Citation : 2009 Latest Caselaw 896 Del
Judgement Date : 19 March, 2009
* HIGH COURT OF DELHI AT NEW DELHI
+ FAO (OS) 267/1996
% Decided on: 19th March, 2009
Delhi Development Authority ..... Appellant
Through Mr.Gaurav Sarin, Advocate
versus
Madhur Krishna ..... Respondent
Through Mr.S.K. Rungta, Advocate
CORAM:
HON'BLE THE CHIEF JUSTICE HON'BLE MR. JUSTICE S. MURALIDHAR
1. Whether reporters of the local papers be allowed to see the judgment ? YES
2. To be referred to the Reporter or not ? NO
3. Whether the judgment should be reported in the Digest? NO
AJIT PRAKASH SHAH, CHIEF JUSTICE :
This appeal is directed against the order dated 10 th January,
1996 passed by Devinder Gupta, J in IA No.10912/1990 and Suit
No.2431-A/1990. By the impugned order the learned Judge was
pleased to overrule the objections raised by the appellant DDA
and make the award dated 19th July, 1990 of the sole arbitrator
rule of the court.
2. The facts giving rise to the present appeal are as follows:
The appellant DDA entered into an agreement being
Agreement number 4/EE/HD/XXIX/83-84 for "Construction of
Office Building for Circle V and Divisions" with the respondent.
The work was awarded to the respondent vide letter dated 13 th
February, 1984. After the work was awarded, the site of the work
was changed from District Park on the west side of the outer ring
road to a new low lying site on the east of the outer ring road in
West Delhi. According to the respondent, in view of the urgency
of the work he had made arrangements and started work at the
old site when he was asked to shift operation to the new site.
The new site being low lying and water-logged required extensive
filling with earth to be brought from outside. There were large
variations in the nature and scope of the work to be done and the
work got abnormally delayed due to reasons beyond the control
of the respondent. Most of the claims of the respondent arose
out of the change in site and revised requirements of work. The
claims were referred to the sole arbitrator, who gave his award on
19th July, 1990 whereby various claims raised by the respondent
were partially granted. The claim for pendente lite interest was,
however, denied by the arbitrator. By the order under appeal the
award was made rule of the court.
3. The basic contention raised by Shri Gaurav Sarin, learned
counsel appearing for the DDA, is that the arbitrator has failed to
give reasons in support of the award and thereby contravened
the express requirement of clause 25 of the agreement. He
contended that the award does not disclose any application of
mind by the arbitrator to specific evidence, oral or documentary,
led before the arbitrator. The arbitrator has merely stated as to
what the party has stated / alleged before him and has not
recorded any finding or reasoning. There is no application of
mind or indication of the trend of the thought process of the
arbitrator in the award. According to the learned counsel, the
rational process of evaluating and assessing the evidence is
totally missing in the award.
4. In reply, Shri S.K. Rungta, learned counsel appearing for the
respondent, contended that it is settled legal position that where
arbitrator is required to state reasons for award, as is in the
present case, it does not imply that the arbitrator has to give a
detailed judgment. He contended that the only requirement is
that a reading of the award should indicate the thought process
of the arbitrator and if award is capable of reading the mind of
the arbitrator, the requirement of stating the reasons is met. He
submitted that the arbitrator has looked into the contentions
raised by the respective parties and also into the evidence led by
the parties by dealing with each of the claims separately. In
addition, the arbitrator has also given his findings on the basis of
his observations and on the basis of inspection of the site in
question. Furthermore, the findings of the arbitrator in respect of
each of the claims were also based on admitted facts such as the
fact that the site for which the tender was awarded and on the
basis of which the respondent gave his rates in the bid, was
shifted by the appellant and the shifted site was not of the same
nature. Therefore, according to Mr.Rungta the award cannot be
said to be a non-speaking award.
5. Having regard to the rival submissions made at the Bar, the
short question which arises for our consideration is whether the
award of the sole arbitrator is without the support of any reason.
In other words, whether the award is a non-speaking award.
There is no dispute that the arbitrator was supposed to give
reasons in view of the mandate in the arbitration agreement.
Whereas contention of the DDA is that the award on many claims
is non-speaking. The respondent, who has got the award in his
favour, contends otherwise and asserts that sufficient reasons,
which are required to be given by the arbitrator, are found in the
award.
6. Both the learned counsel agreed that it was not essential for
the arbitrator to give a detailed reasoned decision indicating each
minute step of his mental meanderings. The reasons given
should reflect the thought process of the arbitrator, whereby it
can be ascertained as to how he arrived at a particular
conclusion. This principle is succinctly laid down in College of
Vocational Studies v. S.S. Jaitley AIR 1987 Delhi 134 wherein
the Division Bench observed:
"By reasons it mean that the award should be a speaking one. In the reasoned award what is expected from the arbitrator is that he should indicate his mind whereby it can be
ascertained as to how he arrived at a particular conclusion. In case of a reasoned award, the arbitrator is required to indicate the trend of his thought process but not his mental meanderings, the purpose of commercial arbitration being speedy certainly and a cheaper remedy."
