Citation : 2009 Latest Caselaw 3109 Del
Judgement Date : 11 August, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No.573/2008
% Date of decision: 11th August, 2009
The Union of India & Anr. ....Petitioners
Through: Mr. Ambar Qamaruddin, Advocate
Versus
M/s. Raj Construction Company .... Respondent
Through: Ms. Deepika Jain, Advocate
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may No
be allowed to see the judgment?
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported No
in the Digest?
RAJIV SAHAI ENDLAW, J.
1 The petitioner Union of India has preferred this petition under
Section 34 of the Arbitration Act, 1996 with respect to the arbitral
award dated 5th July, 2008. Notice of the petition was issued and
reply has been filed by the respondent. Though the arbitral award
has not been requisitioned and is not before this court but the
counsel for the petitioner has submitted that the arbitral record is
not necessary for adjudication of this petition and the points urged in
this petition are limited and the petition can be taken up for hearing.
The counsels for the parties have been heard.
2 The respondent was awarded the work for construction of
Model Station Building at Ambala Cantt. vide letter dated 17th
October, 2001 of the petitioner; the value of the contract was
Rs.21,36,103/- and the work was required to be completed by 16th
April, 2002. A formal contract was executed on 9th January, 2002.
The admitted position is that only 50% of the site was provided by
the petitioner to the respondent on 15th January, 2002. Upon the
respondent digging the earth for foundation pits, sub soil water
starting oozing and accumulated in the pits. The Engineer Incharge
of the petitioner could not suggest any solution and first an attempt
was made to bail out the water which had accumulated but the sub
soil water continued oozing out. The petitioner then approached
experts at Regional Engineering College, Kurukshetra who
suggested pile foundation design to be opted in lieu of the design
earlier opted by the petitioner. The petitioner then floated two
separate pile foundation contracts which also came to be allotted to
the respondent. The work of pile foundation under the subsequent
contracts could be completed only on 15th November, 2002 and
during which period the work under the original contract aforesaid
remained suspended.
3 After the petitioner had made payments to the respondent
under the original contract also and had refunded the security
deposit of the respondent, the respondent made the claims on
account of prolongation of work under the original contract, owing to
increase in rates of material, labour, steel etc. in the interregnum
and which delay the respondent claimed was not attributable to it.
Upon the petitioner not accepting the said claims and also not
appointing the arbitrator as demanded by the respondent, the
respondent filed an Arbitration Application No.308/2005 in this court
under Section 11(6) of the Act and which came to be allowed on 4th
May, 2006 and a retired Judge of this court appointed as the
arbitrator.
4 The respondent had made a claim of Rs.29,33,967/-. The
arbitrator,
(i) negated the plea of the petitioner of applicability Section
80 of the CPC holding the same to be not applicable to
arbitration;
(ii) also negated the plea of the petitioner of the respondent
being not entitled to prefer the claim for the reason of
having received the payments under the contract in full
and final settlement and having given a no claim
certificate - the arbitrator held that the question whether
the no claim certificate was signed voluntarily or not was
arbitrable as held in Union of India Vs. L.K. Ahuja and
Company AIR 1988 Supreme Court 1172; found that the
no claim certificate in this case was on a printed form
required to be submitted for receiving the final payment;
that it was signed mechanically and in fact contained
several blanks; that the petitioner had admitted that as
per its practice before final bill for payment is processed,
the contractor is required to sign the said certificates.
The arbitrator thus inter alia held that no claim
certificate in the present case to have been not signed
voluntarily and held the respondent entitled to maintain
the claim;
(iii) negated the plea of the petitioner of the respondent
being not entitled to the claim for the reason of allied
contracts of pile foundation having also been awarded to
it; the arbitrator held that those contracts were separate
from the contract whereunder the claim had been made;
(iv) held that the petitioner has extended the time under the
original contract without imposing any condition that the
respondent would not be entitled for losses he may suffer
on account of escalation;
(v) held that the delay was attributable to the petitioner in
the circumstances aforesaid and the respondent was not
required to test for the sub soil water before accepting
the contract and the same was to be done by the
petitioner;
(vi) applied the Hudson's Formula for calculating the losses
suffered by the respondent owing to the delay;
(vii) negated the plea of the petitioner of the respondent
being required to prove actual loss, on the basis of the
dicta of the Supreme Court in McDermott
International Inc. Vs. Burn Standard Co. Ltd. 2006
(11) SCC 181 and the provisions of Sections 55 and 73 of
the Contract Act;
(viii) Applying the said formula the arbitrator found the
entitlement of the respondent to damages in the sum of
Rs.10,26,975/- only;
(ix) besides the aforesaid award, the arbitrator also allowed
Rs.60,000/- in lump sum to the respondent for pumping
out the water which had accumulated.
