Citation : 2009 Latest Caselaw 3131 Del
Judgement Date : 12 August, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: July 29, 2009
Date of Order: August 12, 2009
+ AA Nos.9/09 & 10/09
% 12.08.2009
M/S. RITMAY BUILDERS PVT. LTD. .... Petitioner
Through : Mr. Rajive Sawhney, Sr. Adv. with
Mr. Sanjay Bhatt & Mr. Abishek Kumar, Advs.
Versus
MR. PRATAP DUBE & ORS. .... Respondent
Through: Mr. Dhruv Mehta with Mr. Vijay Nair &
Mr. Rajat Joneja, Advs.
&
M/S. PROVIDENCE BUILDTECH PVT. LTD. .... Petitioner
Through : Mr. Rajive Sawhney, Sr. Adv. with
Mr. Sanjay Bhatt & Mr. Abishek Kumar, Advs.
Versus
MR. PRATAP DUBE & ORS. .... Respondent
Through: Mr. Dhruv Mehta with Mr. Vijay Nair &
Mr. Rajat Joneja, Advs.
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the
judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
1. The above applications are made by the petitioner for appointment of
an Arbitrator. The petitioner has relied upon the agreement dated 28 th
November, 2007 entered into between the parties which contains an
Arbitration Clause and provides that in case of dispute or controversy arising
from the agreement, the parties shall take recourse to arbitration under
Indian Arbitration Act as applicable at the time of filing of Arbitration
Applications. The contention of respondent is that this agreement dated 28 th
November, 2007 was obtained by fraud and the parties had already settled
all their disputes and the petitioner had given „No Due Certificate‟ dated 30th
May, 2007 to the respondent discharging respondent from all liabilities.
2. The brief facts relevant for purpose of deciding this petition are that
the parties initially entered into an MOU dated 19th December, 2006. Under
this MOU a Special Purpose Vehicle/Joint Venture Company was formed for
buying, selling and developing agricultural land. This MOU was between the
same parties. The MOU also contained an arbitration clause. Under the MOU,
the respondent who was to contribute money but in lieu of his share had
undertaken to provide expert service and obtain change of land user for the
company; gave security of his property namely 8, Golf Links, New Delhi. It
was provided in the MOU that the amount due under MOU shall be the first
charge over this property for recovery of all payments made as loan and
interest thereon in case of failure of the respondent to obtain CLU (change of
land user) for the agricultural land in question. Thereafter, another MOU
dated 30th May, 2007 was signed between the parties wherein it was
recorded that due to change in certain conditions and circumstances which
enabled the execution of MOU dated 19th December, 2006, the parties have
mutually agreed to vary the terms and condition of the MOU. In this MOU it
was stated that all the sums paid by second party (petitioner) in the form of
loan, advance, interest to the third party shall be treated as having been
adjusted against the services and expertise provided by the third party to the
second party in the business and nothing remained due. In pursuance of this
MOU a „No Due Certificate‟ was also issued.
3. Agreement dated 28.11.2007 relied upon by the petitioner is stated to
have been executed by the respondent after this second MOU. The
contention of petitioner is that the second MOU did not discharge respondent
from his liability under the MOU dated 19.12.2006, moreover it was obtained
by the petitioner by playing fraud and misrepresentation. The MOU dated
30.5.2007 and letters of „No Due Certificate‟ were liable to be set aside and
declared void because of the misrepresentation and falsehood. It is stated
that immediately when the petitioner learnt about this misrepresentation, the
petitioner contacted the respondent and the respondent agreed to fulfill the
following terms and conditions:
"To immediately send his letter of resignation as a director of PBPL and transfer the shares and his rights to the shares of PBPL to the Petitioner's directors and at par.
To refund Rs.15 crores in a maximum of three installments to PBPL and that he would accordingly give fresh cheques to PBPL for the same in lieu of three earlier cheques of Rs.5 crores each that he had given in favour of the petitioner but on the account and for the benefit of MIPL. He was allowed some time before encashing these cheques. The said time period was to be discussed further and finalized.
That the Respondent no. 1 would complete the acquisition of the NOIDA land from the Society and in the name of PBPL and not in the name of Respondent no. 2 as had been initially proposed.
That on his arranging and completing the purchase by PBPL of the above Noida land, the Respondent no. 1 would then refund a further Rs.3.87 crores only and within an agreed time period, and
That if the Respondent No. 1 failed to secure and complete the purchase of the Noida land for PBPL within a
time period to be agreed, he would then refund the entire Rs.14.87 crores to PBPL also and in addition to the Rs.15 crores for which he was to give Post Dated Cheques."
4. Petitioner submitted that subsequently an exit agreement was
executed between the parties on 28th November, 2007 which contained an
arbitration clause and which has been invoked by the petitioner for
settlement of pending disputes between the parties.
5. The contention of respondent is that the talks of settlement were going
on between the parties. The agreement dated 28th November, 2007 was
prepared but was not signed by the parties. Since the respondent was to
leave for abroad, he signed the agreement and left it with his Chartered
Accountant Mr. TAS Mani and gave instructions that it should be given to the
petitioner only when instructed to do so. The respondent came back from
abroad and enquired from his Chartered Accountant, Mr. TAS Mani, who told
him that the agreement was still lying with him. Thereafter, one day the
petitioner sent one of his representatives to Mr. TAS Mani who mislead Mr.
Mani that the parties have arrived at a settlement and some changes were to
be made in the agreement. On the basis of this misrepresentation, the
agreement was obtained from Mr. TAS Mani and the respondent put his
signatures on it. The agreement dated 28.11.2007 was thus obtained by
fraud. It is also submitted by the respondent that in view of the MOU dated
30th May, 2007 signed between the parties, 5 lakh shares held by nominees
of petitioner were liable to be transferred to the respondent no. 1 or its
nominees and the petitioner was illegally holding all the said 5 lakh shares.
