Citation : 2009 Latest Caselaw 3342 Del
Judgement Date : 25 August, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: 20.07.2009
Date of Order: 25th August, 2009
CS(OS) No. 488A/1991
% 25.8.2009
M/s Krishna Construction Co. ... Petitioner/Plaintiff
Through: Mr. Harish Malhotra, Sr. Advocate with
Mr. Rajender Aggarwal, Advocate
Versus
DDA & Anr. ... Respondents/Defendants
Through: Mr. Bhupesh Narula, Advocate &
Mr. H.L.Narula, Advocate
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment? Yes.
2. To be referred to the reporter or not? Yes.
3. Whether judgment should be reported in Digest? Yes.
JUDGMENT
By this order I shall dispose of objections under Section 30/33 of the
Arbitration Act, 1940 raised by the respondent/DDA against the award dated 08.1.1991
passed by the learned sole Arbitrator. In the objection petition the respondent/DDA has
stated that it seeks to challenge the award made by the Arbitrator in respect of claims
no. 2,4,5,6,7 & 8 of the original claims and in respect of additional claims no. 1, 2 & 4
made by the petitioner.
2. The facts in brief are that the petitioner was given a contract for
redevelopment of Sarai Khalil involving construction of 138 LIG and 138 MIG houses at
Sarai Khalil vide contract dated 2.2.1977. The date of commencement of work was
12.2.1977 and the work was to be completed within one year however, during
continuation of the work it was found that there was a stone quarries underneath the
land which had been filled up after extraction of the stones. Consequently, foundation
design of some of the blocks had to be changed from conventional foundation to pile
foundation and in some of the blocks strip foundation was to be done. The
contractor/claimant in this case was not competent to do the work of pile foundation
therefore an outside agency was hired by DDA to do the work of pile foundation and
after completing the work of pile foundation the blocks were handed over to the
contractor for rest of the work. It is also apparent from record that there was a stay
granted by the High Court and due to stay of the Court the work got delayed and the
time for completion of the work was accordingly extended. However, the work could not
be completed even within the extended time and the Advisory Board of the respondent
closed the work on 20.9.1980 and intimated the contractor about the same. The
contractor after closing of the work raised various claims against the respondent and
filed a suit before the High Court invoking arbitration clause. The claims raised by the
claimant in the suit were directed to be referred to the arbitration. The result was that
the respondent appointed Arbitrator in terms of clause 25 of the contract. When the
Arbitrator was proceeding with the claims some additional claims were preferred by the
claimant which were also referred by the Engineer-in-Charge to the Arbitrator subject to
their admissibility under the contract.
Objections regarding Claim No.2
3. Claim No.2 which is subject matter of challenge by the respondent
pertains to an award of Rs.81,058/- made by the learned Arbitrator in favour of the
Contractor towards additional expenditure incurred on chowkidar on account of default of
DDA in not taking over the building and material at site. The learned Arbitrator observed
that delay was due to stay granted by High Court against the construction in 4 ½ blocks
and due to pile foundation required to be done. The learned Arbitrator stated that the
claimant had contended that the work was completed in October 1980 and the dwelling
units were allotted sometime in 1985 and till then the claimant had maintained watch and
ward staff. The Arbitrator held that since non-execution of balance part of the work was
on account of failure of the respondent to make the blocks available for construction and
on account of decision to opt for pile foundation and the respondent also did not take
over material for which the secured advance had been paid, rather called upon the
claimant to refund the advance with interest, the respondent/objector was in default and
considering the locality around the site of work, the claimant had claimed reasonable
rates for watch and ward staff and the claimant was entitled for Rs.81,058/- in respect of
the claim.
4. The objector's contention is that this claim could not have been allowed
since it was petitioner's responsibility to keep the watch and ward staff till the building
and material were handed over to DDA. It is also submitted that there was no provision
in the agreement entered into between the parties providing for payment of watch and
ward staff additionally to the contractor.
