Citation : 2009 Latest Caselaw 3289 Del
Judgement Date : 21 August, 2009
* HIGH COURT OF DELHI AT NEW DELHI
+ OMP No.116/2006
Judgment delivered on: August 21, 2009
# RITES LIMITED ..... Petitioner
! Through : Mr. Anil Airi, Advocate
Ms. Sadhna Sharma, Advocate
Versus
$ RAMJEE POWER CONSTRUCTION LIMITED
.....Respondent
^ Through : Mr. Raman Kapur, Advocate
Ms. Nidhi Jain, Advocate
%
CORAM:
HON'BLE MS. JUSTICE ARUNA SURESH
(1) Whether reporters of local paper may be
allowed to see the judgment?
(2) To be referred to the reporter or not? Yes
(3) Whether the judgment should be reported
in the Digest ? Yes
JUDGMENT
ARUNA SURESH, J.
OMP No.116/2006 & IA No. 4585/2006 (objections)
1. This is a petition filed under Section 9 of the
Arbitration and Conciliation Act, 1996 (hereinafter
referred to as Act).
2. Petitioner was awarded work of construction of 11
KV/Line/LT Line/D/S/S on 200 kg. working load
PSC Poles including supply of all related materials
on turnkey basis for electrification of 4923 villages.
Petitioner entered into an agreement with M/s.
Jharkhand State Electricity Board (JSEB) for the
execution of the said work. Petitioner thereafter
entered into a sub-contract with respondent
Ramjee Construction Ltd. on 25th September, 2004
for the execution of the work. As per the petition,
this sub-contract was entered with the consent of
the client i.e. JSEB. The said agreement entered
into between the parties contained an arbitration
clause which has been invoked by the parties as a
dispute has arisen between them within the
meaning of the contract. Petitioner came to know
that 27 bank guarantees furnished by the
respondent to the petitioner as original bank
guarantees were in fact not original but were
forged bank guarantees. Some of these bank
guarantees were towards mobilisation advance and
others by way of bank guarantee/security deposit.
As per the petition letters from the bank also
indicate that the bank guarantees which were in
the possession of the petitioner as supplied by the
respondent were not original bank guarantees. As
a matter of fact 22 out of 27 bank guarantees had
been cancelled by the bank upon request being
made by the respondent, whereas petitioner
remained under the impression that the original
bank guarantees were with it and could be invoked
whenever the necessity and exigency arose. This
conduct of the respondent indicated that it retained
the original bank guarantees with it and handed
over the forged copies to the petitioner, claiming
them to be the originals though they are nothing
but, worthless piece of papers. Since petitioner felt
that his rights under the contract were in jeopardy,
he has filed the present petition seeking interim
measures for protecting its rights under the
contract which, otherwise would have been
protected by the genuine bank guarantees.
3. Respondent contested this petition on various
grounds, contended inter alia, that the petition is
not maintainable as this court at Delhi has no
territorial jurisdiction to entertain the petition. The
pleadings in the petition do not disclose any cause
of action or the events which happened within the
territorial jurisdiction of Delhi. The memorandum
of understanding dated 15.4.2002 for participation
in tender invited by JSEB for rural electrification
work was executed in Ranchi and bears the stamp
of Ranchi treasury. This MoU was further amended
on 17.6.2005 which also bears the stamp of Ranchi
treasury. It is further averred that agreement was
entered into between the parties for rural
electrification work in the State of Jharkhand on
25.9.2004 which was signed and executed at
Ranchi by petitioner's Additional General Manager,
Electric, Ranchi bearing Ranchi's treasury stamp.
The said agreement is signed by witnesses at
Ranchi. It is further averred that work of rural
electrification was monitored by the petitioner's
office at Ranchi where it has its subordinate office
and the respondent is solely Ranchi based company
which does not reside or carry out business in
Delhi. The entire correspondence between the
parties was carried out from Ranchi and Gurgaon.
