Citation : 2009 Latest Caselaw 2739 Del
Judgement Date : 21 July, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS)202-A/1996
% Date of decision: 21stJuly, 2009
SHRI RAMESH CHANDER GUPTA .... Plaintiff
Through: Mr. Girish Aggarwal, Advocate
Versus
DELHI DEVELOPMENT AUTHORITY
& ANOTHER .... Defendants
Through: Ms. Anusuya Salwan, Advocate
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? No
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported
in the Digest? No
RAJIV SAHAI ENDLAW, J.
1 The suit was filed under Section 14 of the Arbitration Act,
1996 for filing of the arbitral award dated 20th December, 1995 in
this Court. Upon the award being filed, the notice of filing thereof
was issued to the parties. The defendant / DDA filed IA
No.3134/1996 in this Court under Section 30 and 33 of the Act.
The plaintiff Ramesh Chander Gupta also filed objections to the
award under Section 30 and 33 of the Act by way of IA
No.6082/1996. On completion of pleadings in both set of
objections, the usual issues were framed on 21st February, 1997.
The counsel for the parties at the time of framing of the issues
agreed that no evidence was required to be adduced and the
records of the arbitration proceedings be read as evidence. The
plaintiff died during the pendency of the proceedings before this
court and vide order dated 20th February, 2004 the legal
representative of the plaintiff allowed to be substituted.
2 The matter was called for final hearing today. However it
transpired that neither the arbitral award nor the arbitral record
was contained in the two files. However the matter being old, the
counsel for the parties in all fairness stated that the matter be not
adjourned and made their submissions and wherever necessary
made their own records available for appreciation of the
submissions being made by them. The copy of the arbitral award is
placed on the file of the present suit.
3 The counsel for the plaintiff at the outset stated that he has
instructions to withdraw IA No.6082/1996, being the objections to
the award preferred on behalf of the plaintiff and withdraw the
same. The counsel for the defendant has no objection to the same.
IA No.6082/1996 is dismissed as withdrawn.
4 The counsels have been heard on IA No.3034/1996.
5 The counsel for the defendant/DDA with respect to the award
generally contended that the award on various claims of the
plaintiff was without any reasons, though under the agreement, the
arbitrator was required to record reasons; it is also contended that
the arbitrator ignored important documents and has thus
misconducted himself.
6 Claim No.1 of the plaintiff was for Rs.15,000/- illegally
withheld. The award records that the defendant/DDA admitted that
the said sum had been withheld and in fact during the pendency of
the arbitration proceedings released/refunded Rs.4755.89 p. out of
therefrom. The arbitrator for the reason that defendant/DDA could
not produce any cogent evidence justifying withholding of the
balance amount, directed refund of the balance of Rs.10244.11 p.
It is contended by the counsel for the DDA that the said monies
were withheld for defective work done and towards
reduction/deduction items statement and that the arbitrator has
ignored Ex.R-25 under which the work was accepted at reduced
rates.
7 However this court in the jurisdiction even under Section 30
and 33 of the 1940 Act cannot interfere with the factual findings
arrived at by the arbitrator. Reference if any required can be made
to Coimbatore District Podu Thozillas Samgam Vs. Bala
Subramania Foundry AIR 1987 SC 2045 and Arosan Enterprises
Ltd. Vs. U.O.I. (1999) 9 SCC 449. In the absence of any plea of
bias, I do not find any reason not to believe the arbitrator when he
has recorded that the DDA did not produce before the arbitrator
any cogent evidence for deduction of the said sum of Rs.10244.11
p. Moreover it cannot be lost sight of that the DDA had initially
withheld a total sum of Rs.15,000/- out of which Rs.4755.89 p. was
released on claim being made by the plaintiff. The same is also
indicative of the withholding of the balance amount also being
without any reason.
8 Claim No.2 of the plaintiff before the arbitrator was for
Rs.13593/- on account of illegal recoveries made from the bill. The
defendant DDA claimed to have made the said recoveries at penal
rates for material issued to the plaintiff for carrying out of the
works and non-return of excess material by the plaintiff to the
defendant. The arbitrator found that the said material, in terms of
the agreement was to be kept in the joint custody of the plaintiff
and the defendant and further that the defendant had not issued
any notice claiming the balance material or notifying the loss
suffered if any on that account. The arbitrator finding the claim to
the extent of Rs.11601/- only to be justified, allowed the same. The
objection of the defendant is that the excess material not returned,
was under clause 42 to be recovered at double the issue rate and
thus it is contended that the award on this account is bad.
9 The defendant / DDA has not controverted the findings of the
arbitrator of the material under the agreement being required to be
kept in joint custody or of the defendant having not issued any
notice required to be issued under clause 42(1). In the absence of
contravention of the reasons given by the arbitrator, it cannot be
said that there is any error apparent on the face of the award or
that the arbitrator has misconducted himself.
10 Claim No.4 of the plaintiff was for Rs.85,000/- under clause
10(c) of the contract. The award records that the plaintiff however
restricted the claim for Rs.46624.70 p. only. The arbitrator found
that no delay had been attributed to the plaintiff and found the
claim of the plaintiff for Rs.39,237/- to be justified and allowed the
same. The objection of defendant/DDA is that the said claim was
not raised during the course of execution of the work and the
conditions of clause 10 (c ) were not satisfied by the plaintiff i.e. the
plaintiff did not submit any details to prove that there was any
statutory increase during the execution of work and payment to the
labour had been made at the increased rate of wages. Thus it was
averred that the award under the said claim was liable to be set
aside. The counsel for the defendant/DDA however in all fairness
admitted that in the present case there was delay on the part of the
defendant/DDA. She contended that the plaintiff neither at the
relevant time of execution nor before the arbitrator showed any
proof of increase in prices of material or increase in wages.
