Citation : 2009 Latest Caselaw 2417 Del
Judgement Date : 2 July, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS) 206A/1989 & CS(OS) 387A/1989
% Date of decision: 02.07.2009
SHRI SHERPAL SINGH ....... Petitioner
Through: Mr. D. Moitra, Mr. S.K. Jain and Mr.
N.K. Kantawala, Advocates
Versus
DELHI TRANSPORT CORPORATION ...... Respondent
Through: Mr. Vibhu Shankar, Advocate
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? No
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported
in the Digest? No
RAJIV SAHAI ENDLAW, J.
1. Both suits were filed under Section 14 & 17 of the Arbitration
Act, 1940 with respect to the same arbitral award. Upon the arbitral
award being filed in CS(OS) No.206A/1989, objections under
Sections 30&33 of the 1940 Act have been preferred by the DTC to
the arbitral award. The said objections are for consideration.
2. An agreement dated 7th March, 1984 was entered into between
M/s Rajora Builders with the DTC pursuant to the acceptance of the
bid of the said M/s Rajora Builders, for the work of construction of
Bodella Depot of the DTC. Disputes and differences having arisen out
of the said contract, M/s Rajora Builders applied for reference
thereof to arbitration. Upon failure of the DTC to appoint an
arbitrator, this court was approached under Section 20 of the 1940
Act. However, the DTC thereafter on 1st May, 1986 appointed Mr.
N.L. Kakkar, District Judge (Retd.) as the arbitrator.
3. M/s Rajora Builders preferred seven claims for a total sum of
approximately over Rs.25/- lacs besides interest against the DTC.
The DTC admitted a sum of Rs.68,978.39 to be due to the said M/s
Rajora Builders but claimed Rs.3,25,803/- to be due to it by way of
penalty from the said M/s Rajora Builders and after adjusting
Rs.68,978.39 therefrom claimed a sum of Rs.2,56,824/- to be due to
it from the said M/s Rajora Builders. DTC besides the said claim,
during the course of proceedings filed counter claim for a total sum
of Rs.21,80,103.58 inclusive of the aforesaid sum of Rs.3,25,803/-
besides interest, against M/s Rajora Builders.
4. The arbitrator vide award dated 31st December, 1988 awarded
a sum of Rs.14,20,970.57 to M/s Rajora Builders with simple interest
at 15% per annum thereon from 1st October, 1985 to the date of
reference and pendente lite and future interest also at 15% per
annum on the said amount from the date of reference till the date of
actual payment or decree whichever is earlier. The counter claims of
the DTC were dismissed.
5. CS(OS) No.206A/1989 was filed by Shri Sherpal Singh as
proprietor of M/s Rajora Builders. Upon the award being filed in the
court IA No.4230/1989 in CS(OS) No.206A/1989 was filed by the
DTC under Sections 30/33 of the 1940 Act objecting to the award. On
completion of pleadings therein the usual issues were framed on 24th
November, 1989 and parties directed to file evidence by affidavits.
No objections have been preferred by M/s Rajora Builders/Mr.
Sherpal Singh. Neither party applied for cross examination on the
affidavits of the others. IA No.9350/1998 was preferred by one Shri
Sanjeev Kumar under Order 1 Rule 10 r/w Order 6 Rule 17 of the
CPC averring that though at the time of the award of the work M/s
Rajora Builders was a sole proprietorship of Shri Sherpal Singh, it
was subsequently converted into a partnership firm vide deed of
partnership dated 7th June, 1989 and whereunder all the assets and
liabilities of the sole proprietorship concern were taken over by the
partnership. Besides the said Shri Sherpal Singh and Shri Sanjeev
Kumar another Mr. Rajiv Kumar was also stated to be a partner. It
was further averred that Shri Sherpal Singh retired from the
partnership firm vide deed of retirement dated 31st August, 1989 and
his accounts were settled; that M/s Rajora Builders thereafter
continued as a partnership of said Mr. Sanjeev Kumar and Mr. Rajiv
Kumar. Shri Sherpal Singh contested the said application. However,
thereafter the objections preferred by the DTC to the award were
dismissed in default on 1st June, 2001 and consequently the arbitral
award made rule of the court and decree in terms thereof passed.
