Citation : 2009 Latest Caselaw 5228 Del
Judgement Date : 15 December, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Arb.P.No. 208/2009
December 15, 2009.
M/S STUP CONSULTANTS PVT. LTD. ...Petitioner
Through: Mr. D. Moitra, and Mr. P. Roy
Chaudhuri Advocates
VERSUS
M/S INDIAN OIL CORPORATION LTD. ....Respondent
Through: Mr. V.N.Kaura, Advocate with
Ms. Paramjeet Benipal,
Advocate
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see
the judgment?
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be reported in the Digest? Yes
% JUDGMENT(ORAL)
VALMIKI J. MEHTA, J.
*
1. This is a petition under Section 11 of the Arbitration and Conciliation
Act,1996 whereby the petitioner seeks reference of the disputes between it
and the respondents to arbitration. The disputes pertain to the Letter of
Arb.P.208/2009 Page 1 Intent dated 11.12.2000 and the Letter of Acceptance dated 23.3.2001 issued
by the respondent in favour of the petitioner in respect of a contract whereby
the petitioner was to give to the respondent certain consultancy services for
architectural/design engineering, interior decoration/horticulture/
landscaping, project management work etc. The contract in question
contains an Arbitration Clause 15 whereunder the disputes are to be referred
to arbitration of a sole Arbitrator to be agreed upon between the parties.
2. It is not disputed that a contract was entered into between the parties
and it is not further disputed that the contract contains an arbitration clause.
It is further also not in dispute that differences have arisen between the
parties under the subject agreement.
3. Mr. Kaura, counsel for the respondent has however argued against
reference of the disputes on the ground that the relevant part of Clause 15.1
of the contract in question requires that only a notified claim can be referred
to arbitration and the disputes do not pertain to a notified claim and
consequently the right to seek reference of the disputes to arbitration stands
extinguished. The relevant portion of Clause 15.1 is reproduced as below:-
"15.1 Any dispute or difference between the parties hereto arising out of any notified claim of the CONSULTANT hereof and/or arising out of any amount claimed by the OWNER (whether
Arb.P.208/2009 Page 2 or not the amount claimed by the OWNER or any part thereof shall have been deducted from the Final Bill of the CONSULTANT or any amount paid by the OWNER to the CONSULTANT in respect of the work) shall be referred to arbitration in accordance with the UNICITRAL Rules as adopted in India by the Arbitration and Conciliation Act, 1996."
It has additionally been argued by Mr. Kaura that claims which are
preferred by the petitioner are barred by time.
4. A reading of the aforesaid Clause 15.1 of the Conditions of Contract
shows that seemingly only a notified claim can be referred to Arbitration.
On a query by the Court to the counsel for the respondent as to whether the
expression "notified claim" is defined in the contract, the counsel for the
respondent admits that there is no definition of the expression "notified
claim" in the contract. Therefore, I would have to look at the normal
meaning of the expression "notified claim". In the opinion of this court,
"notified claim" would simply mean a claim which is notified by the
petitioner to the respondent. Taking such meaning, I may at this stage, refer
to the letter dated 7.2.2007 written by the petitioner to the respondent, and as
brought to my notice by the counsel for the petitioner. Para 2 of this letter
shows that the claims which are sought to be referred to Arbitration were
duly notified to the respondent. The counsel for the petitioner has also
brought to my attention the reply given to this letter on behalf of the
Arb.P.208/2009 Page 3 respondent through its Advocates on 13.11.2007, and in which reply there is
no denial of the averment with regard to the notification of the claims to the
respondent as stated in the letter of the petitioner dated 7.2.2007. The
counsel for the petitioner has further brought to my notice the last para of the
reply dated 13.11.2007, in which the respondent itself has proposed the
names of the Arbitrators to whom the disputes can be referred to.
5. On the facts itself as stated in para 4 above, therefore, it is quite clear
that there is no bar in terms of Clause 15.1 to hold that the right of a
claimant to seek reference of the disputes to Arbitration is extinguished in as
much it is quite clear that the claimant had very much notified the claims
and the fact that such claims were notified was not disputed by the
respondent.
6. In my opinion, in fact, that part of Clause 15.1 of the Contract, as
reproduced above is wholly illegal and void if it is read as extinguishing the
right to seek arbitration. This conclusion follows from a reading of Section
28 of the Contract Act, 1872 and which Section was amended in 1997 for
this very purpose to declare such clauses as void. Section 28 of the Contract
Act, after amendment by Act-1 of 1997, reads as under:-
"28. Agreement in restraint of legal proceedings, void-
Arb.P.208/2009 Page 4 (a) by which any party thereto is restricted absolutely from enforcing his
rights under or in respect of any contract, by the usual legal proceedings in the ordinary tribunals, or which limits the time within which he may thus enforce his rights; or
(b) which extinguishes the rights of any party thereto,or discharges any party thereto, from any liability, under or in respect of any contract on the expiry of a specified period so as to restrict any party from enforcing his rights, is void to that extent."