It is also averred that the bank guarantees were
also issued from Ranchi, the bills were submitted at
Ranchi, payments were made at Ranchi, the
materials were supplied and stored in Jharkhand
and the work was executed in Jharkhand.
Therefore, this Court has no jurisdiction to
entertain this petition.
4. Mr. Anil Airi, learned counsel for the petitioner, has
submitted that before the filing of this petition
petitioner had appointed arbitrator but it was
respondent who failed to do the needful and since
petitioner is having its office at Delhi, courts at
Delhi have jurisdiction to entertain the present
petition. It is also argued that as per article 11 of
the agreement dated 25.9.2004, executed between
the parties, any dispute arising out of the contract
is subject to the jurisdiction of court located at New
Delhi. It is emphasised that in view of this
agreement between the parties, this Court has the
jurisdiction to entertain the present petition.
5. Mr. Raman Kapur, learned counsel for the
respondent, has submitted that the agreement
between the petitioner and JSEB was executed at
Ranchi, the work of electrification was to be
carried out in the State of Jharkhand in different
districts, the respondent has its office and is
working for gain at Ranchi and petitioner has also
its subordinate office at Ranchi. The dispute if any
within the meaning of agreement has arisen in the
State of Jharkhand and by consent even if the
jurisdiction has been vested by the parties in this
Court, this Court has no jurisdiction because no
part of cause of action arose at Delhi for the filing
of the present petition. He has submitted that the
petition is liable to be rejected for want of
jurisdiction.
6. The petition came up for hearing before this Court
on 27.3.2006. On that day an ex-parte ad-interim
order was passed in favour of the petitioner as
regards prayer contained in paragraph 34 (b), (c)
and (d) of the petition which are as follows:
―(b) respondent is further liable to be restrained from selling, alienating, transferring all its moveable and immovable assets pending arbitration proceedings.
(c) bank accounts of the respondent bearing No. 131010200003360 with UTI Bank, DLF, Gurgaon and bank account with Bank of India, Clubside Branch, Main Road, Ranchi-834 001, Bank of Baroda, 715, Mahatma Gandhi Marg, Kataruka House, 1st Floor, Ranchi- 834 001 be attached.
(d) M/s Jharkhand State Electricity Board, Engineering Bhawan HEC Township, Dhurwa, Ranchi, Jharkhand, be directed to deposit all amounts held by them pertaining to the respondent in this Hon'ble Court.
7. Subsequently, an application was filed by the
respondent being IA No.5833/2006 seeking
clarification of order dated 27.3.2006 in view of the
interim orders granted in favour of the petitioner in
terms of para 34 (b), (c) and (d) of the petition.
This application was considered and disposed of by
this Court on 18.5.2006. It was made clear that the
interim order/protection granted to the petitioner
was in relation to the contract in question and not
pertaining to unconnected and unrelated works as
the OMP filed is under Section 9 of the Act which
can only refer to interim measures/protection in
relation to dispute in question.
8. The only issue to be considered by this Court is
whether this Court has the territorial jurisdiction to
entertain the present petition. As per Section 2(E)
of the Act, a Court means the principal Civil Court
of original jurisdiction in a State and includes the
High Court in exercise of its ordinary original
jurisdiction having jurisdiction to decide the
questions forming the subject matter of the
arbitration if the same had been the subject matter
of a suit. Section 42 of the Act speaks of
jurisdiction of a Court to entertain petition under
the Act. As per this section, where in an arbitration
agreement any application has been made in a
court, that court alone has the jurisdiction over the
arbitral proceedings and all subsequent
applications arising out of that agreement and the
arbitral proceedings have to be made in that court
and in no other court. Therefore, Section 20 of the
Civil Procedure Code (hereinafter referred to as
CPC) regulates the jurisdiction and consequent
proceedings of a Court under the Act. Section 20
CPC so far as is relevant for the purposes of this
petition reads as under:
―S. 20. Other suits to be instituted where defendants reside or cause of action arises.--Subject to the limitations aforesaid, every suit shall be instituted in a court within the local limits of whose jurisdiction--
(a)....
