Friday, 10, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Jindal Steel And Power Ltd vs Chhattisgarh State Electricity ...
2026 Latest Caselaw 1089 Chatt

Citation : 2026 Latest Caselaw 1089 Chatt
Judgement Date : 30 March, 2026

[Cites 93, Cited by 0]

Chattisgarh High Court

Jindal Steel And Power Ltd vs Chhattisgarh State Electricity ... on 30 March, 2026

                                                              1




                                                                                    2026:CGHC:14839

                                                                                                    AFR

                                  HIGH COURT OF CHHATTISGARH AT BILASPUR

                                                 WPC No. 1927 of 2016
                                            Order reserved on 19/12/2025
                                            Order delivered on 30/03/2026

                      1 - Jindal Steel And Power Ltd. S/o A Company Registered Under The
                      Provisions Of Companies Act, 1956, Having Its Corporate Office At Jindal
                      Centre, 12 Bhikaji Cama Place, New Delhi- 110066, Through Mr. Rajesh
                      Agrawal, Associate- Vice- President., Delhi


                      2 - Mr. Rajesh Agrawal, S/o Shri B.K. Agrawal Aged About 45 Years
                      Shareholder Of Petitioner No.1, A V P- Electrical Power System, Jindal
                      Steel And Power Ltd., R/o Hill View Colony, J S P L, Raigarh, Chhattisgarh,
                      District : Raigarh, Chhattisgarh
                                                                                          ... Petitioners
                                                          versus

                      1 - Chhattisgarh State Electricity Regulatory Commission Irrigation Colony,
                      Shanti Nagar, Raipur, Chhattisgarh 492001, Chhattisgarh


                      2 - Chhattisgarh State Power Distribution Company Ltd., A Successor
                      Company Of C S E B, 4th Floor, Vidyut Sewa Bhavan, Daganiya, Raipur,
                      Chhattisgarh 492013, District : Raipur, Chhattisgarh


                      3 - Chhattisgarh State Power Transmission Company Ltd., A Successor
                      Company Of C S E B, Energy Info Tech Centre, Danganiya, Raipur,
VED                   Chhattisgarh 492013, District : Raipur, Chhattisgarh
PRAKASH
DEWANGAN                                                                              ... Respondents

VED PRAKASH (Cause title taken from Case Information System)

For Petitioners : Mr. Abhimanyu Bhandari, Senior Advocate (through virtual mode) along with Mr. Bhaskar Payasi, Mr. Jai Dhanani, Ms. Divya Chaturvedi, Mr. Saransh Shaw, Mr. Pranav Sood and Mr. Pankhuri Gupta, Advocates

For Respondent No.1 : Mr. Adhiraj Surana, Advocate

For Respondents No. 2 & 3 : Mr. Rajkumar Mehta, Advocate (through virtual mode) with Mr. Varun Sharma, Advocate

Hon'ble Shri Justice Ravindra Kumar Agrawal

C.A.V. Order

1. For the sake of convenience, the following terms shall hereinafter be

referred to as under:

Power Purchase Agreement - "PPA"

Chhattisgarh State Power Distribution Co. Ltd. - "CSPDCL"

Chhattisgarh State Power Transmission Co. Ltd. - "CSPTCL"

Short Term Open Access - "STOA"

Indian Electricity Grid Code - "IEGC"

Inter State Generating Station - "ISGS"

Availability Based Tariff - "ABT"

State Load dispatch Centre - "SLDC"

Electricity Power Survey - "EPS"

Inter State Generation Station - "ISGS"

Load Factor - "LF"

National Electricity Policy - "NEP"

2. The petitioners have filed the present writ petition challenging the

judgment dated 26-05-2016 (Annexure P-1) passed by the Appellate

Tribunal for Electricity, in Appeal Nos. 41 and 67 of 2015, and also

against the demand notice dated 07-07-2016 (Annexure P-2) issued

by the Respondent No. 2, letter dated 21-07-2016 (Annexure P-3),

letter dated 25-07-2016 (Annexure P-4), to issue No Objection

Certificate to allow the petitioner to open access from the

Respondent No. 3, and also to declare that the petitioner No. 1 is not

liable to refund of amount of Rs. 153.55 Crore to the Respondent No.

2, and prayed for the following reliefs:-

"It is therefore most respectfully prayed that this

Hon'ble Court may be pleased to:

10.1. Admit the Petition and set aside the Impugned

Judgment dated 26.05.2016 (marked as Annexure P-

1) passed by the Appellate Tribunal for Electricity in

Appeal Nos. 41 & 67 of 2015 : CSPDLC vs. CSERC;

10.2. Quash the Impugned Demand Notice dated

07.07.2016 (marked as Annexure P-2) passed by the

Chhattisgarh State Power Distribution Company Ltd.;

10.3. Quash the Impugned Letter dated 21.07.2016

(marked as Annexure P-3) passed by the Chhattisgarh

State Power Distribution Company Ltd.;

10.4. Quash the Impugned Rejection Letter dated

25.07.2016 (marked as Annexure P-4) passed by the

Chhattisgarh State Power Distribution Company Ltd.;

10.5. Direct the Chhattisgarh State Power Distribution

Company Ltd. to issue No Objection Certificate to

allow the Petitioner No.1 to avail Open Access from

the Chhattisgarh State Power Transmission Co. Ltd;

10.6. Direct the Chhattisgarh State Power

Transmission Company Ltd. to grant open access to

the Petitioner No.1 to supply power;

10.7. Declare that Petitioner is not liable to refund

Rs.153.55 Crore to the Chhattisgarh State Power

Distribution Company Ltd. in relation to the power

supplied to it in the FY 2011-12 and FY 2012-13; and

10.8. Pass any such other Order or Orders as this

Hon'ble Court may deem fit and proper in facts of the

present case."

3. Petitioner No.1 is a company incorporated under the Companies Act,

1956 and is engaged inter-alia in the business of manufacturing

sponge iron and steel, as well as the generation of power. The

Petitioner No.1 has established Captive Power Plants (CPPs) at

Village Patrapali, District Raigarh, and is a "generating company"

within the meaning of Section 2(28) of the Electricity Act, 2003. The

installed capacity of its captive power plant was initially 265.7 MW,

which was subsequently enhanced to 325.7 MW. Mr. Rajesh Agarwal

has been authorized to prosecute the petition on behalf of Petitioner

No.1 by virtue of a Board Resolution dated 26.07.2016.

4. On 02-11-2011, a PPA was executed between the Petitioner No. 1

and the Respondent No. 2, CSPDCL, for the supply of Electricity.

The initial PPA provided for the sale of 150 MW power for the period

01.11.2011 to 30.06.2012 and incorporated specific provisions

regarding load factor calculation, scheduled power, and tariff

determination based on formulae adopted from the State

Commission's Suo Motu Order. The agreement permitted injection of

power up to 110% during off-peak hours and 120% during peak

hours, with excess supply beyond these limits compensated at Rs. 1

per unit. The tariff was linked to the load factor, with a minimum

effective rate of Rs. 1.50 per unit.

5. Subsequently, supplementary PPAs were executed on 12.07.2012,

13.08.2012, and 24.01.2013 covering different periods up to

30.06.2013, including variation in contracted capacity (150 MW and

later 75 MW). The Petitioner supplied power in terms of these

agreements during Financial Years 2011-12 and 2012-13 and

raised invoices, including load factor-based billing and concessional

rates for excess injection. Respondent No.2 accepted the supplies

and made payments without any protest, at average rates of Rs. 2.42

per kWh and Rs. 2.66 per kWh, respectively.

6. In 2014, Respondent No.2 filed Tariff Petition No. 07/2014 before the

State Commission seeking true-up and tariff determination. By order

dated 12.06.2014, the State Commission approved a minimum base

rate of Rs. 1.50 per kWh for power procured from the Petitioner,

treating such power as "non-firm". It is the case of the petitioners that

this classification was not contemplated under the agreements

between the parties. A Review Petition was filed by Respondent No.2

before the State Commission, which was dismissed on 08.12.2014,

affirming the earlier findings.

7. The Respondent No.2 thereafter challenged the tariff and review

orders before the Appellate Tribunal for Electricity in Appeals Nos. 41

and 67 of 2015. By judgment dated 26.05.2016, the Appellate

Tribunal upheld the orders of the State Commission. Following the

Tribunal's judgment, Respondent No.2 issued a demand notice dated

07.07.2016 claiming a refund of Rs. 153.55 crore along with interest,

alleging overcharging by the Petitioner for power supplied during FYs

2011-12 and 2012-13. The Petitioner disputes this demand as

arbitrary and contrary to the binding contractual terms, emphasizing

that all invoices were raised strictly in accordance with the PPAs and

duly honoured without objection at the relevant time.

8. The Petitioner sought Short Term Open Access (STOA) in July 2016

for the supply of power through power exchanges. However,

Respondent No.2 refused to grant a No Objection Certificate (NOC),

citing the alleged outstanding dues arising from the impugned

demand. Consequently, Respondent No.3 (CSPTCL) also rejected

the Petitioner's application for open access on 25.07.2016 on the

same ground, thereby preventing the Petitioner from participating in

power exchange transactions.

9. It is also the case of the petitioner that the Petitioner No.1 duly

supplied power to Respondent No.2/CSPDCL during FYs 2011-12

and 2012-13 and raised invoices in accordance with the terms of the

PPAs, computing tariff on the basis of load factor during peak and

off-peak hours and charging only Re. 1.00 per kWh for power

injected beyond 110% (off-peak) and 120% (peak) limits, with load

factor calculated on a weekly basis. Respondent No.2 accepted such

supplies and made payments at average rates of Rs. 2.42 per kWh in

FY 2011-12 and Rs. 2.66 per kWh in FY 2012-13 without any

objection, and at no point prior to the impugned demand did it allege

that the power supplied was non-firm or that the Petitioner had

overcharged. The PPAs, being binding contracts, cannot be

unilaterally disregarded by Respondent No.2 after a lapse of several

years to seek refund of amounts already paid. It is further apparent

that the said PPAs were neither placed before the State Commission

under Section 62 of the Electricity Act, 2003 nor adequately

explained during tariff proceedings, thereby depriving the

Commission of the opportunity to examine their terms. Significantly,

Respondent No.2 itself admitted in the Review Order that the PPAs

were in consonance with the State Commission's orders, that

payments were made in accordance with their terms, and that no

retrospective alteration of such concluded transactions is

permissible.

10. The Petitioners also challenged the demand notice and denial of

NOC through representations dated 22.07.2016 and 23.07.2016,

asserting that no direction had been issued by the State Commission

or the Appellate Tribunal requiring refund, and that liability could not

be imposed without affording the Petitioner an opportunity of hearing.

The Petitioner further contended that the PPAs were binding and

could not be retrospectively altered, particularly after full performance

and settlement of payments.

11. Aggrieved by the demand of Rs. 153.55 crore, denial of open access,

and reliance on orders passed in proceedings to which it was not a

party, the Petitioner has filed the present petition seeking quashing of

the Appellate Tribunal's judgment dated 26.05.2016, the demand

notice, and related communications. The Petitioner also seeks

directions restraining Respondent No.2 from recovering the said

amount and for the grant of NOC and open access facilities.

12. The Respondent No. 1, Chhattisgarh State Electricity Regulatory

Commission, contested the claim of the petitioner and filed its return

with the preliminary objection that the present petition is not

maintainable and is liable to be dismissed in limine on account of the

availability of efficacious alternative remedies under the provisions of

the Electricity Act, 2003. It is submitted that the Petitioner has a

statutory remedy under Section 125 of the Act of 2003 to assail the

order dated 26.05.2016 passed by the Appellate Tribunal before the

Hon'ble Supreme Court. Further, the Petitioner could have availed

the remedy of review under Section 120(2)(f) of the Act before the

Appellate Tribunal, particularly on the ground of alleged denial of

opportunity of hearing. It is also pleaded that the Petitioner has an

alternative remedy under Section 86(1)(f) of the Act to approach the

State Commission for adjudication of disputes, which remedy has not

been exhausted. The consequential proceedings, including the

demand notice dated 07.07.2016, emanate from the order of the

Appellate Tribunal, and therefore, unless the said order is set aside

by the competent forum, no interference with the consequential

actions is warranted.

13. The Respondent No. 1 also pleaded that the demand raised against

the Petitioner is justified and in consonance with the Tariff Orders

dated 12.06.2014 and 08.12.2014 passed by the State Commission

in exercise of its statutory powers. The Commission, while

undertaking the true-up exercise for FYs 2011-12 and 2012-13,

examined the nature of power supplied by the Petitioner and found

the same to be non-firm and unstable, based on load curve analysis

and findings recorded in earlier appellate proceedings. The

Commission accordingly approved only a minimum base rate of Rs.

1.50 per kWh for such power, observing that the burden of procuring

non-firm power at higher rates cannot be passed on to consumers. It

is further pleaded that the PPAs themselves contained a stipulation

making them subject to directions and guidelines issued by the

Commission, thereby rendering the tariff orders binding upon the

parties.

14. It is also the reply of the Respondent No. 1 that due process was

followed by the State Commission as well as the Appellate Tribunal,

including issuance of public notices and affording opportunity of

hearing to stakeholders. The notices of tariff and review proceedings

were published in newspapers, and that a representative of the

Petitioner had participated in the review proceedings, thereby

negating the plea of lack of opportunity of hearing or knowledge of

the proceeding. Similarly, the Appellate Tribunal also issued public

notices prior to deciding the appeals. Therefore, the Petitioner cannot

now claim ignorance of the proceedings or violation of principles of

natural justice.

15. The Respondent No. 2/CSPDCL have filed their return and have

raised a preliminary objection as to the maintainability of the present

writ petition on the ground that the petitioners had an effective and

statutory alternative remedy. It is submitted that the order dated

12.06.2014 passed by the State Commission in Petition Nos. 05 to

08 of 2014 (T), including Petition No. 07/2014 filed by respondent No.