Section 28 was amended by adding sub-section (b) thereto and as per
which any clause in a contract which extinguishes the rights of any party
thereto, or discharges any party thereto, from any liability, under or in
respect of any contract on the expiry of a specified period so as to restrict
any party from enforcing his rights, is void to that extent.
7. A learned Single Judge of this Court, Hon'ble Mr. Justice Sanjay
Kishan Kaul, in the judgment reported as Pandit Construction Company vs
DDA 2007 (143) DLT 270 has held that any such clause in a contract which
extinguishes the rights of the parties on the expiry of a period would be
considered as void. The learned Single Judge has referred to the earlier
judgments on this aspect and has also gone into the aspect of amendment to
Section 28 while also referring to the Supreme Court judgment prior to the
amendment and has distinguished them.
8. No doubt the relevant part of Clause 15.1 does not contain a time
period, however, when no time period is specified for doing of an act under
Arb.P.208/2009 Page 5 the contract, then, the time requirement will be a reasonable period of time
vide Section 46 of the Contract Act. Thus a conjoint reading of Clause 15.1
and Section 46 would mean that if the claims are not notified in a reasonable
period, the rights thereto get extinguished and which is exactly what Section
28 of the Contract Act prohibits.
9. When this judgment was being dictated in open Court after the
counsel for the parties were heard, and when I came to the stage of dictating
the aforesaid portion under Section 28 of the Contract Act, Mr. Kaura
argued that the judgment should not be passed by making a reference to
Section 28 as that issue was not argued. I do not think it is fair on the part of
the counsel for the respondent to urge that the court cannot independently
rely upon any Section or any judgment if it is of the opinion that such a
Section or that judgment applies. A court is bound, not by the limited
submissions of the counsel, but by the law of the land. I would only state
that the prerogative of the counsel comes to an end when the arguments are
concluded. I could have as well reserved the judgment and thereafter while
dictating the judgment relied upon Section 28 of the Contract Act and the
judgment in the case of Pandit Construction Company(supra) but, I have
chosen to dictate the judgment in the open court, but, this however, cannot
Arb.P.208/2009 Page 6 mean that the counsel can in the middle of the dictation of the judgment seek
to interfere with the court proceedings and say that the judgment should not
be passed. Accordingly, I reject the contention as raised by Mr. Kaura on
behalf of the respondent.
10. So far as the issue that the claims are within limitation or barred by
limitation, this is an issue of merits as held by the Supreme Court in the
judgment reported as National Thermal Power Corporation Ltd. Vs.
Siemens, 2007(4) SCC 451. In fact, a decision on the issue of limitation has
been held in this judgment to be an interim award under the provisions of the
Arbitration and Conciliation Act, 1996 entitling the party to file an objection
to the same under Section 34 thereof. Accordingly, this issue of limitation I
feel would be decided by the Arbitrator in the arbitration proceedings and
not by this court while appointing an arbitrator under Section 11 of the
Arbitration and Conciliation Act.
11. Accordingly, I am of the opinion that this petition deserves to be
allowed. At this stage of referring the disputes to the Arbitration, I put it to
the counsel for the parties that whether they are agreeable to refer the
disputes to the Arbitration Centre of the Delhi High Court and be bound by
the rules thereof. To this position the counsel for the petitioner had no
Arb.P.208/2009 Page 7 objection but the counsel for the respondent states that since the judgment is
not acceptable to the respondent, the respondent would not agree to the
Arbitration of the Delhi High Court Arbitration Centre.
12. The petition under Section 11 is accordingly allowed and I appoint
Justice Arun Kumar, (Retired), 9, Tyag Raj Marg, New Delhi-110011,
9810398777, 26510146, (who is on the panel/list of Arbitrators of the Delhi
High Court Arbitration Centre) as an Arbitrator to decide
disputes/claims/counter-claims/differences in any manner connected with or
arising out of the subject contract between the parties whereby consultancy
services were provided by the petitioner to the respondent. I may state that
the fees of the Arbitrator will be the same as per the schedule of fees as
given under the rules of the Delhi High Court Arbitration Centre. The
Arbitrator as far as possible should decide the matter before him within a
period of one year from the date of his entering upon the reference. The
petitioner shall file its statement of claim before the Arbitrator within a
period of six weeks from today. The respondent shall file the written
statement and counter claim if any, within another period of four weeks
thereafter. Replication and written statement to the counter-claim will be
filed within another period of four weeks thereafter. Parties to appear before
Arb.P.208/2009 Page 8 the Arbitrator on 26th March, 2010 at 5.00 PM. A copy of this judgment be
sent to the Arbitrator.
13 With the aforesaid observations, the present petition is disposed of as
allowed with costs quantified at Rs.50,000/-.
DECEMBER 15, 2009 VALMIKI J. MEHTA, J. ib Arb.P.208/2009 Page 9
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!