Citation : 2009 Latest Caselaw 2260 Del
Judgement Date : 26 May, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 26th May, 2009
+ ARBITRATION PETITION NO.246 OF 2005
M/S. CHANDER KANT & CO. ..... Petitioner
Through: Mr. R. Rajappan, Advocate.
versus
THE VICE CHAIRMAN, DDA & ORS. ..... Respondents
Through: Ms. Geeta Mehrotra,
Advocate for DDA/R-1 to 3.
Mr. Puneet Taneja, Advocate
for respondent No.4.
CORAM:
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE NEERAJ KISHAN KAUL
1. Whether Reporters of the local newspapers may be allowed to
see the judgment?
2. Whether to be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
AJIT PRAKASH SHAH, CJ (ORAL)
1. This is a petition under Section 11 (5) of the Arbitration
& Conciliation Act, 1996 for appointment of an arbitrator to
adjudicate the disputes between the parties. The petitioner had
entered into a contract with the respondents/DDA for construction of
256 numbers L.I.G. Houses at Kondali/Gharli, Delhi as per letter
dated 10.9.1985 under agreement No.13/EE/HDXXII/DDA/85-86.
The contract was to be completed on or before 19.9.1986, i.e., within
twelve months. The work was completed on 11.10.1990. The final
bill was released on 7.11.2002 after withholding various amounts.
The petitioner raised several claims and disputes with the DDA. The
agreement contained an arbitration clause. The petitioner invoked
the arbitration clause vide notice dated 17.6.2004. The respondents
failed to respond to the notice of the petitioner and, hence, the
Arb. P. No.246/2005 Page No.1 of 12
petitioner has approached this Court under Section 11 (5) of the
Arbitration & Conciliation Act for appointment of an arbitrator.
2. The petition is opposed by the DDA mainly on the ground that it
is barred by virtue of Clause 25 of the agreement. According to the
respondents, the requirement of this Clause is that on the final bill
being ready for payment, the arbitration clause should be invoked
within 90 days thereafter. Failure to make demand for arbitration
within 90 days would result in forfeiture or waiver of the right.
3. When this petition was placed before one of us (the Chief
Justice), it was contended on behalf of the petitioner that Clause 25
dealing with the period of limitation is invalid in view of the amended
provisions of Section 28 (b) of the Indian Contract Act. In this
connection, reliance was placed on the judgment of Mohd. Shamim,J.
in Hindustan Construction Corporation Vs. Delhi Development
Authority; 1999 (1) Arb. LR 272 (Delhi) and that of M.K. Sharma, J.
(as he then was) in Kalyan Chand Goyal Vs. Delhi Development
Authority; 1999 (3) Arb. LR 79 (Delhi) as well as two judgments of
Sanjay Kishan Kaul, J. in Explore Computers Pvt. Ltd. Vs. Cals Ltd. &
Anr.; 131 (2006) DLT 477 and in Pandit Construction Company Vs.
Delhi Development Authority; 2007 (3) Arb. LR 205 (Delhi). On behalf
of the respondents/DDA, however, it was contended that these
decisions no longer hold good in view of the recent judgment of the
Supreme Court in P. Manohar Reddy & Bros. Vs. Maharashtra
Krishna Valley Development Corporation & Ors.; 2009 (2) SCC 494
wherein a similar clause in the contract was held to be valid and
binding. As the issue is of some importance it was deemed
appropriate to refer the matter to a larger bench.
4. The question that thus falls for our consideration is
whether there can be such limitation of a period of 90 days in view of
the amended provisions of Section 28 (b) of the Indian Contract Act
read with Article 137 of the Limitation Act. Clause 25 of the
agreement which is material for our purpose reads as follows:
"CLAUSE 25 Except where otherwise provided in the contract all questions and disputes relating to the specifications, designs drawings and instruction herein before mentioned and as to the quality in workmanship or materials used on the work out of or relating to the contract designs drawings, specifications estimates, instruction, orders or these conditions or otherwise concerning the words or the execution or failure to execute the same whether arising during the progress of the work or after the completion or abandonment thereof shall be referred to the sole arbitration of the person appointed by the Engineer Member Delhi Development Authority at the time of dispute. It will be no objection to any such appointment that the arbitrator so appointed is a Delhi Development Authority employee that he had to deal with the matters to which the contract relates and that in the course of his duties as Delhi Development Authority employees he had expressed view on all or any of the matters in dispute of difference. The arbitrator to whom the matter is originally referred being transferred or vacating his office or being unable to act for any reason, such Engineer Member Delhi Development Authority as aforesaid at the time of such transfer, vacation of office or inability to act shall appoint another person to act as arbitrator in accordance with the terms of the contract. Such person shall be entitled to proceed with the reference from the stage at which it was left by his predecessor it is also a term of this contract that no person other than a person appointed by such Engineer Member, Delhi Development Authority as aforesaid should act as arbitrator and, if for any reason that is not possible, the matter is not to be referred to arbitration at all. In
all cases where the amount of the claim in dispute is Rs. 50,000/- (Rupees Fifty thousand) and above, the arbitrator will give reason for the award.
