Citation : 2026 Latest Caselaw 1054 Chatt
Judgement Date : 27 March, 2026
1
2026:CGHC:14472-DB
NAFR
Digitally
signed by
BABLU
BABLU RAJENDRA
HIGH COURT OF CHHATTISGARH AT BILASPUR
RAJENDRA BHANARKAR
BHANARKAR Date:
2026.03.30
10:59:27
+0530
WPC No. 1251 of 2026
M/S RKTC-PHIL (JV) Registered Office HIG 07, Sector- 02, Behind
Madan Complex, Shankar, Nagar, Raipur, Chhattisgarh Through Rohit
Kumar Sinha, The Assistant Account Manager And Authorized Signatory
S/o Late S.K. Sinha, Aged About 40 Years R/o MIG-30 R.P. Nagar,
Housing Board Colony, Phase -II Niharika, Korba Chhattisgarh
... Petitioner
versus
1 - Coal India Limited Head Office Coal Bhawan, Premise No. 04, MAR
Plot No. AF III, Action Area, 1A New Town, Rajarhat, Kolkata , -700156
2 - South Eastern Coal Field Limited, Through General Manager
(Civil/HOD), S.E.C.L. Seepat Road, Bilaspur (C.G.) -495006
3 - The Chairman - Cum Managing Director, S.E.C.L. Seepat Road,
Bilaspur (C.G.) - 495006
... Respondents
For Petitioner : Mr.Bhaskar Payasi, Advocate For Respondents : Ms.Fouzia Mirza, Senior Advocate assisted by Mr.Vaibhav Shukla, Advocate
Hon'ble Mr. Ramesh Sinha, Chief Justice Hon'ble Mr. Ravindra Kumar Agrawal, Judge
Order on Board
Per Ramesh Sinha, Chief Justice 27/03/2026
1. Heard Mr.Bhaskar Payasi, learned counsel for the petitioner as well
as Ms.Fouzia Mirza, learned Senior Advocate assisted by Mr.Vaibhav
Shukla, learned counsel appearing for the respondents.
2. The petitioner has prayed for the following relief(s):
"10.1 This Hon'ble Court may kindly be pleased to call for the entire records in relation to the case of the petitioner from the Respondent authorities.
10.2 This Hon'ble Court be kindly be pleased to set- aside/quash the Annexure P/1 dated 10.03.2026 passed by the Respondent no1 disqualifying the petitioner in the technical bid.
10.3 This Hon'ble Court be kindly be pleased to direct the respondents to allow the petitioner to participate in the final bid.
10.4 This Hon'ble Court may kindly be pleased to grant any other relief(s), which is deemed fit and proper in the aforesaid facts and circumstances of the case."
3. Facts of the case are that the Respondent, S.E.C.L., floated NIT No.
GM(C)/SECL/BSP/e-T_TK/Amadand-CHP/2025-26/12 dated
22.10.2025 for Planning, Design, Engineering, Construction,
Fabrication, Erection, Supply, Installation, Testing, Trial Run, and
Commissioning of a Coal Handling Plant (CHP), including Operation
& Maintenance (O&M) during a Defect Liability Period (DLP) of five
(5) years, on a turnkey basis at Amadand OCP (4.00 MTY) of
Jamuna & Kotma Area (Tender ID No. 2025_SECI_346075_1).
Seven tenderers, including the Petitioner, submitted their respective
bids in response to the aforesaid NIT. Clause 8.4(A) of the NIT
provides that the intending tenderer must have experience, in its own
name, of successfully completing similar works during the last ten
(10) years ending on the last day of the month preceding the one in
which bid applications are invited. The clause further stipulates that
such experience must satisfy any one of the following criteria: (i)
three similar completed works, each costing not less than 20% of the
estimated cost; or (ii) two similar completed works, each costing not
less than 25% of the estimated cost; or (iii) one similar completed
work costing not less than 40% of the estimated cost.
