Citation : 2009 Latest Caselaw 96 Del
Judgement Date : 15 January, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP.No.17/2009
%15.01.2009 Date of decision: 15.01.2009
BJCL-BRITE(JV) through ITS LEAD ... Petitioner
PARTNER M/S BHOLASINGH JAIPRAKASH
CONSTRUCTION LIMITED (BJCL)
Through: Mr Ashish Bhagat with Mr Abdhish
Chaudhary and Ms Manisha Suri,
Advocates.
Versus
NATIONAL HIGHWAY AUTHORITY .... Respondent
OF INDIA (NHAI)
Through: Mr Chetan Sharma, Sr Advocate with
Mr Ashim Bhatt and Mr Ranjit Sharma,
Advocates.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? No
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported
in the Digest? No
RAJIV SAHAI ENDLAW, J. (ORAL)
1. The petition under Section 9 of the Arbitration Act, 1996 was
got listed yesterday post lunch. Finding no case for the grant of ex
parte order and on the submission of the counsel for the petitioner
that if the notice for a longer date is issued, the petition would
become infructuous, notice of the petition was issued to the
respondent for today. The counsel for the petitioner today in the
morning informed that some of the banks had, in pursuance to the
invocation of the bank guarantee by the respondent No.1, already
issued and delivered cheques thereunder to the respondent. It was
also informed that notice of termination of contract had also been
received from respondent. The senior counsel for the respondent
also confirmed the said fact and stated that he had been unable to go
through the voluminous paper book in the short time and requested
the matter to be taken up later in the day. It was agreed that the
cheques already received by the respondent shall not be encashed
till then.
2. The counsel for the parties have been heard. The petitioner in
this petition has claimed three reliefs. Firstly, of a direction to the
respondent to constitute Dispute Review Board (DRB) under clause
67.1 of the contract; secondly for restraining the respondent from
encashing and/or receiving payments under the bank guarantees and
lastly for a direction to the respondent not to terminate the contract.
3. The senior counsel for the respondent has urged that since the
contract has already been terminated, the DRB also cannot be
constituted. However, I do not consider it necessary to adjudicate
the said aspect since in my view the relief claimed of constitution of
DRB does not fall within the ambit of Section 9 of the Act.
4. As far as the third relief claimed is concerned, the senior
counsel for the respondent has urged that the same has become
infructuous, the notice of termination of contract having been
already served on the petitioner. The counsel for the petitioner
controverts, arguing that the notice is not effective as yet and
termination will come into effect on 14th day from the said notice
dated 13th January 2009 and as such the said relief can still be
granted. A copy of the notice has been handed over in court. Clause
63.1 of the contract enables the respondent to terminate the
contract in the eventualities prescribed therein, upon giving 14 days
notice to the petitioner and in certain other eventuality, immediately.
In my view, the 14 days time is to expel the contractor from the
project site. The said time is to enable the contractor i.e., the
petitioner, to remove itself and its goods and equipment from the
site, whereafter the respondent becomes entitled to expel. It cannot
be said that the termination does not come into effect till expiry of 14
days.
5. The grant of interim orders by the court, in relation to
arbitration proceedings, under Section 9, in my view, is to be
governed by the provisions to grant of prohibitory, mandatory and
other interim reliefs in the suits. Section 41(e) of the Specific Relief
Act bars the grant of permanent injunction to prevent the breach of
contract the performance of which would not be specifically
enforced. The contract in the present case was for the construction
of the balance work for 8-laning of 16.500 to 29.300 km of NH-1 in
the State of Delhi. The counsel for the petitioner has also, fairly not
urged that the said contract is specifically enforceable. He has,
however, urged that the work is in national interest and the disputes
had arisen between the respondent and the contractor earlier
engaged for the said work, and the respondent took a fairly long time
thereafter in assigning the work to the petitioner. It is stated that if
the respondent is permitted to terminate the agreement with the
petitioner also, it would not be in the interest of the work and would
lead to further delays in completion of the works. It is urged that the
petitioner is in a position to complete the works within the next six
months provided the respondent complies with its obligations under
the agreement and does not cause any hindrance as has been doing
till now. It is stated that the disputes, in fact, are not between the
petitioner and the respondent but of the petitioner with one
particular official of the respondent and this court should intervene
and refer the parties to a committee or to the mediation cell for the
purpose of ensuring and in the interest of timely execution and
completion of the works. The petitioner is stated to be willing in all
respects to ensure the same. It is further urged that the delays were
not attributable to the petitioner but owing to running traffic, of
flooding and caused by villagers and delays in obtaining change of
land use. The senior counsel for the respondent has, of course,
controverted the aforesaid. He has argued that it is the utter failure
on the part of the petitioner to complete the work inspite of
opportunities which has led to the notice of termination and there is
no possibility of the petitioner completing the works and if mediation
is attempted or further opportunity given to the petitioner, it would
lead to further delays. Various factors in this regard have been
mentioned but opportunity for filing the counter affidavit having not
been granted, I do not deem it necessary to record the same. Suffice
it is to state that this court at this stage is not equipped to or to go
into such disputed facts. The completion of work, as per the
petitioner, is still dependent upon performance of certain tasks by
the respondent.