7. In this regard reference may be made to a Division Bench
judgment of this Court in Delhi Development Authority v. M/s
Alkaram, New Delhi AIR 1982 Delhi 365. The Division Bench
held that it was not necessary for the arbitrator to set out the
actual calculations, figures, as worked out by him, what was
important was that there was material / evidence before him and
the thought process indicated that the arbitrator had taken the
said material into consideration while arriving at particular
figures. Following observations of Avadh Behari Rohatgi, J are
pertinent and need verbatim reproduction:
"What reasons are sufficient in any particular case must, of course, depend upon facts of the case. I approach the matter in this way; that reasons are not deficient merely because every process of reasoning is not set out. I further think that reasons are not insufficient merely because they fail to deal with every point raised before the arbitrator at the hearing. No universal; generalization can be made. Everything depends on the subject matter. In deciding a controversy the arbitrator works in an environment which is quite different from
that of the Judge. He is not bound by the technical rules of evidence. The „ropes and pulleys‟ that he uses in the arbitral process are different from the foot rules and set squares that we use in the judicial process. From the arbitrator what is wanted is "a practical decision on the disputed issues" (Abasalom Ltd. V. Great Western (London) Garden Village Society, 1933 AC 592 (616) per Lord Wright). He knows that businessmen want to do business and not to argue about it. He gives not judicial justice, but rough justice of the world. Because he is not bound by the "codeless myriad of precedents". Many have found salvation in the faith they reposed in this private domestic forum for the settlement of their disputes. xxxx My conclusion in his case is that the arbitrator was the final judge of fact. The Court is bound by the arbitrator‟s findings of fact and cannot review them unless they are unsupported by evidence and unless it appears from the award itself that there was no evidence to support the finding. It is not open to the court to examine the adequacy of evidence which led the arbitrator to his findings of fact. His findings are final."
8. In the concurring judgment Leila Seth, J, as she then was,
observed:
"42. There was material before him to establish that the price had risen substantially. He was
justified in not accepting the calculations of either party and arriving at his own figure in accordance with the facts ascertained by him. He has not based his decision only on the claim of the contractor, as contended by learned counsel for the appellant.
43. In these circumstances I feel that the arbitrator was well within his jurisdiction to come to this conclusion. The question whether I would have come to the same conclusion or arrived at the same figures is not material. Once there is evidence, there is no apparent error and/or misconduct. I cannot go into the sufficiency of the evidence; nor is it necessary for the arbitrator to set out the actual calculation figures as worked out by him; his reasons, as mentioned, are adequate and clear; it is not essential for him to give a detailed reasoned decision indicating each minute step of his mental meanderings."
9. In DDA v. Bhagat Construction Co. (P) Ltd. & Another
2004 (3) Arb. L.R 548 (Delhi), a Division Bench observed that if
award shows application of mind, it is to be taken as correct and
it was not necessary for the arbitrator to disclose mathematical
calculations in the award. The Court observed in para 8 of the
judgment that where the arbitrator was retired Chief Engineer of
the CPWD and thus well conversant with the kind of disputes on
which he was adjudicating and further that he had given his
detailed reasons for arriving at a finding that delay was
attributable to the DDA, thereafter while discussing each claim it
was not necessary for him to disclose the mathematical
calculations in the award for arriving at particular figures, if the
award shows the application of mind and view which is plausible
by the arbitrator.
10. In Bharat Furnishing Co. v. Delhi Development
Authority and another 1992 (1) Arb.Law Reporter 327, Jaspal
Singh, J laid down that where the arbitrator is required to give
reasons for the award, he need neither proceed to write a
detailed judgment nor set out every process of reasoning. But
there must be reasons. The Court is entitled to examine the
reasonableness of the reasons. The reasons being the links on
the material adduced before the arbitrator on which certain
inferences are drawn and conclusions are made, there has to be
some rational nexus to indicate in the award itself. The learned
Judge came to the conclusion that many claims were awarded by
the arbitrator without disclosing any reasons.
