Citation : 2026 Latest Caselaw 658 Chatt
Judgement Date : 17 March, 2026
1
2026:CGHC:12587
NAFR
HIGH COURT OF CHHATTISGARH AT BILASPUR
MAC No. 727 of 2026
The Executive Engineer CSPDCL, Kurud, Dhamtari, Dhamtari, Dist,
C.G. State
... Appellant
versus
Digitally
signed by
SHOAIB
SHOAIB ANWAR
ANWAR Date:
2026.03.18
10:32:41
+0530
1 - Smt. Sita Bai W/o Bhuvan Aged About 51 Years R/o Goshala
Chowk, Village And Post, Avari, Tah. Kurud, Dist. Dhamtari, C.G.
State
2 - Bhuvan Sukalu Aged About 47 Years R/o Goshala Chowk, Village
And Post, Avari, Tah. Kurud, Dist. Dhamtari, C.G. State
3 - M/s Maa Annapurna Rice Mill Purrena, Prop. Dilip Kumar Sinha
S/o Sri Ram Sinha, R/o Sihawa Road, In Front Of Vinayak Industries,
Ps And Tahsil Dhamtari, Dist. Dhamtari, C.G. State
4 - The Divisional Manager New India Insurance Co. Ltd, Paphadi
Chowk, Raipur, C.G State
... Respondent(s)
(Cause title taken from CIS)
For Appellant : Dr. Veena Nair, Advocate
Hon'ble Shri Bibhu Datta Guru, Judge
Order on Board 17/03/2026
1. Heard on I.A. No. 01/2026, an application filed under Section
30 of the Employees' Compensation Act for condonation of
delay in filing the present appeal. By the said application, the
appellant seeks condonation of delay of 122 days in preferring
the appeal.
2. Learned counsel for the appellant submits that the appellant
is aggrieved by the order dated 07.11.2025 passed in
Application No. 68/2025, whereby the modification sought for
was rejected, read with order dated 25.08.2025 passed in
Application No. 49/2025 by the learned Labour Court,
Dhamtari. It is submitted that while preferring the present
appeal challenging the aforesaid orders, a delay of 122 days
has occurred due to time consumed in collecting necessary
and relevant documents and also due to lack of proper
knowledge regarding the prescribed limitation period. It is
further submitted that the delay is neither intentional nor
deliberate, but bona fide and on account of sufficient cause.
3. It is further contended that the appellant has a good case on
merits and, if the delay is not condoned, the appellant shall
suffer irreparable loss and injury. Therefore, it is prayed that,
in the interest of justice, equity and fair play, the delay in filing
the appeal be condoned.
4. I have considered the submissions made by learned counsel
for the appellant and perused the application for condonation
of delay along with the material available on record.
5. Upon due consideration, this Court finds that the appellant
has sought condonation of delay of 122 days on the grounds
of delay in collecting documents and lack of knowledge of the
limitation period. This Court is of the considered opinion that
the reasons assigned by the appellant are vague and general
in nature and do not constitute "sufficient cause" within the
meaning of law. No cogent or satisfactory explanation, much
less a day-to-day explanation, has been furnished to justify
the inordinate delay. It is well settled that the law of limitation
is to be applied with all its rigour and cannot be relaxed in a
routine manner.
6. The Hon'ble Supreme Court in the matter of Postmaster
General and others v. Living Media India Limited and another,
(2012) 3 SCC 563, has dealt with the limitation issue and held
as under:-
"27. It is not in dispute that the person(s) concerned were well
aware or conversant with the issues involved including the
prescribed period of limitation for taking up the matter by
way of filing a special leave petition in this Court. They cannot
claim that they have a separate period of limitation when the
Department was possessed with competent persons familiar
with court proceedings. In the absence of plausible and
acceptable explanation, we are posing a question why the
delay is to be condoned mechanically merely because the
Government or a wing of the Government is a party
before us.
28. Though we are conscious of the fact that in a matter of
condonation of delay when there was no gross negligence or
deliberate inaction or lack of bonafide, a liberal concession
has to be adopted to advance substantial justice, we are of
the view that in the facts and circumstances, the Department
cannot take advantage of various earlier decisions. The
claim on account of impersonal machinery and inherited
bureaucratic methodology of making several notes
cannot be accepted in view of the modern technologies
being used and available. The law of limitation
undoubtedly binds everybody including the Government.
29. In our view, it is the right time to inform all the
government bodies, their agencies and instrumentalities that
unless they have reasonable and acceptable explanation for
the delay and there was bonafide effort, there is no need to
accept the usual explanation that the file was kept pending
for several months/years due to considerable degree of
procedural red-tape in the process. The government
departments are under a special obligation to ensure that
they perform their duties with diligence and commitment.
Condonation of delay is an exception and should not be used
as an anticipated benefit for government departments. The
law shelters everyone under the same light and should not be
swirled for the benefit of a few.