The dispute regarding transfer of shares was taken to Company Law Board.
The petitioner did not disclose to the Company Law Board about the
existence of the Arbitration Agreement between the parties nor moved an
application before the Company Law Board under Section 8 of Arbitration and
Conciliation Act alleging the existence of Arbitration Agreement. It is only
when the respondent filed a suit being CS(OS) No.938/08 before this Court
seeking a declaration regarding notice issued by the petitioner, claiming
himself to be director and shareholder of respondent‟s company, to be bad in
law along with other reliefs, the petitioner moved application under Section
11(5) of the Arbitration and Conciliation Act. The stand taken by the
petitioner regarding facts in that suit and stand taken by the petitioner in the
present application also did not match.
6. It is argued by counsel for the respondent that since the respondent
had assailed the existence of the Arbitration Agreement, this Court should not
entertain this application under Section 11(5) of the Arbitration and
Conciliation Act and should not appoint the Arbitrator. On the other hand, it
is stated by counsel for the petitioner that the respondent‟s stand that the
MOU dated 28th November, 2007 was obtained by fraud, is a false stand. The
signatures on the MOU have not been denied by respondent. The witness to
the MOU was Mr. TAS Mani, the Chartered Accountant of the respondent. The
respondent cannot take a stand that the agreement was obtained by fraud.
The agreement also contained signatures of parties on those portions of the
MOU, which were scored off. Thus, there can be no doubt that there was an
Arbitration Agreement between the parties and the dispute was required to
be settled through arbitration.
7. In SBP & Company vs. M/s. Patel Engineering Ltd. AIR 2006 SC
450, the Supreme Court observed that at the stage of appointment of
Arbitrator the satisfaction required is merely of a prima facie nature and the
Chief Justice does not decide lis nor contentious issues between the parties.
Section 11 neither contemplates detailed inquiry nor trial nor a finding on
controversial or contested matters. In the present case, the Court has
therefore to see whether prima facie there was an Arbitration Agreement
between the parties and whether there was a dispute between the parties
under the agreement containing arbitration clause which required reference
to the arbitrator. The perusal of material placed by both the parties on
record show that the parties entered into an MOU dated 19.12.2006 initially
for procuring agricultural land for the purpose of development and the
respondent had agreed to Mortgage his property No. 8, Golf Links, New Delhi
since the respondent was not contributing the amount required to the joint
venture. The property was mortgaged for security of payment of dues by the
respondent. After this MOU dated of 19th December, 2006, a collaboration
agreement was entered into between the parties on 3rd February, 2007. In
the collaboration agreement, it was recorded that the respondent had
handed over the actual physical possession of the property bearing no. 8,
Golf Links, New Delhi to the developer. The developer in this case was the
petitioner. This agreement was entered into to ensure the refund of huge
amounts involved in the MOU dated 19.12.2006 payable by the respondent.
Thereafter, came MOU dated 30th May, 2007 which again gave detailed terms
and conditions and it was recorded that the petitioner has issued „No Due
Certificate‟ to the respondent for the amount given/paid by the petitioner.
The amount payable by the respondent was to be treated as
service/expertise charges of the respondent. Consequently, letters were also
written. The petitioner has alleged that this agreement dated 30th May, 2007
was obtained through falsehood and by playing upon the emotions of the
petitioner and making false representation. However, the fact remains that
the transaction between the parties continued and this fact is clear from the
subsequent correspondence between the parties and subsequent payments
exchanged between the parties. Then, came the third MOU dated 28th
November, 2007 which the respondent alleges was obtained by
misrepresentation from his Chartered Accountant. It is admitted fact that
respondent filed a suit against the petitioner in respect of the disputes which
arose between the parties because of the transactions which took place in
furtherance to MOU of December, 2006 and continued even after MOU dated
28.11.2007. This Court cannot hold trial whether the MOU dated 28 th
November, 2007 was kept by the respondent duly signed by himself and his
Chartered Accountant only for a future date. The very fact that this MOU was
prepared and was signed by the respondent and his Chartered Accountant, to
be signed by the petitioner at a future date, shows that the transaction
between the parties which started on 19th December, 2006 was not yet over
and the contractual relationship between the parties was continuing and the
contract was continuing. It is for this reason that MOU dated 28th November,
2007 provided a mechanism for settlement of disputes between the parties
through arbitration. Prima facie, there exists an Arbitration Agreement
between the parties executed in writing and duly signed by both the parties.
Whether this agreement was signed voluntarily by the respondent or it was
obtained by misrepresentation from the Chartered Accountant of the
respondent is a matter of trial and at this stage the Court cannot go into this
issue and only the Arbitrator can decide this during the arbitration
proceedings on the basis of evidence. I, therefore, consider that prima facie
there exists an Arbitration Agreement between the parties and the disputes
between the parties have to be decided through the arbitration. The
existence of a dispute between the parties is not an issue. The respondent
has filed a suit against the petitioner seeking certain declarations and other
reliefs. The petitioner also has specified disputes in this application which
arise out of the MOU. I, therefore, consider that this application under
Section 11 made by the petitioner has to be allowed. I therefore allow these
applications.
8. Sh. G.P. Thareja, Retd. Additional District Judge is appointed as an
Arbitrator to adjudicate disputes between the parties. The parties shall
appear before Sh. G.P.Thareja, Retd. Additional District Judge on 3rd
September, 2009.
9. Copy of this order be sent to Sh. G.P. Thareja, Retd. Additional District
Judge. Sh. Thareja shall fix his own fee taking into account the labour
involved in the matter.
August 12, 2009 SHIV NARAYAN DHINGRA J. ak
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!