Execution was applied of the said decree and an amount of
approximately Rs.48 lacs was attached in execution and received in
this court. Thereupon DTC applied for setting aside of the ex-parte
decree and for restoration of its objections and which were allowed
on 7th August, 2002 and the amount of Rs.48 lacs received in this
court ordered to be kept in a fixed deposit. DTC subsequently
applied for release of the said sum of Rs.48 lacs deposited in this
court and ordered to be kept in FDR and the said amount was
ordered to be released to the DTC on 15th May, 2006. The application
aforesaid of Mr. Sanjeev Kumar was allowed on 22nd March, 2001.
Thus the suit was ordered to be treated as by M/s Rajora Builders, a
partnership firm instead of by Mr. Sherpal Singh as sole proprietor
of M/s Rajora Builders. IA No.10209/2003 was filed for recalling of
the order dated 22nd March, 2001 and on which vide order dated 13th
February, 2008 the order dated 22nd March, 2001 recalled and the
proceedings ordered to be continued in the name of Sherpal Singh.
It was however clarified that the said order was not detriminative of
the inter se rights of the said Shri Sherpal Singh on the one hand
and M/s Sanjeev Kumar & Rajiv Kumar on the other. FAO(OS)
No.162/2008 was preferred by the said M/s Sanjeev Kumar & Rajiv
Kumar against the said order and which was disposed of vide order
dated 30th September, 2008 by permitting the advocates of both Mr.
Sherpal Singh as well as M/s Sanjeev Kumar & Rajiv Kumar to
address this court. The counsels have accordingly been heard.
6. At the outset, it may be stated that DTC has not challenged the
arbitral award in so far as dismissing its counter claims save its
counter claim for Rs.3,25,803/-. The objections by the DTC are
confined to the award of Rs.14,20,970.57 to the plaintiff and to the
dismissal of its counter claim for Rs.3,25,803/-.
7. The objections are hereafter taken in the order in the
application under Sections 30/33 of the 1940 ACT.
8. Objections qua dismissal of counter claim of DTC of
Rs.3,25,803/-.
A. This claim was made under Clause 14 on account of
compensation levied for non rectification of defects and
deficiencies. The amount claimed represents 10% of the
contract value.
B. The arbitrator negatived this claim for the reasons:
i) The claim having not been preferred prior to the
reference and having been raised for the first time
before the arbitrator. It was held that the existence
of a dispute is an essential condition for the
jurisdiction of the arbitrator and DTC having made
no claim prior to reference the question of the
same being disputed did not arise and hence the
claim was not maintainable before the arbitrator.
ii) The claim being not maintainable for the reason of
DTC having issued the letter dated 1st May, 1986
expressing satisfaction of the work and
commending the said work. It was held that the
counter claim had been made as a counter blast to
the claim of the plaintiff and to put pressure on the
plaintiff.
iii) That the six months for defect/liability period
ceased on 30th September, 1985
iv) No notice in this regard having been issued by DTC
to the plaintiff.
C. The objections of the DTC are:-
i) That the certificate dated 1st May, 1986 has been
wrongly interpreted. It was issued in terms of the
agreement and was not meant to be in discharge of
the defect/liability of the plaintiff.
ii) That the arbitrator erred in holding that the
defect/liability period came to an end on 30th June,
1985, having himself held the works to have been
completed on 31st March, 1985.
iii) That the liability for the defects in bitumen work
(road work) in fact was for one year and for other
works was for a period of six months. Thus the
defect/liability period ended on 30th September,
1985 and 31st March, 1986.
iv) That no notice of defect/liability was required to be
issued in terms of the agreement, however letters
calling upon the plaintiff to rectify the defects had
been issued and had been ignored by the
arbitrator.
