Citation : 2009 Latest Caselaw 1906 Del
Judgement Date : 6 May, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ W.P.(C) 1512/1980
Reserved on : 05.02.2009
Date of decision : 06.05.2009
IN THE MATTER OF :
M/S AJAY ENTERPRISES P. LTD. & ANR. ..... Petitioners
Through: Mr. Harish Malhotra, Sr. Adv. with
Mr. Tanuj Khurana and
Mr. Vipul Gupta, Advs.
versus
MCD & ORS. ..... Respondents
Through: Mr. Ajay Arora and Mr. Kapil Datta, Advs.
for MCD.
CORAM
* HON'BLE MS.JUSTICE HIMA KOHLI
1. Whether Reporters of Local papers may
be allowed to see the Judgment? Yes.
2. To be referred to the Reporter or not? Yes.
3. Whether the judgment should be
reported in the Digest? Yes.
HIMA KOHLI, J.
1. The present writ petition is filed by the petitioners praying inter
alia for a declaration that the respondent No.1/MCD has no power and
authority to forfeit 25% of the bid amount deposited by the petitioners
towards the auction of two commercial plots bearing Nos.D-3 and D-4, at
Najafgarh Road Community Centre, Opposite Milan Cinema, Karampura,
Delhi and declare that the said forfeiture is illegal. In the alternative, a
declaration is sought by the petitioners to the effect that there was no
proper completed auction for want of approval of the highest bid by the
respondent/MCD and hence the amount received by the respondent No.1
has to be refunded to the petitioners with interest payable @ 18% per
annum. The petitioners have also sought quashing of notices, including the
notice dated 24.10.1980 issued by the respondents, forfeiting the earnest
money deposited by the petitioners in respect of the aforesaid plots and for
re-auctioning of the said plots. The last relief sought by the petitioners is for
directions to the respondent/MCD to carry out development of the
Community Centre, in accordance with law before demanding the balance of
the premium in respect of the bid amounts for the two plots from the
petitioners, or in the alternative, for directions to the respondent/MCD to
refund to the petitioners, the earnest money received in respect of the
aforesaid plots.
2. At the outset, counsel for the petitioners stated that he did wish
to press for the relief of declaration to the effect that there was no proper
completed auction for want of approval of the highest bid by the competent
authority, as the MCD had been superceded by the Government of India, at
the relevant time under the provisions of Section 490 of the Delhi Municipal
Corporation Act, on the ground that the said issue had been conclusively
decided by a judgment of the Division Bench dated 25.07.2008 in two
appeals, registered as RFA(OS) Nos.12 & 14 of 1983 arising out of a
common judgment and decree dated 9.3.1983 passed in two connected suits
instituted by two private parties against the MCD, pertaining to two
commercial plots put to auction by MCD in the year 1976, in the very same
Commercial Complex, i.e., the Najafgarh Road Community Centre. Vide
judgment dated 25.7.2008, the effect of dissolution of the MCD was duly
considered and the Division Bench concurred with the findings of the Single
Judge to the effect that even though the Corporation stood superceded, the
Central Government, by virtue of a Notification, had empowered the
Commissioner, MCD to exercise the powers and perform the duties conferred
upon the Corporation by or under the Act. This leaves the relief with regard
to refund of the earnest money deposited by the petitioners and forfeited by
the respondents.
3. The facts of the case, when encapsulated, are that in May 1979,
the respondent/MCD issued an advertisement in the National newspapers
proposing to auction eight commercial plots situated at Najafgarh Road
Community Centre, Opposite Milan Cinema, Karampura, Delhi. The terms
and conditions of the auction stipulated that the successful bidder would pay
25% of the bid amount at the fall of the hammer and the balance was to be
paid within two months from the date of the receipt of the acceptance letter.
The relevant extract of the advertisement issued by the respondent/MCD in
the press reads as below :
"The MCD will dispose of, on perpetual lease hold basis, the following four storeyed commercial plots in the above noted Community Centre situated on the road connecting main Najaf Garh Road with Punjabi Bagh on Sunday, 10th June, 1979 at 10-30 a.m. in the Municipal Auditorium, Town Hall, Chandni Chowk, Delhi. The centre has a provision of large number of four storeyed commercial shop-cum-office unit plots of various sizes".