2, was subjected to challenge before the Appellate Tribunal for

Electricity (APTEL) by way of Appeal Nos. 41 and 67. The said

appeals, directed against both the original order and the review order

dated 08.12.2014, were dismissed by APTEL by a common judgment

dated 26.05.2016. The petitioners have not preferred any appeal

before the Hon'ble Supreme Court under Section 125 of the

Electricity Act, 2003. Therefore, the judgment of APTEL has attained

finality and is binding on the petitioners, thereby precluding the

petitioners from re-agitating the same issues in the present writ

proceedings.

16. It is further pleaded that the petitioner company had entered into

Power Purchase Agreements offering 150 MW of firm power on a

round-the-clock basis, with a permissible reduction up to 20% and a

guaranteed minimum supply of 120 MW, subject to the provisions of

the Electricity Act, 2003 and regulatory guidelines issued by the State

Commission from time to time. Respondent No. 2, being a

distribution licensee under Section 14 of the Act, procured power on

a short-term basis in accordance with tariff orders and regulatory

framework evolved by the State Commission through various suo

motu proceedings since 2009, wherein ceiling tariffs and

procurement conditions were determined after due public

consultation and stakeholder participation, including that of the

petitioners. In continuation thereof, the State Commission, while

determining tariff in Petition Nos. 05 to 08 of 2014 (T), examined the

short-term power purchases made by respondent No. 2 from the

petitioner and, on analysis of the load curve and injection pattern,

concluded that the power supplied was intermittent and non-firm in

nature, causing grid disturbances, and accordingly restricted the tariff

to a lower rate treating it akin to infirm power. Though respondent

No. 2 initially contested these findings, its challenge failed, as the

review petition was partly allowed and the subsequent appeals

preferred before APTEL against the orders dated 12.06.2014 and

08.12.2014 were dismissed by a common judgment dated

26.05.2016, affirming that unstable and fluctuating power supply

cannot be equated with firm power and must be compensated at a

lower tariff.

17. It is further pleaded that the proceedings before the State

Commission were conducted in accordance with the Chhattisgarh

State Electricity Regulatory Commission (Conduct of Business)

Regulations, 2009. Under the said Regulations, individual notices to

stakeholders are not mandatory; rather, the procedure contemplates

issuance of public notice to ensure wider participation. In the present

case, the petitions were uploaded on the Commission's website,

copies were made available at the offices of the petitioners, and a

public notice along with the gist of the petitions was published in

newspapers inviting objections and suggestions. Public hearing was

conducted at Raipur on 21.05.2014, followed by a separate

interaction on 22.05.2014 with representatives of industries, HT

consumers, and industrial associations. Additionally, consultations

were held with members of the State Advisory Committee. The

Commission, after considering all objections and performing due

diligence, finalized its findings. A further public notice dated

26.04.2014 was also issued. Thus, the petitioners were duly notified

and had full opportunity to participate.

18. The respondent No. 2 had filed Review Petition No. 35 of 2014 on

31.07.2014 before the State Commission. During the course of

hearing on 28.10.2014, the authorized representative of petitioner

No. 1, namely N.K. Chandiramani (DGM, JSPL), was present, as

reflected in the order sheet. The review petition was ultimately

disposed of on 08.12.2014. Despite having knowledge of and

participating in the proceedings, the petitioners failed to effectively

pursue their remedies or challenge the outcome at the appropriate

stage. Even thereafter, when APTEL dismissed the appeals on

26.05.2016, the petitioners did not avail the statutory remedy of

appeal before the Hon'ble Supreme Court. The respondents submit

that such conduct demonstrates negligence and attracts the doctrine

of acquiescence.

19. It is also pleaded that the dispute pertains to highly technical issues

involving tariff determination, nature of power supply, and grid

stability. The State Commission, exercising powers under Sections

62 and 86 of the Electricity Act, examined the power purchase

agreements, load curves, and injection patterns, and concluded that

the power supplied by the petitioner was non-firm in nature due to its

fluctuating and unstable characteristics. Consequently, the tariff was

restricted in line with the treatment of infirm power. This finding was

specifically affirmed by APTEL, which observed that such unstable

injection patterns create commercial complications and disturb the

demand-supply balance. The respondents contend that such

findings, based on technical data and expert analysis, are not

amenable to judicial review under Article 226, particularly where

disputed questions of fact are involved.

20. The respondent No. 2 further pleaded that the present petition suffers

from non-joinder of necessary and proper parties. Several

stakeholders, including industries and associations, who participated

in the proceedings before the State Commission and opposed the

claims, have not been impleaded in the present writ petition.

Additionally, the petitioners have not challenged the foundational

order dated 12.06.2014 or the applicability of the 2009 Regulations,

which governed the entire process. In the absence of such challenge,

the relief sought becomes untenable. It is also pleaded that the

petitioners had knowledge of the APTEL judgment at least by

07.07.2016 through the demand notice issued by respondent No. 2,

yet failed to take any appropriate remedial steps.

21. On the issue of recovery, the respondent No. 2 pleaded that the

demand raised is in accordance with Section 62(6) of the Electricity

Act, 2003, which mandates that any excess tariff recovered by a

generating company shall be refundable along with interest at the

bank rate. The demand of Rs. 153.55 crore has been raised pursuant

to the findings of the State Commission and APTEL, and is

supported by audited accounts and financial records considered

during tariff determination. It is also pleaded that permitting the

petitioners to retain such excess amount would result in unjust

enrichment and would be contrary to public interest, particularly as

respondent No. 2 is a public utility accountable to consumers.

22. Respondent No. 3 has also filed its return separately and in

preliminary submissions, have pleaded the statutory framework of

the Electricity Act, 2003, to justify their actions. It is pleaded that

under Section 31 of the Act, the State Load Dispatch Centre (SLDC)

has been constituted as the apex body for integrated operation of the

power system within the State, and is operated by the State

Transmission Utility in terms of Section 39. The SLDC is statutorily

prohibited from engaging in the trading of electricity and is entrusted

with critical operational responsibilities relating to grid management,

scheduling, and dispatch. Further, under Section 86(1) of the Act, the

State Regulatory Commission is vested with wide powers, including

the determination of tariff, the regulation of procurement of electricity

by distribution licensees, facilitation of intra-State transmission,

adjudication of disputes, and specification of the State Grid Code,

while ensuring transparency and adherence to national policies. In

furtherance of its statutory functions, the State Commission has

notified the Chhattisgarh State Electricity Grid Code, 2011, and the

SLDC discharges its functions under Section 32 of the Act, which

include ensuring optimum scheduling and dispatch of electricity,

monitoring grid operations, maintaining quality of electricity,

supervising intra-State transmission, and carrying out real-time grid

control for secure and economic operation. Additionally, under

Section 33, the SLDC is empowered to issue binding directions to

generating companies and licensees to maintain grid discipline, and

such directions are mandatorily required to be complied with, failing

which penal consequences may follow. The SLDC is also obligated

to act in coordination with higher load dispatch centres and to ensure

safe and stable grid operations.

23. The Respondent No. 3 further pleaded that the petitioner No. 1 has

consistently injected fluctuating and non-firm power into the State

grid over a prolonged period of time, including during the subsistence

of the Power Purchase Agreements executed with respondent No. 2.

The SLDC had repeatedly issued communications and directions to

the petitioners, calling upon them to adhere to scheduled injection

and grid discipline. The petitioner not only failed to comply but also

admitted its inability to supply firm power on account of fluctuating

internal consumption patterns. The SLDC, in multiple letters dated

between 2014 and 2016, highlighted substantial deviations in

injection ranging from zero to excessive levels, violation of open

access regulations, and potential threat to grid security, even warning

of disconnection in case of continued non-compliance.

Simultaneously, the SLDC also apprised the State Commission of

the persistent issues arising from such fluctuating power supply and

sought appropriate guidelines for the identification and treatment of

"non-firm" or "poor quality" power. Several communications

addressed to the Commission between 2014 and 2016 emphasized

the operational difficulties faced in maintaining grid discipline,

including warnings received from higher load dispatch centres. The

SLDC specifically requested clarity on the criteria for non-firm power,

permissible actions against defaulting generators, and the

permissibility of granting open access in such cases. These

communications were made in discharge of statutory obligations,

including under Section 33(4) of the Act.

24. It is further pleaded that the State Commission, while passing the

tariff order dated 12.06.2014 in Petition No. 07 of 2014 (T), examined

the load curve and injection pattern of the petitioner and recorded a

categorical finding that the power supplied was highly fluctuating,

unstable, and non-firm in nature. It was observed that such erratic

supply adversely impacted grid stability and compelled the

distribution licensee to resort to overdrawal or underdrawal from the

grid, attracting penalties. Consequently, the Commission held that

such power could not be treated at par with firm power and restricted

the tariff to a base rate of Rs. 1.50 per unit, further issuing specific

directions to discourage procurement and injection of such non-firm

power and mandating the SLDC to monitor and regulate the same.

25. The review petition filed by respondent No. 2 was disposed of on

08.12.2014, wherein the Commission reaffirmed its earlier findings,

noting that no new material or error apparent on record had been

brought forth. The Commission also relied on independent studies

and consistent observations of the SLDC regarding the fluctuating

injection pattern of the petitioner. The directives issued in the original

order, including those relating to grid discipline and monitoring of

non-firm power, thus attained finality at the regulatory level.

Aggrieved thereby, respondent No. 2 preferred appeals before the

Appellate Tribunal for Electricity (APTEL), which, by its judgment

dated 26.05.2016, upheld the findings of the State Commission in

entirety. The Tribunal took note of the petitioner's own admissions in

earlier proceedings regarding the fluctuating nature of surplus power

and inability to supply consistent power due to variable industrial

demand. It was categorically held that such an unstable power

supply has commercial as well as operational implications, disturbs

demand-supply balance, and cannot be equated with firm power. The

Tribunal affirmed that such power must be treated as akin to infirm

power and compensated at a significantly lower rate.

26. It is further pleaded that the petitioners have neither challenged the

tariff order dated 12.06.2014 nor the directives issued therein, nor the

judgment of APTEL. In compliance with the said binding decisions

and statutory mandate, the SLDC has continued to regulate and

restrict open access to the petitioner in view of its non-compliance

with grid discipline and continued injection of non-firm power. The

rejection of short-term open access applications made by the

petitioners in July-August 2016 was thus based on statutory

obligations, regulatory directives, and binding judicial findings, and

not merely on account of any monetary dispute as alleged. The

answering respondent has acted strictly within the framework of the

Electricity Act, 2003, the State Grid Code, and the binding directions

of the State Commission and APTEL. The continued conduct of the

petitioner in injecting fluctuating power, coupled with its admitted

inability to maintain firm supply, justified regulatory intervention and

denial of open access in the interest of grid security, discipline, and

public interest.

27. Learned counsel for the petitioners would submit that the present writ

petition has been filed by the Petitioner, Jindal Steel & Power Limited

(JSPL), assailing the demand notice dated 07.07.2016 issued by the

Respondent No. 2, Chhattisgarh State Power Distribution Company

Limited (CSPDCL), seeking recovery of Rs. 153.55 crores, along with

the consequential denial of open access and the underlying judgment

dated 26.05.2016 passed by the Appellate Tribunal for Electricity

(APTEL). The core challenge of the Petitioner is that the impugned

demand is wholly without jurisdiction, contrary to the settled

principles of law, and has been raised in complete violation of

principles of natural justice.

28. The undisputed fact that the Petitioner was never impleaded as a

party in the proceedings before the State Commission or before

APTEL. The true-up proceedings initiated by CSPDCL, the

subsequent review proceedings, and the appeals before APTEL

were all conducted without issuing any notice to the Petitioner,

despite the fact that the entire dispute pertained to power supplied by

the Petitioner under duly executed Power Purchase Agreements.

The Petitioner was thus denied any opportunity to place its case,

clarify the nature of supply, or defend the contractual arrangement. It

is a settled proposition of law that no adverse order can be passed

against a party without affording it a reasonable opportunity of

hearing, and any action taken in breach thereof stands vitiated. The

impugned demand is ex facie illegal, as it seeks to impose a financial

liability upon the Petitioner on the basis of proceedings to which it

was not a party and in which no findings have been recorded against

it. A perusal of the true-up order, review order, and the appellate

judgment would reveal that the findings, if any, are against CSPDCL

alone, particularly attributing negligence to it in procuring power.

There is not even a whisper in the said orders directing recovery from

the Petitioner or holding that the Petitioner is liable to refund any

amount. In such circumstances, the unilateral issuance of the

demand notice is nothing but an afterthought and is wholly

unsustainable.

29. Learned counsel for the petitioners further submits that it had no

occasion to challenge the orders passed by the State Commission or

APTEL, as it was neither a party to those proceedings nor was any

liability fastened upon it therein. The cause of action for the Petitioner

arose only upon issuance of the impugned demand notice dated

07.07.2016. Therefore, the contention of CSPDCL that the Petitioner

ought to have availed alternative remedies is misconceived. It is well

settled that where a party has not been heard and suffers civil

consequences, the writ jurisdiction of this Hon'ble Court can be

directly invoked. The Petitioner was a necessary party to the

proceedings before the State Commission and APTEL, as the

adjudication directly concerned the nature of power supplied by it and

the payments made under the PPAs. In the absence of the

Petitioner, no effective or binding determination could have been

made on issues that ultimately form the basis of the impugned

demand. The failure of CSPDCL to implead the Petitioner, despite

having full knowledge of the contractual relationship and

transactions, renders the entire exercise procedurally flawed. Such

omission cannot now be used to prejudice the Petitioner by fastening

liability upon it without due process.

30. It is further argued that the petitioner had supplied electricity strictly in

terms of the Power Purchase Agreements executed with CSPDCL,

which were based on the Suo-Motu Order passed by the State

Commission. The contractual framework specifically recognized the

nature of supply from captive generating plants, including permissible

variations and the mechanism for computation of tariff through load

factor and eligible units. The invoices raised by the Petitioner were in

accordance with these agreed terms and were duly verified and paid

by CSPDCL without any demur. It is an admitted position that

CSPDCL accepted the power supplied by the Petitioner, utilized the

same for distribution to consumers, and recovered the corresponding

tariff. Payments were made over the relevant period in full

satisfaction of contractual obligations, and at no stage during the

subsistence of the PPAs did CSPDCL raise any dispute regarding

the nature or quality of power supplied. In such circumstances, the

attempt to retrospectively reclassify the supply as "non-firm" and

seek recovery of amounts already paid is impermissible in law and

contrary to the doctrine of finality of concluded transactions.