D. As far as the objection regarding date of termination of
defect/liability period concerned, I may record that
though at one place the award mentions the
defect/liability to have come to an end on 30th June, 1985
but at another place the liability is stated to have come to
an end on 30th September, 1985. It thus cannot be said
that the arbitrator has wrongly noted the date or the
award can be faulted for the said reason. 30th June, 1985
appears to be a typographical mistake.
E. Though several objections as aforesaid have been taken
but in my view, if the award on the above aspect cannot
be faulted with for anyone reason given by the arbitrator,
the other reasons even if having an error apparent on
their face, would not call for setting aside of the award
on this aspect. I find the reason given by the arbitrator
of the issuance of the letter dated 1st January, 1986 to be
one such reason. The letter dated 1st January, 1986
issued by the DTC and reproduced in para 8 of the award
records completion of the works on 31st March, 1985 and
the performance of the plaintiff to be quite satisfactory.
The said letter is admittedly issued after defect/liability
period of six months with respect to all other works
except the road work. The arbitrator has on the basis of
the said document accepted the plea of the claimant of
the defects earlier pointed out by DTC having been
satisfactorily removed and the letter having been issued
thereafter only. The arbitrator has also held the
subsequent letters dated 10 February, 1986 and 18th
March, 1986 of DTC levying penalty to be malafide for
the reason of having been issued after the plaintiff had
made his demands. The arbitrator has also noted that
the claim for the said amount was first by way of penalty
and thereafter only expressed to be by way of
compensation.
F. I find the aforesaid reasoning of the arbitrator to be such
which cannot be interfered with under Sections 30/33 of
the 1940 Act. The same pertains to a factual controversy
and/or interpretation of documents the jurisdiction of this
court under Sections 30/33 is neither appellate nor
supervisory. The court is only to satisfy itself that the
approach of the arbitrator conforms to the law and that
the award does not suffer from any patent or manifest
illegality in the findings or in the applications of law. The
counsel for the plaintiff has in this regard rightly relied
upon Vijay Power Generators Ltd. Vs. Union of India
2008 (1) Arbitration Law Reporter 475 (Delhi) and
Shree Krishna Woolen Mills (P) Ltd. Vs. Union of
India 2008 (3) Arbitration Law Reporter 477 (Delhi).
Reliance was also placed on State of Rajasthan Vs.
Puri Construction Co. Ltd. 1995 1 Arbitration Law
Reporter 1 (SC) & Sudersan Trading Co. Vs. Govt. of
Kerala 1989 2 Arbitration Law Reporter 6 (SC) laying
down that whether any particular amount was liable to
be paid lay within the competence of the arbitrator and
the court cannot take upon itself the burden of saying
that what was actually found was contrary to the
contract and as such beyond the jurisdiction of the
arbitrator. The correctness of reasonableness of the
reasons was held to be not subject to the scrutiny of the
court.
9. The next challenge by the DTC is to the finding of the
arbitrator of the delay in completion of works being attributable to
the DTC and consequences thereof.
A. The contract period was six months commencing from 11th
February, 1984 i.e. till 10th August, 1984. Actual date of
completion is 31st March, 1985. The arbitrator has found that
the prolongation of the contract was on account of non
fulfillment of reciprocal promises and contractual obligations
by the DTC. The award refers to Exhibit C-23,C-24,C-27,C-
30,C-33 & C-34 pointing to delay in making the site available
and inadequate payments by the DTC. Though the award refers
to the argument of the DTC of there being no delay on its part
and of the payments being timely and commensurate to the
work and of the letters/notices of DTC to the petitioner for
expediting the work, the arbitrator has held the delay to be
attributable to the DTC. As a consequence of the said delay the
arbitrator under claim No.5 has awarded Rs.3,30,000/- to the
petitioner @55,000/- per month for about six months delay. The
sum of Rs.55,000/- has been computed at 10% of profits that
would have accrued to the petitioner for maintenance of
rollers, trucks, employees etc.
B. The objection of the DTC is :-
That on a reading of the documents filed as R-4,R-16, R-17,
R-19,R-22,R-24,R-25&R-27, the delay could not have been
attributed to the DTC. Even though, the said objection does not
constitute a ground under Sections 30 and 33. I have looked
into the said documents. The said documents are of the time
when the time for completion of the work had already expired.