Subject as aforesaid the provisions of the Arbitration Act, 1940 or any statutory modification or re- enactment thereof and the rules made thereunder and for the time being in force shall apply to the arbitration proceeding under this Clause. It is a term of the contract that the party invoking arbitration shall specify the dispute or disputes to be referred to arbitration under this clause together with the amount or amounts claimed in respect of each such dispute.
It is also a term of the contract that if the contractor
(s) does/do not make any demand for arbitration in respect of any claim (s) in writing within 90 days of receiving the intimation from the Engineer-in-Charge that the Bill is ready for payment, the claim (s) of the contractor (s) will be deemed to have been waived and absolutely barred and the Delhi Development Authority shall be discharged and released of all liabilities under the contract in respect of those claims."
(emphasis supplied)
5. Section 28 of the Indian Contract Act before amendment
read as follows :-
"Section 28. Agreements in restraint of legal proceedings, void - Every agreement, by which any party thereto is restricted absolutely from enforcing his rights under or in respect of any contract, by the usual legal proceedings in the ordinary tribunals, or which limits the time within which he may thus enforce his rights, is void to that extent.
Exception 1 - Saving of contract to refer to arbitration dispute that may arise - This section shall not render illegal a contract, by which two or more persons agree that any dispute which may arise between them in respect of any subject or class of subjects shall be referred to arbitration, and that only the amount awarded in such arbitration shall be recoverable in respect of the dispute so referred.
Exception 2 - Saving of contract to refer questions that have already arisen - Nor shall this section render illegal any contract in writing, by which two or more persons agree to refer to arbitration any question between them which has already arisen, or
affect any provision of any law in force for the time being as to reference to arbitration."
6. Section 28 was amended by Indian Contract
(Amendment) Act, 1996 (Act 1 of 1997) with effect from 8.1.1997 and
amended Section 28 reads as follows :-
"28. Agreements in restraint of legal proceedings, void - Every agreement,
(a) by which any party thereto is restricted absolutely from enforcing his rights under or in respect of any contract, by the usual legal proceedings in the ordinary tribunals, or which limits the time within which he may thus enforce his rights; or,
(b) which extinguishes the rights of any party thereto, or discharges any party thereto, from any liability, under or in respect of any contract on the expiry of a specified period so as to restrict any party from enforcing his rights, is void to that extent.
Exception 1 : Saving of contract to refer to arbitration dispute that may arise - This section shall not render illegal a contract by which two or more persons agree that any dispute which may arise between them in respect of any subject or class of subjects shall be referred to arbitration, and that only the amount awarded in such arbitration shall be recoverable in respect of the dispute so referred.
Exception 2: Saving of contract to refer questions that have already arisen - Nor shall this section render illegal any contract in writing by which two or more persons agree to refer to arbitration any question between them which has already arisen, or affect any provision of any law in force for the time being as to references to arbitration."
7. Before the amendment of Section 28 in 1997, the
agreements reducing the period of limitation were distinguished from
those which did not limit the time within which a party might enforce
his rights, but which provided for a release or forfeiture of rights if no
suit was brought within the period stipulated in the agreement; and
the latter class of agreements, outside the scope of the present
section, were binding between the parties. Thus, in National
Insurance Co. Ltd. Vs. Sujir Ganesh Nayak & Co.; AIR 1997 SC 2049,
the Supreme Court drew a clear distinction between the agreement
which in effect curtails the period of limitation and an agreement
which provides for the forfeiture or the waiver of the right itself if no
action is commenced within the period stipulated by the agreement.
The first was held to be void as offending under Section 28 but the
later was held not to be a clause which shall fall within the mischief
of the Section 28. It was, thus, held that curtailment of the period of
limitation is not permissible in view of Section 28 but extinction of
the right itself unless exercised within the specified time is
permissible and can be enforced. This view was reiterated in Wild
Life Institute of India, Dehradun Vs. Vijay Kumar Garg; (1997) 10 SCC
528. Earlier the Supreme Court in the case of Vulcan Insurance Co.
Ltd. Vs. Maharaj Singh; 1976 (1) SCC 943 had taken the same view.