31. The impugned demand, in effect, seeks to compel the Petitioner to

refund monies for electricity that has already been generated,

supplied, consumed, and paid for. Such a course of action is not only

inequitable but also legally untenable, as there exists no provision in

the PPAs or under any statutory framework permitting such recovery.

In the absence of any contractual stipulation or regulatory direction

requiring refund, CSPDCL cannot unilaterally impose a financial

burden upon the Petitioner. Further, the findings of the State

Commission, as affirmed by APTEL, clearly attribute negligence to

CSPDCL in procuring power without due prudence. The regulatory

authorities have held that the consequences of such negligence

cannot be passed on to consumers. However, CSPDCL now seeks

to shift this very burden onto the Petitioner, who was not even heard

in the proceedings. This attempt to transfer liability is contrary to the

findings of the regulatory authorities themselves and is legally

impermissible.

32. It is further argued that the objection raised by CSPDCL regarding

the availability of an alternative remedy under Section 125 of

the Electricity Act, 2003 is wholly misconceived and untenable in the

facts of the present case. The remedy of appeal to the Hon'ble

Supreme Court under Section 125 is available only to a "person

aggrieved" by an order passed by the Appellate Tribunal for

Electricity (APTEL). In the present case, the Petitioner was neither a

party to the proceedings before the State Commission nor before

APTEL, and no adverse findings or directions have been issued

against it in the impugned judgment. Consequently, the Petitioner

cannot be said to be an "aggrieved person" within the meaning of

Section 125 so as to avail the said appellate remedy. The cause of

action for the Petitioner arose only upon issuance of the impugned

demand notice dated 07.07.2016, whereby, for the first time, a

liability has been sought to be imposed upon it without any

adjudication or hearing. It is a settled principle of law that the

existence of an alternative remedy does not bar the exercise of writ

jurisdiction under Article 226 of the Constitution of India, particularly

where the impugned action is wholly without jurisdiction, violative of

principles of natural justice, or results in manifest injustice. In the

present case, the Petitioner has been fastened with a substantial

financial liability without being heard and without any legal basis, and

therefore, the writ petition is not only maintainable but constitutes the

only efficacious remedy available to the Petitioner.

33. The action of CSPDCL is also hit by the principles of estoppel,

approbation and reprobation. Having accepted the contractual terms,

acted upon them, and derived benefit from the Petitioner's

performance, CSPDCL cannot now take a contradictory stand to the

detriment of the Petitioner. The law does not permit a party to accept

benefits under a contract and subsequently challenge its validity or

seek restitution without any legal basis. The impugned demand

notice is vitiated by violation of principles of natural justice, absence

of jurisdictional foundation, lack of contractual or statutory basis, and

arbitrariness. The Petitioner, having neither been heard nor held

liable in any adjudicatory proceedings, cannot be subjected to

recovery of amounts already paid for duly supplied electricity.

Accordingly, the impugned demand and all consequential actions

deserve to be quashed, and the Petitioner is entitled to appropriate

reliefs from this Hon'ble Court.

34. In support of his submission, he would rely upon the judgments of

"Ramesh Hiranand Kundanmal v. Municipal Corporation of

Greater Bombay" 1992 (2) SCC 524, "Whirlpool Corporation v.

Registrar of Trade Marks" 1998 (8) SCC 1, "State of Himachal

Pradesh v. Gujarat Ambuja Cement Ltd." 2005 (6) SCC 499,

"Harbans Lal Sahnia v. Indian Oil Corporation Ltd." 2003 (2) SCC

107, "Dhampur Sugar Mills Ltd. v. State of U.P. and Others" 2007

(8) SCC 338, "Har Shankar and Others v. Dy. Excise and

Taxation Commissioner and Others" 1975 (1) SCC 737, "State

Bank of Haryana and Others v. Jage Ram and Others" 1980 (3)

SCC 599, "Mumbai International Airport (P) Ltd. v. Golden

Chariot Airport" 2010 (10) SCC 422, "Hari Bans Lal v. Sahodar

Prasad Mahto" 2010 (9) SCC 655, "Mohindar Singh Gill v. Chief

Election Commissioner, New Delhi" 1978 (1) SCC 405, "Sharda

Singh v. State of U.P." 2009 (11) SCC 683, "Chandi Prasad v.

Jagdish Prasad" 2004 (8) SCC 724, "Pimpri Chinchwad New

Town Development Authority v. State of Maharashtra" 2005 (4)

Mh.L.J. 941, "Haryana Power Purchase Centre v. Sasan Power

Ltd. and Others" 2023 SCC OnLine SC 577, "Karnataka Power

Corporation Limited v. EMTA Coal Limited and Another", order

dated 20-05-2022, by Hon'ble Supreme Court in Civil Appeals Nos.

5401-5404 of 2017, "Gujarat Urja Vikas Nigam Limited v. Solar

Semiconductor Power Company (India) Private Limited and

Another" 2017 (16) SCC 498.

35. Per contra, learned counsel appearing for the Respondent Nos. 2

and 3, at the outset, raises a preliminary objection regarding the

maintainability of the present writ petition on the ground of the

availability of efficacious statutory remedies under the Electricity Act,

2003. It is submitted that the petitioners had the remedy of filing an

appeal before the Hon'ble Supreme Court under Section 125 against

the judgment dated 26.05.2016 passed by the Appellate Tribunal for

Electricity (APTEL), which has not been availed. The said judgment

has thus attained finality and is binding upon the parties. The

petitioners, by invoking writ jurisdiction, are impermissibly seeking to

reopen issues already adjudicated by expert statutory forums, which

is contrary to settled principles governing the exercise of jurisdiction

under Article 226 of the Constitution of India.

36. It is further submitted that the dispute in question arises out of tariff

determination and true-up proceedings undertaken by the State

Commission in exercise of its statutory powers under Sections 62

and 86 of the Electricity Act, 2003. The State Commission, after

detailed examination of load curves, injection patterns, and

operational data, recorded a categorical finding that the power

supplied by the petitioner was non-firm, intermittent, and unstable in

nature. Such findings, based on technical expertise and regulatory

analysis, were affirmed by APTEL. The respondents submit that

these concurrent findings of fact are not amenable to judicial review

in writ jurisdiction, particularly when they involve highly technical and

disputed questions requiring specialized adjudication.

37. It is further submitted that the Power Purchase Agreements (PPAs)

relied upon by the petitioners were expressly subject to the

provisions of the Electricity Act, 2003 and regulatory directions

issued by the State Commission from time to time. Therefore, tariff

determination by the Commission overrides contractual stipulations

to the extent of inconsistency. The Commission, in its tariff order

dated 12.06.2014, lawfully restricted the tariff for non-firm power to a

base rate of Rs. 1.50 per kWh, in order to safeguard consumer

interest and prevent undue financial burden on the distribution

licensee. The petitioners cannot rely on contractual terms to defeat

statutory tariff orders having an overriding effect. The demand of Rs.

153.55 crore has been raised strictly in accordance with Section

62(6) of the Electricity Act, 2003, which mandates the refund of

excess tariff recovered by a generating company along with

applicable interest. The excess amount was computed on the basis

of audited financial data and in line with the findings recorded in the

tariff and appellate proceedings. Retention of such an excess amount

by the petitioner would result in unjust enrichment at the cost of

public funds and electricity consumers, which is impermissible in law.

38. Learned counsel for Respondents Nos. 2 and 3 further submits that

the petitioners were not denied an opportunity of hearing, as alleged.

The proceedings before the State Commission were conducted in

accordance with the applicable Conduct of Business Regulations,

which provide for the issuance of public notices rather than individual

notices. The tariff petitions were widely publicised through

newspapers and the official website, and public hearings were

conducted wherein stakeholders, including industry representatives,

were given an opportunity to participate. In fact, the authorized

representative of the petitioner was present during the review

proceedings, demonstrating knowledge and participation in the

process. Similarly, APTEL also issued public notices before deciding

the appeals. It is also submitted that the petitioners, despite having

knowledge of the proceedings and their outcome, failed to avail

appropriate remedies at the relevant stages, including review before

APTEL or appeal before the Hon'ble Supreme Court. Such inaction

and acquiescence disentitle the petitioners from seeking

discretionary relief under Article 226. The writ petition is thus liable to

be dismissed on the ground of delay, laches, and waiver, apart from

being an attempt to bypass statutory remedies.

39. It is further submitted that under Sections 31, 32, and 33 of the

Electricity Act, 2003, the State Load Dispatch Centre (SLDC) is

entrusted with the responsibility of maintaining grid discipline,

ensuring secure and economic operation of the power system, and

issuing binding directions to generating companies. The petitioner,

however, has consistently violated grid discipline by injecting highly

fluctuating and non-firm power, thereby jeopardizing grid stability.

Repeated communications and directions were issued by the SLDC

to the petitioner between 2014 and 2016, calling upon it to adhere to

scheduled generation and maintain consistency in power supply. The

petitioner not only failed to comply but also admitted its inability to

supply firm power due to fluctuating internal consumption. Such

erratic injection patterns caused operational difficulties, including

overdrawal and underdrawal situations, attracting penalties and

affecting overall grid management. The State Commission, taking

note of these issues, issued directions to regulate and discourage

such non-firm power. Denial of No Objection Certificate (NOC) and

rejection of Short Term Open Access (STOA) applications were not

arbitrary but were based on statutory obligations, regulatory

directives, and the petitioner's continued non-compliance with grid

discipline. Grant of open access to an entity injecting unstable power

would pose a serious threat to grid security and reliability. The

impugned actions were therefore taken in the interest of maintaining

stability of the power system and in compliance with binding

directions of the State Commission and APTEL.

40. Lastly, it is also submitted that the present writ petition suffers from

non-joinder of necessary parties, including stakeholders who

participated in the tariff proceedings and whose interests are affected

by the outcome. The petitioners have also failed to challenge the

foundational tariff orders and regulatory framework, which form the

basis of the impugned actions. In the absence of such a challenge,

the reliefs sought are untenable. The respondents thus pray for

dismissal of the writ petition as being devoid of merit, not

maintainable, and contrary to the statutory scheme of the Electricity

Act, 2003.

41. He would rely upon the judgment of "Power Grid Corporation of

India Limited v. Madhya Pradesh Power Transmission Company

Limited and Others" 2025 (8) SCC 705, "State of Himachal

Pradesh and Another v. JSW Hydro Energy Limited and Others"

2025 SCC OnLine SC 1460, "Jaipur Vidyut Vitran Nigam Limited

and another v. MB Power (Madhya Pradesh) and Others" 2024

(8) SCC 513, "Educanti Kistamma (Dead) through L.Rs. v. S.

Venkatareddy (Dead) through L.Rs. and Others" 2010 (1) SCC

756, "Uttar Haryana Bijli Vitran Nigam Limited and Another v.

Adani Power (Mundra) Limited and Others" 2023 (14) SCC 736,

"Maharashtra State Electricity Distribution Company Limited v.

Adani Power Maharashtra Limited and Others" 2023 (7) SCC 401,

"GMR Warora Energy Ldt. V. CERC" 2023 (10) SCC 401, "R.

Muthukumar and Others v. Chairman and managing Director

TANGEDCO and Others" 2022 SCC OnLine SC 151.

42. Learned Counsel appearing for the Respondent No. 1 would submit

that the present writ petition under Article 226 of the Constitution of

India is not maintainable. The petitioners have a complete and

efficacious statutory remedy under Section 125 of the Electricity Act,

2003, to challenge the judgment dated 26.05.2016 of the Appellate

Tribunal for Electricity (APTEL) before the Hon'ble Supreme Court. In

addition, Section 120(2)(f) provides a remedy of review before

APTEL. The petitioners' failure to exhaust these statutory remedies

precludes interference under writ jurisdiction as held in "Union of

India v. Satyawati Sharma", (1965) 1 SCR 363, writ jurisdiction is

discretionary and cannot be exercised where an alternative statutory

remedy exists. By adopting the submissions made by learned

counsel for the Respondents Nos. 2 and 3, he would submit that

functions under the Electricity Act, 2003, with statutory powers

defined under Sections 61, 62, and 86. Section 61 empowers the

Commission to specify the principles for the determination of tariffs.

Section 62 empowers the Commission to determine the tariff for the

supply of electricity by a generating company to a distribution

licensee. Section 86(1)(b) and (f) authorise the Commission to

adjudicate disputes between licensees and generating companies,

and to ensure compliance with the Act. All actions of the

Commission, including the tariff orders dated 12.06.2014 and review

dated 08.12.2014, were taken within the statutory framework,

following due process. The Commission, in Petition No. 07/2014,

undertook the true-up exercise for FYs 2011-12 and 2012-13 and

determined the minimum base tariff at Rs. 1.50 per unit for non-firm

power. Section 62(3) and 62(6) mandate that only the tariff

determined under the Act is payable, and any excess collection must

be refunded with interest. The petitioner's claim to receive a higher

tariff or to avoid refund is contrary to statutory provisions and the

principle that regulatory tariffs prevail over contractual agreements in

matters of public utility and consumer interest.

43. He would further submit that principles of natural justice were fully

complied with. Regulation 10 of the CSERC (Conduct of Business)

Regulations, 2009, provides that public notices are sufficient to afford

hearing to stakeholders. Notices were published in newspapers,

petitions were uploaded on the Commission's website, and public

hearings were conducted at Raipur on 21-22.05.2014.