In the said documents, DTC is denying the plea of the
petitioner of the delay being attributable to it. However on
perusal thereof I am unable to decipher therefrom any error in
the finding of the arbitrator of the delay being attributed to
DTC. There is no such document which can show the finding of
the arbitrator attributing delay to the DTC to be erroneous on
the face of it. I thus decline the said objection of the DTC.
C. I am however unable to sustain the award of Rs.55,000/- per
month under claim No.5. Just like it has been held that DTC
was not entitled to levy penalty of 10% of the contract value for
non rectification of the defects, on the petitioner, in the
absence of any proof thereof on the same parity of reasoning I
find that the arbitrator could not have awarded damages of
Rs.55,000/- per month total amounting to Rs.3,30,000/- to the
petitioner for delay. The award to that extent neither has any
basis nor logic in that regard and the award to that extent is
liable to be set aside. Though in accordance with the law laid
down in Tarapore & Co. Vs. Cochin Shipyard Ltd. (1984) 2
SCC 680 even without any agreement in that regard, the
petitioner would be entitled to compensation for delay
attributable to DTC but the said compensation can be awarded
only on furnishing proof of the loss suffered by the petitioner in
that regard. Here though @10% a sum of Rs.55,000/- has been
arrived at but the award does not state as to on what basis
figure of which Rs.55,000/- is 10% has been arrived at. The
award also does not disclose whether the compensation for
delay is calculated at 10% per annum in which case the figure
would not be Rs.55,000/- per month. If it is to be 10% per
mensem, then that is not so stated in the award.
D. Moreover, the impact of delay on the rates applicable to the
work done beyond the stipulated date of completion has been
taken into consideration by the arbitrator. For this reason also
I find that the arbitrator having already compensated the
petitioner for delay by awarding higher rates than agreed, for
the work done beyond the stipulated date, could not have
separately under issue No.5 awarded damages for prolongation
of contract.
10. The next challenge by the DTC is to the award of
Rs.8,58,847.52 under claim No.1 for non- payment of the final bill
and of refund of security deposit of Rs.1 lac. The challenge by the
DTC thereto is manifold. It is pleaded that the findings under this
head of extra work having been awarded are erroneous in as much
as under Clause 12 the Engineer in charge was competent to add to
alter or substitute the work and if any additional work was awarded,
side by side certain other works were curtailed thus keeping the cost
of the executed work same. The award in this regard is also
challenged on the ground of the arbitrator having exceeded the
measurements from time to time on the basis whereof payments of
the running bills were made. Bias and favourtism is also imputed to
the arbitrator and it is alleged that records of the petitioner which
were not filed appear to have been seen by the Arbitrator. The
arbitrator is pleaded to have ignored the relevant documents
produced before him by DTC in this regard. It is further pleaded that
the arbitrator inspite of contention of the DTC did not have the site
which was existing as it is, re-measured to resolve the controversy
regarding measurements. It is further urged that the arbitrator erred
in accepting the measurements pleaded by the petitioner, without
the same being substantiated. The findings of the arbitrator, of the
petitioner being not bound by the measurements which he had
signed at the time of receiving running payments, is also challenged.
11. However, in my view if this court enters into all the aforesaid
challenges, the jurisdiction then exercised by this court would not be
different from the jurisdiction in an appeal and which is not
permissible under Sections 30&33. I thus dismiss the objections of
the DTC to this part of the award.
12. The remaining award is on the claims of the petitioner under
Clause 10 that of the agreement i.e. owing to increase in prices
during the implementation of the contract. The objection of DTC is
that neither was there any increase nor was there any evidence
before the arbitrator for granting such increase of Rs.66,509/- on
account of labour escalation and Rs.35,614/- on account of escalation
of costs of material, under claims No.2&4 respectively. The
arbitrator has held that during the execution of the work, w.e.f. 1st
June, 1984 the labour wages were increased under the orders of the
Delhi Administration, Exhibit C-13. The arbitrator has under the said
claims also taken into consideration the delay in completion of the
works being attributable to the DTC. Similarly, the arbitrator for the
purposes of granting escalation on account of increase in cost of
material has relied upon the photocopies of Joint Plan Committee
filed by the petitioner. No error on the face of the award can be
found against the said award also.