4. In response to the aforesaid advertisement, the petitioner No.1
participated in an auction held on 16.6.1979 and was declared the highest
bidder in respect of plots No.D-3 and D-4. It is an undisputed position that
though the petitioners paid 25% of the bid amount at the fall of the
hammer, the balance 75% of the bid amount was not deposited by them
within the stipulated time or even thereafter. It is also not disputed by
either side that the time for depositing the balance 75% of the bid amount
could be extended by a period of 1 year, after a lapse of 2 months from the
date of the receipt of the acceptance letter.
5. Counsel for the petitioners referred to the letter dated 15.5.1980
sent by the petitioners to the respondent/MCD to indicate that they did not
deposit the balance bid amount for the reason that the Community Centre
had not been developed by the respondent/MCD, contrary to its promise.
In the aforementioned communication, the petitioners pointed out a number
of unauthorized shops and tombs that existed right in front of the
Community Centre, which were not removed. At the end of the said letter,
the petitioners requested the respondent/MCD for permission to make full
and final payment by 22.8.1980, along with interest payable in accordance
with terms and conditions of the bid.
6. Counsel for the petitioners relied upon Resolution No.63 of the
Works Committee of the respondent/MCD dated 5.8.1970 and the Resolution
No.641 to contend that it was incumbent for the respondent/MCD to have
developed the Community Centre at Karampura before putting the plots in
question, to public auction and that having failed to undertake the
development, the respondent/MCD could not have taken steps to dispose of
the plots by a public auction on a perpetual lease hold basis. He stated that
as the respondent/MCD failed to take any steps to develop the community
centre, it could neither have demanded the balance bid amount from the
petitioners, nor could it have forfeited the amount paid by the petitioners or
put the plots for re-auction.
7. In support of his contention that Section 74 of the Contract Act
does not permit any forfeiture by the respondent without the loss being
proved and the onus to prove such loss or damage on account of breach so
committed is on the forfeiting party, which option should be exercised as a
last resort, counsel for the petitioners relied on the following judgments:
(1) Fateh Chand Vs. Balkrishan Dass AIR 1963 SC
(2) Maula Bux Vs. Union of India AIR 1970 SC 1955
(3) Union of India Vs. Rampur Distillery & Chemical Co.Ltd. AIR 1973 SC 1098
(4) Teri Oat Estates (P) Ltd. Vs. U.T.Chandigargh and others (2004) 2 SCC 130
(5) Kailash Nath and Associates Vs. Delhi Development Authority & Anr. 144(2007) DLT 1
(6) Jagmohan Singh Vs. State of Punjab and others 2008 7 SCC 38
8. Counsel for the respondent/MCD disputed the aforesaid stand of
the petitioners and stated that the petitioners were in gross default of the
terms and conditions of auction and having failed to pay the balance amount
in accordance with the terms and conditions of the auction, the
respondent/MCD was well within its right to forfeit 25% of the bid amount
deposited by the petitioners. He further stated that even a perusal of the
correspondence emanating from the petitioner No.1 establishes that the
petitioners did not rely upon Resolution No.63 dated 5.8.1970 or Resolution
No.641 to claim that construction of a Community Shopping Centre at
Karampura was a pre-condition for the petitioners to deposit the balance bid
amount and that the said plea is a sheer after-thought. He argued that the
tone and tenor of the correspondence between the petitioners and the
respondent/MCD reflects that the anxiety of the petitioners was primarily to
seek extension of time for paying the balance bid amount and that its claim
of non-development of the Community Centre or existence of unauthorized
shops and tombs in front of the Community Centre, were only lame excuses
to buy time.
9. Before dealing with the respective contentions of the parties, it
would be appropriate to examine the terms and conditions of the auction. As
already noted above, the respondent/MCD had proposed to dispose of on a
perpetual leasehold basis, the four storeyed commercial plots in the
Community Centre by way of auction to be held on 10.6.1979, for which
Rs.1,000/- was required to be deposited as an advance security. 25% of the
bid amount was to be deposited at the fall of the hammer and the balance
amount was to be paid within two months from the date of acceptance
letter. Apart from the contents of the terms and conditions of the auction,
as contained in the Press Release enclosed with the writ petition as
Annexure P-2, both the parties have also referred to the document entitled,
"Terms and Conditions for the sale by auction by the Municipal Corporation
of Delhi of Commercial Plots on perpetual lease-hold basis", which governed
all plots put up for auction by the respondent/MCD at the relevant time.