(b)....
(c) the cause of action, wholly or in part, arises.
Explanation.-- A corporation shall be deemed to carry on business at its sole or principal office in India or, in respect of any cause of action arising at any place where it has also a subordinate office, at such place.‖
9. ‗Cause of action' means the circumstances forming
the infraction of the right or the immediate
occasions for the action. In wider sense it means
the necessary conditions for the maintenance of the
suit, including not only the infraction of the right,
but the infraction coupled with the right itself.
Cause of action consists of bundle of facts which
give cause to enforce the legal injury for redress in
a court of law. It means every fact which if
traversed, would be necessary for the plaintiff to
prove in order to support his right to a judgment.
An application for appointment of an arbitrator in
matter of dispute arising out of breach of contract
is maintainable in Court where a part of cause of
action arises even though the contract between the
parties was executed outside the jurisdiction of the
Court. In suits on contract where two courts have
jurisdiction, choice of forum is with the plaintiff.
10. There are numerous decisions of the Supreme
Court wherein it has been specifically held that
where may be two or more competent Courts which
can entertain a suit consequent upon a part of the
cause of action having arisen therein, if the parties
to the contract agree to vest jurisdiction in one
Court to try the dispute which might arise as
between themselves such an agreement ousting the
jurisdiction of the other court is valid and binding
on the parties. However, parties by a consent
cannot confer jurisdiction by way of an agreement
on a Court which otherwise does not possess such
jurisdiction under the Act. Parties to arbitration
agreement, therefore by consent cannot confer
jurisdiction on a Court where no part of cause of
action accrued.
11. In A.B.C. Laminart (P) Ltd. v. A.P. Agencies -
MANU/SC/0001/1989, the Supreme Court
observed:
―21. From the foregoing decisions it can be reasonably deduced that where such an ouster clause occurs, it is pertinent to see whether there is ouster of jurisdiction of other courts. When the clause is clear, unambiguous and specific accepted notions of contract would bind the parties and unless the absence of ad idem can be shown, the other courts should avoid exercising jurisdiction. As regards construction of the ouster clause when words like ―alone, ―only‖, ―exclusive‖ and the like have been used there may be no difficulty. Even without such words in appropriate cases the maxim ―expressio unius est exclusio alterius‖
- expression of one is the exclusion of another - may be applied. What is an appropriate case shall depend on the facts of the case. In such a case mention of one thing may imply exclusion of another. When certain jurisdiction is specified in a contract an intention to exclude all others from its operation may in such cases be inferred. It has therefore to be properly construed.‖
12. In Harshad Chiman Lal Modi v. DLF Universal
& Anr. - (2005) 7 SCC 791, it was held that if a
particular Court does not have jurisdiction to deal
with the matter and no part of cause of action has
arisen within the jurisdiction of that court, the
parties of their own cannot vest jurisdiction in the
said Court. Therefore, a clause vesting jurisdiction
on a Court which otherwise does not have
jurisdiction to decide the matter would be void as
against the public policy.
13. Reference is also to made to S.B.P. & Co. v. Patel
Engineering Ltd. - (2005) 8 SCC 618, Patel
Roadways Limited Bombay v. M/s Prasad
Trading Company - (1991) 4 SCC 270, Oil &
Natural Gas Commission v. Utpal Kumar Basu
and others - (1994) 4 SCC 711, South East
Asia Shipping Co. Ltd. v. Nav Bharat
Enterprises Pvt. Ltd. - (1996) 3 SCC 443,
Escorts Ltd. v. M/s G.K. Automobile - 2006
DLT 127-559, Sri Ganesh Research Institute v.
