Saturday, 11, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

D.K. Bhuiya vs A. K. Sinha
2026 Latest Caselaw 145 Chatt

Citation : 2026 Latest Caselaw 145 Chatt
Judgement Date : 27 February, 2026

[Cites 7, Cited by 0]

Chattisgarh High Court

D.K. Bhuiya vs A. K. Sinha on 27 February, 2026

                                                          1
                                                                               ARBA No. 4 of 2023




                                                                          2026:CGHC:10217
                                                                                          AFR

      Digitally
      signed by
      RAHUL
                             HIGH COURT OF CHHATTISGARH AT BILASPUR
RAHUL JHA
JHA   Date:
      2026.02.27
      13:29:57
      +0530                                Judgment reserved on 24/02/2026
                                          Judgment delivered on 27/02/2026

                                                ARBA No. 4 of 2023

                   D.K. Bhuiya S/o S.R. Bhuiya Aged About 54 Years R/o Flat No. 21,
                   Kanchanapuram Apartment Ashish Nagar, Risali, Bhilai, Tehsil And District
                   Durg. (Chhattisgarh)
                                                                                    Appellant(s)


                                                       Versus
                   A. K. Sinha S/o M.P. Sinha Aged About 52 Years R/o Quarter No. 210/17,
                   Ashish Nagar East, Risali, Bhilai, Tehsil And District Durg. (Chhattisgarh)
                                                                                   Respondent(s)

(Cause-title taken from Case Information System) For Appellant(s) : Ms. Sweksha Sharma, Advocate

For Respondent(s) : Mr. Punit Ruparel, Advocate

Hon'ble Shri Bibhu Datta Guru, J C A V Judgment

1. This Appeal under Section 37 of the Arbitration and Conciliation Act,

1996 (henceforth 'the Act, 1996') is directed against the order dated

05.11.2022 passed by the learned II Additional District Judge, Durg

(C.G.) in M.J.C. Civil No. 17/2022, whereby the learned Court has

rejected the application preferred by the appellant under Section 34 of

the Act, 1996 on the ground of limitation by declining to condone the

delay, and consequently affirmed the arbitral award dated 18.08.2016

passed by the learned Sole Arbitrator.

2. (a) Briefly stated facts of the case are that the appellant purchased

Flat No. 21 situated on the second floor of "Kanchanpuram Apartment"

from the respondent/developer pursuant to an agreement dated

19.12.2007 for a total sale consideration of ₹16,50,000/-, which amount

was admittedly paid through cheques. Subsequently, the said amount

reached upto ₹25,00,000/- owing to interior, furniture, putti work, etc.

According to the appellant, despite receipt of the entire consideration,

the respondent failed to provide the promised amenities and delivered

possession of a flat suffering from serious construction defects,

including deficient finishing work, non-functional lift facility, etc.

thereby compelling the appellant to institute Consumer Complaint No.

CC/14/69 before the District Consumer Disputes Redressal Forum,

Durg, on 12.03.2014 alleging deficiency in service and unfair trade

practice. The District Forum, upon appreciation of the material on

record, allowed the complaint vide order dated 22.08.2015 and awarded

compensation of ₹4,55,000/- in favour of the appellant. In appeal

preferred by the respondent, the State Commission remanded the matter

for technical inspection. Thereafter, upon reconsideration and in light of

the inspection report, the District Forum once again awarded

compensation of the same amount of ₹4,55,000/- by order dated

19.12.2016. The respondent carried the matter in further appeal,

whereupon the State Commission, vide order dated 22.04.2017, partly

modified the award and reduced to ₹3,23,000/- (Rs.2,23,000/- towards

compensation and Rs.1,00,000/- towards mental harassment). The

respondent herein thereafter filed Revision Petition No. 1421/2017

(Arvind Sinha @ A.K. Sinha v Dilip Kumar Bhuiyan) before the National

Commission, New Delhi, wherein the respondent herein personally

appeared before the Forum and the appellant herein represented through

his counsel and made a submission that the parties arrived at an amicable

settlement for a sum of ₹2,23,000/-, and the proceedings were finally

disposed of on 06.02.2018 in terms of the compromise, thus bringing the

consumer dispute between the parties to a quietus.

