Citation : 2009 Latest Caselaw 1792 Del
Judgement Date : 1 May, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ LPA No. 193/ 2009 & C.M. Nos. 6190-91/2009
SHRI AMAR BANSAL ..... Appellant
Through: Mr. Ujjawal K. Jha and Mr. B.P.
Agarwal, Advocates.
versus
NORTH DELHI POWER LIMITED ..... Respondent
Through: Mr. Sudhir Nandrajog, Senior
Advocate with Mr. Siddharth
Bambha and Mr. Diwakar
Sinha, Advocates.
CORAM:
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE NEERAJ KISHAN KAUL
ORDER
% 01.05.2009
C.M. No. 6191/2009 (for exemption)
1. Exemption allowed, subject to all just exceptions.
2. The application stands disposed of.
LPA No. 193/ 2009 & C.M. Nos. 6190/2009 (for stay)
3. Notice.
4. Mr. Diwakar Sinha, learned counsel accepts notice on behalf of
the respondent.
5. The present appeal is directed against the order of the learned
Single Judge dated 23rd March, 2009. The learned Single Judge in
the said impugned order has directed the appellant (the original
petitioner in the Writ Petition) to pay a sum of Rs. 8,00,000/- to the
respondent (the original respondent in the Writ Petition) in three
staggered installments. The learned Single Judge has also stayed the
impugned bill dated 23rd February, 2009, subject to the appellant
depositing the amounts as directed by the learned Single Judge.
6. Briefly stated, the facts of the case are as follows:-
The respondent inspected the premises of the appellant on 4th
September, 2008 when the following salient observations were made:-
1. A load of 59.268 KW was found connected against sanctioned load of 45 KW for industrial purpose. Shunt capacitor found installed/not installed.
2. Meter No. 02266242 found as Injection of high voltage (AC/DC) into the meter.
7. As per the North Delhi Power Limited (in short 'NDPL'), the
above observations prima facie indicated Dishonest Abstraction of
Energy (DAE)/Misuse, Unauthorised Use, LPF. The appellant was,
therefore, issued a show-cause notice asking him to file his response
to the said allegations. The appellant gave a detailed response to the
allegations contained in the show-cause notice. Thereafter a
speaking order was passed by the respondent on 23rd February,
2009. The respondent rejected the reply of the appellant and inter-
alia observed in its order that on the basis of analysis of downloaded
data which showed abnormal events of prolonged power failures on
number of occasions and its comparison with data of same source
meter which did not reflect any such abnormalities. The contention
of the appellant as regards ways of injection of high voltage and
absence of any artificial means were held to have become totally
irrelevant in view of the fact that all evidence on record conclusively
established the appellant's deliberate act of high voltage (AC/DC)
injection into the meter as the irregularities detected were such
which could not occur in normal circumstances unless someone
would cause or create them. It was further held in the speaking
order that moreover, the data analysis of the other meter also ruled
out the impact of all extraneous factors and, therefore, led to the only
conclusion that it was done deliberately and by doing so illegal and
unlawful gain was taken. After a detailed discussion, the respondent
came to the conclusion that dishonest abstraction, consumption or
use of electricity was conclusively established against the appellant.
8. It is the contention of the appellant inter-alia that though the
show-cause notice alleged that there was injection of high voltage
(AC/DC) into the meter, but it was nowhere mentioned that how and
when such alleged high voltage was injected and what was the effect
of injecting the high voltage into the meter. The petitioner also
contended that the data was analyzed by the Manager/Senior
Manager of the respondent Company, who was an interested party
whereas, as per the regulations, the data was to be analyzed in a
third party laboratory. It is also the case of the petitioner that if the
high voltage as alleged is indicated then there will be no display in
the meter and the screen will show blank but in this case the meter
was showing the display and as the meter was showing the actual
reading regularly, the meter was still working at site and thus
allegation of injection of high voltage into the meter was incorrect.
9. It was submitted by the learned senior counsel appearing on
behalf of the respondent that this method adopted by the appellant of
high voltage (AC/DC) injection into the meter was a relatively recent
but rampant practice now being adopted by some consumers for
dishonest abstraction of energy.
10. In view of what has been stated hereinabove, we deem it fit and
appropriate to request the Dean of IIT, Delhi to nominate a Two
Member Committee consisting of Electronic and Electrical Engineers
competent to deal with such issues to examine the matter and file a
report in this Court before the next date of hearing i.e. 9th July, 2009.
The composition of the said Committee would be intimated by the
Dean, IIT Delhi to both the appellant and the respondent. The
appellant and the respondent would also be entitled to make written
representations before the Committee. It will be open to the
respondent to send all relevant material/data as also the site
inspection meter to the Committee for its perusal and analysis. The
Registry is directed to send a copy of this order to the Dean, IIT Delhi
for necessary compliance.
11. Renotify on 9th July, 2009.
12. In the meantime, there will be a stay of the impugned order
dated 23rd March, 2009.
CHIEF JUSTICE
NEERAJ KISHAN KAUL, J May 01, 2009/sb
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!