11 I may however notice that the arbitrator has while allowing
the said claim to extent aforesaid, recorded that the Executive
Engineer of the defendant had at no time demanded records from
the plaintiff in terms of clause 10 (c ). Clause 10 (c ) provides for
variation of the amount of the contract on account of delay, if in the
opinion of the Superintendent Engineer not attributable to or not
within the control of the contractor. The said clause also imposes
an obligation on the contractor to keep such books of accounts and
other documents as are necessary to show the amount of increase
claimed and also requires the contractor to allow inspection of the
same by a duly authorized representative of the DDA. The said
clause also requires the contractor to give notice within a
reasonable time of becoming aware of increase in prices, stating
that the same is given in pursuance to the said clause. The
objection of the defendant/DDA is not that the plaintiff did not give
notice of increase but is that proof of increase was not submitted.
One possible interpretation of the said clause is of the contractor
being required to only give a notice of increase within reasonable
time and to keep proof of increase ready with him and to give
inspection thereof if demanded. The arbitrator has found that the
defendant did not demand the said inspection. No fault can be
found with the said reasoning or logic of the arbitrator. The
counsel for the defendant/DDA has also contended that the
arbitrator has not recorded as to how he has arrived at the figure of
Rs.39237/- awarded. The same also in my view does not constitute
a ground to interfere with the award. The arbitrator has recorded
that he has considered and applied his mind to the pleadings
evidence etc. and the matter in dispute. The arbitrator has not
given a lump sum figure but has arrived at a specific figure of
Rs.39237/-. The award, merely for the reason of the arbitrator
having not given the break up of the amount awarded, does not
warrant interference.
12 Claim No.5 of the plaintiff of Rs.1,26,000/- was on account of
damages for keeping the establishment, T&P Machinery in the
extended period of delay. The arbitrator finding the delay to be of
634 days, held that owing to the delay the plaintiff was compelled
to maintain the establishment and overheads amounting to about
3.5% of the cost of the work and awarded a sum of Rs.41832.50p. to
the plaintiff on this account. The contention of the counsel for the
defendant / DDA is that the arbitrator having allowed the claims
under clause 10 (c ) for the reason of delay and having further
allowed claim No.7 for extra cost spent in executing the work after
stipulated period on account of rise in cost of man and material,
ought not to have allowed the claim No.5 for establishment
charges. It is urged that the same amounts to overlapping and
giving to the plaintiff something not provided for under the
agreement. The argument is that once the agreement provides the
formula for compensating the contractor for delay, no other
amounts for delay can be allowed. Per contra the counsel for the
plaintiff has contended that the claims under clause 10 (c ) are
dehors the claims on account of delay for establishment charges
which had to be maintained by the plaintiff for throughout the
period of delay.
13 This court in Narain Das Israni Vs. DDA CS(OS) 2488/2000
decided on 28.10.2005 has held that claims for damages on account
of delay under heads other than those provided for in the
agreement can be awarded. In the present case there is
considerable delay, admittedly attributable to the defendant/DDA.
The damage to the contractor on account of such delay, for the
reason of establishment costs is inherent. No misconduct /
perversity can be found in the award under claim No.5.
14 Claim No.7 was made by the plaintiff for Rs.312978/- on
account of extra cost spent in executing the work after the
stipulated period and due to rise in cost of man and material. The
arbitrator has on the basis of the sale price index of materials,
worked out the claim of the plaintiff on this account at Rs.59933.40
p. The counsel for the defendant has challenged the said award for
the reason of the plaintiff having agreed in documents filed before
the arbitrator that the delay was on his part. In this regard it may
be noticed that it is not in dispute that the delay was on the part of
the defendant. Once that is admitted, then the work done after the
stipulated date and the cost index applied by the arbitrator is not
controverted. The award on this ground is also not found to be
interferable.
15 Lastly the counsel for the defendant has made submissions
with respect to high rate of interest of 18 % per annum awarded by
the arbitrator. Per contra the counsel for the plaintiff has
contended that the plaintiff was awarded merely a sum of about
Rs.1.62 lacs and the arbitrator had given an opportunity to the
defendant to pay the said amount within three months; the
defendant having failed to pay the amount, there is justification for
award of future interest at 18% per annum.
16 The arbitrator has awarded pre suit interest to the plaintiff at
the rate of 12% per annum. No interference is required with the
same. The arbitrator has also awarded interest at 18% per annum
for the period the arbitration proceedings remained pending before
him. Considering the short term thereof, I do not find any reason to
interfere with the same also. The proceedings have remained
pending before this court for long. Objections to the award were
preferred by the plaintiff also and have been withdrawn today only.
In view of falling interest rates, sustaining interest @ 18% p.a. is
not found justified. Thus as far as the award of future interest at
18% per annum is considered, following of the dicta in Krishna
Bhagya Jala Nigam Vs. G. Haris Chandra Reddy AIR 2007 SC
817 and Flex Engineering Limited Vs. Antartica Construction
Co. 2007 (2) Arbitration Law Reporter 387 Delhi, the rate of
interest post award is reduced from 18% per annum to 10% per
annum till decree. The plaintiff shall also be entitled to future
interest from the date of the decree under Section 29 of the Act on
the principal amount at the rate of 10% per annum for a period of
60 days here from. If the defendant fails to pay the decreetal
amount within 60 days, the plaintiff shall thereafter be again
entitled to interest at 18% per annum.
17 The arbitral award as modified for interest as aforesaid is
thus made rule of the court and judgment is pronounced in terms
thereof. Decree sheet be drawn up. Parties to bear their own
costs.
RAJIV SAHAI ENDLAW (JUDGE) July 21, 2009 j
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!