Representatives of the petitioner, including DGM N.K. Chandiramani,

were present and participated in the review proceedings. Thus, the

claim of denial of opportunity of hearing is wholly misconceived. The

tariff orders passed by the Commission and affirmed by APTEL are

binding on the parties under Section 62(6) and Section 111. The

petitioners cannot seek collateral review through a writ petition to

avoid statutory obligations. It is well-settled that once an order of a

specialised tribunal attains finality, collateral attack under writ

jurisdiction is impermissible (NTPC Ltd. v. CERC & Ors., 2006 11

SCC 154). Any attempt to circumvent these orders undermines the

statutory framework.

44. It is further argued that petitioners supplied fluctuating, non-firm

power, which was duly examined in tariff proceedings. Sections 32

and 33 empower the SLDC and the Commission to monitor grid

operations and issue binding directions for maintaining system

stability. The petitioner's continued injection of unstable power

created operational and commercial risks, which the Commission

duly considered while limiting tariff. The denial of open access by the

licensee (Respondent No. 2) was in conformity with the

Commission's directives. The petitioners had full knowledge of the

tariff orders, review proceedings, and APTEL judgment. Their failure

to challenge the orders before the Supreme Court demonstrates

acquiescence. The orders under challenge are in furtherance of

public interest and consumer protection, as mandated under Section

61(g) and 86(1)(b) of the Electricity Act, 2003. Allowing the

petitioners to retain amounts already paid in excess of the statutory

tariff would result in unjust enrichment and adversely affect

consumers. The Commission's regulatory mandate cannot be

undermined by private contractual claims. In view of the foregoing,

he also prays that the writ petition be dismissed on the grounds of (i)

non-maintainability due to existence of alternative statutory remedies,

(ii) compliance with principles of natural justice and due process, (iii)

binding nature of tariff orders and APTEL judgment, (iv) technical and

regulatory basis of the orders, and (v) protection of public interest.

The petitioners' claims are wholly unsustainable in law.

45. I have heard learned counsel for the respective parties and gone

through the pleadings and documents annexed thereto.

46. The present writ petition consists of the challenge to the demand

notice dated 07.07.2016 issued by Respondent No. 2 (CSPDCL), the

consequential denial of Short Term Open Access (STOA) and No

Objection Certificate (NOC), and the extent to which the judgment

dated 26.05.2016 passed by the Appellate Tribunal for Electricity

(APTEL) can be relied upon to fasten liability upon the petitioner. The

foundational question which arises is whether the petitioner No. 1,

admittedly not impleaded in the tariff proceedings before the State

Commission or in the appellate proceedings before APTEL, can be

subjected to adverse civil and pecuniary consequences on the

strength of findings recorded in such proceedings, and whether such

action satisfies the mandate of the Electricity Act, 2003 and the

settled principles of natural justice.

47. Before adverting to the merits of the controversy, it is necessary to

deal with the preliminary objection raised by the respondents with

regard to the maintainability of the present writ petition. The objection

proceeds on the footing that the petitioner had efficacious alternative

remedies under Sections 120(2)(f), 125, and 86(1)(f) of the Electricity

Act, 2003, and having failed to avail the said remedies, the present

writ petition ought not to be entertained. This Court is unable to

accept the said contention for more than one reason.

48. It is trite that the rule of alternative remedy is a rule of self-imposed

restraint and not a jurisdictional bar. The power of judicial review

under Article 226 of the Constitution of India is plenary in nature and

cannot be curtailed by statutory provisions. The Hon'ble Supreme

Court in "Whirlpool Corporation v. Registrar of Trade Marks",

(1998) 8 SCC 1, has authoritatively held that in at least three

contingencies, namely, where the writ petition seeks enforcement of

fundamental rights, where there is violation of principles of natural

justice, and where the impugned orders are wholly without

jurisdiction, the existence of an alternative remedy would not operate

as a bar. This principle has been consistently reiterated

in "Harbanslal Sahnia v. Indian Oil Corporation Ltd.", (2003) 2

SCC 107, wherein it has been held that the rule of exclusion of writ

jurisdiction in view of the availability of an alternative remedy is a rule

of discretion and not one of compulsion.

49. In the case of "Whirlpool Corporation" (supra), the Hon'ble

Supreme Court has held that:-

"15. Under Article 226 of the Constitution, the High

Court, having regard to the facts of the case, has a

discretion to entertain or not to entertain a writ petition.

But the High Court has imposed upon itself certain

restrictions one of which is that if an effective and

efficacious remedy is available, the High Court would

not normally exercise its jurisdiction. But the alternative

remedy has been consistently held by this Court not to

operate as a bar in at least three contingencies, namely,

where the writ petition has been filed for the

enforcement of any of the Fundamental Rights or where

there has been a violation of the principle of natural

justice or where the order or proceedings are wholly

without jurisdiction or the vires of an Act is challenged.

There is a plethora of case-law on this point but to cut

down this circle of forensic whirlpool, we would rely on

some old decisions of the evolutionary era of the

constitutional law as they still hold the field."

50. In the case of "Harbanslal Sahnia" (supra), it has been held by their

lordships of the Hon'ble Supreme Court that:-

"7. So far as the view taken by the High Court that the

remedy by way of recourse to arbitration clause was

available to the appellants and therefore the writ petition

filed by the appellants was liable to be dismissed is

concerned. suffice it to observe that the rule of

exclusion of writ jurisdiction by availability of an

alternative remedy is a rule of discretion and not one of

compulsion. In an appropriate case, in spite of

availability of the alternative remedy, the High Court

may still exercise its writ jurisdiction in at least three

contingencies: (i) where the writ petition seeks

enforcement of any of the fundamental rights; (ii) where

there is failure of principles of natural justice: or (n)

where the orders or proceedings are wholly without

jurisdiction or the vires of an Act is challenged. (See

Whirlpool Corpn. v. Registrar of Trade Marks The

present case attracts applicability of the first two

contingencies. Moreover, as noted, the petitioners

dealership, which is their bread and butter, came to be

terminated for an irrelevant and non-existent cause. In

such circumstances, we feel that the appellants should

have been allowed relief by the High Court itself instead

of driving them to the need of initiating 9 arbitration

proceedings."

51. In the case of "Gujarat Ambuja Cement Ltd." (supra), it has been

held that:-

"18. The Constitution Benches of this Court in K.S.

Rashid and Son v. Income Tax Investigation

Commission, AIR 1954 SC 207; Sangram Singh v.

Election Tribunal, Kotah, AIR 1955 SC 425; Union of

India v. T.R. Varma, AIR 1957 SC 882; State of U.P. v.

Mohd. Nooh, AIR 1958 SC 86 and K.S. Venkataraman

and Co. (P) Ltd. v. State of Madras, AIR 1966 SC 1089

held that Article 226 of the Constitution confers on all

the High Courts a very wide power in the matter of

issuing writs. However, the remedy of writ is an

absolutely discretionary remedy and the High Court has

always the discretion to refuse to grant any writ if it is

satisfied that the aggrieved party can have an adequate

or suitable relief elsewhere. The Court, in extraordinary

circumstances, may exercise the power if it comes to

the conclusion that there has been a breach of

principles of natural justice or procedure required for

decision has not been adopted.

19. Another Constitution Bench of this Court in State of

M.P. v. Bhailal Bhai, AIR 1964 SC 1006 held that the

remedy provided in a writ jurisdiction is not intended to

supersede completely the modes of obtaining relief by

an action in a civil court or to deny defence legitimately

open in such actions. The power to give relief under

Article 226 of the Constitution is a discretionary power.

Similar view has been reiterated in N.T. Veluswami

Thevar v. G. Raja Nainar, AIR 1959 SC 422; Municipal

Council, Khurai v. Kamal Kumar, AIR 1965 SC 1321;

Siliguri Municipality v. Amalendu Das, (1984) 2 SCC

436; S.T. Muthusami v. K. Natarajan, (1988) 1 SCC

572; Rajasthan SRTC v. Krishna Kant, 1995) 5 SCC 75;

Kerala SEB v. Kurien E. Kalathil, (2000) 6 SCC 293; A.

Venkatasubbaiah Naidu v. S. Chellappan, (2000) 7

SCC 695; L.L. Sudhakar Reddy v. State of A.P., (2001)

6 SCC 634; Shri Sant Sadguru Janardan Swami

(Moingiri Maharaj) Sahakari Dugdha Utpadak Sanstha

v. State of Maharashtra, (2001) 8 SCC 509; Pratap

Singh v. State of Haryana, (2002) 7 SCC 484 and GKN

Driveshafts (India) Ltd. v. ITO, (2003) 1 SCC 72.

20. In Harbanslal Sahnia v. Indian Oil Corpn. Ltd.,

(2003) 2 SCC 107, this Court held that the rule of

exclusion of writ jurisdiction by availability of alternative

remedy is a rule of discretion and not one of compulsion

and the Court must consider the pros and cons of the

case and then may interfere if it comes to the

conclusion that the petitioner seeks enforcement of any

of the fundamental rights; where there is failure of

principles of natural justice or where the orders or

proceedings are wholly without jurisdiction or the vires

of an Act is challenged.

21. In G. Veerappa Pillai v. Raman & Raman Ltd., AIR

1952 SC 192; CCE v. Dunlop India Ltd., (1985) 1 SCC

260; Ramendra Kishore Biswas v. State of Tripura,

(1999) 1 SCC 472; Shivgonda Anna Patil v. State of

Maharashtra, (1999) 3 SCC 5; C.A. Abraham v. ITO,

AIR 1961 SC 609; Titaghur Paper Mills Co. Ltd. v. State

of Orissa, (1983) 2 SCC 433; H.B. Gandhi v. Gopi Nath

and Sons, 1992 Supp (2) SCC 312; Whirlpool Corpn. v.

Registrar of Trade Marks, (1998) 8 SCC 1; Tin Plate

Co. of India Ltd. v. State of Bihar, (1998) 8 SCC 272;

Sheela Devi v. Jaspal Singh, (1999) 1 SCC 209 and

Punjab National Bank v. O.C. Krishnan, (2001) 6 SCC

569, this Court held that where hierarchy of appeals is

provided by the statute, party must exhaust the

statutory remedies before resorting to writ jurisdiction.

22. If, as was noted in Ram and Shyam Co. v. State of

Haryana, (1985) 3 SCC 267 the appeal is from "Caesar

to Caesar's wife" the existence of alternative remedy

would be a mirage and an exercise in futility. In the

instant case the writ petitioners had indicated the

reasons as to why they thought that the alternative

remedy would not be efficacious. Though the High

Court did not go into that plea relating to bias in detail,

yet it felt that alternative remedy would not be a bar to

entertain the writ petition. Since the High Court has

elaborately dealt with the question as to why the

statutory remedy available was not efficacious, it would

not be proper for this Court to consider the question

again. When the High Court had entertained a writ

petition notwithstanding existence of an alternative

remedy this Court while dealing with the matter in an

appeal should not permit the question to be raised

unless the High Court's reasoning for entertaining the

writ petition is found to be palpably unsound and

irrational. Similar view was expressed by this Court in

First ITO v. Short Bros. (P) Ltd., AIR 1967 SC 81 and

State of U.P. v. Indian Hume Pipe Co. Ltd., (1977) 2

SCC 724 That being the position, we do not consider

the High Court's judgment to be vulnerable on the

ground that alternative remedy was not availed. There

are two well-recognised exceptions to the doctrine of

exhaustion of statutory remedies. First is when the

proceedings are taken before the forum under a

provision of law which is ultra vires, it is open to a party

aggrieved thereby to move the High Court for quashing

the proceedings on the ground that they are

incompetent without a party being obliged to wait until

those proceedings run their full course. Secondly, the

doctrine has no application when the impugned order

has been made in violation of the principles of natural

justice. We may add that where the proceedings itself

are an abuse of process of law the High Court in an

appropriate case can entertain a writ petition."

52. Tested on the anvil of the aforesaid principles, the facts of the

present case clearly bring it within the well-recognized exceptions.

The petitioner was neither impleaded nor afforded any effective

opportunity of hearing in the proceedings before the State

Commission or before APTEL, despite the fact that the entire subject

matter of those proceedings pertained to power supplied by the

petitioner under duly executed Power Purchase Agreements.

53. The contention of the respondents that the petitioner ought to have

availed the appellate remedy under Section 125 of the Electricity Act,

2003 also does not merit acceptance. The said provision enables an

appeal to the Hon'ble Supreme Court by a "person aggrieved" by an

order of APTEL. In the present case, the petitioner was not a party to

the proceedings before APTEL, nor does the impugned judgment

record any finding or direction against it. In the absence of any lis

involving the petitioner or any adjudication affecting its rights, it

cannot be said that the petitioner was a "person aggrieved" so as to

invoke Section 125. A remedy which is illusory or not efficacious in

the given factual matrix cannot be pressed into service to non-suit

the petitioner. It is necessary here to notice Section 125 of the

Electricity Act, 2003, which reads as under:-

"Section 125. (Appeal to Supreme Court):

Any person aggrieved by any decision or order of the

Appellate Tribunal, may, file an appeal to the Supreme

Court within sixty days from the date of

communication of the decision or order of the

Appellate Tribunal, to him, on any one or more of the

grounds specified in section 100 of the Code of Civil

Procedure,1908:

Provided that the Supreme Court may, if it is satisfied

that the appellant was prevented by sufficient cause

from filing the appeal within the said period, allow it to

be filed within a further period not exceeding sixty

days."

54. Similarly, the remedy of review under Section 120(2)(f) before

APTEL cannot be said to be efficacious, as the petitioner was not on

record in the appellate proceedings and could not have sought

review of an order passed in a matter to which it was not a party. The

suggestion that the petitioner could approach the State Commission

under Section 86(1)(f) for adjudication of disputes is equally

misconceived, inasmuch as the impugned demand has already been

raised unilaterally on the basis of concluded proceedings, and the

petitioner cannot be relegated to initiate fresh adjudicatory

proceedings merely to contest an action of recovery of Rs. 153.55

crores.

55. It is also significant to note that the cause of action for the petitioner

arose only upon issuance of the demand notice dated 07.07.2016,

whereby, for the first time, a concrete and enforceable liability was

sought to be imposed. Prior to this, there was neither any

adjudication against the petitioner nor any indication that the

amounts received under the PPAs were liable to be refunded.