4. The NIT defines "Similar Nature of Work" to include design, supply,
installation, construction, and commissioning of Integrated Coal
Handling Plants (CHP) or other bulk material handling systems with
conveyor systems, Rapid Loading Systems (RLS), Unit Train Loading
Systems (UTLS), RCC or structural steel silos, bunkers, surge bins
or burden hoppers with conveyor systems, or any plant including
CHP or bulk material handling systems with conveyor systems, as
well as work identical in name and nature to the tendered work. It is
further specified that conveyor systems include belt conveyors, pipe
conveyors, high-angle conveyors, and chain conveyors. The NIT
further requires that the intending tenderer submit documentary
evidence in support of the aforesaid experience in the form of copies
of work orders and completion certificates indicating the value and
period of work, and that TDS certificates may be submitted during
clarification, if required. The Petitioner duly submitted all requisite
experience documents with respect to similar work involving design,
supply, installation, construction, and commissioning of a coal
washery, clearly indicating the quantum and period of work in
Annexure B, along with the tender documents.
5. It is noteworthy that the conditions relating to work experience do not
state anywhere that a work order issued by one department or unit of
a company to another department or unit of the same company
would not be considered valid experience. Respondent No. 1
disqualified the technical bid of the Petitioner on grounds which are
not expressly provided in the NIT, as reflected in the impugned
decision annexed as Annexure P/1. The reason stated for
disqualification is that the bidder was required to submit copies of
work orders and work completion certificates issued by the employer
indicating the value and period of work. There is no stipulation in the
relevant clause of the NIT requiring that such documents must
mandatorily be issued by an "employer," nor has any corrigendum or
clarification been issued by the Respondents to this effect. The NIT
does not define or explain the phrase "issued by employer," nor does
it state that any certificate not issued by an employer would be
invalid.
6. In the present case, the work order and completion certificate
submitted by the Petitioner pertain to work assigned by one wing of
the company, namely the Washery Unit, to another wing, namely the
Civil/Construction Unit. It cannot be held that work involving
construction, design, supply, and installation assigned internally
between distinct wings of the same company should be disregarded,
especially in the absence of any specific prohibition in the NIT. The
Respondents cannot assign vague and baseless reasons for
disqualification without citing any specific clause, provision, or
condition of the NIT, particularly when the Petitioner is otherwise
technically qualified. Clause 14(b) of the NIT mandates that the
Tender Committee shall furnish information online clearly indicating
any shortcomings or omissions and allow seven (7) days' time for
submission of clarifications. In the present case, there has been a
gross violation of the aforesaid provision, as no opportunity or
intimation was provided to the Petitioner regarding any alleged
shortcomings in the documents submitted. The Petitioner submitted a
representation dated 14.03.2026 via email as well as speed post to
the Respondents, raising its grievance. In the said representation,
the Petitioner specifically stated that all requisite experience
certificates had been duly submitted and that the rejection appeared
to be hyper-technical in nature, and requested an opportunity to
justify and substantiate its credentials, as well as a request to open
its price bid on a provisional basis. No response has been received
from the Respondents to the aforesaid representation till date.
Hence, this petition.
7. Learned counsel for the Petitioner submits that the impugned action
of the Respondent authority is wholly illegal, arbitrary, erroneous, and
contrary to the terms of the NIT as well as settled principles of law. It
is submitted that the Petitioner has duly furnished valid and sufficient
experience certificates in accordance with the eligibility criteria
prescribed under the NIT, thereby fully qualifying for the technical bid.
It is further submitted that the work order and completion certificate
relating to work executed by RKTC Infratech Ltd. (Coal Washery
Unit), which was assigned to its Civil/Construction wing for
construction, installation, design, and commissioning of a coal
washery with a conveyor system, clearly demonstrate the Petitioner's
requisite experience in similar nature of work. Similarly, the work
order and completion certificate pertaining to PHIL Coal Beneficiation
Pvt. Ltd. (Coal Washery Unit), assigned to its Civil/Construction wing
for execution of similar works, also establish the technical capability
and experience of the Petitioner in handling such projects. Learned
counsel submits that there is no legal prohibition or restriction on a
company assigning work from one of its specialized units to another
unit or division possessing the requisite expertise. Such internal
allocation of work is a recognized and valid business practice and
cannot be a ground for disqualification.