(b) It is the appellant/buyer's case that notwithstanding the aforesaid

proceedings, disputes purportedly arising out of the same agreement

dated 19.12.2007 were referred to arbitration, and the learned Sole

Arbitrator proceeded ex parte to pass an award dated 18.08.2016

directed the appellant/buyer to pay an amount of Rs.4,03,000/- along

with interest at the rate of 18% per annum to the respondent/developer.

The appellant asserts that no signed copy of the arbitral award was ever

delivered to him in the manner contemplated under Section 31(5) of the

Act, 1996, and that he remained unaware of the said award. According to

him, knowledge of the award was acquired for the first time on

23.07.2019 during the course of execution proceedings initiated by the

respondent under Section 36 of the Act in Execution Case No. 267/2017.

Immediately upon gaining such knowledge, the appellant, acting bona

fide and within the statutory period computed from the date of

knowledge, filed an application under Section 34 of the Act, 1996 on

07.09.2019, however, the said application was inadvertently filed in the

pending execution proceedings instead of by way of an independent

application. The application was subsequently withdrawn on 21.12.2021,

and thereafter a properly constituted application under Section 34,

accompanied by an application under Section 5 of the Limitation Act

seeking condonation of delay explaining the bona fide circumstances,

was instituted on 04.01.2022. The said application having been

dismissed by the II Additional District Judge, Durg vide the impugned

order on the ground of delay and laches. Hence, the present appeal has

been preferred.

3. Learned counsel for the appellant submits that limitation under Section

34(3) commences only from the date of receipt of a signed copy of the

award. In absence of proper service in terms of Section 31(5), the

question of delay does not arise. The appellant had acted with due

diligence immediately upon gaining knowledge of the award and had

been bona fide in prosecuting the remedy. According to the learned

counsel, the learned Court has failed to consider that a litigant

prosecuting a remedy in good faith ought not to be non-suited on

technical grounds. Learned counsel would submit that the learned Court

has not at all appreciated the fact that copy of the award was not

provided to the appellant by the arbitrator. She would submit that when

in the execution proceedings the copy of the award provided to the

appellant, he immediately moved the application under Section 34.

Despite the said fact and without appreciating the entire facts and

circumstances of the case in its true perspective rejected the said

application. The impugned order, therefore, suffers from patent illegality

and misapplication of the law relating to limitation and deserves to be set

aside.

4. Per contra, learned counsel for the respondent/developer would submit

that the appeal is devoid of merit and is liable to be dismissed at the

threshold. It is contended that the arbitral award was passed on

18.08.2016 and the statutory period prescribed under Section 34(3) of

the Act, 1996 expired long ago. The application under Section 34 having

been filed only on 04.01.2022 suffers from gross and inordinate delay

which is beyond the period that can be condoned under the scheme of

the Act. It is further submitted that Section 34(3) prescribes a strict

limitation period of three months with a further grace period of thirty

days, and the Court has no jurisdiction to condone delay beyond the said

period. The respondent would contend that the plea of non-service of

award is an afterthought and that the appellant had sufficient opportunity

and knowledge of the proceedings. The earlier application filed in

execution proceedings does not save limitation, nor can withdrawal of

such application revive a time-barred remedy. Therefore, it is submitted

that the learned Court has rightly rejected the application under Section

34 on the ground of limitation and the present appeal under Section 37

does not warrant any interference.

5. I have heard learned counsel for the parties at length and perused the

material available on record.

6. The short question which arises for consideration in the present appeal is

whether the learned II Additional District Judge, Durg was justified in

rejecting the application preferred by the appellant under Section 34 of

the Act, 1996 on the ground of limitation by holding that the delay was

beyond the condonable period prescribed under Section 34(3) of the Act.

7. Section 34(3) of the Arbitration and Conciliation Act, 1996 provides that

an application for setting aside an arbitral award shall not be made after

the expiry of three months from the date on which the party making the

application had received the arbitral award. The proviso thereto

empowers the Court to entertain the application within a further period

of thirty days, if sufficient cause is shown for the delay, but not

thereafter. The expression "had received the arbitral award" occurring in

Section 34(3) must be read in conjunction with Section 31(5) of the Act,

which mandates delivery of a signed copy of the award to each party.