5. A perusal of clause 12 of the contract between the parties would show
that it was within the power of Engineer-in-Charge to make alterations, additions or
omissions or do substitution for the drawings, designs and original specifications that
may appear to him necessary during the progress of the work and the contractor had to
carry out the work in accordance with such alterations, omissions, additions,
substitutions of the original specifications with such change in designs. It is specifically
provided that such additions or substitutions shall not invalidate the contract in any
manner and were to be carried out by the contractor on same terms and conditions on
which he had agreed to do the main work. The only thing under such circumstances to
be done was that the time for completion of the work was to be extended in proportion to
the alterations made. Over and above this, a further period to the extent of 25% of such
extension was to be allowed to the contractor. The contractor was to be entitled for
rates for such additions/alterations, to be worked out in accordance with the provisions
given in the clause 12. In case the rates for additions or substituted work could not be
determined, then the contractor within 07 days of receipt of order to carry out the work
had to inform the Engineer-in-Charge the rates, which he intended to charge for such
work and the Engineer-in-Charge either could accept the rate or cancel the order to
carry out such additional work. It is also specifically provided in the contract (under
clause 13) that the work awarded could be reduced and the contractor may not be
required to do the whole of the work tendered. The contractor under such
circumstances was not to be entitled to payment of any compensation or loss of profit.
6. It is thus clear that providing of pile foundation in view of the discovery of
stone quarries underneath the land was within the scope of the contract and in view of
this development the only thing which the contractor could demand was the extension of
time. Similarly, the respondent had no control over the stay order given by the High
Court. The plea of the claimant that respondent had failed to take effective steps for
early vacation of stay order is not tenable. Merely by taking steps by a party, a case in
the High Court is not decided early. Had it been so, there would have been no
pendency in the Courts and every party would have taken effective steps for early
disposal of his case and got the case disposed of. It is not within the hands of a party to
get the stay vacated early. I, therefore, consider that delay in this case cannot be
blamed on the part of the Objector and the Arbitrator's conclusion that delay was on the
part of DDA/Objector is contrary to contractual provisions. When the contract
specifically provided that the designs, drawings and specifications could be altered
according to ground situation during the continuation of the work, the Arbitrator's
conclusion of delay being responsibility of the respondent was not tenable.
7. For allowing any claim in respect of payment to the workers, the learned
Arbitrator could not have ignored the terms of contract. It is provided in the contract
under clause 19-D that the contractor had to submit by 4th and 19th of every month to
Engineer-in-Charge a true statement showing the number of workmen employed by him,
their working hours and wages paid to them. In this case, the contractor had only
submitted an estimate of the expenditure on wages. He had not submitted either before
the Arbitrator or to the Engineer-in-Charge the necessary evidence showing that any
workmen were employed by him. Even otherwise under Clause 19-K it was the
responsibility of contractor to see that the building under construction was not occupied
by any unauthorized person during construction and he was to handover to the
Engineer-in-Charge vacant possession of complete building. It is not recorded by the
Arbitrator that the Contractor at any point of time had offered vacant possession of the
complete building to the respondent and asked the respondent to take over the
possession of the entire building. Unless and until the contractor/claimant had offered
the building to Engineer-in-Charge who had refused to take over the building, the
contractor could not have claimed any charges for chowkidars etc. After expiry of notice
given by him for handing over building, the contractor would have been at liberty to leave
the building so that DDA could have taken the responsibility. Looking into the terms and
conditions of the contract whereunder the contractor till handing over the building was to
see that the building was not unauthorizedly occupied by somebody and it was also
responsibility of the contractor to submit fortnightly report to the Engineer-in-Charge of
the workmen employed and the wages paid, in case of absence of record of wages paid
and in absence of notice of the contractor of tendering vacant possession of the building
to Engineer-in-Charge, no amount could have been awarded by the learned Arbitrator.
The award of the Arbitrator on this count is contrary to contract and is liable to be set
aside.
Objections regarding Claim No.4
8. Under Claim No. 4, the Arbitrator had allowed a sum of Rs.12,375/- to the
contractor on account of additional expenses incurred by the contractor for extending the
bank guarantee. The learned Arbitrator after recording contention of both the sides
observed that the plea of the contractor that the contractor was required to keep the
bank guarantee alive beyond the defect liability period because of the respondent was
justified. He (learned Arbitrator) therefore allowed amount of Rs.12,375/- for keeping the
bank guarantee alive upto 4.8.1989. The contractor had taken the plea that he had to
keep the bank guarantee alive without any justification because of the demand of the
respondent/DDA. I find that allowing of this claim by the learned Arbitrator is strange. If
the demand of DDA to keep the bank guarantee was unjustified, the contractor was at
liberty not to extend the bank guarantee and let the law take its own course. The
contractor kept the bank guarantee alive for his own interests and not because of DDA.