8. It is contended that the reasons assigned by the Respondents for
disqualification of the technical bid are vague, unsustainable, and
devoid of any reference to a specific clause or provision of the NIT,
thereby rendering the impugned action arbitrary and legally
untenable. It is further submitted that the Respondents have acted
arbitrarily in presuming that the experience certificates submitted by
the Petitioner are not valid for the purpose of technical qualification,
despite there being no such disqualification criterion in the NIT.
Learned counsel draws attention to the circular relating to
"Guidelines for e-Procurement of Works and Services, 2023,"
particularly Chapter 2, Clause 7.6(1), which mandates that public
authorities, including subsidiaries of Coal India Limited, should keep
the experience criteria broad-based so as to enable participation of
bidders having experience in similar nature of work across various
sectors. The impugned action is contrary to the spirit and mandate of
the said guidelines. It is submitted that the Respondents have
adopted a hyper-technical approach in rejecting the Petitioner's bid,
which is discriminatory, unreasonable, and violative of Article 14 of
the Constitution of India. Learned counsel further submits that, in the
impugned decision itself, the Respondent authority has categorically
recorded that the NIT does not stipulate any requirement regarding
"employer" or "end user." This admission clearly establishes that the
ground taken for disqualification is dehors the terms of the NIT and
hence unsustainable. It is contended that the observations made by
the SECL Tender Committee in the evaluation document are merely
based on subjective interpretation and are not supported by any
express provision of the NIT. Such interpretation cannot be used to
disqualify an otherwise eligible bidder. It is further submitted that the
Respondents have failed to consider that the experience certificates
and completion certificates issued by an Independent Chartered
Engineer, in respect of work assigned internally between different
wings of the bidder companies (including JV partners), adequately
demonstrate execution capability and technical competence
equivalent to that of any other bidder. Therefore, the rejection of the
Petitioner's technical bid on such untenable and extraneous grounds
is arbitrary, unreasonable, and violative of the Petitioner's
fundamental rights guaranteed under Article 14 of the Constitution of
India.
9. On the other hand, learned Senior Advocate appearing for the
respondents opposes the submissions made by learned counsel for
the petitoners and submits that for work experience biddeers
required to submit copy of work order, work completion certificate
indicating value and period of work, issued by the employer against
the Experience of similar work containing all the information as
sought on-line. In case of Sub-contractor suitable document as per
provision of eligibiity, if applicable. She further submits that the action
of the Respondent authority in disqualifying the Petitioner from the
technical bid is lawful, justified, and in consonance with the terms
and conditions of the NIT, and therefore does not call for any
interference by this Court. It is submitted that the mere submission of
work experience certificates issued by one department or unit of a
company to another department or unit of the same company does
not constitute valid experience for the purpose of technical
qualification. Learned Senior Advocate contends that the term
"employer," as contemplated under the NIT, necessarily refers to an
independent and external entity, distinct from the bidder itself. The
requirement of submission of work order and completion certificate
issued by the employer inherently presupposes an arm's-length
relationship between the contracting parties. It is further submitted
that acceptance of the Petitioner's contention that internal certificates
issued between different units of the same company constitute valid
experience would defeat the very object and purpose of prescribing
eligibility criteria in a public tender. Learned Senior Advocate submits
that, in such a situation, the Evaluation Committee would not be in a
position to fairly and objectively assess the experience and capability
of the bidder, as such internal certificates are susceptible to
fabrication, manipulation, or procurement without actual execution of
the work. It is further contended that there exists a legal embargo in
recognizing work certificates issued internally within the same
company. A company, being a single legal entity, cannot enter into a
contract with itself, and its departments or units do not possess
separate legal personality. Consequently, no valid employer-
contractor relationship can arise between different units or
departments of the same company, and any work purportedly
executed under such internal arrangements cannot be treated as
valid "completed work" for the purpose of meeting the experience
criteria. Learned Senior Advocate further submits that, in the present
case, the work experience certificate relied upon by the Petitioner
has not been issued by any independent employer or project
authority. On the contrary, the said certificate has been issued by a
third-party Chartered Engineer engaged by the bidder itself, which
lacks the element of independence and objectivity required for such
certification. It is submitted that such certification effectively amounts
to self-certification by the bidder, which is not legally permissible and
cannot be equated with a work completion certificate issued by an
independent employer. Learned Senior Advocate submits that the
requirement of certification by an independent employer is
fundamental to ensuring transparency, authenticity, and credibility in
the tender evaluation process. It is therefore submitted that the
Evaluation Committee has rightly rejected the Petitioner's technical
bid on valid and reasonable grounds, and the said decision is neither
arbitrary nor contrary to the provisions of the NIT. In view of the
above, it is prayed that the present petition, being devoid of merit, be
dismissed.
