Citation : 2009 Latest Caselaw 319 Del
Judgement Date : 30 January, 2009
1.
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Pronounced on: 30.01.2009
+ W.P. (C) 1497/2000
INDIAN INSITITUTE OF ARCHITECT ..... Petitioner
Through: Mr. K.R. Chawla with
Ms. Monika Singhal, Advocates.
versus
UOI ..... Respondent
Through: Ms. Monica Garg, Advocate.
CORAM:
HON'BLE MR. JUSTICE S. RAVINDRA BHAT
1. Whether the Reporters of local papers
may be allowed to see the judgment?
2. To be referred to Reporter or not?
3. Whether the judgment should be
reported in the Digest?
S.RAVINDRA BHAT, J. (ORAL)
% Issue Rule. Ms. Monica Garg, Advocate on behalf of respondent waives
notice of Rule. With consent of counsel, the matter was heard finally.
2. The petitioner claims the Writ for quashing of an order issued by the
Land & Development Office (L&DO) whereby the allotment of its plot No.4,
Lodi Road Industrial Area (hereafter called the „plot‟) cancelled.
3. The facts necessary to decide this case are that the petitioner is a
Society of Architects. It had applied for allotment of a plot; on 22.3.1979,
L&DO allotted the plot, which measures 1051.33 Square Yards on perpetual
lease hold basis. An agreement was executed in this regard on that day.
Clause-II of the lease deed stated that within 24 calendar months from the
date of handing over of the possession, the lessee was to, at its own
expenses construct a building, upon the plot. The petitioner adverts to a
further demand for additional payment of consideration by the L&DO on
12.6.79 and its expressed inability to do so, (in its letter) accepted by the
L&DO on 30.11.1979. It is alleged that the possession of the plot was handed
over on 19.12.1979. Soon thereafter the plot was sought to be re-developed
in view of a proposed road widening. It is contended that this process
involved diminution of plot area by 29.6 Sq. Yards. Eventually the plot was
handed back to the petitioner, sometime in 1987. It is claimed that in the
meanwhile, the petitioner had applied for sanction to construct upon the
plot. It is a matter of record that the petitioner sought for "No Objection
Certificate" from the L&DO sometime in 1990. In the meanwhile, the plot
apparently was encroached upon; the respondent had inspected the land
and issued notice to the petitioner on 23.1.1987 alleging contravention of
the lease deed.
4. The L&DO issued NOC to the petitioner on 26.11.1990; the latter
applied to the local authority i.e. Municipal Corporation of Delhi (MCD) for
sanction of its building plans. This was eventually granted on 28.2.92. Soon
thereafter apparently in 1993, the alleged encroachers (who had occupied a
part of the plot) approached the Civil Court claiming injunction; an ex-parte
stay was granted. The ex parte injunction was vacated on 25.4.1993 after
which the plaintiff in that case approached this Court through a Civil
Revision, which was dismissed on 26.4.94. It is contended that the said suit
was dismissed in 1998.
5. The petitioner had on 12.12.1990 furnished an undertaking stating that
it would pay such sums as were to be determined by the L&DO and get the
encroachment cleared within six months. However, in view of the
subsequent events whereby the suit was filed, the petitioner was unable to
do so. In the circumstances, on 29.9.1999, the L&DO issued the impugned
order demanding a sum of Rs.2,16,26,904/- on account of misuse of the land,
non-construction and unauthorized occupation.
6. It is contended by the learned counsel that the impugned order should
be set aside because the petitioner was a victim of circumstances beyond its
control. He contends that initially construction could not be undertaken on
account of re-development of the plot. That process was completed in 1987.
By that time, a part of the plot had been encroached. The encroacher himself
sought a restraint order against the petitioner, the lawful owner. The
proceedings in that regard finally ended sometime in 1998. In the
meanwhile, the petitioner sought for building sanction, which was granted on
28.2.1992 by the local authority. The petitioner also filed a Suit for
possession impleading the said alleged encroachers being Suit No.1918/1999
on the file of this Court. The Suit was, however, transferred after the
pecuniary limit of the jurisdiction of the Court was raised to Rs.20 lacs. The
suit is pending and has not proceeded further.
7. The L&DO contends that the impugned order is justified in the
circumstances of the case. Counsel points to the impugned order where
differential rates are disclosed for the period 1986-1999. It is contended that
the authorities were conscious of the fact that the plot was subject to
development and, therefore, excluded the period of 8 years. It is further
claimed that the petitioner has not explained why delay occurred in its
approaching the Court for a decree of possession. These clearly point to its
ineptitude and indifference regarding protection of the plot. It is further
contended that the misuse and damage charges have further increased, for
which the Petitioner is squarely responsible. Urging that the Court should
not intervene, L&DO contends that the plot can be re-allotted to some other
deserving organization.