If it was not in the interest of the contractor to keep the bank guarantee alive, the
simplest thing he was to do was to ask his banker not to extend the bank guarantee.
The learned Arbitrator could not have awarded him expenses for keeping the bank
guarantee alive. The contractor kept the bank guarantee alive because he considered
that he was on a weak footing and continued the bank guarantee as demanded by DDA.
A bank guarantee is furnished by a contractor in accordance with the contract. If a
contractor considers that he is not required to furnish a bank guarantee or to extend the
bank guarantee he is at liberty to do so. He cannot claim expenses for either furnishing
the bank guarantee or extending the bank guarantee at the instance of the
employer/DDA. I find that the award of this amount is contrary to the terms of contract.
Objections regarding Claim No.5
9. Under claim no. 5 the Arbitrator had allowed a sum of Rs.61,828/- to the
contractor on the ground that there was existence of sub-soil water and the claimant had
to pump out the water by employing pumps. It is not disputed that the claimant had
been paid for foundation in accordance with contract for quantity which involved "under
water" foundation as in the DSR. Under the contract for execution of this quantity,
removal of seepage water due to sub soil water, was the responsibility of the contractor.
The learned Arbitrator observed that he was of the opinion that the marginal difference in
the rates for excavation in dry and wet conditions as given in the contract did not
contemplate the use of long hours of continuous pumping out of water by employing
pumps and therefore allowed the claim of the contractor. It is contended by the
respondent that the learned Arbitrator went beyond the terms of contract. The contract
fully covered the excavation and laying of foundation in wet conditions "under water" and
the contractor had been paid in accordance with the terms of contract, the Arbitrator
could not have allowed additional amount to the contractor.
10. The claimant in this case had been paid as per DSR which included
charges and rates for bailing out seepage water. When there is a specific quantity
mentioned in the clause of contract, no additional amount could have been allowed by
the Arbitrator. It is settled law that the Arbitrator is prisoner of the contract and he is not
a judge in equities. It is for the contractor to tender or not to tender for work considering
the rates prescribed by the employer. Once the contractor had agreed to a specific rate,
he cannot be allowed additional amount by the Arbitrator on the ground that additional
work was involved in the item. Even otherwise, if there was an additional or substituted
work involved in a contract, under Clause 12 (v) the contractor was supposed to give a
notice within 07 days of the order for carrying out the additional work and inform the
Engineer-in-Charge of the rate which he intended to charge for such work. It is not
within the jurisdiction of the Arbitrator to determine the rates of the additional work. It
was within the jurisdiction of Engineer-in-Charge, during the continuation of the contract,
to determine the rate of additional work or to cancel the additional work to be done by
the contractor. The Arbitrator exceeded his jurisdiction in allowing this claim and mis-
conducted himself. The award under this claim is therefore liable to be set aside.
Objections regarding Claim No.6
11. Under Claim No.6 (i), the Arbitrator had allowed a sum of Rs.15,300/- to
the claimant on account of shifting of material collected on site of work so that pile
foundation could be taken up by another agency. I consider that this claim could not
have been entertained by the learned Arbitrator. The pile foundation was constructed
sometime in 1980-81 and shifting of material had taken place at that time, if the
contractor had to raise a claim in respect of shifting of material he could have submitted
the bill for shifting of material to the respondent/DDA only at that time. This shifting of
material was not a contractual item, it was an additional work which the contractor claims
to have done. He could have told DDA that he was not prepared to shift the material
and let DDA engage its own labour and in case he had agreed to shift the material, he
was to act in accordance with clause 12(v). If he had not given his rates for shifting of
material to DDA at that time he could not raise this claim afterwards. Shifting of material
was not an item provided under the contract. Moreover, a contractor is given drawings
and lay out plans of the building in advance. He had to stack material at the site
ensuring that place occupied by material was not within the construction area and was
outside construction area. If he had stacked material within the construction area, he
could not claim charges for removing material from construction area to non construction
area. It was his responsibility to keep the material at non construction area. The claim
therefore was barred for two reasons, one it was a time barred claim, the claimant could
have raised this claim within three years of shifting of material and it is also barred as
stacking of the material was part of his job under the contract and he was not to be paid
anything extra because of improper stacking of material and then shifting the same. I,
therefore find that the award under this claim being contrary to contract and of a time
barred claim is not tenable and is liable to be set aside.