Clause II referred to "Bidding at Auction etc.". For the purpose of the
present petition, Clauses II (2), (4) and (6) being relevant, are reproduced
hereinbelow for ready reference :
"II. Bidding at Auction etc.:
(1) XXXX
(2) The highest bidder shall, at the fall of the hammer, pay to the Municipal Corporation of Delhi through the officer conducting the auction 25% of the bid amount as earnest money either in cash or by Bank draft or cheque guaranteed by a scheduled Bank as "good for payment for three months" drawn in favour of the Municipal Corporation of Delhi. In the event of non-payment as above, the auction in respect of that plot shall stand cancelled.
(3) xxxxxx
(4) In case of breach of or non-compliance with any of the terms and conditions of the auction or misrepresentation by the bidder the earnest money shall be liable to be forfeited in whole or in part as the circumstances of the case may warrant.
(5) xxxxxx
(6) Within two months of the receipt by him of communication of acceptance of his bid the intending purchaser shall pay to the Municipal Corporation of Delhi the balance amount of the bid in cash or by Bank Draft or cheque guaranteed by a schedule bank as "good for payment for three months" drawn in favour of the Municipal Corporation of Delhi. In appropriate cases, the balance amount of the bid may be accepted upto six months with interest at the rate of 15% per annum and
beyond six months upto a maximum period of one year with interest at the rate of 18% per annum. "
10. Thus it is clear that not only the terms and conditions of the
auction as released in the press, but also the terms and conditions for the
sale mandated that 25% of the bid amount was to be paid by the successful
bidder at the fall of the hammer. The consequences of non-payment were
elaborated in clause II(2) of the terms and conditions of sale which
stipulated that in the event of non-payment of the 25% of the bid amount as
earnest money, the auction in respect of the plot would stand cancelled.
Clause II(4) contemplated that in the case of breach of or non-compliance
with any of the terms and conditions of the auction or in the case of
misrepresentation by the bidder, the earnest money would be liable to be
forfeited in whole or in part as the circumstances of the case may warrant.
The respondents relied on the aforesaid terms and conditions of the auction
to forfeit the earnest money deposited by the petitioner.
11. The plea of the petitioners that they repeatedly took up the issue
of development of the site with the respondents and on account of failure on
the part of the respondents to take any steps in that regard, the petitioners
did not pay the balance 75% of the bid amount, has to be examined in the
light of the correspondence between the parties. The original file produced
by the respondents shows that the petitioners wrote a number of letters to
the respondents, including letters dated 16.8.1979, 10.11.1979, 18.2.1980,
22.3.1980 and 15.5.1980. In all the aforesaid communications, the
petitioners mentioned their inability to make necessary arrangement for
payment of the balance amount due to "stringent financial conditions and
credit squeezed by the banks". In the letter dated 15.5.1980, the
petitioners claimed that they had called upon the respondent to remove the
unauthorized shops and tombs for proper development of the Community
Centre. However, a perusal of the aforesaid letter shows that the same was
not issued suo motu by the petitioners, but was written in response to a
letter dated 13.5.1980 issued by the respondent/MCD to the petitioners,
calling upon them to make full and final payment in respect of the plots in
question within three days. It is also relevant to note that even prior thereto,
the respondent/MCD had written a letter dated 4.4.1980, followed by a letter
dated 28.5.1980, to the petitioner No.1 giving it a final opportunity to pay
the balance bid amount and warning it that in case of failure to pay the
amount, the earnest money equivalent to 25% of the bid amount would
stand forfeited without any further notice and the plots will be put up for re-
auction.
12. Once the petitioners participated in the auction process, they
bound themselves to the terms and conditions thereof. Hence, the
petitioners cannot urge that they were assured by the respondent/MCD that
as the Community Centre in question was not developed by the MCD, the
petitioners could not be expected to pay the balance 75% of the bid amount.
An oral assurance, even if given, cannot override the terms and conditions of
the auction/sale. Fact of the matter is that there was no such stipulation
contained in the terms and conditions of the auction to the effect that the
Community Centre was required to be developed by the respondents before
disposing of the same on perpetual leasehold basis. The condition stipulated
in the advertisement inserted by the respondent/MCD inviting bids, bears
out the aforesaid position. Hence, there is no force in the argument
advanced on behalf of the petitioner that based on an assurance of the
respondent/MCD that it would develop the Community Centre, the
petitioners did not pay the balance 75% of the bid amount.