10. We have heard learned counsel for the parties, perused the NIT
document and other documents appended writ petiton and also
perused the return filed by the respondnets.
11. The principal issue which arises for consideration is whether the
experience certificates submitted by the Petitioner, issued internally
between different units/departments of the same company and
certified by a Chartered Engineer engaged by the bidder, satisfy the
eligibility criteria prescribed under the NIT.
12. It is not in dispute that the NIT requires submission of copies of work
orders and completion certificates indicating the value and period of
work, issued by the "employer" against the experience of similar
work. Though the NIT does not expressly define the term "employer,"
the same must be interpreted in the context of a public procurement
process, which necessarily demands objectivity, transparency, and
independent verification of credentials.
13. This Court finds merit in the submission advanced by learned Senior
Counsel for the Respondents that the term "employer" inherently
denotes an independent and external entity, distinct from the bidder.
The requirement of submission of experience certificates issued by
the employer presupposes the existence of an arm's-length
contractual relationship between two legally distinct entities.
14. In the present case, the experience certificates relied upon by the
Petitioner pertain to work allegedly executed by one unit/department
of a company for another unit/department of the same company.
Admittedly, such units or departments do not possess independent
legal status separate from the company itself. A company, being a
single legal entity, cannot enter into a contract with itself, and
therefore, no valid employer-contractor relationship can be said to
exist in such internal arrangements.
15. In absence of such a relationship, any work purportedly executed
internally cannot be equated with "completed work" for the purposes
of satisfying eligibility conditions in a competitive tender process.
Accepting such internal certifications would dilute the sanctity of the
tender conditions and undermine the level playing field required to be
maintained amongst bidders.
16. This Court also finds substance in the contention that permitting
internal experience certificates would render the evaluation process
susceptible to manipulation, as such documents may not carry the
same degree of credibility and independent verification as those
issued by an external employer. Further, it is an admitted position
that the experience certificate relied upon by the Petitioner has not
been issued by any independent employer or project authority, but by
a Chartered Engineer engaged by the bidder itself. Such certification,
in the considered view of this Court, lacks the element of
independence and amounts, in effect, to self-certification, which
cannot be treated at par with a completion certificate issued by an
employer in the ordinary course of business.
17. The scope of judicial review in tender matters is limited. Unless the
decision-making process is shown to be arbitrary, mala fide, or in
violation of statutory or contractual provisions, this Court would be
slow to interfere. In the present case, the decision of the Evaluation
Committee appears to be based on a reasonable and plausible
interpretation of the tender conditions and is aimed at ensuring
fairness and transparency in the process.
18. This Court does not find the impugned action to be arbitrary or
violative of Article 14 of the Constitution of India. On the contrary, the
rejection of the Petitioner's technical bid is founded upon valid
considerations and cannot be said to suffer from any illegality
warranting interference under writ jurisdiction.
19. The Apex Court, in the matter of Banshidhar Construction Pvt.
Ltd. v. Bharat Coking Coal Ltd. & Others, {Civil Appeal No. 11005
OF 2024, decided on 04.10.2024}, taking note of the decisions
rendered in various other celebrated judgments, observed as under:-
"21. There cannot be any disagreement to the legal proposition propounded in catena of decisions of this Court relied upon by the learned counsels for the Respondents to the effect that the Court does not sit as a Court of Appeal in the matter of award of contracts and it merely reviews the manner in which the decision was made; and that the Government and its instrumentalities must have a freedom of entering into the contracts. However, it is equally well settled that the decision of the government/ its instrumentalities must be free from arbitrariness and must not be affected by any bias or actuated by malafides. Government bodies being public authorities are expected to uphold fairness, equality and public interest even while dealing with contractual matters. Right to equality under Article 14 abhors arbitrariness. Public authorities have to ensure that no bias, favouritism or arbitrariness are shown during the bidding process and that the entire bidding process is carried out in absolutely transparent manner.