8. The 1997 Amendment to the Section now also prohibits
clauses which seek to extinguish the rights of any party thereto, or
discharge any party from any liability under or in respect of any
contract on the expiry of a specified period so as to restrict any party
from enforcing his rights. The amendment gave effect to the 97th
report of the Law Commission of India. The effect of the amended
Section 28 was considered by the learned single judges of this Court
in Hindustan Construction Company Vs. DDA; Kalyan Chand Goyal
Vs. Delhi Development Authority (supra); J.K. Anand Vs. DDA & Anr.;
2001 (59) DRJ 380 and Union of India Vs. Simplex Concrete Piles India
(P) Ltd.; 2003 (3) Arb. LR 536 (Delhi) in which similar causes were held
to be not valid in view of the amended provisions of Section 28 (b) of
the Contract Act. In Explore Computers Pvt. Ltd. Vs. Cals Ltd. & Anr.
(supra), Sanjay Kishan Kaul, J considered the decision of Supreme
Court in National Insurance Co. Ltd. Vs. Sujir Ganesh Nayak & Co.
(supra) and other decisions and held as follows :-
"48. The effect of the amendment of Section 28 thus made it clear that any clause extinguishing the right of a party or discharging any party from the liability in respect of any contract on expiry of specific period so as to restrict the time period would be void.
53. On a conspectus of the aforesaid judgments, two aspects have to be noted. The first is that it is the terms of the bank guarantee which have to be given due weight and the second is the distinction which is sought to be carved out in National Insurance Company Ltd. Case between a clause curtailing the period of limitation being void under Section 28 of the Contract Act and a clause which provides for forfeiture or waiver of a right if no action is commenced within the period stipulated by the agreement. Insofar as the second aspect is concerned, it cannot be lost sight of that the judgment in National Insurance Company Ltd. Case was delivered on 23.3.1997 and thus related to the provisions of Section 28 as it stood prior to the amendment because that was the substantive law in force at the time when the cause of action had arisen. The amendment to Section 28 was made with effect from 8.1.1997 and it is not disputed that the cause of action in respect of the subject matter in the present suit arose after the amendment. Sub-clause (b) of the amended Section 28 deals with the clauses which extinguish the rights of any party thereto or discharge any party from any liability being void under the said section. Thus, the scope of Section 28 has been widened whereby clause (a) deals with the position prior to the amendment alone and clause (b) is in addition.
54. In view of the amended section coming into force, the distinction sought to be carved out earlier by the legal pronouncements would not hold good.
55. In my considered view it is not open for defendant no.2 to contend that if any suit or claim is not filed within one month of the expiry of the bank guarantee,
the right of the plaintiff to institute any legal proceedings itself is extinguished. Such a plea would fly in the face of the amended Section 28 as defendant no.2 cannot be discharged from the liability nor can the rights of the plaintiff be extinguished by inclusion of the clause providing so. I am thus of the considered view that to the extent there is restriction on any suit or claim being filed by the plaintiff beyond a period of one month from the expiry of the bank guarantee, the said clause would not prohibit the plaintiff from instituting the suit as it would be barred by the provisions of the amended Section 28 of the Contract Act."
9. We are in respectful agreement with the view taken by
the learned Judge. In our opinion, in view of the amendment, the
distinction which was drawn earlier has been obliterated and the
clauses providing for extinction or discharge of the rights of the
parties on the expiry of the specified period are also covered by
inserting Clause (b) in Section 28 of the Contract Act.
10. The contention of the DDA's counsel that the decisions of
this Court no longer hold good in view of the decision in P.Manohar
Reddy's case is misconceived. That decision is clearly
distinguishable on facts. In that case Clause 54 of the contract
provided that if the contractor considers any work demanded of him
outside the requirements of the contract, he shall promptly ask the
Executive Engineer, in writing, for written instructions or decisions.
Thereupon, the Executive Engineer shall give his written instructions
or decision within a period of 30 days of such request. If the
Executive Engineer fails to give his decision in writing within a period
of 30 days after being requested, or if the contractor is dissatisfied
with the instructions or decision of the Executive Engineer, the
contractor may within 30 days after receiving the instructions or
decision, appeal to the upward authority who shall afford an
opportunity to the contractor to be heard and to offer evidence in
support of his appeal. It was further provided that if the contractor is
dissatisfied with this decision, the contractor within a period of 30
days from receipt of the decision shall indicate his intention to refer
the dispute to arbitration as per Clause 55 failing which the said
decision would be final and conclusive. Clause 55 of the contract
provided that all the disputes or differences in respect of which the
decision has not been final and conclusive as per Clause 54 shall be
referred for arbitration to a sole arbitrator appointed in the manner
prescribed by that clause. It is thus seen that Clause 54 of the
contract did not seek to forfeit or extinguish the right of the
contractor but it merely provided that failure to make a demand for
arbitration within the specified time would make the decision final
and conclusive and consequently such claim will not be referable to
arbitration under Clause 55 of the contract. In other words, the
claim would fall in excepted category. The argument before the
Supreme Court was that the limitation for raising a claim as
envisaged under Clause 54 was not applicable to the case and in view
of the fact that the claim was rejected only on 26.2.1992 by the
appellate authority, the period of 30 days ought to have been counted
therefrom and it was also argued that under Section 8 of the
Arbitration Act, the court was concerned only with the question as to
whether there was a triable issue. Repelling the argument, the
Supreme Court held as follows:
"18. The arbitration clause, thus, could be invoked only in a case where the decision has not become final and conclusive as per Clause 54.