8. The factual discussion shows that the petitioner entered into a lease
deed with the L&DO on 22.2.1979, in terms of which, it had to construct
upon the plot within 24 months of handing over of the possession. There is
no dispute about certain facts, which occurred till 1987 such as possession
being handed over in December, 1979 and the plot being subject to re-
development, which led to decrease in its size - the process being completed
in 1987. At that point of time, the L&DO inspected site and discovered some
encroachment; the petitioner was put to notice and asked to take steps to
have the encroachment removed and misuse rectified. The matter remained
thus till 1990 when the petitioner sought for an NOC; the same too was
granted on 26.11.1990. The petitioner‟s application for sanction of its plan
was granted on 28.2.1992. In the meanwhile, the L&DO had granted
extension to the petitioner; in respect of the condition to construct upon the
plot, by its letter dated 7.2.1991. The material part of that letter reads as
follows: -
"With reference to your letter dated 19.12.1990, I am to say that the extension of time for execution of the construction on the plot allotted to the Institution is allowed up to 30-6-1991. The terms and conditions as mentioned in this office letter No.LII-1(209)/86/502 dated 4-9-1990 and 26-11-1990 will be settled separately".
9. The alleged encroacher filed a Suit in 1993 and secured an ex parte
injunction. The injunction was later vacated in 1994; however, the Suit
continued to be pending on the file of the Trial Court till it was dismissed in
1998. The respondents issued the impugned demand on 29.9.1999. The
said demand is premised on misuse charges for the period 9.7.1986 to
30.9.1999. The L&DO has based its demand on 4 different block periods i.e.
7.9.1986 - 23.4.1990; 24.4.1990 - 9.2.1992; 10.2.92 - 7.12.1998 and
8.12.1998 - 28.1.1999. All these are based on misuse charges in respect of
specific areas occupied by the encroachers described as tea stall and M/s Taj
Nursery. The L&DO has also demanded damages towards unauthorized
construction and collective interest. After the orders of this Court, the L&DO
issued further demand on 23.11.2004 for a total amount of Rs.5,37,34,627/-.
10. The above narration of facts discloses that the petitioner showed
indifference towards the condition of the plot and did not secure it at least
from 1987. The first time when it approached the authority for NOC was in
1990. The discussion would show that the petitioner was casual to its
commitment and disinterested as did not care to take steps towards putting
up any construction; it approached the authorities in 1990 when the NOC
was granted. The sanction for construction was granted by the MCD on
28.2.1992. At that stage, the alleged encroachers approached the Court and
obtained a stay. The petitioner could perhaps legitimately claim
helplessness on that score. Yet it cannot completely disclaim any
responsibility because it filed the Suit to seek eviction from the land and
obtain possession in 1999. The alleged encroacher‟s suit was dismissed only
in 1998. The petitioner suit is still pending and has not been decided by the
Trial Court. According to counsel, the Trial Court has not taken further steps
in view of the pendency of the present writ proceedings.
11. Having regard to the above facts, the picture which emerges is that
although the petitioner showed indifference, it would be harsh to saddle it
with liability for the entire period. No doubt, the L&DO noticed the
encroachment in 1987, yet the petitioner took steps to have the NOC and
sanction between 1990-92. In between the respondent also granted
extension of time, (of course subject to the condition of payment of charges).
In these circumstances, the L&DO should not have sought damages for
misuse and unauthorized construction from the petitioner for the entire
period. Doing so would be unreasonable, because for some periods the
matter was in fact beyond the petitioner‟s control. No doubt, the allotment
made was for purpose of utilization of the plot; yet the period between 1992
and 1999 should not be included for the purpose of calculating misuse and
damage charges.
12. In view of the above, at least in respect of two distinct periods i.e.
9.3.1990 to 28.2.1992 (till it obtained the sanction from the MCD), and
thereafter as the petitioner was subject to an interim order, which prevented
it from taking any steps towards recovery of possession and the clearance of
the encroachment, the L&DO should not claim any damages and charges. In
the circumstances, L&DO could not have claimed misuse and damage
charges for the period 9.3.1990 till 1.1.1999.
13. Having regard to the above, the following directions are issued: -
(a) The petitioner‟s suit, which is now re-numbered as 348/2007
pending before the Additional District Judge, Tis Hazari titled as
Institute of Architects v. Shri Narender Singh & Ors. shall be
decided on its merits within six months from today.
(b) The impugned orders dated 29.1.1999 and 24.9.1999 are hereby
quashed.
(c) The petitioner shall intimate the outcome of the Suit to the
L&DO, which shall thereafter proceed to take an informed decision
having regard to the pendency of the Suit and after considering the
order sheet in the same, and subject to the above judgment.
The Writ Petition stands disposed of, in the above terms.
Order dasti.
S. RAVINDRA BHAT (JUDGE) JANUARY 30, 2009 /vd/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!