13. The arbitrator has also awarded another Rs.15,000/- to the
petitioner against its claim of Rs.30,000/- for water and electricity
charges for three months. Reference thereto is made at the end of
para 2 of the award. However, there is no reference thereto in para
13 wherein claims of petitioner are listed. However under claim No.7
(cost of arbitration), though recording that no documents have been
filed by the petitioner to substantiate the said claim, the arbitrator
has awarded Rs.15,000/- for DTC having "availed the facility of water
and electricity which was the property of the claimant". Though I do
not find any objection having been preferred by DTC to this part of
the award, but I do not find any basis for award of this amount; in
fact the same is incomprehensible. The award of this Rs.15,000/- is
set aside.
14. The arbitrator has also awarded to the petitioner interest, pre
reference, pendente lite and future at 15% per annum. In my view,
the award of the arbitrator of pre reference interest in the
circumstances of the case is not justified. It is not as if the claims of
the petitioner have been accepted in toto by the arbitrator. The
claims have been considerably reduced by the arbitrator himself and
against which no objections have been filed by the petitioner. A party
which makes exaggerated claims leading to non settlement thereof,
and leading to protracted arbitration/litigation runs the risk of being
found disentitled to any interest even on the lesser amount found
due, unless shown that the claim for exaggerated amounts was
bonafide. I do not find any bonafides in the present case. For arriving
at the amounts due, a detailed inquiry was held by the arbitrator. No
fault can be found with the respondent not making the payments
demanded by the petitioner since all the said payments have not
been found due, by the arbitrator also, to the petitioner. Thus till the
said amounts were determined, in the facts of the case the award of
interest is not found to be justified. The award of interest pre
reference and pendente lite is set aside. The petitioner is thus found
entitled to interest from the date of the award only. I find the rate of
interest applied by the arbitrator also to be excessive. It is common
knowledge that the interest rates have been falling and in fact the
courts in such arbitral matters have been awarding interest only at
9% per annum. I find the petitioner in the present case also to be not
entitled to interest at a rate higher than that. Further I may notice
that while going through the records, the findings of the arbitrator
though not found interferable in exercise of jurisdiction under
Sections 30&33, are not found to be such, which if had been
rendered by the court would not have been interfered in appeal. In
my view, the equities will be balanced by, while upholding the award
to the aforesaid extent, by reducing the rate of interest. I thus find
the petitioner entitled to interest from date of award at 6% per
annum only.
15. I therefore sum up my findings as under:-
i) The award in favour of the petitioner under Claim No.1
of Rs.9,58,847.52 is upheld.
ii) The award in favour of the petitioner under Claim No.2
of Rs.66,509/- is upheld.
iii) The award in favour of the petitioner under Claim No.4
for Rs.35,614/- is upheld.
iv) The award in favour of the petitioner under Claim No.5
of Rs.3,30,000/- is set aside.
v) The award under Claims No.3&6 of interest is modified.
The petitioner shall be entitled only to interest on the
awarded amount upheld @6% per annum from the date
of the award and till the date of this decree. The
petitioner shall also be entitled to future interest under
Section 29 of the Arbitration Act, 1940 on the principal
amount only @9% per annum from the date of the decree
till the date of payment.
vi) The award in favour of the petitioner of costs of
arbitration of Rs.15,000/- under claim No.7 is upheld.
vii) The award of Rs.15,000/- towards water and electricity
charges is set aside.
viii) The award dismissing all the counter claims of the
respondent DTC is upheld.
16. Accordingly, judgment is pronounced in terms of the award as
modified above. Decree sheet be drawn up. No costs.
RAJIV SAHAI ENDLAW (JUDGE) July 2, 2009 PP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!