Citation : 2008 Latest Caselaw 1904 Del
Judgement Date : 24 October, 2008
Reportable
* HIGH COURT OF DELHI AT NEW DELHI
+ OMP No.206/2007
Date of decision : October 24, 2008
# NBCC ..... Petitioner
! Through : Mr. Saket Sikri, Advocate
Versus
$ M/S. MOBILE KRAFT .....Respondent
^ Through : Mr. B.K.Dewan, Advocate with
Mr. Bhavesh Kumar, Advocate.
%
CORAM:
HON'BLE MS. JUSTICE ARUNA SURESH
(1) Whether reporters of local paper may be
allowed to see the judgment?
(2) To be referred to the reporter or not? Yes
(3) Whether the judgment should be reported
in the Digest ? Yes
JUDGMENT
ARUNA SURESH, J.
1. This objection petition has been filed by the
Petitioner challenging arbitral award dated 6th July,
2006 passed by Retired Justice Ramamoorthy
whereby while awarding the claim to the
respondent, the arbitrator was also pleased to
award interest @ 15% per annum from 30.03.1998
till the date of payment.
2. Petitioner; erstwhile Bharat Heavy Electricals Ltd.
had awarded work to the claimant respondent M/s.
Mobile Craft for furniture and furnishing works of
hotel block of BHEL, HRDI & ESI Complex at Noida
on 10.07.1995. After completion of work in
October, 1995 respondent submitted its final bill on
30.03.1996 for Rs.36,98,764.19, out of which
respondent was paid a sum of Rs.20,98,000/- and
the balance amount of Rs.16,00,764/- was not paid.
Hence, the respondent invoked arbitration clause
and by the order of this court, Justice
Ramamoorthy was appointed as an arbitrator to
adjudicate upon the disputes inter se the parties.
Claim of the respondent as regards issues Nos. 1 to
4 was allowed whereas the other claims were
rejected. The arbitrator was pleased to award
interest @ 15% per annum on the sum of
Rs.3,58,734.41/- from 30.03.1998 till the date of
payment and also fixed the cost of proceedings at
Rs.35,000/-.
3. When Petitioner failed to make the due payment,
Execution Petition No.265/2006 was filed by the
respondent/decree holder for recovery of
Rs.8,88,900/- inclusive of interest. On receipt of
notice of the Execution Petition, Petitioner paid
principal awarded amount of Rs.3,50,683.41/- to
the respondent by way of Account Payee cheque
dated 21.02.2007 after deduction of TDS of
Rs.8,051/- as per the statutory rules. Therefore, the
principal amount as awarded stood paid to the
decree holder/respondent.
4. The award has been challenged by the petitioner
only to the extent of interest and cost awarded by
the arbitrator to the decree holder/respondent.
5. It is submitted by the learned counsel for the
Petitioner that the interest awarded by the
arbitrator is exorbitant and highly onerous on the
petitioner which is a Government of India
Enterprise and the award of interest is baseless
and without any merit. It is further submitted that
the arbitrator did not consider the fact while
awarding interest that the rate of interest has
dropped down and the high rate of interest as
awarded is inconsistent with the prevalent rate of
interest in the banking industry and other financial
institutions as per the law of the land. It is also
submitted that the interest cannot be taken as a
compensation for delayed payment and cannot be
treated as a punitive measure for the judgment
debtor especially when no evidence was adduced
by the claimant which could justify grant of such
high rate of interest.
6. It is further submitted that under the
circumstances, the arbitrator acted arbitrarily in
awarding cost assessed to Rs.35,000/- to the
claimant.
7. Learned counsel for the respondent argued that the
respondent/ decree holder claimed interest @ 18%
per annum but the arbitrator only awarded interest
@ 15% per annum on the awarded amount which
was quite reasonable and therefore cannot be
considered as arbitrary and contrary to the
principles of equity, justice and good conscious. It
is also emphasized that the cost followed the suit
and the arbitrator awarded reasonable cost to the
decree holder and no reason has been assigned in
the objection petition as to why cost should be
waived.
8. The arbitrator while considering the claim of the
decree holder for interest @ 18% per annum as per
the provisions of the Arbitration and Conciliation
Act, 1996 observed:-
"The Claimant is now making a claim of interest @ 18% per annum as per the provisions of the Arbitration and Conciliation Act, 1996. In view of the market conditions and taking into account the attitude of the Respondent in not paying the amount in spite of the claimant accepting the revised bill, I fix the interest @ 15% per annum from 30.3.1998 on the sum of Rs.3,58,734.41 till the date of payment."
9. Section 31 (7) (b) of the Arbitration and
Conciliation Act, 1996 (in short „Act‟) empowers the
arbitrator to award interest on the amount directed
to be paid by an arbitral award and this rate of
interest can be 18% per annum from the date of the
award to the date of payment. In the case in hand,
the arbitrator after considering the facts and
circumstances of the case was pleased to award
interest @ 15% per annum on the principal amount
w.e.f. 30.03.1998 and not from the date of the
award i.e. 6.7.2006.
10. The learned arbitrator however has not justified as
to on what basis he awarded interest @ 15% per
annum to the claimant. Under the circumstances,
this court is within its rights to consider if the
interest awarded to the claimant was in the right
perspective or it needed modification. The learned
arbitrator had to exercise his powers to award
interest in a reasonable manner keeping in view
the rate of interest that was prevailing during the
period for which the same was being awarded. It is
a common knowledge that the rate of interest on
term deposits have been fluctuating for the last
about more than one decade between 6% to 8%.