12. Under Claim No. 6(ii) the learned Arbitrator awarded a sum of
Rs.1,41,172/- to the claimant for infructuous expenditure because of the stay of the High
Court. The learned Arbitrator observed that the contractor had incurred expenditure on
the shuttering and reinforcement of beams and the reinforcement material placed on the
shuttering prior to the court stay order. Since, it was the employer's responsibility to
provide site free from hindrances and DDA could not obtain vacation of stay
immediately, DDA was to bear the burden of expenditure of centering, shuttering,
reinforcement and scaffolding from 1.5.1977 to 30.9.1977 as already observed by me in
para 6 above that it is not within the hands of a party to get the stay vacated nor it is a
case that Courts do not grant ex parte stay without hearing the other party. I consider
that DDA cannot be held responsible for act of the High Court in continuing an ex parte
stay for a period of 05 months. Moreover, there is no certainty that the stay would be
vacated by the Court in any specific period. The contractor after coming to know the
stay of the Court was supposed to act accordingly. The stay is normally applicable to
the party and every other person who is indirectly involved with the subject matter of the
stay order. The stay was therefore, equally effective against the contractor who was
working at the site in question. The learned Arbitrator's observation that DDA failed to
provide hindrance-free site is therefore untenable and the awarding of this amount of
Rs.41,172/- on this ground is also not tenable and is liable to be set aside.
Objections regarding Claim No.7
13. Under the Claim No.7, the learned Arbitrator allowed additional amount
over and above the contractual amount to the claimant of Rs.95,248/- for the work done
by the claimant from 11.2.1978 to 15.4.1979 and another amount of Rs.2,56,516/- from
15.4.1979 to October, 1980 on the ground that the claimant was entitled to these
additional costs because of work getting prolonged beyond the period of one year which
was the contract period and the claimant was entitled to additional costs. It only shows
that the learned Arbitrator had not considered the terms of the contract at all. The terms
of contract provided for extension of the period of completion of contract under several
circumstances including the circumstances of change in designs, drawings as already
observed above in para 5 above. A contractor who considers that performing of contract
by him beyond the period stipulated in contract was not profitable; he is always at liberty
to walk out of the contract. In case he considers that he is entitled for additional amount
for working beyond a period, he should give a notice to the Engineer-in-Charge in terms
of the contract and unless and until the Engineer-in-Charge accepts the additional
payment as claimed by him, he should not work. If the contractor continued to work
beyond the period of one year which was the stipulated period, it only shows that he had
agreed for extended period of contract and was aware that the contract period was
extendable and the contract had to be performed within the extended period on same
terms and conditions. Merely by writing a letter that he would charge 10% or 20% or
30% extra, no concluded contract comes into operation for payment of extra amounts.
Additional payment for prolongation of the work can be claimed by the contractor only
under the contract and not beyond the contract. The concluded contract does not come
into operation between the parties if one party writes a letter and other party does not
respond to the letter. Under Clause 12(v), in case the DDA had not agreed to the
enhanced rates as demanded by the contractor, the contractor was free to stop the work
and free to walk out of the contract. DDA in such a case would have been at liberty to
get the work done from other contractor. The time as provided under the contract was
not essence of the contract rather the contract between the parties specifically provided
that the work and the time period under the contract could be increased. The designs
and specifications could be altered according to change in circumstances and the time
period for execution of the contract can be increased keeping in view changed
specifications it is specifically provided that in case of an eventuality of change in
specifications made during the continuation of the work, the contractor would not be
entitled to any additional rates except as provided in the contract and he will have to
work on the agreed rates. Under these circumstances, entertaining claim by the
Arbitrator on the ground of laying pile foundation as stone quarries were discovered
underneath of ground and on the ground of grant of stay by the High Court is contrary to
contract. The learned Arbitrator had already awarded additional amount for increase in
cost of material and labour to the contractor in terms of Clause 10C under Claim No.1
which has not been challenged by the respondent. I, therefore, consider that the
additional amounts awarded by the learned Arbitrator under claim no.7 (i) and (ii) were
not tenable and the award of this claim is liable to be set aside.