13. The other plea of the counsel for the petitioners that Resolution
No.63 dated 5.8.1970 and Resolution No.641 of the respondent/MCD had
made it incumbent upon the respondent/MCD to develop the Community
Centre at Karampura before putting up the plots in question for public
auction and having failed to undertake development work, the respondent
could not dispose of the plots on a perpetual leasehold basis, can only be
treated as an attempt on the part of the petitioners to wriggle out of their
obligation to make the payment of the balance amount either within the
stipulated period, or within the extended period as allowed by
respondent/MCD in accordance with the terms and conditions of the auction.
It is not as if the petitioners participated in the auction bid on the basis of
the Resolutions passed by the respondent. It is not even the case of the
petitioners that such was the position. There is no mention of the said
Resolution in the communications addressed by the petitioners at the
relevant time to the respondent No.1. It is apparent that the petitioners
were unaware of the existence of the said Resolution at the relevant time
and as an after thought, they have sought to take cover of the aforesaid
Resolutions when they found themselves financially in a tight spot and
unable to pay the balance 75% of the bid amount to the respondent/MCD.
The said payment was not linked in any manner with the purported
development work to be undertaken by the respondent, nor was any such
assurance given by the respondents to the public at large, in the
advertisement inserted before putting the plots to public auction. Hence,
any reliance placed by the petitioners on the aforesaid Resolutions is
misconceived.
14. Thus, the counsel for the respondents is justified in arguing that
the contention of the petitioners that the respondents had not undertaken
the development work, was a mere attempt to camouflage their own breach
and gloss over the default committed by them of the terms and conditions of
the auction, governing the plots in question. The respondents cannot be
faulted in issuing the impugned letters dated 3.12.1979, 3.5.1980 and
24.10.1980 to the petitioners intimating them that the earnest money of
Rs.1,92,000/-, in respect of Block No.D-3 and Rs.1,90,000/-, in respect of
Block No.D-4 were forfeited and the plots were being put up for re-auction.
Forfeiture was not done in a haste by the respondent/MCD. Rather, the
petitioners were given ample opportunity, as the 75% balance amount was
due and payable by August 1980, whereas forfeiture was ordered only in the
end of October, 1980.
15. This leaves the last plea taken by the counsel for the petitioners
that forfeiture by the respondent/MCD without proving the loss suffered by
them was not permissible and that such an option of forfeiture ought to have
been exercised as a last resort.
16. It may be noted that the aforesaid plea was not taken by the
petitioners either after receipt of notice of forfeiture from the
respondent/MCD or for that matter, in the writ petition itself and has been
taken by the counsel for the petitioner only in the course of arguments.
Certain case law was cited to support the aforesaid proposition. However, a
closer look at the aforesaid judgments reveals that the cases of Maula Bux,
Fateh Chand and Kailash Nath (supra) referred to by the counsel for the
petitioner were based on civil suits claiming either compensation, or specific
performance of contract or, liquidated damages, wherein the effect of the
provision of Section 74 of the Contract Act was discussed. Section 74 deals
with the measure of damages in case of compensation for breach of
contract, where a penalty is stipulated for. The said provision curtails right
of the party complaining of the breach to receive from the defaulting party
who has broken the contract, reasonable compensation not exceeding the
amount so named in the contract, or the penalty stipulated in the contract
depending on the circumstances. Such an eventuality would have arisen in
the present case, had the petitioners instituted civil proceedings against the
respondent/MCD, wherein for the purpose of adjudication, evidence would
have had to be led to establish the actual damage suffered by the
respondent/MCD on account of breach of contract on the part of the
petitioners. However, the petitioners having chosen not to invoke such a
remedy against the respondents, cannot place reliance on the aforesaid
judgments, rendered by the courts after sifting the evidence on the record.