Therefore, the petitioner cannot be faulted for not challenging the

tariff order or the APTEL judgment, as no prejudice had been caused

to it at that stage.

56. The objection of the respondents, if accepted, would lead to a

situation where a party is saddled with serious civil consequences

without being heard, and is then denied access to judicial review on

the ground that it failed to challenge proceedings to which it was not

even a party. Such an interpretation would be wholly unjust and

contrary to the basic tenets of fairness embedded in Article 14 of the

Constitution.

57. In view of the foregoing discussion, this Court is of the considered

opinion that the present case falls squarely within the recognized

exceptions to the rule of alternative remedy, namely, violation of

principles of natural justice. The remedies suggested by the

respondents are neither efficacious nor available in the true sense to

the petitioner in the peculiar facts of the case. Accordingly, the

preliminary objection regarding maintainability is rejected, and the

writ petition is held to be maintainable for adjudication on merits.

58. The factual matrix, as borne out from the record, indicates that the

petitioner had entered into multiple Power Purchase Agreements

(PPAs) with CSPDCL during the period between 2011 and 2013 for

the supply of electricity, which were acted upon by both parties. The

petitioner supplied electricity and raised invoices in terms of the

agreed contractual mechanism, including a load factor-based tariff. It

is also not in dispute that CSPDCL accepted such supply and

effected payments during the relevant financial years. However, the

mere fact that payments were made at a particular point in time, or

that the transactions were not immediately disputed, cannot be

construed to mean that such transactions attained irrevocable finality

so as to be insulated from subsequent statutory scrutiny. It is

necessary to notice here the initial PPA dated 02-11-2011, which is

as under:-

POWER PURCHASE AGREEMENT

******* THIS AGREEMENT made on this 2nd day of

November 2011 between the Chhattisgarh state

Power Distribution Co. Ltd. (A Government of

Chhattisgarh undertaking, a successor company of

Chhattisgarh State Electricity Licensee, hereinafter

referred to as "Licensee") which expression shall

where the context so admits shall include its

successors in office and assigns of the one part and

M/s Jindal Steel & Power Limited (hereinafter referred

as Company) a company incorporated under the

companies Act 1956 having it's registered office at

O.P. Jindal Marg, Hisar - 125005, Haryana which

expression shall where the context so admits includes

its successors in business executors administrators,

legal representatives, and assigns of the other parts.

******* AND WHEREAS the company has set up the

Captive Generating Plant at Dongamahua, District

Raigarh and whereas the company has offered to sell

power on firm basis to the Licensee based on

anticipated availability, which has been accepted by

the Licensee vide letter No.02-02/ACE-I/2124 dt.

21.10.2011.

******* NOW This agreement witnesses and the

parties hereto have agreed as below:-

(1) (a) The Company has offered 150 MW firm power

on Round the Clock basis i.e. 00.00 hrs to 24.00 hrs,

hereinafter referred to as maximum contracted

quantum of power. The Company may reduce the

quantum of power supply to the extent of 20% of

maximum contracted power due to the reason which is

not under the control of company to supply maximum

contracted power. The minimum contracted power

shall be 120 MW, which is not less than 80% of

maximum contracted power. Load factor of company

having minimum contracted power less than 10 MW

will be calculated on monthly basis and having

minimum contracted power of 10 MW and above will

be calculated on weekly basis, during the term of this

agreement the Licensee has agreed to purchase

power generated by the company as per contracted

capacity subject to the provisions contained in the

Electricity Act, 2003 (herein after referred as 'the Act')

and rules made there under as per Chhattisgarh State

Electricity Regulatory Commission (CSERC) guideline

for power purchase and procurement and the terms

and conditions of power purchase by Licensee as

approved by CSERC from time to time.

(1) (b) The billing and scheduling modalities are as

under:-

(i) Agreed rate:- Rs.3.00 (Rs.Three) per kWh for RTC

power.

(ii) Merit order purchase:-

******* The power from the company will be purchased

in accordance to merit order purchase principle under

Section 32(2) of the Act. The State Load Despatch

Centre (SLDC) will carry out real time operation for

grid control and dispatch of electricity within the state

through secured and economic operation of the grid.

Both parties of this agreement shall abide themselves

by the instructions issued by the SLDC for maintaining

grid discipline. The SLDC may restrict power supply

from the company by backing down of the generation /

reduction in injection, if required, for secured and

economic operation of the State grid. In case of clear

instruction from SLDC, if, the company do not back

down their generation / reduce their injection to the

quantum as required by the SLDC, the company shall

be liable for the payment at the rate which may be

imposed on the licensee due to congestion in grid, or

panel UI charges or any other penalty in any form due

to over injection in the grid.

******* In case, supply of power by the company is

restricted by SLDC due to backing down of the

generation / reduction in injection, then that backing

down period of supply shall be considered as deemed

generation with respect to the scheduled quantum of

power and this deemed generation shall be taken into

account for calculation of load factor, subject to

certification of deemed generation from SLDC. The

quantum of deemed generation will be considered for

purpose of calculation of load factor only. Payment for

purchase of power shall be done on the basis of actual

energy injection.

(3) Scheduling:-

******* Company shall give a monthly schedule of

quantum of power intended to be supplied to the

Licensee for the ensuing month by 23rd of the month.

The scheduled quantum of power shall be either

maximum / minimum contracted power or between

minimum and maximum contracted power. In case the

monthly schedule for month is not submitted by the

company upto prescribed date, to SLDC under

intimation to the Licensee then the running schedule

shall be considered as schedule for ensuing month

also.

(4) Limit of Power Injection:-

(a) During off peak hour (00.00 to 18.00 hrs & 23.00

hrs to 24.00 hrs)

The company shall be permitted to inject up to 110%

of scheduled power for off peak hours i.e. 00.00 hrs to

18.00 hrs & 23.00 hours to 24.00 hours subject to the

technical limitation of equipment / line rating at

sending and receiving ends. However, payment @

Rs.1.00 (Rs.One only) per unit shall be made for the

energy injected over & above 110% of schedule

subject to condition that technical limitation to be

observed by Supplier. Units supplied upto permitted

injection rate of 110% will be taken as eligible units for

calculation of load factor and payment. Eligible units

shall mean the units (energy) supplied upto permitted

injection rate of 110% of schedule (schedule energy in

time block) during off peak hours.

(b) During peak hours (18.00 hrs to 23.00 hrs)

The company shall be permitted to inject upto 120% of

schedule for peak hours i.e. 18.00 hrs to 23.00 hrs

subject to the technical limitation of equipment / line

rating at sending and receiving ends. However,

payment @ Rs.1.00 (Rs.One only) per unit shall be

made for the energy injected over & above 120% of

schedule subject to condition that technical limitation

to be observed by supplier. Units supplied upto

permitted injection rate of 120% will be taken as

eligible units for calculation of load factor and

payment. Eligible units shall mean the units (energy)

supplied upto permitted injection rate of 120% of

schedule (schedule energy in time block) during peak

hours.

(5) Load Factor:-

(a) For the power supplied the load factor will be

calculated as below:-

LF = Number of eligible units supplied during a month /week Monthly schedule quantum of power×24 hrs.×No. of days in a month/week

Effective Rate in Rs. = 3.00×Actual LF % (monthly / weekly) 80%

In addition to the above, the following modalities for

accounting & calculation of LF shall be taken into

account :-

(i) Schedule power means quantum of power declared

by generator for the month which is equal to maximum

/ minimum contracted power or in between maximum

contracted power and minimum contracted power as

per clause 1(a).

(ii) Load Factor shall be calculated on monthly /

weekly basis as per clause 1(a).

(iii) The payment will be done on monthly basis.

(iv) The minimum effective rate shall be Rs.1.50 per

unit.

(6) Rate of Infirm power:-

Power supplied by the company after synchronization

with licensee's grid and before the COD (date of

commercial operation) of their power plant shall be

treated as infirm power and shall be paid @ Re.1/- per

unit. This rate of infirm power is applicable to the

power plant who enters PPA with licensee.

(7) The company having power purchase agreement

with licensee only for peak hours, the injected

between 17.30 hrs to 18.00 hrs and 23.00 hrs to 23.30

hrs shall be paid at a fixed rate of Rs 1.00 (Rs one

only) per unit. No payment will be made for any

injection prior to 17.30 hrs and after 23.30 hrs.

However, if the company is having contract /

agreement with other than licensee to supply of power

during off peak hours i.e. between 23.00 hrs to 18.00

hrs, next day, no payment will be made for the power

injected between 17.30 hrs to 18.00 hrs and 23.00 hrs

to 23.30 hrs.

(8) Notwithstanding to the above in case the CSERC

issues any other guidelines or specifies / modifies

terms and conditions of power purchase by the

licensee, the same shall be acceptable and binding on

both the parties.

(9) Company shall abide by the grid discipline as per

the provisions of State Electricity Grid Code and shall

maintain technical parameters regarding voltage,

frequency, power factor, within the limit as per prudent

utility practices, subject to the technical plant limits

and in Line with prudent utility practices, the company

shall operate and maintain the plant in such a manner,

so as not to have an adverse effect on the operation of

Licensee's Grid System. In case arry violation is noted

in abiding by Grid Discipline, the Licensee/SLDC may

isolate company's power supply from its grid system,

will out any liability on the licensee when system

security aspect of the State grid is involved, taking into

consideration the provision of State Grid Code.

(10) For power supplied to Licensee, joint

monthly/weekly reading or any other mechanism

(AMR) as approved by CSERC. in respect of power

exported to Licensee shall be laken by the authorized

representative of company and Licensee. Company

shall submit monthly invoice of energy sold to

Licensee, to Superintending Engineer (O&M)

CSPDCL at Raigarh under intimation to Chief

Engineer (Comm.) of Licensee. Reinur after each

monthly / weekly metar reading duly supported by the

documents.

(11) PAYMENT

Normally, licensee shall make the payment within 30

days from the date of receipt of bill in the office of the

Superintending Engineer(O&M) CSPDCL at Raigarh

under intimation to Chief Engineer(Comml) (licensee)

Raipur. However, in case the company desires

payment within fifteen days from the date of

presentation of bill, they shall allow 2% (Two percent)

rebate on the billed amount for supply of power

Further, in case payment is made after 30 days, a

delayed payment surcharge of 1.00% (one percent)

per month shall be paid by licensee. This delayed

payment surcharge shall be calculated on simple

interest basis on the number of days outstanding after

the said period. In the event of 15/30th day being a

holiday, the next working day shall be the due date for

the payment for this purpose.

(12) METERING

12.1 The metering point for power purchese arid billing

purpose for generating plants which are connected to

gnd shall be at point of injection at Licensee /

Chhattisgarh State Power Transmission Co. Ltd.

(herein after referred as CSPTCL) sub-station. The

provision related to metering shall be governed by the

Central Electricity Authority (Installation and Operation

of Meters) Regulation, 2006 as amended from time to

time.

12.2 The energy loss for dedicated lines, ie. from the

power plant to the point of injection at the sub-station

is to be borne by the company. The energy. loss from

the point of Injection onwards has to be acrne by the

licensee. In case billing and check meter installed at

metering point l.e. at sul station end becomes

defective, then the billing shall be done on the basis of

injection recorded at generating station end meter if

found functioning properly. However, in this case the

company shall have to bear line loss as approved by

CSERC.

12.3 Export/Import meters capable of recording active

as well as reactive power shall be installed at the

interconnection point. Reactive energy billing shall be

as per the orders of CSERC issued from time to time:

In case the CSERC approves reactive power billing on

the basis of ABT meter then the rates and other

modalities shall be as per CSERC's order.

12.4 The specifications of the Special Energy Meters

shall be as approved by The Licensee/CSPTCL.

12.5 The meter shall be jointly tested and inspected

and sealed on behalf of both the parties and shall not

be interfered by either party except in the presence of

the other party or its representatives.

12.6 Billing meters and the check meters (wherever

provided) shall be tested for accuracy once in a year

in presence of both the parties.

12.7 The meters shall be deemed to have working

satisfactorily if the errors as determined in the tests

are within the permissible limits as allowed in the

relevant IS specifications or I.E. rules, 1958 applicable

to high precision energy meters.

12.8 If during the periodical testing the billing meter is

found to have errors, beyond permissible limits but the

check meters (wherever provided) are found to have

error within the permissible limit, billing shall be

revised on the basis of generation / injection recorded

by the check meter. However, billing meter shall be

attended / replaced immediately and biling thereafter

shall be as per generation / injection recorded by new

tested biling meter.

12.8 If during the periodical testing both billing & check

meters (wherever provided) are found to have error

peyond permissible limits, the bill shall te revised by

applying correction factor to the injection registered by

the billing meter. The correction factor shall mean the

percentage of error between the R.S.S. meter & billing

meters.

12.10 If both the meters i.e. the billing meter and the

check meter (wherever provided) fall to record or if

any of the PT fuse is blown out, then the energy

accounting shall be done as per clause 12(2) or on a

mutually agreeable basis between licensee and the

company, in case the generator end meter also found

defective.

12.11 All the tests on the billing and check meters

(wherever provided) shall be conducted by the meter

relay testing staff of the Licensee/CSPTCL jointly with

the staff of company.

12.12 The licensee / CSPTCL will have access to the

meters and metering equipments at any point of time

for which company woule provide entry to the

Licensee/CSPTCL staff authorized "or this purpose.

12.13 All the data transfer facilities shall be provided

by the Company for monitoring, billing and other

accounting purpose.

(13) Dispute Resolution: in the event of any dispute

arising between the Company and the licensee as

regards to the interpretation of this agreement or any

other matter arising out of or in connection with this

agreement, such dispute or difference shall be

referred to the CSERC for settlement of the dispute.