11. In an unreported decision in Anil Garg v. Delhi
Development Authority & Ors. bearing Suit No.21-A of 1996
decided on 17th December, 1999, a learned Judge of this Court
dealt with the same question. Taking into account the aforesaid
judgments as well as discussing a few judgments of the Supreme
Court, the learned Judge culled out the ratio of those judgments
as follows:
"The ratio established in Municipal Corporation of Delhi vs. Jagan Nath Ashok Kumar & Anr., AIR 1987 SC 2316 was that the reasonableness of the reasons given by an arbitrator in making his award cannot be challenged in proceedings under Article 136 of the Constitution. This was reaffirmed in the subsequent decision of the Apex Court in State of Rajasthan v. Puri Construction Co. Ltd. & Anr, JT 1994 (6) SC 412 and it was further observed that "it is not necessary to indicate in the award computation made for various heads and it is open to the arbitrator to give a lump sum award"
A Constitution Bench of the Supreme Court had reversed the decision of a Division Bench of the Bombay High Court in the case of Goa, Daman & Diu Housing Board v. Ramakant V.P. Darvotkar, AIR 1991 SC 2089, on facts singularly similar to the case in hand. A clause in the covenant between the parties stipulated that where the amount of claim in dispute was Rs.50,000/- and above, the arbitrator was bound to give reasons for his award. The arbitrator had detailed the rival contentions and the documents relied upon by them. In setting aside the award the Bombay High Court had observed that "the award nowhere contained any reasoning and did not even obliquely mention that he had adopted the reasoning of either party". Even in the context of this cryptically worded award, the
apex court had reversed the High Court‟s decision and given its imprimatur to the Award. To my mind, the legal obligation of giving reasons is far more onerous than that of disclosing the "trend of thought process", and the former would necessarily encompass the latter. By an extrapolation of the ratio of the Apex Court, if the words employed in the Bombay Award under scrutiny fulfilled the obligation of disclosing reasons (being over Rs.50,000/-), similarly used words would overwhelmingly fulfill the requirement of the Arbitrator disclosing the trend of his thought process. If, by merely referring to the rival contentions and their documents, without more, the Arbitrator in that case had been held to have given a reasoned award, where a similar practice is adopted in other cases, it would more than sufficiently comply with the need of disclosing the trend of the thought process of the Arbitrator.
The essence of the decisions of the Supreme Court appears to be that if on a reading of the award it is obvious that the arbitrator had kept the rival contentions in perspective at the time of the passing of the award, then the award sufficiently complies with the compulsion to give reasons. As shown above, AIR 1991 SC 2089 is a case of a mere narration of the parties‟ contentions, followed by the mention of the quantum awarded. It was however found to be a reasoned award
and upheld. I am fortified in distilling the various judgments thus, in large measure, by the other observations to the effect that the reasonableness of reasons is non justiciable. In any event, in the Bombay case the Supreme Court having given its approval to the award which after setting out the rival contentions immediately proceeded to specify the quantum awarded, can be inferred to have opined that in such circumstances, the thought process of the Arbitrator was obviously present. The Supreme Court had reversed the judgment of the Division Bench of the Bombay High Court which had taken the view that the impugned award was liable to be set aside for failure to give reasons therein."
12. In a recent judgment delivered in CS(OS) Nos.1436/1993,
2209/1993 titled M/s Kalyan Chandra Goyal & Co. and
another v. Delhi Development Authority & Another and
other cases delivered on 6th July, 2007, A.K. Sikri, J, after
considering the previous judgments summarised the principles as
under:
"I. The Arbitrator is not supposed to pass a speaking award except when it is provided under terms of reference or the arbitration agreement.
II. Where the arbitrator is under obligation to give reasoned award:
(i) it is not essential for the Arbitrator to give a detailed reasoned decision
indicating each minute step of his mental meanderings. The reasons given should reflect the thought process of the Arbitrator, whereby it can be ascertained as to how he arrived at a particular conclusion;
(ii) mere conclusion and verdict would not be sufficient; reasons are the links on the material, documentary or oral evidence, adduced before the Arbitrator on which certain inferences are drawn and conclusions are made. There must be some rational nexus between the conclusion and reasons given in the Award;
(iii) the Award shall be intelligible so that the Court may come up to the conclusion whether there is any error of law apparent on the face of the award;
(iv) it is not necessary for the Arbitrator to set out the actual calculations, figures as worked out by him; and
(v) when the reasons given by the Arbitrator are germane, relevant and have rational nexus with the conclusions arrived at by him, the reasonableness of the reasons cannot be challenged and it cannot be said to be unreasonable."
13. In the light of this well established principle, we may now
proceed to deal with the various claims raised by the respondent,
which have been partially allowed by the arbitrator.
CLAIM NO.1:
14. The respondent claimed Rs.1.35 lacs due to change in the
scope of the work and also on account of change of site
previously shown. The arbitrator awarded an amount of
Rs.45,000/- against the claim of Rs.1.35 lacs. While allowing the
amount of Rs.45,000/- towards claim No.1, the arbitrator after
recording the contentions of both the parties awarded the said
sum on the basis of records and evidence before him. On a
perusal of the award it is seen that the appellant did not dispute
the change of site on the basis of which the tender was awarded.
