact of this admitted document being the final bill.
The Arbitrator has while arriving at the conclusion that the claims are
barred by limitation has referred to the supplementary agreement
which is the document earlier in point of time dated 31.8.1988, but
has not referred to the vital, crucial and admitted later document
being the final bill dated 18.1.1994. By not considering this most
relevant document, the Arbitrator has mis-conducted himself and the
proceedings as per K.P Poulose Vs. State of Kerala, (1975)2SCC 326.
How the parties understand the terms of a contract is best understood
by their actions in terms of such a contract (vide Godhra Electricity
Company Vs. State of Gujrat, AIR 1975 SC32). I consequently hold C.S(OS)No.674A/1997 Page 5 that the findings of the Arbitrator of the claims being time barred are
illegal and hence liable to be set aside. The objections are therefore
allowed, though for the record only, as the objections have to be
ultimately dismissed as held by me later in this judgment.
5. The issue which now I have to consider is what to do in a
very old case like the present one where the contract is more than 26
years old and work under which contract was duly completed more
than 16 years from today. Once the issue of limitation is decided in
favour of the petitioner/objector, and it is held that the Arbitrator was
not justified in dismissing the claims on the ground that the same were
barred by the limitation, the issue is that while hearing objections
under Sections 30 and 33 of the Arbitration Act, 1940 is it necessary
for the Court to necessarily remit the matter back to the Arbitrator for
redetermination or can the Court look into the merits of the disputes
itself for arriving at a final decision itself . I am of the opinion that in a
particular case where detailed and lengthy arguments on many issues
are required, many documents are to be looked into, detailed
evidence has to be considered, that case may be a case where the
C.S(OS)No.674A/1997 Page 6 matter may have to be remitted, but, is it so required also in such a
case where it is obvious from the facts as pleaded and the evidence as
led that remission would serve no purpose inasmuch as the
conclusions which are to be arrived at are obvious from the
arbitration record. I am of the firm opinion that this Court can, in
such a latter scenario, the Court can as well look into the issue with
respect to the merits of the claims which are made since not much
time is to be taken for arriving at a decision on those issues. Every civil
court has inherent power under Section 151 CPC to do justice and I,
therefore, invoke this power in the facts and circumstances of this case.
Accordingly, in view of the fact of the pendency of these disputes
since the last over 16 years and the objections itself having been filed
in the year 1997 i.e. more than 12 years back and the state of the
pleadings and evidence as led before the Arbitrator, I have persuaded
myself to look into the issue as regards the merits of the claims which
were made by the claimant before the Arbitrator. Long pendency of
litigation itself is a prejudice which ought to be addressed.
C.S(OS)No.674A/1997 Page 7
6. The main claims which have been rejected by the
Arbitrator, for the main contract of the value of Rs.3,89,688/- and the
supplementary agreement of the value of Rs.33,292/-, are
disproportionately high when compared to the value of the contracts.
Some of the claims are:- a claim of Rs.5,00,000/- for loss on account
of overheads at site; at head office; alongwith loss and profits due to
prolongation of the contract, a claim of Rs.3,15,000/- as damages on
account of idle labour and staff due to prolongation of work, a claim
of Rs.1,25,000/- on account of increase in cost of material and labour
and so on. On looking at all these claims as per the claim petition, I
enquired from the counsel for the objector that what is the break-up
of these claims because no break-up of the same as relatable to which
contract i.e. they pertain to the period of the original contract period
or the supplementary contract period and considering type/nature of
the claims whether they have been effectively broken up for the two
different periods and in what manner each of these claims is
established and proved before the Arbitrator. The counsel for the
objector in this regard has been very fair in stating that there is no
break up available in the claim petition with regard to the different C.S(OS)No.674A/1997 Page 8 heads of claims or otherwise. The counsel for the objector said that
the claims are conjoint claims for the complete period right from the
work being awarded in 1983 till the same was completed in 1993.
The next question then posed by me to the counsel for the objector is
how and in what manner these claims have been substantiated by
filing of the requisite evidence before the Arbitrator if the same have
to be allowed. To this, the counsel says that arbitrators are experts in
the field and no evidence is required and consequently, such claims
can be regularly allowed by the Arbitrator.
7. I do not agree at all with the contention which has been
urged by counsel for the objector. Surely, mere statements contained
in the statement of facts or pleadings without being supported by
evidence cannot mean that in spite of the same having not been
proved as required by the doctrine of discharge of onus on balance of
probabilities, leave alone to the complete conviction of the Arbitrator,
yet such status can still entitle the contractor/claimant to the damages
as claimed. This argument urged by the objector is against all cannons
of justice, equity, law and the principle of burden/discharge of proof.
C.S(OS)No.674A/1997 Page 9 No doubt burden of proof in a civil case is on balance of probabilities
but surely some reasonable amount of evidence has to be there on the
basis of which an Arbitrator can make an honest guess work for
allowing the claims. It is not an argument available to the
contractor/claimant to say that on the basis of very tennuous and
almost non existent evidence, the Arbitrator is entitled to make a guess
work merely because he is allegedly an expert in the field being an
Engineer. The Arbitrator being an engineer cannot mean that basic
minimum requirements of the Evidence Act have to be thrown to the
winds when huge monetary liability by the Award can be fastened on
to the opposite party. Surely basic and fundamental principles of
Evidence Act, 1872 are applicable even to arbitration proceedings. I
find that, and which could not be at all rebutted by the objector, that
there is no evidence as available before the Arbitrator to discharge the
onus of proof as required in a civil case. The claimant has therefore
miserably failed to discharge the onus, which he has to, in order to
succeed in establishing the claims. The claims, therefore, as filed are
clearly liable to be dismissed.
C.S(OS)No.674A/1997 Page 10
8. Accordingly, though the objection petition is allowed for
the purpose of record in that it is held that the Arbitrator was not
justified in holding the claims to be beyond limitation, however,
having examined the merits of the matter with respect to the claims
which were made before the Arbitrator, and the other details
including the evidence. I am of the opinion that objection petition is
liable to be dismissed and it is not required that the matter should be
remitted to the Arbitrator for fresh consideration. Accordingly, the
objection petition is dismissed and the Award is made the rule of the
Court.
9. At this stage, the counsel for the objector has relied upon
Union of India Vs. Madhya Pradesh Export Corporation Ltd.
1998(suppl.) Arb.LR. 618 to contend that this Court should not
decide the issue on merits. I find that the said judgment is only with
respect to modification or correction of the Award and not with
respect to the fact whether if on account of delays caused by long
pendency of cases and the lack of evidence a Court cannot and shall
not look into the case on merits and it is necessary that an exercise in
C.S(OS)No.674A/1997 Page 11 futility should and ought to be resorted to by referring the matter back
to the Arbitrator though the same will serve no purpose because the
claims in no circumstances are at all proved as the onus to prove the
claims has not even been the least bit discharged.
The Supreme Court in the Constitution Bench case reported as
Padma Sundra Rao Vs. State of Tamil Nadu 2002(3)SCC 533 has held
that the ratio of a case has to be read with reference to the facts of
each particular case and even a single fact which is different may make
a difference to the ratio. Thus on the facts of the present case I do not
find the judgment cited by the Objector is applicable.
10. Ordinarily, I would have imposed costs for disposal of the
objections, however, since objections are for the purpose of record
qua the issue of limitation allowed, but since ultimately the objections
are being dismissed because I am not remitting back to the Arbitrator,
I am not imposing costs in the matter and leave the parties to bear
their own costs.
VALMIKI J.MEHTA, J
November 6, 2009
Ne
C.S(OS)No.674A/1997 Page 12
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!