19. A plain reading of the aforementioned provisions clearly shows that Clause 54 does not envisage raising of a claim in respect of extra or additional work after the completion of contract. The jurisdiction of the civil court under Section 8 of the Act or under Section 20 thereof can be invoked if the disputes and differences arising between the parties was the one to which the arbitration agreement applied.
20. The contractual clause provides for a limitation for the purpose of raising a claim having regard to the provisions of Section 28 of the Contract Act. It is no doubt true that the period of limitation as prescribed under Article 137 of the Limitation Act would be applicable, but it is well settled that a clause providing for limitation so as to enable a party to lodge his claim with the other side is not invalid."
11. In P.Manohar Reddy's case the Supreme Court had no
occasion to consider the effect of the insertion of Clause (b) in Section
28 by Amending Act 1 of 1997. The Court did refer to the judgments
in Vulcan Insurance Co. Ltd. Vs. Maharaj Singh and Wild Life Institute
of India, Dehradun Vs. Vijay Kumar Garg but it was obvious that the
observations were made in the context of unamended Section 28 of
the Contract Act. It is also seen from the judgment that the cause of
action had arisen in that case on 29.10.1991 on which date the
appellant's claim was rejected. It is thus clear that the Court
considered the case in the light of the unamended provisions of
Section 28 of the Contract Act.
12. The next contention raised by learned counsel appearing
for DDA is that the contract was executed prior to the amendment to
Section 28 and, therefore, the case would be governed by unamended
Section 28 of the Contract Act. In support of his submission, she
placed reliance on the judgment of V.S. Aggarwal, J. in Continental
Construction Ltd. Vs. Food Corporation of India and others; AIR 2003
Delhi 32 where learned judge observed in paragraph 11 as under :-
"Section 28 of the Contract Act as reproduced above was introduced on the recommendation of the Law Commission in order to remove the anomalies created by the earlier Act. The position of law settled before the amendment was that Section 28 would invalidate only a clause in an agreement which restricts a party from enforcing his right absolutely or which limits the time within which he may enforce his right. Section 28 before the amendment does not come into operation when contractual term spell out an extension of a right of a party to sue or spell out the discharge of a party from the liabilities. It is true that the argument of the applicant's learned counsel as per the amended provisions of Section 28 of the Act would come to his rescue but the snag in the argument is that Section 28 of the Contract Act as amended is not retrospective in its operation. The present contract between the parties had been arrived at before the amendment and even the work executed before that. Consequently, the provisions of the amended provisions of Section 28 of the Contract Act will not have a role to pay, so far as the present dispute is concerned. In that view of the matter the said argument so much thought of will be of little avail."
13. In our opinion, the aforesaid observations are not of any
assistance to the counsel for the DDA. That was a case where not
only the contract was arrived at between the parties before the
amendment but even the work was executed before the amendment.
In the present case, it is not in dispute that though the contract may
have entered into before the amendment to Section 28 starting right
from the preparation of the final bill everything has happened after
the amended provision came into play and thus the amended
provision would certainly apply to the contract in question. In the
present case, the final bill was released only in 2002 and, thus, the
provisions of amended Section 28 are clearly attracted.
14. In the result, we allow the petition. Considering the fact
that under Clause 25 Engineer Member, DDA was empowered to
appoint any person as arbitrator including an employee of the DDA
and that no specific qualification was prescribed for the appointment
of the arbitrator Sh. Dinesh Dayal, retired District Judge is appointed
as a sole arbitrator to adjudicate upon the disputes between the
parties. The fee of the arbitrator is fixed at Rs.1,25,000/- (rupees
one lac twenty five thousand), to be borne by both the parties equally.
The petition stands disposed of accordingly.
CHIEF JUSTICE
NEERAJ KISHAN KAUL, J.
MAY 26, 2009 'AA/nm'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!