17. In the present case, the forfeiture clause entitles the
respondent/MCD to forfeit the earnest money either in whole or in part
depending on the circumstances of the case. The respondent/MCD invoked
the said clause to forfeit the entire earnest money deposited by the
petitioners in respect of the two commercial plots in question, which was
only 25% of the bid amount. As to whether the said forfeiture can be
treated as a reasonable compensation or in the nature of penalty has to be
examined in the light of the factual matrix of each case. As observed by
the Supreme Court in the case of Jagmohan Singh (supra), while taking note
of the factual matrix of the case, on rare occasions, the Court can take into
consideration subsequent events. In the present case, it is relevant to take
note of the fact that rule was issued in the writ petition on 21.7.1981, on
which date, on the interim application filed by the petitioners, praying for an
order restraining re-auction of the plots in question and restraining forfeiture
of the amounts deposited with the respondent, a stay was granted in favour
of the petitioners. As a result, ever since, i.e. for the past 28 years, the
aforesaid two commercial plots could not be put to re-auction by the
respondents. It is also pertinent to note that when the present petition
came up for hearing on 7.3.2002, as none was present on behalf of the
petitioners, though the respondents were represented, the same was
dismissed in default. An application for restoration of the said writ petition
came to be filed by the petitioners after a period of over five years, in
October 2007. Subject to payment of costs, the writ petition was restored to
its original position vide order dated 27.3.2008.
18. The present case can certainly not stated to be one where the
respondent/MCD has not suffered any loss. Two valuable pieces of
commercial properties have been lying unutilized and have remained
unproductive for the past 28 years, on account of the stay operating in
favour of the petitioners. None of the judgments relied upon by the
petitioners, advance their case for refund of the forfeited amount. In the
case of Maula Bux (supra), the Supreme Court observed that in every case
of breach of contract, the person aggrieved by the breach is not required to
prove actual loss or damage suffered by him before he can claim a decree,
and the court is competent to award reasonable compensation in case of
breach even if no actual damage is proved to have been suffered in
consequence of the breach of contract. In the case of Rampur Distillery &
Chemical Co.Ltd.(supra), which arose out of an arbitration award, the
Supreme Court, following the decision in the case of Maula Bux (supra), held
that a party taking security deposit from the other party to ensure due
performance of the contract, is not entitled to forfeit the deposit on the
ground of loss, when no loss is caused to him in consequence of such a
default. In the present case, the amount forfeited by the MCD was not
offered as security deposit by the petitioner, but as earnest money. As far
as loss caused to the respondent is concerned, they were not required to
prove that they had suffered actual loss to claim forfeiture, particularly
considering the fact that the two plots in question have remained blocked
and commercially unexploited for almost three decades, on the strength of
an unconditional interim order granted in favour of the petitioners.
19. The present case is also quite unlike the case of Kailash Nath
(supra), where the defendant/DDA therein while continuing to enjoy the
earnest money of the plaintiff, sold the disputed plot to a third party at three
times of the price at which the plot was to be purchased by the plaintiff
therein. In the said case, the Court also took note of the conduct of
defendant/DDA in takings its own time in the decision making process and
the exchange of communications with the parties, to ultimately hold that the
plaintiff therein was entitled to refund of the earnest money.
20. The conduct of the respondent herein has neither been
irresponsible, casual, or lackadaisical. Rather, as noted above, the
respondent/MCD gave a long rope to the petitioners herein before invoking
the forfeiture clause. It is not as if the petitioners paid or offered to pay any
part of the outstanding 75% of the bid amount to the respondent at any
stage to show their bona fides. Instead, under the garb of non-development
of the Community Centre, they kept seeking extension of time for making
the payments, when in reality, they were facing a major cash crunch.
Examining the factual background of the present case, the action of the
respondent/MCD in invoking the forfeiture clause, cannot be faulted. This
Court has therefore no hesitation in holding that the said option of forfeiture
was exercised by the respondent/MCD as a last resort, in view of failure on
the part of the petitioners to abide by the terms and conditions of the
contract, by making payment of the balance 75% of the bid amount within
the stipulated time or for that matter, within the extended time, as per the
terms and conditions of the contract governing the parties. In such
circumstances, the respondent was under no obligation to prove the losses
suffered by them before exercising the forfeiture clause.
21. In view of the foregoing discussion, the present writ petition is
dismissed as being devoid of merits with costs quantified at Rs.30,000/-,
payable by the petitioners to the respondents within four weeks.
( HIMA KOHLI ) JUDGE MAY 06, 2009 sk/mk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!