22. At this juncture, we may reiterate the well-established tenets of law pertaining to the scope of judicial intervention in Government Contracts.
23. In Sterling Computers Limited vs. M/s. M & N Publications Limited and Others1, this Court while dealing with the scope of judicial review of award of contracts held: -
"18. While exercising the power of judicial review, in respect of contracts entered into on behalf of the State, the Court is concerned primarily as to whether there has been any infirmity in the "decision making process". In this connection reference may be made to the case of Chief Constable of the North Wales Police v. Evans [(1982) 3 All ER 141] where it was said that: (p. 144a)
1 (1993) 1 SCC 445
"The purpose of judicial review is to ensure that the individual receives fair treatment, and not to ensure that the authority, after according fair treatment, reaches on a matter which it is authorised or enjoined by law to decide for itself a conclusion which is correct in the eyes of the court."
By way of judicial review the court cannot examine the details of the terms of the contract which have been entered into by the public bodies or the State. Courts have inherent limitations on the scope of any such enquiry. But at the same time as was said by the House of Lords in the aforesaid case, Chief Constable of the North Wales Police v. Evans [(1982) 3 All ER 141] the courts can certainly examine whether "decision-making process" was reasonable, rational, not arbitrary and violative of Article 14 of the Constitution."
24. In Tata Cellular vs. Union of India2, this Court had laid down certain priniciples for the judicial review of administrative action.
"94. The principles deducible from the above are:
(1) The modern trend points to judicial restraint in administrative action.
(2) The court does not sit as a court of appeal but merely reviews the manner in which the decision was made.
(3) The court does not have the expertise to correct the administrative decision. If a review of the administrative decision is permitted it will be substituting its own decision, without the necessary expertise which itself may be fallible. (4) The terms of the invitation to tender cannot be open to judicial scrutiny because the invitation to tender is in the realm of contract. Normally speaking, the decision to accept the tender or award the contract is reached by process of negotiations through several tiers. More often than not, such decisions are made qualitatively by experts.
2 (1994) 6 SCC 651
(5) The Government must have freedom of contract. In other words, a fair play in the joints is a necessary concomitant for an administrative body functioning in an administrative sphere or quasi-administrative sphere. However, the decision must not only be tested by the application of Wednesbury principle of reasonableness (including its other facts pointed out above) but must be free from arbitrariness not affected by bias or actuated by mala fides.
(6) Quashing decisions may impose heavy administrative burden on the administration and lead to increased and unbudgeted expenditure. Based on these principles we will examine the facts of this case since they commend to us as the correct principles."
25. It has also been held in ABL International Limited and Another vs. Export Credit Guarantee Corporation of India Limited and Others3, as under: -
"53. From the above, it is clear that when an instrumentality of the State acts contrary to public good and public interest, unfairly, unjustly and unreasonably, in its contractual, constitutional or statutory obligations, it really acts contrary to the constitutional guarantee found in Article 14 of the Constitution."
26. In Jagdish Mandal vs. State of Orissa and Others 4, this Court after discussing number of judgments laid down two tests to determine the extent of judicial interference in tender matters. They are: -
"22. (i) Whether the process adopted or decision made by the authority is mala fide or intended to favour someone; or Whether the process adopted or decision made is so arbitrary and irrational that the court can say: "the decision is such that no responsible authority acting reasonably and in accordance with relevant law could have reached;"
(ii) Whether public interest is affected. If the answers are in the negative, there should be no interference under Article 226. Cases involving blacklisting or
3 (2004) 3 SCC 553 4 (2007) 14 SCC 517
imposition of penal consequences on a tenderer/contractor or distribution of State largesse (allotment of sites/shops, grant of licences, dealerships and franchises) stand on a different footing as they may require a higher degree of fairness in action."