(14) FORCE-MAJEURE AND OUTAGE:

14.1 Force Majeure: Any event which is beyond the

control of the agencies involved which they could not

foresee or with a reasonable amount of diligence

could not have foreseen or which could not be

prevented and which substantially affect the

performance by either of the agency such as but not

limited to:

(a) Acts of God, natural phenomena, including but not

limited to floods, droughts, earthquakes and

epidemics.

(b) Acts of any Government domestic or foreign,

including but not limited to war declared or

undeclared, hostilities priorities, quarantines,

embargoes,

(c) Riol or Civil Commotion

(d) Grid's failure not attributable to agencies involved

During force majeure period neither party shall be

entitled for claiming compensation for damages in the

event of force majeure.

14.2 Forced Outage: An outage of Generating Unit(s)

of the compary due to a fault or other reasons which

has not been planned shall be considered as forced

outage. The company supplying power to the licensee

shall be eligible to claim a maximum of 240 hours in a

year as forced outage period. There shall not be any

requirement to verify the forced outage of the power

plant of the company but company will intimate

licensee and SLDC immediately in writing (by fax)

regarding breakdown / forced cutage and probable

time to restore power supply and subsequently inform

wnen generator comes on the bus. The forced outage

period of maximum 240 hours in a year shall be

considered for LF calculation.

14.3 Planned Outage: The power plant of the

company shall be eligible for maximum 15 days in a

year for planned outage. The company shall declare

about their outage planning to the licensee and SLDC

well in advance at least 15 days from the date of

starting of planned outage. The planned outage period

shall be considered for L.F. calculation maximum to 15

days in a year.

14.4 The provision under clause 14.2 i.e. maximum

240 hours for force outage and urider clause 14.3 i.e.

maximum 15 days for planned outage in a year shall

be considered for the purpose of LF calculation only, if

company executes PPA with licensee for complete

one year.

14.5 In case the company falls to supply power to the

licensee for all the 12 months le. contracted period the

company will not be entitled to get benefit of

forced/planned outage for considering load factor

calculation purpose. In such case the benefit avalled

by the company in this caspect shall be refundable to

the licensee.

(15) DURATION:

This agreement shall remain operative for a period

upto 30 June 2012 from the fate of commencement of

the agreement. The date of commencement of this

agreement shall be 1" November 2011 and cease to

operate automatically without any notice after 30 June

2012.

Notwithstanding to the above, this agreement shall be

terminable during the currency period of the

agreement by either party by serving one month notice

or on the specific direction from CSERC.

(16) IDEMNITY: Company shall indemnify the

Licensee/CSPTCL from any all damages which may

occur to the Licensee/CSPTCL personnel duning the

operation of the interconnection

(17) INSPECTION BY LICENSEE/ CSPTCL,

Company shall allow and accord necessary facilities

for inspection at all times of its generation,

interconnection equipments and records by personnel

of the licenseal CSPTCL to ensure their proper

functioning. Records or such inspections shall be

signed by the authorized representatives of company

and licensee/CSPTCL.

(18) NOTICES- All notices shall be deemed to have

been served when sent ty registered post at the

address given below:

(1) The Managing Director.

Chhattisgarh State F'ower Distribution Company Ltd.,

Vidyut Sewa Bhawan, PO: Sunder Nagar

Danganiya, Raipur-492013.

(ii) The Executive Director

M/s. Jindal Steel & Power Ltd.

Post Box No.16. Kharsia Road

Raigarh-496001 Chhattisgarh

(19) LOAD MANAGEMENT: The licensee shall

endeavor to evacuate all the electricity offered by

Company as per this agreement. However, licensee/

CSPTCL may ask the company to temporarily curtait

or stop its electricity export to grid when necessary on

account of.

(a) Inspection/repair/maintenance to its transmission

network and associated equipments.

(b) Safety of equipment of the licensee/CSPTCL and

(c) Force-maieure conditions.

No compensation, whatsoever shall be paid by the

licensee / CSPTCL due to non-evacuation of the

power due to reasons stated above.

(20) NO WAIVER- No waiver of any of the terms &

conditions of this agreement shall ce binding or

effectual for any purpose, unless expressed in writing

and signed by the party giving the same and any such

waiver shall be effective only in the specific instance

and for the purpose given, No failure or delay on the

part of either party hereto in exercising any right,

power of privilege hereunder shall operate as a waiver

thereof.

(21) The terms and conditions (except rate) as

mentioned in the CSERC order dated 30.04.2010

passed in suo motu petition No.05 of 2010 & orrler

dated 15.07 2011 pessed in suo motu petition No.23

of 2011 are applicable for this PPA Any change in the

existing rates and terms and conditions of power

purchase of licensee, by CSERC will be made

applicable to this power purchase agreement In that

case supplementary PPA to incorporate such

changes! modification shall be executed between

licensee and company.

IN WITNESS WHEREOF parties through their

respective duly authorized Officer/ representative have

signed this agreement.

59. Paragraph (1)(a) of the said PPA clearly stipulates that "During the

term of this agreement, the licensee has agreed to purchase

power generated by the company as per contracted capacity

subject to the provisions contained in the Electricity Act, 2003,

(hereinafter referred as "the Act") and rules made there under

as per Chhattisgarh State Electricity Regulatory Commission

(CSERC) guideline for power purchase and procurement and the

terms and conditions of power purchase by Licensee as

approved by CSERC from time to time." So, the PPA was

governed under the terms of the Electricity Act, 2003 and guideline

of CSERC.

60. The CSERC in its suo motu Petition No. 05 of 2010, decided on 30-

04-2010, observed the Limits on over-injection that:-

"7. Limits on over-injection

******* The CSPDCL has requested to impose limits

on over-injection during peak hour supply of power

also. CSPDCL has submitted that, unrestricted

injection during peak hours is misutilized by some of

the generators to avail undue benefit from the market.

The CSPDCL has proposed to limit injection rate to

110% throughout the day. Chhattisgarh Vidhyut

Mandal Abhiyanta Sangh has requested the

Commission to investigate into the matter and then

proceed in this case. M/s JPL, M/s BMPL, CII, CUM,

UIA, BALCO and others had opposed this proposal of

CSPDCL and suggested to continue the existing

mechanism. CSPDCL submitted that over-injection by

the generators resulted into under-drawal by State,

and the average rate for Ul under-drawal for three

consecutive months was about Rs 2.50 per unit. This

position of the State requires attention. Although the

CSPDCL has not submitted any fact or analysis on

commercial Implications of such under-drawal, but

what we understand is that, if the average cost of

short-term power purchase of CSPDCL is more than

Rs 2.50 per unit in the respective three months (as

indicated by CSPDCL) then this would adversely

affect the commercial aspect of CSPDCL and

ultimately the end consumers of the State. The tariff

order 2009-10 emphasized to adopt merit order

purchase principle during power procurement. The

previous three tariff orders also directed the licensee

to adopt merit order purchase principle. A mechanism

was already in place, to prevent such situation, but

whether it has been followed or not is not known to us.

This may be examined in detall during truing up

exercise of CSPCL's petition.

******* However, the fact submitted by CSPDCL

cannot be overlooked. The loss on account of such

power procurement by the CSPDCL will affect the

consumers of the State. One more aspect needs to be

seen. The CSPDCL is a Ul pool member (regional

entity as per IEGC) for regional grid operations. The

Central commission has passed an order in suo-motu

petition No. 01/2010 "in the matter of rate of

congestion charge in real time operation in inter-State

transmission of electricity". para 2(5) of this order

says:

******* "It is important to note that at a frequency

greater than 50 Hz, the congestion would not be

caused by the overdrawing utility but by the utility

injecting power into the congested transmission

corridor and the congestion charge would instead be

applied on the Injecting utility. The detailed procedure

for levy of congestion charge is given in the

Congestion Charge Regulations. For the injecting

utility, the remedy would be to reduce injection through

reduction of generation in its control area.

******* Further 22 (c) of the referred CERC order says:

******* "at frequency below 50 Hz, congestion charge

would be levied for over-drawal in the importing

control area and at frequencies above 50 Hz,

congestion charge would be levied for under-drawal in

the exporting control area."

******* These two provisions of CERC relating to

congestion charges requires special attention. As

mentioned above, CSPDCL is a regional entity and UI

pool member for inter-State power transactions. The

power developers connected to the State grid are the

intra-State entities. Now, at a situation when there is

under-drawal position by CSPDCL, at frequency

above 50 Hz, if power injection (supply) is not

regulated then the CSPDCL is liable to pay congestion

charge at Rs 5.45 per kwh. This penal clause will

definitely have an adverse impact. This situation can

be avoided mainly by two methods. First, by adopting

merit order purchase principle and second by properly

controlling and regulating the Injection into the State

grid. The first method of regulating power supply by

adopting merit order purchase will be discussed in

coming paragraphs. So here we will examine the

second point i.e. injection limit only. There are two

modes of power purchase by CSPDCL, long-term and

short-term. Major portion of CSPDCL's power

purchase is through long-term route. The rate of

power purchase through long-term route is generally

less than short-term power purchase price. For

Central generating station, the IEGC and UI

Regulations specifies provisions for controlled

injection to avoid over-injection, misuse and gaming.

The CSPGCL supplies its full power to State and also

the tariff of State generating utility is less than rates of

short-term power purchase by CSPDCL. So the

supply from CSPGCL into the grid can not be

restricted except otherwise under an extreme grid

emergency conditions and for safety purpose. Hence,

among the entities which are connected to the State

grid, the remaining is the suppliers who supply power

through short-term route. According to the existing

terms and conditions of short-term power supply, for

off-peak hours there is an over-injection limit of 110%,

which may take care of the situation to some extent.

For off-peak hours supply, there is disincentive, if the

IPPs/CGPs continue supplying power beyond 110% of

the contracted quantum. For short-term peak hours

supply, there is no limit of injection. Of course a power

plant can supply power only upto its capacity of

generation, but here in the State, most of the power

plants who supply power to CSPDCL are CGPs which

have in house captive load. The supply to the grid can

vary (upto the capacity of generation), depending

upon drawal of their captive load. Some IPPs supply

power to the buyers outside the State, during peak

hours also. Such IPPs may vary the quantum of power

injection into the State grid as per their commercial

interest. If an IPP or CGP understates Its capacity and

enters into contract for less quantum of power than

what it can actually supply (for power supply during

the peak hours) it has no disincentive as it can inject

power to the extent to attain load factor of 80% and

get the full rate (price) for supply of power though It

may cause under-drawal by CSPDCL and congestion

in the system. The associations and some generators

have stated that there is TOD tariff for peak hours and

so there should not be any injection limit. On this

point, the Commission would like to clarify that TOD is

the tariff for supply to consumers during peak and

other hours and here we are concerned with quantum

of injection and drawal. In the order dated 18.04.09,

the over-injection limit was kept at 110% for peak

hours supply also, but on the request of the power

developers and keeping in view that CSPDCL faces

shortage of power specially during peak hours, this

restriction was removed by order dated 23.06.09.

******* In the light of above discussions, the

Commission comes into conclusion that there is a

need to impose over-injection limit for peak hour short-

term supply also. Summing up this issue, there are

three main reasons for imposing injection limit during

peak hour. First, commercial Implication to the State

because of congestion charges. Second, to avoid

possibility of misuse of the existing provisions for

unlimited injection (for short-term supply) during peak

hours. The third reason for imposing such limitation

shall be covered in succeeding paragraphs 9 below.

******* Now what shall be the limit of over-injection is

another important issue. Except a few, most of the

power plants in the State are of low capacity. So in a

general context, taking a liberal view the Commission

fixes an over-injection limit of 120% for peak hours

supply, however, for off-peak hours the injection limit

of 110% is maintained.

******* The over-injection limit has to be monitored on

real time basis by SLDC. The real time data may not

be available to SLDC in some cases. The Commission

is of the view that apart from monitoring injection

during real time operations, there should be a

disincentive if the suppliers continue supplying power

over the specified limit. For power supply during off-

peak hours, the rate of power supply beyond the

specified limits, was fixed at Re 1/- per unit which is

maintained during 2010-11 also. This provision was

incorporated with a view to discourage injection

beyond the permissible limits and the same shall be

continued for the year 2010-11. This rate of Re.1/- per

unit shall also be applicable for supply during peak

hour beyond the permissible limit."

61. After having considered all the surrounding circumstances and the

nature of the transaction and supply of electricity, the Commission

decided the base rate, effective rate, minimum effective rate during

the off-peak hours and peak hours, which is as under:-

"18. In view of the above, the Commission decides

as follows:

(1) The maximum base rate for power supply at 80%

and above load factor of the schedule power shall be

Rs. 3.10 per kwh, which is 5% more as compare to the

maximum base rate for the year 2009-10.

(2) The effective rate for power supply below 80% load

factor will be calculated as follows:

Effective Rate in Rs. - Agreed base rate XLFN 80% The agreed base rate is the rate agreed between the

supplier and CSPDCL, which may be equal to or less

than the maximum base rate of Rs. 3.10 per kwh.

(3) The minimum effective rate shall be Rs 1.50 per

unit.

(4) The rate for power supply during peak hours i.e.

18:00 hrs. to 23:00 hrs. shall be 5% more than the

agreed base rate /effective rate, as the case may be.

(5) Rate for power supplied beyond over-injection limit:

Off peak hour supply: The rate for excess supply, i.e.

for over-injection over and above 110% of scheduled

energy in time block, Re 1/- per KWh.

Peak hour supply: The rate for excess supply, l.e. for

over-injection over and above 120% of scheduled

energy in time block, Re. 1/- per Kwh.

(6) The rate of infirm power, i.e. power supplied by any

CGP/IPP, before the date of COD of their power plant

shall be Rs. 1/- per unit. This rate of infirm power is

applicable to the power plants who may enter PPA

with CSPDCL."

62. In the case of "Power Grid Corporation of India Ltd." (supra), it has

been considered that:

"11.4. Further, APTEL had already addressed a similar

question in Nuclear Power Corpn. of India Ltd. v. CERC

wherein it was held as under: (SCC OnLine APTEL

para 10)

"10. ... 10.5. Accordingly, in absence of specific

provisions in the Sharing Regulations/Tariff

Regulations, 2014 to deal with the situation under

question the Central Commission through exercise

of its regulatory powers has prescribed a principle for

sharing of transmission charges of the Transmission

System of Respondent 2 in the impugned order.