8. It is pertinent to mention here that when a copy of the signed award is

not delivered to the party itself, it would not amount to compliance with

the provisions of sub-section (5) of Section 31 of the Act, 1996. Proper

compliance with section would mean delivery of a signed copy of the

arbitral award on the party, which gives the right to proceed under sub-

section (3) of Section 34 of the Act, 1996.

9. The Supreme Court in the matter of Benarshi krishna Committtee &

Others v. Karamyogi Shelters Private Limited, (2012) 9 SCC 496 held

that if copy of signed award is not delivered to party itself, it would not

amount to compliance with provisions of Section 31 (5) of the Act, 1996.

In the case at hand, delivery of arbitration award having not been made

delivered on the party and as such in the considered opinion of this

Court, the provisions of Section 31 (5) has not been complied with in its

true perspective.

10. From the above decision renderred by the Supreme Court, it is crystal

clear that if the copy of signed arbitral award is not delivered to party

itself, it would not amount to compliance with provisions of Section

31(5) of the Arbitration and Conciliation Act, 1996 and hence limitation

of three months under Section 34 (3) has to be reckoned from the date

on which, the party itself received a signed copy of the award.

11. In the present case, the categorical stand of the appellant is that no

signed copy of the award dated 18.08.2016 was ever delivered to him

and that he acquired knowledge of the award for the first time on

23.07.2019 during the execution proceedings initiated by the respondent

under Section 36 of the Act, 1996 in Execution Case No. 267/2017. The

record indicates that immediately thereafter, on 07.09.2019, the appellant

filed an application under Section 34, though in the pending execution

proceedings. The said application was later withdrawn on 21.12.2021

and a properly constituted application under Section 34 along with an

application under Section 5 of the Limitation Act seeking condonation of

delay was filed on 04.01.2022.

12. The learned II Additional District Judge, Durg, while rejecting the

application, proceeded on the premise that the award was passed on

18.08.2016 and that the limitation prescribed under Section 34(3) stood

exhausted long prior to the filing of the application on 04.01.2022.

However, the crucial aspect which required consideration was the date of

receipt of the signed copy of the award and not merely the date of

pronouncement of the award. In absence of a finding, based on cogent

material, that the signed copy of the award was duly delivered to the

appellant in terms of Section 31(5), computation of limitation from the

date of the award itself would not be in consonance with the statutory

scheme.

13. Further, the conduct of the appellant in filing an application under

Section 34 soon after acquiring knowledge of the award cannot be

lightly brushed aside. Merely because the said application was filed in

the execution proceedings instead of as an independent petition, the

same would not ipso facto render the prosecution mala fide. The

question whether the appellant was bona fide prosecuting the remedy

and whether such prosecution would have any bearing on limitation

required a considered determination. The approach adopted while

rejecting the application appears to have been hyper-technical, without

adverting to the explanation furnished by the appellant regarding non-

service of the award and the circumstances leading to the filing and

withdrawal of the earlier application.

14. At the same time, it cannot be lost sight of that Section 34(3) prescribes a

strict timeline and the Court has no jurisdiction to condone delay beyond

the aggregate period of three months and thirty days from the date of

receipt of the award. Therefore, the foundational issue as to when and in

what manner the award was served assumes pivotal significance. In

absence of a clear finding on service in terms of Section 31(5), rejection

of the application solely on the basis of the date of the award would not

be legally sustainable.

15. In view of the aforesaid discussion, the impugned order dated

05.11.2022 passed in M.J.C. Civil No. 17/2022 cannot be sustained and

accordingly the same is hereby set aside. The matter is remitted to the

learned II Additional District Judge, Durg for fresh consideration of the

application under Section 34 of the Act, 1996 filed by the

appellant/buyer, in accordance with law and on its own merits without

insisting on the question of delay.

16. Consequently, the appeal is allowed to the extent indicated above,

leaving the parties to bear their own cost(s).

Sd/-

(Bibhu Datta Guru) Judge Rahul/Gowri

HEAD NOTE

If the copy of signed arbitral award is not delivered to party itself, it

would not amount to compliance with provisions of S. 31(5) of the Arbitration

and Conciliation Act, 1996 and hence limitation of three months u/S 34 (3) has

to be reckoned from the date on which, the party itself received a signed copy

of the award.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Media

 
 
Latestlaws Newsletter