14. Under Claim no.8 claimant had claimed Rs.3,66,528/- towards
compensation for cumulative loss of productivity due to non/under utilization of
establishment, equipment and T & P and the learned Arbitrator had awarded a sum of
Rs. 45,000/- for loss of productivity and overheads and a sum of Rs.52,000/- for T&P. It
is seen that in all DDA's contracts after the contract is over, the contractors make
fantastic claims under various heads. Invariably, there is a delay in execution of the
contracts for whatsoever reasons, after the final bill is received the contractors make
claims for enhancement of costs under Clause 10C for increase in cost of labour and
material and make separate claim under Clause 10CC where it is there, apart from that
claims are made for infructuous expenditure like keeping establishment on the site for
longer period, expenditure for keeping tools and machinery idle, loss of productivity,
under-utilization of establishment/equipment, capacities etc. and loss of profits etc.. All
these claims are made by the contractors only because of one factor i.e. that the work
got delayed, claims under different heads are made for the same factor and every such
claim is made time and again. This is despite the fact that Clause 25 of the contract
between the parties specifically provides that after finalization of the last bill, if a claim is
not made within 90 days no claim could be entertained. No Arbitrator pays attention to
this clause and all such claims are entertained and fantastic amounts are allowed under
these claims irrespective of the provisions of contract between the parties. It seems that
the only intention of the contractor to make these kinds of claims is to take benefit of
DDA officials' tacit consent and the Arbitrator's latitude and to have unjust enrichment at
the cost of public exchequer.
15. The Arbitrator under no circumstances could have ignored Clause 25 of
the contract which reads as under:
Clause 25. x x x x x x x x x
It is also a term of the contract that if the contractor does not make any demand for arbitration in respect of any claim(s) in writing within 90 days of receiving the intimation form the Engineer-in- Charge that the Bill is ready for payment, the claim(s) of the contractor will be deemed to have been waived and absolutely barred and the Delhi Development Authority shall be discharged and released of all liabilities under the contract in respect of those claims.
16. The Arbitrator has to first ensure that the claim was raised by the claimant
in terms of this clause and conditions of it were satisfied. Unless the Arbitrator gives a
finding that the claim was within the scope of Clause 25, the Arbitrator cannot entertain
such claims. These kinds of claims smack of a kind of syndicate running in DDA
between the contractors and DDA officials, who seem to be benefitted largely from these
kinds of arbitration where the contractors are awarded amounts which are a substantial
part of the contract value after the contract is over and the contractor had already taken
the payment of contract value. I find that no reason is given by the Arbitrator while
allowing claim no.8 as to how this claim fall within the scope of Clause 25. The learned
Arbitrator has not even addressed this issue and has awarded amounts towards loss of
productivity and under-utilization of equipment and T&P on the basis he had assessed
and computed loss of productivity, overheads and T&P. No basis of his computation has
been given. I consider that this claim is not tenable and is liable to be disallowed.
Objections regarding Additional Claim No.1
17. This claim was made for Rs.2,98,256/- and a sum of Rs.1,36,362/- was
allowed by the learned Arbitrator as interest for withholding the different amounts by
respondent/DDA out of running bills. The claimant is stated to have served notices
dated 30.9.77, 8.12.77m 17.9.80 and 10.2.81 demanding interest on withheld amounts.
Thus, the cause of action for claiming this interest on alleged withheld amounts could
have survived only for three years from the date of notice. The claim itself was made
before the learned Arbitrator after expiry of period of limitation. The Arbitrator did not
consider, if any of the claims raised before him was barred by limitation or not. He
entertained every claim irrespective of fact when the claim was made, whether the claim
was within the contract or it was outside the contract, whether it was barred by limitation
or not and allowed the claims. Since, these claims were barred by limitation these could
not have been entertained. I set aside the award passed by the learned Arbitrator under
Additional Claim no.1.
Objections regarding Additional Claims No. 2 & 4
18. Under Additional Claims No. 2 & 4 the learned Arbitrator had allowed
interest to the claimant @ 15% p.a. on different claims from 14.8.1985 onwards and
pendent lite and future reckoned from the date of the Award till the date of payment.
The claimant would be entitled to this interest on the surviving claims for a period as
allowed by the Arbitrator.
19. In view of above the award in respect of claims no. 1 & 3 is upheld the
award in respect of Claims No. 2, 4, 5, 6, 7, 8 & Additional Claim no. 1 are set aside.
The award in respect of Claims No. 1 & 3 and interest thereon @ 15% p.a. from the date
of arbitration till realization of the amount is made a rule of the Court.
With this, the suit and the objections stand disposed of.
August 25, 2009 SHIV NARAYAN DHINGRA, J. vn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!