The fluctuating rate did range upto 10% or so since
the year 1987 but again this rate of interest came
down from 6% to 8% after about few years. Similar
situation arose before the Division Bench of this
court in „Delhi Development Authority v. Anand
and Associates, 2008 (1) ARB LR 490 (Delhi)'
wherein it was observed:-
"7. Coming then to the question whether the arbitrator was legally right in awarding interest @ 18% per annum for a period of 17 years or so, the arbitrator has justified the same on the authority of Santok Singh Arora v. Union of India and Ors. MANU/SC/0343/1992. There can be no quarrel with the proposition stated in the said decision which recognises the right of a claimant to be compensated for denial of its legitimate dues during the period the claim remained under adjudication. Having said that, we are of the opinion that the rate of interest awarded by the arbitrator appears to be excessive. As noticed earlier, the arbitrator has directed payment of interest @ 18% per annum from 25/4/87 subject to the condition that in case the award amount is paid with interest and cost within a period of two months from the date of award, the DDA would pay interest @ 12% per annum only for the entire period. Higher rate of interest thus awarded by the arbitrator appears to us to be in terrorem only to ensure that DDA pays as quickly as possible the amount held payable. The alternative rate at which the arbitrator stipulated in the event of payment is indeed more realistic though still on the higher side. In the
circumstances, therefore, we are inclined to interfere with the award made by the arbitrator but only to that limited extent. While the power of the arbitrator to award interest is not under challenge before us the said power has to be exercised in a reasonable manner keeping in view the rate of interest that was prevailing during the period for which the same is being awarded. It is common knowledge that the rate of interest on term deposits has for the last decade fluctuated between 6 to 8 per cent. It is true that for the period of a decade after April, 1987 the rate of such deposit ranged up to 10% or so, yet keeping the totality of the facts and circumstances of the case in view and especially the long period for which the interest is being awarded, we are of the opinion that interest @ 9% per annum instead of 18% per annum from 25/4/87 till date of deposit of the amount in this Court on the principal amount of Rs. 20,32,358/- would meet the ends of justice. We may in this regard draw support from the decision of the Hon'ble Supreme Court in State of Rajasthan and Anr. v. Nav Bharat Construction Co. MANU/SC/0747/ 2001, where the Hon'ble Supreme Court had, in similar circumstances, reduced the rate of interest from 18% per annum to 6% per annum".
11. In this case, this court modified the rate of interest
awarded @ 18% per annum for pre-arbitration
period, for the pendent lite period and future
interest to 9% per annum.
12. Similarly, in 'Krishna Bhagya Jala Nigam Ltd. v.
G. Harischandra Reddy and Anr., AIR 2007 SC
817', the Supreme Court was pleased to reduced
rate of interest awarded by the arbitrator from 18%
to 9% and it was observed:-
"On the merits of the claims made by the contractor we find from the impugned Award dated 25.6.2000 that it contains several Heads. The Arbitrator has meticulously examined the claims of the contractor under each Page 0711 separate Heads. We do not see any reason to interfere except on the rates of interest and on the quantum awarded for letting machines of the contractor remaining idle for the periods mentioned in the Award. Here also we may add that we do not wish to interfere with the Award except to say that after economic reforms in our country the interest regime has changed and the rates have substantially reduced and, therefore, we are of the view that the interest awarded by the Arbitrator at 18% for the pre-arbitration period, for the pendent lite period and future interest be reduced to 9%."
13. In 'State of Rajasthan and Anr. V. Nav Bharat
Construction Co., AIR 2002 SC 258', the only
issue for consideration was whether the arbitrator
had awarded interest contrary to the conditions in
the agreement. In the said case, the arbitrator had
granted interest on the principal amount of
different claims from different dates at the rate of
18% and the district court had awarded interest @
15% from the date of the decree. That part of the
award and decree was modified and the rate of
interest was reduced from 15% to 6% only.
14. Similarly, this court in Delhi Development
Authority v. Harbans Singh and Sons, 2008 (3)
ARBLR 276 (Delhi)', in similar circumstances was
pleased to reduced rate of interest awarded by the
arbitrator from 12% to 8.25% per annum keeping
in mind the rate as was admissible for Fixed
Deposits and the interest was paid from the date of
award.
15. Mr. B.K. Dewan, learned counsel for the
respondent has referred to 'Union of India v.
Harbans Singh Tuli & Sons Builders (P) Ltd.,
2001 (1) Arb. LR 234 (Punjab & Haryana)', to
emphasise that the learned arbitrator has rightly
awarded interest @ 18% on the principal sum. He
has also referred to „M/s. Krishan Kumar
Madhok v. Union of India, AIR 1982 Delhi
332'. These two cases under the circumstances of
this case are of no help to the respondent.
16. Respondent has also referred to „Delhi Jal Board
v. Subhash Pipes Ltd., 2005 (2) Arb. LR 213
(Delhi)'. In the said case, the court upheld the
findings of the arbitrator in awarding interest @
18% per annum on the amount found due and
observed that the interest awarded to the claimant
in the said case was in accordance with the
statutory provisions of law.
17. Since there is no specific and serious challenge to
the cost as awarded by the learned arbitrator, I
find no reason to interfere in the quantum of cost
awarded by the arbitrator.
18. Under the facts and circumstances of the case and
keeping in mind the rate of interest which was
legally permissible at the relevant time, the
impugned award dated 6th July, 2006 is modified to
the extent that the judgment debtor/petitioner shall
pay interest @ 9% per annum on the principal
amount of Rs.3,58,734.41 for the period as
awarded. It is pertinent to mention here that the
principal amount has already been paid by the
Petitioner.
19. Petition stands allowed to the extent as stated
above. There are no orders as to costs.
ARUNA SURESH (JUDGE) OCTOBER 24, 2008 vk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!