Union of India an Ors - 2004-AD (Del) - 7-327,
Jitendra Nath Banerjee & Ors. v. Union of
India & Ors. - 2006-DLT-129-1.
14. Thus, it is clear that emphasis has been given to
the place where the cause of action has
substantially arisen. The principle of law
enunciated by the Supreme Court while
interpreting clause (c) of Section 20 of CPC has
been repeatedly followed by this Court in various
judgments.
15. The relevant articles of the agreement dated
25.9.2004 need consideration in the light of the
above said principles which govern the jurisdiction
of a Court to entertain this petition. It is not in
dispute that there is an arbitration article no.10
contained in the Schedule III, General Conditions of
Contract executed inter se the parties. Article 11
contained in the agreement dated 25.9.2004 read
as under:
―Jurisdiction of Court‖ Dispute arising out of the contract if any will be subject to the jurisdiction of court located at New Delhi.
16. Thus, by agreement parties conferred jurisdiction
on Delhi Court to entertain this petition. It is be
seen, if any part of cause of action arose in Delhi so
as to vest jurisdiction in this Court. Cause of action
is a prerequisite to confer jurisdiction in a Court to
ouster the jurisdiction of other Courts which may
also have jurisdiction to entertain the dispute inter
se the parties.
17. Agreement which is the subject matter of the
dispute dated 25.9.2004 admittedly was executed
at Ranchi. It was signed by the parties at Ranchi
and was witnessed at Ranchi only. The work to be
executed by the respondent by virtue of this sub-
contract was electrification of villages in the State
of Jharkhand only. The agreement between the
petitioner and Jharkhand State Electricity Board
was also executed at Ranchi. It is pertinent that
the bank guarantees provided by the respondent to
the petitioner were also of various banks at Ranchi
only. Respondent is a company which has its roots
at Ranchi and has no office at Delhi whereas
petitioner has its subordinate office at Ranchi.
18. On 15.4.2002 the parties to the petition had
entered into MoU for participation in the tender
invited by JSEB at Ranchi. This memorandum of
understanding was amended on 17.6.2005 at
Ranchi. Petitioner had been monitoring the work
of rural electrification through Ranchi office. The
dispute inter se the parties arose at Ranchi only.
Therefore, no part of cause of action arose inter se
the parties at Delhi.
19. On the day when this petition was filed petitioner
also filed a petition being AA No.202/2006 under
Section 11 of the Act for appointment of an
arbitrator. Before the petitioner filed these two
petitions in this Court respondent had already filed
a petition under Section 11 of the Act in the High
Court of Jharkhand on 20.3.2006. In its petition
AA No.202/2006 petitioner did plead ―both the
parties have appointed their nominee (Mr. S.M.
Singla by petitioner and Mr. R.K. Sarkar by
respondents) and the said arbitrators so appointed
have failed to agree on a common name for the
third Arbitrator‖. Order dated 27.3.2006 of this
Court whereby interim protection was granted to
the petitioner also finds mention that arbitration
clause has already been invoked by the parties in
respect of the dispute which arose between them.
20. Arbitration Application No. AA No.9/2006 was filed
by the respondent, Ramjee Power Construction Ltd.
in the Ranchi High Court. Parties mutually agreed
to give the name of the umpire and sought short
adjournment. The relevant order dated 16.6.2006
in the said petition reads as follows:
―Heard the counsel for the parties at length.
After some arguments, both the counsels have finally agreed to give the name of a third person to act as umpire and for that purpose they jointly seek a short adjournment.