Thus, it is observed that by way of exercising its

regulatory power by a way of judicial order(s) the

Central Commission has laid down the principles of

payment of transmission charges in such an

eventuality. However, it is felt that the Central

Commission in the impugned order has abruptly

concluded the payment liability on the appellant just

by referring to its earlier orders and not establishing

the linkage with the present case explicitly. This

Tribunal would like to clarify the same."

Respondent 1 submitted that APTEL had taken a

peculiar view of the matter. Although CERC exercises

twin powers of adjudication and regulation, yet the f fact

remains that the regulatory power cannot be exercised

by way of a judicial order. Since APTEL took a contrary

view on the issues at hand, Respondent 1 was of the

view that no useful purpose would be served by filing an

appeal under Section 111.

12. Having heard the parties, the High Court affirmed

that despite the availability of an alternative remedy, a

writ petition can be entertained if any of the factors

mentioned in Whirlpool are satisfied. Since Respondent

1 had challenged the constitutionality of the orders of

CERC dated 21-1-2020 and 27-1-2020, respectively, on

the grounds that the power exercised by CERC was

beyond the powers vested in it as per the relevant

regulation and that the relief granted to the appellant

was beyond the reliefs prayed for, the High Court was

of the opinion that the principles of natural justice were

breached. Therefore, despite the availability of an

alternative remedy, the writ petition deserved to be

entertained. Having held so, the High Court admitted

the writ petition for hearing on merits.

67. In view of the aforesaid exposition of law, we find

that this Court's observations in Whirlpool are of no

avail to Respondent 1 as the present matter falls in

none of the cases enumerated therein. Therefore, there

was no occasion for the High Court to admit the writ

petition of Respondent 1.

68. For all the foregoing reasons, we have reached the

conclusion that the High Court committed an egregious

error in passing the impugned judgment. We are left

with no other option but to set aside the impugned

judgment and order dated 25-2-2021 passed by the

High Court and dismiss both the writ petitions. In the

result, the appeals succeed and are hereby allowed."

63. In a regulated sector such as electricity, all commercial arrangements

remain subject to statutory tariff determination and regulatory

oversight under the Electricity Act, 2003. Reliance has been placed

on the judgment of "Haryana Power Purchase Centre v. Sasan

Power Ltd. and Others", 2023 SCC OnLine SC 577, wherein it has

been held that:-

"95. We are of the view that what the parties

contemplated under Article 13.2 was that change in

law must be viewed through the specific provisions of

clauses (a) and (b). In other words, a change in law

may occur during the period of construction. Then it is

to be treated as falling under Article 13.2 (a). A

change in law may occur during the period of its

operation. It would then appear to be dealt with under

clause (b). If a change in law takes place during the

period of construction then its impact is to be

measured with reference to the capital cost of the

project. The word "capital cost" understandably has

been defined in PPA. A formula has been engrafted.

The formula contemplates that for every

increase/decrease of each Rs 50 crores in the capital

cost as a result of the change in law, the

increase/decrease in the non-escalable capacity

charges is to be 0.267% of the non-escalable capacity

charges. No doubt, this is if the seller provides to the

procurers documentary proof of such

increase/decrease in establishing the impact of such

change.

96. In other words, the effect of change in law during

the construction period is captured by Article 13.2(a).

We must understand that this is a meticulously

thought through contract which emerged after a long

rigorous process. Parties were clear about how the

change in law had to be compensated and

methodology has been set out clearly. Therefore, any

appeal made to the general part in Article 13.2 which

speaks about the affected party being restored to the

same economic condition as if such change in law had

not occurred cannot result in departing from the

specific formula which has been set in place. This

meaning is inevitable from the words "to the extent

contemplated in this Article 13", which precedes the

general words."

64. The proposition emerging from paragraph 95 of "Haryana Power

Purchase Centre" (supra), that regulatory authorities cannot

override contractual terms, is not of universal application and is

confined to the specific context of tariff discovered through

competitive bidding under Section 63 of the Electricity Act, 2003. This

position is qualified by earlier decisions of the Hon'ble Supreme

Court, which have consistently held that contractual arrangements in

the electricity sector are subservient to statutory regulation and public

interest. In All India Power Engineer Federation v. Sasan Power

Ltd., (2017) 1 SCC 487, the Hon'ble Supreme Court categorically

held that even contractual waivers or arrangements cannot be

enforced if they are contrary to public interest or affect tariff

determination, emphasizing the primacy of Sections 61 to 63 of the

Act. Further, in "Energy Watchdog v. Central Electricity

Regulatory Commission", (2017) 14 SCC 80, the Hon'ble Supreme

Court has reiterated that tariff fixation is a statutory function of the

Regulatory Commission and cannot be left to private agreements

between parties, thereby underscoring that PPAs operate within, and

are subject to, the regulatory framework particularly in matters

affecting tariff and public interest. These decisions clearly establish

that tariff fixation is not a matter of private contract alone but is

governed by statutory regulation.

65. In the case of "Adani Power Maharashtra Ltd." (supra), the Hon'ble

Supreme Court has observed that:

"119. In this respect, we may refer to the following

observations of this Court in Reliance Infrastructure Ltd.

v. State of Maharashtra18: (SCC pp. 376-77, paras 38-

39)

"38. MERC is an expert body which is entrusted with

the duty and function to frame regulations, including

the terms and conditions for the determination of

tariff. The Court, while exercising its power of judicial

review, can step in where a case of manifest

unreasonableness or arbitrariness is made out.

Similarly, where the delegate of the legislature has

failed to follow statutory procedures or to take into

account factors which it is mandated by the statute

to consider or has founded its determination of tariffs

on extraneous considerations, the Court in the

exercise of its power of judicial review will ensure

that the statute is not breached. However, it is no

part of the function of the Court to substitute its own

determination for a determination which was made

by an expert body after due consideration of material

circumstances.

39. In Assn. of Industrial Electricity Users v. State of

A.P.19 a three-Judge Bench of this Court dealt with

the fixation of tariffs and held thus: (SCC p. 717,

para 11)

'11. We also agree with the High Court20 that the

judicial review in a matter with regard to fixation

of tariff has not to be as that of an appellate

authority in exercise of its jurisdiction under

Article 226 of the Constitution. All that the High

Court has to be satisfied with is that the

Commission has followed the proper procedure

and unless it can be demonstrated that its

decision is on the face of it arbitrary or illegal or

contrary to the Act, the court will not interfere.

Fixing a tariff and providing for cross-subsidy is

essentially a matter of policy and normally a court

would refrain from interfering with a policy

decision unless the power exercised is arbitrary

or ex facie bad in law."

66. In the case of "Sasan Power Ltd. (2017)" (supra), the Hon'ble

Supreme Court has held that:-

"21. Regard being had to the aforesaid decisions, it is

clear that when waiver is spoken of in the realm of

contract, Section 63 of the Indian Contract Act, 1872

governs. But it is important to note that waiver is an

intentional relinquishment of a known right, and that,

therefore, unless there is a clear intention to relinquish

a right that is fully known to a party, a party cannot be

said to waive it. But the matter does not end here. It is

also clear that if any element of public interest is

involved and a waiver takes place by one of the

parties to an agreement, such waiver will not be given

effect to if it is contrary to such public interest. This is

clear from a reading of the following authorities.

22. In Lachoo Mal v. Radhey Shyam, (1971) 1 SCC

619, it was held:-

"The general principle is that everyone has a right to

waive and to agree to waive the advantage of a law or

rule made solely for the benefit and protection of the

individual in his private capacity which may be

dispensed with without infringing any public right or

public policy. Thus the maxim which sanctions the

non-observance of the statutory provision is cuilibet

licet renuntiare juri pro se introducto. (See Maxwell on

Interpretation of Statutes, Eleventh Edn., pp. 375 and

376). If there is any express prohibition against

contracting out of a statute in it then no question can

arise of anyone entering into a contract which is so

prohibited but where there is no such prohibition it will

have to be seen whether an Act is intended to have a

more extensive operation as a matter of public policy."

23. In Indira Bai v. Nand Kishore, (1990) 4 SCC 668, it

was held:-

"The test to determine the nature of interest, namely,

private or public is whether the right which is

renunciated is the right of party alone or of the public

also in the sense that the general welfare of the

society is involved. If the answer is latter then it may

be difficult to put estoppel as a defence. But if it is right

of party alone then it is capable of being abnegated

either in writing or by conduct."

24. In Krishna Bahadur v. Purna Theatre, (2004) 8

SCC 229, it was held:

"9. The principle of waiver although is akin to the

principle of estoppel; the difference between the two,

however, is that whereas estoppel is not a cause of

action; it is a rule of evidence; waiver is contractual

and may constitute a cause of action; it is an

agreement between the parties and a party fully

knowing of its rights has agreed not to assert a right

for a consideration.

10. A right can be waived by the party for whose

benefit certain requirements or conditions had been

provided for by a statute subject to the condition that

no public interest is involved therein. Whenever waiver

is pleaded it is for the party pleading the same to show

that an agreement waiving the right in consideration of

some compromise came into being. Statutory right,

however, may also be waived by his conduct."

25. It is thus clear that if there is any element of public

interest involved, the court steps in to thwart any

waiver which may be contrary to such public interest.

26. On the facts of this case, it is clear that the

moment electricity tariff gets affected, the consumer

interest comes in and public interest gets affected.

This is in fact statutorily recognized by the Electricity

Act in Sections 61 to 63 thereof. Under Section 61, the

appropriate commission, when it specifies terms and

conditions for determination of tariff, is to be guided

inter alia by the safeguarding of the consumer interest

and the recovery of the cost of electricity in a

reasonable manner. For this purpose, factors that

encourage competition, efficiency and good

performance are also to be heeded. Under Section 62

of the Act, the appropriate commission is to determine

such tariff in accordance with the principles contained

in Section 61. The present case, however, is covered

by Section 63, which begins with a non obstante

clause stating that notwithstanding anything contained

in Section 62, the appropriate commission shall adopt

the tariff if such tariff has been determined through a

transparent process of bidding in accordance with the

guidelines issued by the Central Government. The

guidelines dated 19.1.2005 issued by the Central

Government under Section 63 make it clear that such

guidelines are framed with the following objectives in

mind:

"These guidelines have been framed under the above

provisions of section 63 of the Act. The specific

objectives of these guidelines are as follows:

1) Promote competitive procurement of electricity by

distribution licensees;

2) Facilitate transparency and fairness in procurement

processes;

3) Facilitate reduction of information asymmetries for

various bidders;

4) Protect consumer interests by facilitating

competitive conditions in procurement of electricity;

5) Enhance standardization and reduce ambiguity and

hence time for materialization of projects;

6) Provide flexibility to suppliers on internal operations

while ensuring certainty on availability of power and

tariffs for buyers.

Clause 2.3 of the said guidelines reads as follows:

"2.3. Unless explicitly specified in these guidelines, the

provisions of these guidelines shall be binding on the

procurer. The process to be adopted in event of any

deviation proposed from these guidelines is specified

later in these guidelines under para 5.16."

27. Paragraph 4 of the aforesaid guidelines relates to

tariff structure and paragraph 4.11 in particular, which

relates to energy charges, is as follows:-

"4.11 Where applicable, the energy charges payable

during the operation of the contract shall be related on

the base energy charges specified in the bid with

suitable provision for escalation. In case the bidder

provides firm energy charge rates for each of the

years of the contract term, the same shall be permitted

in the tariffs."

28. Para 5.4 then speaks of a model power purchase

agreement proposed to be entered into with the seller

of electricity as follows:-

"(ii) Model PPA proposed to be entered into with the

seller of electricity. The PPA shall include necessary

details on:

(a) Risk allocation between parties;

(b)   Technical     requirements   on    minimum    load

conditions;

(c) Assured offtake levels;

(d) Force majeure clauses as per industry standards;

(e) Lead times for scheduling of power;

(f) Default conditions and cure thereof, and penalties;

(g) Payment security proposed to be offered by the

procurer."

29. Paragraph 5.16 then goes on to state:-

"Deviation from process defined in the guidelines

5.16 In case there is any deviation from these

guidelines, the same shall be with the prior approval of

the Appropriate Commission. The Appropriate

Commission shall decide on the modifications to the

bid documents within a reasonable time not exceeding

90 days."

30. A perusal of the CERC tariff adoption order in the

present case dated 17.10.2007 makes it clear that the

tariff is adopted by the Commission only because the

competitive bidding process which has been

undertaken is in accordance with the guidelines so

issued.

31. All this would make it clear that even if a waiver is

claimed of some of the provisions of the PPA, such

waiver, if it affects tariffs that are ultimately payable by

the consumer, would necessarily affect public interest

and would have to pass muster of the Commission

under Sections 61 to 63 of the Electricity Act. This is

for the reason that what is adopted by the Commission

under Section 63 is only a tariff obtained by

competitive bidding in conformity with guidelines

issued. If at any subsequent point of time such tariff is

increased, which increase is outside the four corners

of the PPA, even in cases covered by Section 63, the

legislative intent and the language of Sections 61 and

62 make it clear that the Commission alone can

accept such amended tariff as it would impact

consumer interest and therefore public interest."

67. Thus, the ratio in Sasan Power (2023) cannot be read as excluding

regulatory intervention altogether; rather, it is confined to situations

where the statute expressly preserves the sanctity of competitively

discovered tariff. In cases falling under Section 62, or involving

issues of grid discipline, public interest, or statutory compliance, the

regulatory authorities retain full jurisdiction, and contractual terms

cannot be enforced in derogation of statutory mandate.