6. The fact remains that there are serious disputes and
differences between the parties and it does not appear that there is
possibility of mediation or conciliation, when the counsel for the
respondent upon instructions has communicated that the respondent
knowing the past conduct of the petitioner is not willing for the
same. In my opinion no purpose would be served in giving an
opportunity to the respondent to file a counter affidavit or a reply to
the petition. In my view, owing to the bar contained in Section 41(e),
the interim measure of restraining termination of contract which is
not specifically enforceable cannot be granted. The Apex Court in
Cotton Corporation of India Ltd v United Industrial Bank AIR
1983 SC 1272 has held that when the relief of permanent injunction
cannot be granted owing to bar in Specific Relief Act, the question of
granting interim relief does not arise.
7. The only other relief remaining is of the stay of the encashment
of the bank guarantees or of receiving payments thereunder. The
bank guarantees are of two kinds i.e., performance bank guarantees
and bank guarantees against retention money. The bank guarantees
are unconditional, whereunder the bank which had furnished the
guarantees at the instance of the petitioner in favour of the
respondent had agreed to make payments to the respondent
thereunder upon the respondent's first written demand and without
any cavil or argument and without the respondent being required to
prove or to show grounds or reasons for the demand for the sum
specified therein.
8. The petition does not even plead fraud in the obtaining of the
bank guarantees of the nature on which ground alone it has been
held that the courts can intervene in the encashment of the bank
guarantees.
9. A faint attempt was made to urge that where cheques have
already been issued, the relief sought is of restraining encashment
thereof and the principles of injunction relating to bank guarantees
shall not apply. The argument does not even deserve a discussion
and is rejected.
10. It is the case of the petitioner that the encashment of the bank
guarantees is malafide. It is averred that the respondent spurred
into invoking the said bank guarantees immediately on receiving
notice of stay by this court of encashment of the bank guarantees for
Rs 3 crores against mobilization advance. It is further argued that
the petitioner has already applied to the respondent for constitution
of DRB and it is the DRB which is to make efforts for settlement of
disputes which have arisen between the parties and till then the
bank guarantees cannot be encashed. It is next contended that if the
stay of the bank guarantee is given, the respondent shall not suffer
adversely in as much as the respondent has provided in the contract
that if the encashment of the bank guarantee is interfered with by
the court, the respondent would be liable for interest for the delay at
12% per annum. It is also contended that the delays in execution of
the work have been occasioned by the respondent or for the reasons
attributable to the respondent. It is urged that the said delays on the
part of the respondent are admitted in the termination notice even.
It is further urged that the earlier contractor had obtained a stay
from this court and of which the petitioner was not informed and
therefore a fraud was committed by the petitioner in obtaining the
bank guarantees from the respondent. The counsel for the petitioner
had also argued that the action of the respondent is malafide, the
respondent had forwarded to the petitioner a supplementary
agreement as signed by the respondent with Nagarjuna Construction
company and which is contrary to the existing contract between the
parties. It was urged that the respondent has invoked the bank
guarantee to coerce the petitioner into signing the said
supplementary agreement. It is also argued that the retention money
bank guarantees cannot be invoked because the question of
appropriating retention money would arise only after the specified
period.
11. The aforesaid averments again are controverted by the senior
counsel for the respondent. It is argued that the contract
commenced from 29th December, 2005 and was to be completed
within 18 months and which time was of the essence of the
agreement. It is further argued that the petitioner was granted
extension of time without any damages from 28th June, 2007 to 24th
July, 2008 and thereafter till 31st December, 2008 with liquidated
damages.
12. The documents filed disclose that the various aspects of the
project were fully in the know of the petitioner. Whether the delay is
attributable to the respondent or not has to be determined in the
arbitration proceedings between the parties. The petitioner at the
time of taking the work was aware of and/or was expected to be
aware of nature thereof. The petitioner knew of disputes of
respondent with earlier contractor. The petitioner raised various
queries before executing the agreement and which were answered
by the respondent. No case of fraud of the egregious nature so as to
vitiate the underlying transaction is made out. Disputes of such
nature are there in all cases of bank guarantee and have not been
held sufficient to grant injunction.
13. As aforesaid the contract being of a nature not specifically
enforceable if the respondent is found to be in the wrong, the
petitioner would be entitled to damages from the respondent. At this
stage, the bank guarantees being unconditional and the Apex Court
having deprecated the practice of the courts interfering in the bank
guarantees in spite of the law having been laid down repeatedly by
the Apex Court with respect thereto, no case for interference in the
bank guarantees is made out. The clause of the contract regarding
the constitution of the DRB and/or regarding payment of interest for
delay in payment of bank guarantee would not justify this court in
interfering with the bank guarantees. Similarly, merely because the
DRB has not been constituted would not entitle the petitioner to have
the stay of the termination or of bank guarantees. If the intent had
been that till the DRB is constituted and/or is in session, the parties
would not take action which they were otherwise entitled to take
under the agreement, the contract would have so provided.
14. The retention money was to be retained by the respondent out
of payments made to the petitioner under the contract. Only as a
facility to the petitioner, it was permitted to furnish bank guarantee
against the same. The petitioner thus is not entitled to restrain the
respondent under the bank guarantee receiving the said money.
Moreover the terms of the bank guarantee, which alone are to be
seen at this stage, do not merit the submission of petitioner.
15. I therefore do not find any merit in the petition. The same is
dismissed. The respondent shall be entitled to encash the cheques
which on the suggestion of the court were ordered to be not
encashed till now.
RAJIV SAHAI ENDLAW (JUDGE) January 15, 2009 M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!