All the other claims of the respondent were disallowed. The
arbitrator has also awarded interest to the respondent at 12% per
annum from the date of the award till realization, besides costs of
arbitration of Rs.4.50 lacs.
5 The counsel for the petitioner/objector has raised only two
contentions. Firstly it is contended that the award upholding the
claims inspite of the no claim certificate is contrary to contract.
Secondly, the applicability of the Hudson's Formula is controverted.
It is urged that the respondent had in its pleadings not made the
claim on the basis of said formula and thus the arbitrator was not
entitled to invoke the same in the award.
6 Per contra the counsel for the respondent has contended that
the petitioner having not disputed its liability for damages, cannot
object on the ground of applicability of the Hudson's Formula by the
arbitrator in the award; it is argued that the arbitrator had to apply
some basis for assessing damages, once liability had been
determined and is not disputed in this court also. It is further the
contention that this court is not exercising the appellate jurisdiction
and cannot interfere with the formula applied by the arbitrator. It is
also urged that the respondent had in its written submissions before
the arbitrator relied on the Hudson's Formula and in fact the
petitioner had during the hearing before the arbitrator agreed to the
same since the damages assessed thereunder were less than the
damages claimed by the respondent. It is also argued that the
arbitration being of a retired Judge of this court the petitioner ought
not to be permitted to indulge in such dilatory tactics.
7 As far as the first submission of the petitioner regarding no
claim certificate is concerned, the Supreme Court recently in
National Insurance Co. Ltd. Vs. Boghara Polyfab Pvt. Ltd. AIR
2009 Supreme Court 170 has reiterated that the said dispute is
arbitrable and that if the party who has executed the discharge
agreement or discharge voucher establishes that the same was
executed on account of fraud, coercion, undue influence practiced by
the other party, the same is not binding on that party and does not
come in the way of that party making a claim.
8 In the present case the arbitrator has returned a finding of fact
that the "no claim certificate" was executed by the respondent to be
able to receive the payments which according to the petitioner were
admittedly due to the respondent and which would not have been
released by the petitioner to the respondent without signing such
certificate. This finding of fact by the arbitrator is non-interferable
under Section 34 of the Act and specially when as in this case it is
based on cogent reasoning. The counsel for the respondent has in
this regard relied upon R.S. Gupta Vs. Executive Engineer, DDA
2001 (Suppl.) Arb. LR 10 (Delhi), M/s. Hindustan Tea Co. Vs. M/s.
K.Sashikant & Co. AIR 1987 Supreme Court 81, MCD Vs. M/s.
Jagan Nath Ashok Kumar AIR 1987 Supreme Court 2316 and Puri
Construction Pvt. Ltd. Vs. Union of India AIR 1989 Supreme
Court 777.
9 As far as the other contention of the petitioner is concerned,
there also I find the award to have correctly relied upon McDermott
International Inc. (Supra). The arbitral award in that case upheld
by the Supreme Court held that once it was established that the
party was entitled to an amount on account of increased overhead
and loss of profit and additional project management cost, the
construction law recognizes that construction contractor incurs two
general jobs of costs in the course of its operation; i.e. the operating
costs that are attributable to a particular project and costs such as
overhead that are expended for the performance of the business as a
whole including the particular project. It was further the award in
that case that construction law recognizes that owner caused delay
entitled the contractor to recover from the owner the increase in
overhead and loss of profit as part of damages. Reference therein
was also made to the various formulas in that regard including the
Hudson's Formula. The Supreme Court relying upon M.N.
Gangappa Vs. Atmakur Nagabhushanam Setty and Co. Manu /
SC/0019/ 1972 held that the method used for computation of
damages will depend upon the facts and circumstances of each case.
The Supreme Court further held that the court could not interfere in
the formula applied by the arbitrator and held the award to be not
contrary to the Indian law for this reason.
10 In the present case also though the petitioner has contended
that the arbitrator ought not to have applied the Hudson's Formula,
nothing has been placed before the court to show that if instead of
the said formula any other accepted formula, as noticed by the
Supreme Court in McDermott International Inc. (Supra) had been
applied, the liability of the petitioner would have been less. In the
absence of any averment to the said effect, no ground is found to
interfere in the award on this ground also. The plea that the
Hudson's Formula was not pleaded also has no merit in the absence
of an averment that it was the case of the petitioner before the
arbitrator that some other formula should be applied.
11 No ground under Section 34 having been made out, the
petition is dismissed. However since the petitioner has cooperated
in early disposal of the petition, no order as to costs.
RAJIV SAHAI ENDLAW (JUDGE)
August 11th, 2009 J
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!