As jointly, agreed, put up this case under the same heading on 29 th June, 2006.‖
21. The question of jurisdiction also arose in the said
petition when respondent; RITES Ltd. pointed out
that it had filed a petition before this court under
Section 11 of the Act for appointment of arbitrator
which was still pending adjudication and had
alleged that Court at Delhi had the jurisdiction as
memorandum of understanding was not executed
at Ranchi though, stamp papers were purchased by
the respondent; RITES Ltd. (petitioner herein) at
Ranchi. Perusal of the order of the High Court of
Jharkhand indicate that Ramjee Power
Construction Ltd. in its rejoinder dated 4.7.2006
filed in the said Court had categorically stated that
respondent RITES Ltd. had admitted before the
Delhi High Court on affidavit that contract (memo
of understanding) was executed at Ranchi. The
relevant observations of M.Y. Eqbal, J. of the High
Court of Jharkhand in his order dated 13.7.2006
read as follows:
―9. It transpires from the record that petitioner appeared in Delhi High Court and took specific stand that no cause of action, either wholly or partly arose within the jurisdiction of the Delhi High Court. Although this fact was not denied by the respondent but in the counter affidavit filed in the instant case, it is stated in paragraph 7 that in C.M.No.12810/05 it was categorically admitted that no part of cause of action arose within the jurisdiction of Delhi High Court. The petitioner in the rejoinder dated 4.7.2006 has very categorically stated that respondents have admitted before the Delhi High Court on affidavit that the Contract
(M.O.U.) was executed at Ranchi.‖
22. Thus, it is clear that petitioner RITES Ltd. itself
disputed the jurisdiction of this Court in the writ
petition CWP(C)No.16350/2005. In the said reply
to CM No.12810/2005 petitioner herein specifically
pleaded that no cause of action or even a part of
cause of action had arisen in Delhi in the ten
contracts awarded by the respondent RITES Ltd. to
Ramjee Power Construction Ltd. for rural
electrification of villages in Jharkhand State. The
contracts were signed at Gurgaon and not in Delhi.
23. Respondent Ramjee Power Construction Ltd. had
filed the petition under Section 11 of the Act in the
Jharkhand High Court on 20.3.2006. The petitioner
RITES Ltd. was informed about filing of the said
petition and report was duly received and
acknowledged by the petitioner. Despite this
knowledge petitioner filed the arbitration
application no.202/2006 under Section 11 of the
Act and OMP No.116/2006 under Section 9 of the
Act in this Court on 25.3.2006. Ramjee Power
Construction Ltd. has also filed objections under
Section 42 of the Act challenging the territorial
jurisdiction of this Court. Since more than one
request had been made to the Chief Justice of
different High Courts, the Chief Justice or his
designate to whom the request has been made
under relevant sub sections (4), (5) and (6) of
Section 11 first, alone is competent to decide the
request petition. Consequently, the said Court
appointed third arbitrator or umpire with directions
to him to enter into reference and give his award
within a period of six months. It is pertinent that
petitioner agreed to give name of the third person
to act as third arbitrator or umpire.
24. Undisputedly, the arbitrator has entered into
reference and the parties have filed their claims
and counter claims. Fate of the arbitration
proceedings is not known despite the fact that
petitioner took time to file certain documents
received by him from Jharkhand High Court and
were relevant for the proper adjudication of this
petition by this Court. No such documents were
placed on record. It is pertinent that the said order
of the Jharkhand High Court was challenged by the
petitioner in appeal. However, petitioner withdrew
the appeal with a view to file an application before
the Jharkhand High Court for modification/
clarification of the order dated 13.7.2006.
25. Since no part of cause of action arose in favour of
the petitioner and against the respondent at Delhi,
this Court has no jurisdiction to entertain this
petition seeking interim relief under Section 9 of
the Act even if the parties by consent vested
jurisdiction in this Court to entertain a dispute
which arose within the meaning of the contract. In
the order dated 3.9.2007 it was observed that since
dispute in the present OMP is the same which has
been referred by Jharkhand High Court to the
arbitrator, present application on the face of it had
become infructuous.
26. In view of the aforesaid findings, since this Court
has no jurisdiction to entertain the present petition,
the same is hereby rejected.
27. The interim order dated 27.3.2006 stands vacated.
ARUNA SURESH (JUDGE) AUGUST 21, 2009 jk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!