30. Considering the fact that there was no proper explanation
offered by the Department for the delay except mentioning of
various dates, according to us, the Department has miserably
failed to give any acceptable and cogent reasons sufficient to
condone such a huge delay. Accordingly, the appeals are
liable to be dismissed on the ground of delay."
7. Recently, a Division Bench of the Hon'ble Supreme Court in the
matter of State of Madhya Pradesh v. Ramkumar Choudhary,
2024 INSC 932, while considering the delay, issued some
directions and observed as follows:-
"5. The legal position is that where a case has been
presented in the Court beyond limitation, the petitioner
has to explain the Court as to what was the "sufficient
cause" which means an adequate and enough reason
which prevented him to approach the Court within
limitation. In Majji Sannemma v. Reddy Sridevi, 2021 SCC
Online SC 1260, it was held by this Court that even though
limitation may harshly affect the rights of a party, it has to
be applied with all its rigour when prescribed by statute. A
reference was also made to the decision of this Court in
Ajay Dabra v. Pyare Ram, 2023 SCC Online 92 wherein, it
was held as follows:
"13. This Court in the case of Basawaraj v. Special Land
Acquisition Officer [(2013) 14 SCC 81] while rejecting an
application for condonation of delay for lack of sufficient
cause has concluded in Paragraph 15 as follows:
"15. The law on the issue can be summarised to the effect
that where a case has been presented in the court beyond
limitation, the applicant has to explain the court as to
what was the "sufficient cause" which means an adequate
and enough reason which prevented him to approach the
court within limitation. In case a party is found to be
negligent, or for want of bona fide on his part in the facts
and circumstances of the case, or found to have not acted
diligently or remained inactive, there cannot be a justified
ground to condone the delay. No court could be justified
in condoning such an inordinate delay by imposing any
condition whatsoever. The application is to be decided only
within the parameters laid down by this Court in regard to
the condonation of delay. In case there was no sufficient
cause to prevent a litigant to approach the court on time
condoning the delay without any justification, putting any
condition whatsoever, amounts to passing an order in
violation of the statutory provisions and it tantamounts to
showing utter disregard to the legislature."
14. Therefore, we are of the considered opinion that the
High Court did not commit any mistake in dismissing the
delay condonation application of the present appellant."
Thus, it is crystal clear that the discretion to condone the
delay has to be exercised judiciously based on facts and
circumstances of each case and that, the expression
'sufficient cause' cannot be liberally interpreted, if
negligence, inaction or lack of bona fides is attributed to
the party.
5.1. In Union of India v. Jahangir Byramji Jeejeebhoy (D)
through his legal heir, 2024 INSC 262, wherein, one of us
(J.B.Pardiwala, J) was a member, after referring to various
decisions on the issue, it was in unequivocal terms
observed by this Court that delay should not be excused as
a matter of generosity and rendering substantial justice is
not to cause prejudice to the opposite party. The relevant
passage of the same is profitably extracted below:
"24. In the aforesaid circumstances, we made it very clear
that we are not going to look into the merits of the matter
as long as we are not convinced that sufficient cause has
been made out for condonation of such a long and
inordinate delay.
25. It hardly matters whether a litigant is a private party
or a State or Union of India when it comes to condoning
the gross delay of more than 12 years. If the litigant
chooses to approach the court long after the lapse of the
time prescribed under the relevant provisions of the law,
then he cannot turn around and say that no prejudice
would be caused to either side by the delay being
condoned. This litigation between the parties started
sometime in 1981. We are in 2024. Almost 43 years have
elapsed. However, till date the respondent has not been
able to reap the fruits of his decree. It would be a mockery
of justice if we condone the delay of 12 years and 158 days
and once again ask the respondent to undergo the
rigmarole of the legal proceedings.
26. The length of the delay is a relevant matter which the
court must take into consideration while considering
whether the delay should be condoned or not. From the
tenor of the approach of the appellants, it appears that
they want to fix their own period of limitation for
instituting the proceedings for which law has prescribed a
period of limitation. Once it is held that a party has lost
his right to have the matter considered on merits because
of his own inaction for a long, it cannot be presumed to be
non-deliberate delay and in such circumstances of the
case, he cannot be heard to plead that the substantial
justice deserves to be preferred as against the technical
considerations. While considering the plea for
condonation of delay, the court must not start with the
merits of the main matter. The court owes a duty to first
ascertain the bona fides of the explanation offered by the
party seeking condonation. It is only if the sufficient cause
assigned by the litigant and the opposition of the other
side is equally balanced that the court may bring into aid
the merits of the matter for the purpose of condoning the
delay.
27. We are of the view that the question of limitation is not
merely a technical consideration. The rules of limitation
are based on the principles of sound public policy and
principles of equity. We should not keep the 'Sword of
Damocles' hanging over the head of the respondent for
indefinite period of time to be determined at the whims
and fancies of the appellants.
xxx xxx xxx
34. In view of the aforesaid, we have reached to the
conclusion that the High Court committed no error much
less any error of law in passing the impugned order. Even
otherwise, the High Court was exercising its supervisory
jurisdiction under Article 227 of the Constitution of India.