Furthermore, the arbitrator before proceeding to deal with the
claims and making the award, inspected both the sites in
presence of both the parties and his award is based on the
pleadings, evidence and record produced before him. In our
opinion, it clearly meets the requirement of reasoned award. The
arbitrator has based his calculations on the material placed on
record. It was not necessary for him, in view of the legal position
noted above, to give the process of mathematical calculation.
CLAIM NO.2:
15. The arbitrator has awarded an amount of Rs.2.50 lacs
against the claim of Rs.5 lacs on account of work done but not
measured and paid. The arbitrator awarded the said amount
under claim No.2 after considering the contentions of the parties.
It is seen from the contentions of the appellant DDA recorded
against this claim in the award that there was no dispute of the
quantity of work that was done by the respondent and also that
there was no dispute with regard to the fact that earth was
brought by the respondent and the appellant DDA could not
procure the earth from its own resources. On the basis of these
admitted positions, the arbitrator partly allowed the claim holding
that the truth lies in between and assessed the value of the work
at Rs.2.5 lacs. The award is clearly on the basis of the material
produced before the arbitrator. Therefore, it cannot be said that
he has not given his reasons for awarding the appropriate
amount.
CLAIM NO.3:
16. The arbitrator awarded an amount of Rs.24,785/- against
the claim of Rs.1 lacs on account of increase in the rates of
materials etc. The appellant opposed this claim on the ground
that they have already made the payment towards this claim
under clause 10(c) of the agreement. However, the arbitrator
gave his finding that the delay was mostly due to change of site
and the revised requirements of work and other impediments
created by the new circumstances and clause 10(c) does not
cover all increases in labour and material. On the basis of this
finding the arbitrator awarded a sum of Rs.24,785/-. We do not
find any illegality in the finding of the arbitrator.
CLAIM NO.4:
17. This claim is towards the loss of profit because only 2/3rd of
the work was got done by the department. As against the claim
of Rs.1 lac the arbitrator has awarded Rs.25,000/-. The arbitrator
has recorded the contentions of both the parties and from the
contention of the appellant it is evident that the claim under this
head was being opposed on the ground that the quantum of work
to be executed was intimated to the respondent at the time of
the award of work. However, since the respondent was claiming
the said amount by reference to annexure C-IV which annexure
was not in dispute, the arbitrator awarded the said sum after
considering the said annexure and as such it cannot be said that
reason for awarding the same is absent and also the mind
process of the arbitrator cannot be gathered.
CLAIM NO.5:
18. This claim was for the damages on account of loss of idling
labour, establishment, tools and plants etc. due to alleged non-
performance of contractual obligations by the department. The
respondent claimed Rs.4 lacs under this head. The arbitrator has
noted the case of the respondent that the work was got
abnormally delayed due to failure of the appellant to fulfill their
obligation under the contract and the respondent had to incur
expenditure on his establishment, idle labour, tools and plants
and due to reduced profitability and miscellaneous overheads etc.
Thus it is seen from the award that the arbitrator has looked into
the details given by the respondent in annexure C-V of the
statement of claims. The arbitrator has also noted the stand of
the appellant that they had duly fulfilled their obligations under
the contract and made available the site, drawings, decisions and
stipulated materials to the respondent in proper time. The
further case of the appellant was that the losses amounted had
not been true. From the pleadings before the arbitrator as well as
from the evidence and the arbitrator‟s own inspection, it is not in
dispute that the site originally shown and marked for the work in
question was shifted after the respondent had employed
machinery, plant and labour and in fact had started the work at
the old site. It is clear that this weighed on the mind of the
arbitrator while allowing the claim partly under this head and,
therefore, it cannot be said that while awarding the same under
this head, the arbitrator failed to give any reason or his award
was without reasons.
CLAIM NO.7:
19. The arbitrator has awarded a sum of Rs.4,862/- as against
the claim of Rs.9,723/- on account of rebate reduced from the
bills as Department could not make regular monthly payments
and also could not finalise the final bill within the time. While
awarding the said amount, after recording the contention of the
parties, the arbitrator has categorically stated that he is awarding
the above mentioned amount under this head on the basis of
usual practice that the bills are prepared and paid by the
Department. We do not find any reason to interfere with the
findings of the arbitrator.
20. In the result, we find no merit in the contention of the
appellant that the arbitrator has not given any reasons for the
award. The appeal is dismissed with costs.
CHIEF JUSTICE
March 19, 2009 (S. MURALIDHAR)
"nm" JUDGE
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!