27. In Mihan India Ltd. vs. GMR Airports Ltd. and Others5, while observing that the government contracts granted by the government bodies must uphold fairness, equality and rule of law while dealing with the contractual matters, it was observed in Para 50 as under: -
"50. In view of the above, it is apparent that in government contracts, if granted by the government bodies, it is expected to uphold fairness, equality and rule of law while dealing with contractual matters. Right to equality under Article 14 of the Constitution of India abhors arbitrariness. The transparent bidding process is favoured by the Court to ensure that constitutional requirements are satisfied. It is said that the constitutional guarantee as provided under Article 14 of the Constitution of India demands the State to act in a fair and reasonable manner unless public interest demands otherwise. It is expedient that the degree of compromise of any private legitimate interest must correspond proportionately to the public interest."
28. It was sought to be submitted by the learned Counsels for the Respondents relying upon the observations made in Central Coalfields Limited and Another vs. SLL-SML (Joint Venture Consortium) and Others6, that whether a term of NIT is essential or not is a decision taken by the employer which should be respected. However, in the said judgment also it is observed that if the employer has exercised the inherent authority to deviate from the essential term, such deviation has to be made applicable to all the bidders and potential bidders. It was observed in Para 47 and 48 as under:-
"47. The result of this discussion is that the issue of the acceptance or rejection of a bid or a bidder 5 (2022) SCC OnLine SC 574 6 (2016) 8 SCC 622
should be looked at not only from the point of view of the unsuccessful party but alsofrom the point of view of the employer. As held in Ramana Dayaram Shetty [Ramana Dayaram Shetty v. International Airport Authority of India, (1979) 3 SCC 489] the terms of NIT cannot be ignored as being redundant or superfluous. They must be given a meaning and the necessary significance. As pointed out in Tata Cellular [Tata Cellular v. Union of India, (1994) 6 SCC 651] there must be judicial restraint in interfering with administrative action. Ordinarily, the soundness of the decision taken by the employer ought not to be questioned but the decision-making process can certainly be subject to judicial review. The soundness of the decision may be questioned if it is irrational or mala fide or intended to favour someone or a decision "that no responsible authority acting reasonably and in accordance with relevant law could have reached" as held in Jagdish Mandal [Jagdish Mandal v. State of Orissa, (2007) 14 SCC 517] followed in Michigan Rubber [Michigan Rubber (India) Ltd. v. State of Karnataka, (2012) 8 SCC 216].
48. Therefore, whether a term of NIT is essential or not is a decision taken by the employer which should be respected. Even if the term is essential, the employer has the inherent authority to deviate from it provided the deviation is made applicable to all bidders and potential bidders as held in Ramana Dayaram Shetty [Ramana Dayaram Shetty v.International Airport Authority of India, (1979) 3 SCC 489] . However, if the term is held by the employer to be ancillary or subsidiary, even thatdecision should be respected. The lawfulness of that decision can be questioned on very limited grounds, as mentioned in the various decisions discussed above, but the soundness of the decision cannot be questioned, otherwise this Court would be taking over the function of the tender issuing authority, which it cannot."
20. Recently, the Apex Court in the matter of M/S. Steag Energy
Services (India) Pvt. Ltd. v. GSPC Pipavav Power Company Ltd.
(GPPC) & Ors. {SLP (C) No(S).30209-30210 of 2025}, decided on
25.03.2026 held that the final choice is of the owner, and it is for the
owner to take the final decision with necessary flexibility and
pragmatism. While exercising judicial review of contractual matters,
constitutional courts do not exercise, should not exercise ex-ante
jurisdiction to pre-empt executive actions. On this count, High Court
has exceeded the first principle of judicial restraint in contractual
matters.
21. Applying the well settled proposition of law to the facts of this case,
we do not find any merit in this petition and the petitioner is not
entitled to any relief as claimed in this petition. As such, the writ
petition is dismissed. No order as to cost.
Sd/- Sd/-
(Ravindra Kumar Agrawal) (Ramesh Sinha)
JUDGE CHIEF JUSTICE
Bablu
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!