35. In a plethora of decisions of this Court, it has been
said that delay should not be excused as a matter of
generosity. Rendering substantial justice is not to cause
prejudice to the opposite party. The appellants have failed
to prove that they were reasonably diligent in prosecuting
the matter and this vital test for condoning the delay is
not satisfied in this case.
36. For all the foregoing reasons, this appeal fails and is
hereby dismissed. There shall be no order as to costs."
Applying the above legal proposition to the facts of the
present case, we are of the opinion that the High Court
correctly refused to condone the delay and dismissed the
appeal by observing that such inordinate delay was not
explained satisfactorily, no sufficient cause was shown for
the same, and no plausible reason was put forth by the
State. Therefore, we are inclined to reject this petition at
the threshold.
6. At the same time, we cannot simply brush aside the
delay occurred in preferring the second appeal, due to
callous and lackadaisical attitude on the part of the
officials functioning in the State machinery. Though
the Government adopts systematic approach in
handling the legal issues and preferring the
petitions/applications/appeals well within the time,
due to the fault on the part of the officials in merely
communicating the information on time, huge revenue
loss will be caused to the Government exchequer. The
present case is one such case, wherein, enormous
delay of 1788 days occasioned in preferring the second
appeal due to the lapses on the part of the officials
functioning under the State, though valuable
Government lands were involved. Therefore, we direct
the State to streamline the machinery touching the
legal issues, offering legal opinion, filing of cases
before the Tribunal / Courts, etc., fix the responsibility
on the officer(s) concerned, and penalize the officer(s),
who is/are responsible for delay, deviation, lapses,
etc., if any, to the value of the loss caused to the
Government. Such direction will have to be followed by
all the States scrupulously.
7. There is one another aspect of the matter which we
must not ignore or overlook. Over a period of time, we
have noticed that whenever there is a plea for
condonation of delay be it at the instance of a private
litigant or State the delay is sought to be explained right
from the time, the limitation starts and if there is a delay
of say 2 years or 3 years or 4 years till the end of the
same. For example if the period of limitation is 90 days
then the party seeking condonation has to explain why it
was unable to institute the proceedings within that period
of limitation. What events occurred after the 91st day till
the last is of no consequence. The court is required to
consider what came in the way of the party that it was
unable to file it between the 1st day and the 90th day. It is
true that a party is entitled to wait until the last day of
limitation for filing an appeal. But when it allows the
limitation to expire and pleads sufficient cause for not
filing the appeal earlier, the sufficient cause must establish
that because of some event or circumstance arising before
the limitation expired it was not possible to file the appeal
within time. No event or circumstance arising after the
expiry of limitation can constitute such sufficient cause.
There may be events or circumstances subsequent to the
expiry of limitation which may further delay the filing of
the appeal. But that the limitation has been allowed to
expire without the appeal being filed must be traced to a
cause arising within the period of limitation. (See: Ajit
Singh Thakur Singh and Another v. State of Gujarat, AIR
1981 SC 733)."
8. Taking into account the facts and circumstances of the present
case, in the light of aforementioned judgments of the Hon'ble
Supreme Court in the matters of Postmaster General (supra)
and Ramkumar Choudhary (supra), it is evident that
Government departments are under a special obligation to
discharge their duties with due diligence and commitment.
Condonation of delay is an exception, not the rule, and cannot
be claimed as a matter of right or anticipated privilege by
Government entities. The law casts its protection equally upon
all litigants and cannot be distorted to confer undue
advantage upon a select few.
9. Very recently on 12.09.2025, the Supreme Court in the matter
of Shivamma (dead) by LRS Vs. Karnataka Housing Board &
Ors., 2025 INSC 1104 categorically held that the High Courts
ought not give a legitimizing effect to such callous attitude of
State authorities or its instrumentalities, and should remain
extra cautious, if the party seeking condonation of delay is a
State-authority. They should not become surrogates for State
laxity and lethargy. The constitutional courts ought to be
cognizant of the apathy and pangs of a private litigant.
10. In the present case, the appellant, being a public authority
(Executive Engineer, CSPDCL), was expected to act with due
promptitude, diligence, and bona fides in prosecuting the
matter. However, the appellant has failed to demonstrate the
same. The conduct reflects a lack of seriousness and proper
attention in pursuing the case. The grounds taken in the
appeal appear to be casual, vague, and insufficient, and they
do not inspire the confidence of this Court.
11. Accordingly, I.A. No. 01/2026 seeking condonation of delay is
hereby rejected. Consequently, the appeal, being barred by
limitation, also stands dismissed.
12. Ordered accordingly.
Sd/-
(Bibhu Datta Guru)
Judge Shoaib
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!