68. It is equally borne out that CSPDCL initiated tariff and true-up

proceedings before the State Commission in 2014, wherein the

Commission, upon detailed examination of load curve data, injection

patterns, and operational parameters, recorded a categorical finding

that the power supplied by the petitioner was non-firm, intermittent,

and unstable in nature. Based on such technical evaluation, the

Commission determined that such power could not be equated with

firm power and accordingly restricted the tariff to a minimum base

rate of Rs. 1.50 per kWh. The said findings were subjected to review

and thereafter carried in appeal before the Appellate Tribunal for

Electricity (APTEL), which, by its judgment dated 26.05.2016,

affirmed the conclusions of the State Commission. These findings,

having attained finality within the statutory framework, are binding

and cannot be lightly interfered.

69. The principal contention advanced by the petitioner is that it was not

impleaded as a party to the tariff or appellate proceedings and was

not afforded any opportunity of hearing before imposing liability, and

therefore, the subsequent demand raised against it is vitiated for

violation of principles of natural justice. While the doctrine of audi

alteram partem is indeed a fundamental facet of fair procedure, its

application must be understood in the context of the nature of the

proceedings in question. The tariff determination and true-up

exercise undertaken by the State Commission are legislative or

quasi-legislative in character, carried out in accordance with the

Conduct of Business Regulations, which contemplate issuance of

public notices and stakeholder participation rather than individual

impleadment of every entity that may be indirectly affected. The

record reflects that public notices were duly issued, proceedings

were conducted transparently, and representatives of industry,

including that of the petitioner, had participated at various stages. In

such circumstances, it cannot be said that the petitioner was wholly

unaware of or excluded from the regulatory process.

70. Moreover, the impugned demand does not arise in isolation but is a

direct consequence of the tariff determination made by the State

Commission and affirmed by APTEL. The statutory scheme under

Sections 61 and 62 of the Electricity Act, 2003, vests exclusive

authority in the Commission to determine tariffs, and such

determination overrides any contractual arrangement to the contrary.

It is well settled that in matters of tariff, the regulatory framework

prevails over private agreements, as the same is guided by

considerations of public interest and consumer protection. Therefore,

even if the PPAs provided for a particular pricing mechanism, the

same would remain subject to the tariff ultimately determined by the

Commission.

71. The submission that the tariff orders did not specifically direct

recovery from the petitioner does not advance the case of the

petitioner. Once it is found, in accordance with law, that the tariff

applicable to the supply in question is lower than what has been paid,

the consequence of adjustment or recovery necessarily follows under

Section 62(6) of the Act, which mandates refund of excess tariff

recovered by a generating company. The absence of an express

direction against the petitioner in the tariff order does not negate the

statutory obligation arising therefrom. The demand raised by

CSPDCL is thus traceable to and supported by the binding tariff

orders and appellate judgment.

72. The argument that concluded transactions cannot be reopened is

also devoid of merit in the present context. The true-up exercise

undertaken by the Commission precisely envisages the adjustment

of past transactions based on actual data and a prudence check.

Such retrospective correction is an integral feature of tariff regulation

and is intended to balance the interests of utilities and consumers.

Accepting the petitioner's contention would defeat the very purpose

of the statutory mechanism and permit retention of amounts found to

be in excess of the permissible tariff, thereby resulting in unjust

enrichment. In this regard, the judgment of Hon'ble Supreme Court in

the case of "Indian Council for Enviro-Legal Action v. Union of

India" 2011 (8) SCC 161 is relevant, in which it has been held that:

"151. Unjust enrichment has been defined as:

"Unjust enrichment. A benefit obtained from another,

not intended as a gift and not legally justifiable, for

which the beneficiary must make restitution or

recompense."

See Black's Law Dictionary, 8th Edn. (Bryan A. Garner)

at p. 1573. A claim for unjust enrichment arises where

there has been an "unjust retention of a benefit to the

loss of another, or the retention of money or property of

another against the fundamental principles of justice or

equity and good conscience".

152. "Unjust enrichment" has been defined by the court

as the unjust retention of a benefit to the loss of

another, or the retention of money or property of

another against the fundamental principles of justice or

equity and good conscience. A person is enriched if he

has received a benefit, and he is unjustly enriched if

retention of the benefit would be unjust. Unjust

enrichment of a person occurs when he has and retains

money or benefits which in justice and equity belong to

another.

153. Unjust enrichment is "the unjust retention of a

benefit to the loss of another, or the retention of money

or property of another against the fundamental

principles of justice or equity and good conscience". A

defendant may be liable "even when the defendant

retaining the benefit is not a wrongdoer" and "even

though he may have received [it] honestly in the first

instance". (Schock v. Nash, A 2d, 232-33.)

154. Unjust enrichment occurs when the defendant

wrongfully secures a benefit or passively receives a

benefit which would be unconscionable to retain. In the

leading case of Fibrosa Spolka Akcyjna v. Fairbairn

Lawson Combe Barbour Ltd 62, Lord Wright stated the

principle thus: (AC p. 61)

"... [A]ny civilised system of law is bound to provide

remedies for cases of what has been called unjust

enrichment or unjust benefit, that is to prevent a man

from retaining the money of or some benefit derived

from another which it is against conscience that he

should keep. Such remedies in English law are

generically different from remedies in contract or in

tort, and are now recognised to fall within a third

category of the common law which has been called

quasi-contract or restitution."

155. Lord Denning also stated in Nelson v. Larholt63 as

under: (KB p. 343)

"... It is no longer appropriate, however, to draw a

distinction between law and equity. Principles have

now to be stated in the light of their combined effect.

Nor is it necessary to canvass the niceties of the old

forms of action. Remedies now depend on the

substance of the right, not on whether they can be

fitted into a particular framework. The right here is

not peculiar to equity or contract or tort, but falls

naturally within the important category of cases

where the court orders restitution, if the justice of the

case so requires."

73. Insofar as the reliance placed by the petitioner on principles of

natural justice is concerned, it must be noted that no prejudice, in the

legal sense, has been demonstrated. The characterization of the

power as non-firm is based on objective technical data relating to

injection patterns, which have been consistently recorded by the

State Commission and affirmed by APTEL. The petitioner has not

placed any material before this Court to dislodge these findings or to

demonstrate that the tariff applied by it was in conformity with the

statutory determination. In the absence of any substantive challenge

to the foundational findings, the plea of violation of natural justice

cannot be invoked as a mere technical ground to invalidate

consequential action.

74. The contention that the dispute involves complex technical issues

further weighs with this Court in declining interference. The

determination of the nature of power supply, its impact on grid

stability, and the appropriate tariff are matters falling within the

domain of expert regulatory bodies. The State Commission and

APTEL, being specialized forums, have examined these aspects in

detail. It is not the function of this Court, in exercise of writ

jurisdiction, to reappreciate such technical findings or sit in appeal

over the conclusions reached by expert bodies.

75. The denial of No Objection Certificate (NOC) and the consequent

rejection of the petitioner's applications for Short Term Open Access

(STOA) by Respondent No. 3 also do not warrant interference. A

scrutiny of the statutory scheme and the material placed on record

would demonstrate that such action is rooted not merely in the

existence of alleged outstanding dues, but in the larger and

paramount consideration of maintaining grid discipline and ensuring

secure, reliable, and economic operation of the power system within

the State. Under Section 31 of the Electricity Act, 2003, the State

Load Dispatch Centre (SLDC) is constituted as the apex body for

integrated operation of the power system within the State, and under

Section 32, it is entrusted with critical functions including scheduling

and dispatch of electricity, monitoring grid operations, keeping

accounts of electricity transmitted, and exercising supervision and

control over intra-State transmission. These functions are not merely

administrative but are technical and operational in nature, requiring

continuous real-time assessment of grid conditions. Further, Section

33 confers wide powers upon the SLDC to issue binding directions to

generating companies, licensees, and other participants in the grid to

ensure stability and discipline. Compliance with such directions is

mandatory, and any deviation has the potential to jeopardize the

entire grid system.

76. In the present case, the record reveals that the petitioner had a

consistent history of injecting power in a fluctuating and

unpredictable manner, with significant variations in generation

ranging from negligible or zero output to sudden high injections. Such

erratic patterns of supply have been specifically noted by the SLDC

in multiple communications issued over a period of time, wherein the

petitioner was repeatedly called upon to adhere to scheduled

generation and maintain grid discipline. These deviations were not

isolated or sporadic but constituted a recurring operational concern,

affecting load management and requiring compensatory adjustments

by the system operator. The consequences of such non-firm and

unstable injection are far-reaching. The grid operates on a delicate

balance between supply and demand, and any significant deviation

can result in overdrawal or underdrawal situations, frequency

fluctuations, and potential grid disturbances. These, in turn, may

attract penalties under applicable regulations and may even pose

risks to the stability and integrity of the transmission system. It is in

this backdrop that the State Commission, in its tariff order, also

recognized the adverse impact of non-firm power on grid operations

and issued directions to discourage such practices.

77. In light of these statutory responsibilities and technical

considerations, the SLDC is duty-bound to exercise caution while

granting open access to any entity. The grant of STOA is not a

matter of right but is subject to the fulfilment of regulatory conditions,

including adherence to grid discipline, technical feasibility, and

system security. Where an entity has demonstrated a pattern of non-

compliance with scheduling norms or has been found to inject power

in a manner detrimental to grid stability, the SLDC would be justified

in withholding or regulating access in the larger public interest.

78. The contention of the petitioner that the denial of NOC was solely on

account of the alleged outstanding dues does not find full support in

the record. While the existence of dues may have been one of the

factors considered, it is evident that the decision was also influenced

by the petitioner's past conduct in relation to grid operations and its

inability to ensure firm and reliable supply. The communications

issued by Respondent No. 3 reflect concerns regarding operational

discipline, compliance with scheduling instructions, and the potential

risk posed to the grid. Therefore, the decision cannot be

characterized as arbitrary or extraneous.

79. It is also pertinent to note that the statutory framework casts a

responsibility upon the SLDC to act in a preventive manner rather

than a reactive one. The objective is to ensure that grid disturbances

are avoided, rather than remedied after occurrence. In such a

scenario, the SLDC is entitled to take into account the past

performance and operational behaviour of an applicant while

considering the grant of open access. The petitioner, having been

repeatedly cautioned and having failed to demonstrate consistent

compliance, cannot claim an indefeasible right to open access.

Judicial review in such matters is necessarily limited. The decision to

grant or deny open access involves technical assessment,

operational expertise, and real-time considerations, which fall within

the domain of specialized authorities. Unless the decision is shown to

be mala fide, perverse, or in clear violation of statutory provisions,

this Court would be slow to interfere. In the present case, no such

infirmity has been demonstrated.

80. The another submission raised by learned counsel for the petitioners

that with respect to other power generators, who are similarly

situated, no order has been passed by the respondents. By

submitting the said contention, the petitioners are claiming negative

parity, which cannot be claimed, as has been held by the Hon'ble

Supreme Court in the case of "R. Muthukumar and others" (supra),

in which in para 28 and 29, it has been held that:

"28. A principle, axiomatic in this country's constitutional

lore is that there is no negative equality. In other words,

if there has been a benefit or advantage conferred on

one or a set of people, without legal basis or

justification, that benefit cannot multiply, or be relied

upon as a principle of parity or equality. In Basawaraj v.

Special Land Acquisition Officer, this court ruled that:

"8. It is a settled legal proposition that Article 14 of

the Constitution is not meant to perpetuate illegality

or fraud, even by extending the wrong decisions

made in other cases. The said provision does not

envisage negative equality but has only a positive

aspect. Thus, if some other similarly situated

persons have been granted some relief/benefit

inadvertently or by mistake, such an order does not

confer any legal right on others to get the same

relief as well. If a wrong is committed in an earlier

case, it cannot be perpetuated."

29. Other decisions have enunciated or applied this

principle (Ref: Chandigarh Admn. v. Jagjit Singh, Anand

Buttons Ltd. v. State of Haryana, K.K. Bhalla v. State of

M.P.17; Fuljit Kaur v. State of Punjab, and Chaman Lal

v. State of Punjab). Recently, in The State of Odisha v.

Anup Kumar Senapati this court observed as follows:

"If an illegality and irregularity has been committed in

favour of an individual or a group of individuals or a

wrong order has been passed by a judicial forum,

others cannot invoke the jurisdiction of the higher or

superior court for repeating or multiplying the same

irregularity or illegality or for passing a similarly

wrong order. A wrong order/decision in favour of any

particular party does not entitle any other party to

claim benefits on the basis of the wrong decision."

81. Accordingly, this Court is of the considered view that the denial of

NOC and rejection of STOA applications by Respondent No. 3 is in

consonance with the statutory mandate under Sections 32 and 33 of

the Electricity Act, 2003, and is justified on grounds of maintaining

grid discipline, system security, and public interest. The action,

therefore, cannot be termed as arbitrary, unreasonable, or without

authority of law.

82. The plea based on the doctrine of approbation and reprobation is

equally untenable. CSPDCL, being a distribution licensee, is bound

to act in accordance with statutory tariff orders and cannot be

estopped from enforcing the same merely because payments were

earlier made under a different understanding. The doctrine of

estoppel cannot operate against a statute, nor can it be invoked to

defeat public interest embedded in tariff regulation. The recovery

sought is not in the nature of repudiation of contract, but in

furtherance of statutory compliance.

83. Having regard to the totality of circumstances, this Court is of the

considered opinion that the demand notice dated 07.07.2016 is not

without jurisdiction, but is a consequential action flowing from binding

tariff orders and the judgment of APTEL. The petitioner has failed to

establish any ground warranting interference under Article 226 of the

Constitution. The issues raised pertain to matters of tariff

determination, technical evaluation, and regulatory policy, which

have already been adjudicated by competent statutory forums.

84. Accordingly, this Court finds no merit in the writ petition. The same is

liable to be and is hereby dismissed. No order as to costs.

85. Interim order granted earlier also stands vacated.

Sd/-

(Ravindra Kumar Agrawal) Judge ved

HEAD NOTE

The principle that regulatory authorities cannot

override contractual terms is not of universal application.

Tariff fixation is a statutory function of the Regulatory

Commission and cannot be left to private agreements

between the parties; it is subject to the regulatory

framework, particularly in matters affecting tariff and

public interest.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Media

 
 
Latestlaws Newsletter