Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

S K S Ispat And Power Ltd vs Chhattisgarh State Electricity ...
2022 Latest Caselaw 7592 Chatt

Citation : 2022 Latest Caselaw 7592 Chatt
Judgement Date : 15 December, 2022

Chattisgarh High Court
S K S Ispat And Power Ltd vs Chhattisgarh State Electricity ... on 15 December, 2022
                                        1




                                                                          AFR
              HIGH COURT OF CHHATTISGARH, BILASPUR

                              WPC No. 36 of 2017

SKS Ispat & Power Ltd., A Company Incorporated Under the Authorized

Signatory, Shir Gopal Garg, having its Office at 501b, elegant business park,

Andheri Kurla Road, J.B. Nagar, Andheri (E), Mumbai - 400059 and factory

at siltara, industrial growth centre, Phase-II, 18 th Milestone, Bilaspur Road,

Raipur, Chhattisgarh.

                                                                ---- Petitioner

                                    Versus

1.   Chhattisgarh State Electricity Regulatory Commission, through its

      Secretary, having its Regd. Office at Civil Lines, G.E. Road, Raipur,

      Chhattisgarh 492001.

2.   State of Chhattisgarh, through the Secretary,Department of Energy,

      Mantralaya, Naya Raipur, Chhattisgarh.

3.   Chhattisgarh State Power Distribution Company Ltd.,Through the

      Managing Director, 4th Floor, Vidyut Sewa Bhawan, Daganiya Raipur,

      Chhattisgarh - 492013.

4.   Chhattisgarh State Power Transmission Company Ltd. Through its

      Managing    Director,    Vidyut   Sewa   Bhawan,    Daganiya,    Raipur,

      Chhattisgarh.

5.   Power Grid Corporation of India Ltd. Through its Director B-9, Qutab

      Institutional Area, Katwaria Sarai, New Delhi - 110016.

                                                            ---- Respondents

(Cause-title taken from Case Information System)

For Petitioner : Mr. Ankit Singhal, Advocate.

For Respondents No.1 : Mr. Anand K. Ganeshan along with Mr. Anumeh Shrivastava, Advocate.

For Respondent No. 2 : Ms. Astha Shukla, Government Advocate. For Respondents No. 3 & 4 : Mr. K.R. Nair and Dr. Veena Nair, Advocates.

Dates of hearing : 18.11.2022, 22.11.2022 and 17.12.2022.

Date of Order : 15.12.2022.

Hon'ble Shri Arup Kumar Goswami, Chief Justice

Hon'ble Shri Sajay Agrawal, Judge

C A V Judgment

By this petition, the petitioner challenges the vires of Regulation 4.4.6

of the Chhattisgarh State Electricity Grid Code, 2011 (for short, 'State Grid

Code') issued by the Chhattisgarh State Electricity Regulatory Commission

(for short, 'State Regulatory Commission') under Section 86(1)(h) of the

Electricity Act, 2003, for short, the Electricity Act, on the ground that the

same is contrary to the Electricity Act. Prayer is also made to set aside the

order dated 30.04.2016 passed by the State Regulatory Commission in

Suo-Motu Petition No. 56/2015 (M) levying "Parallel Operational Charges"

on Captive Power Plants (CPPs) and for a direction that the Chhattisgarh

State Power Distribution Company Limited (CSPDCL) i.e. respondent No.3,

does not have authority and power to levy and collect Parallel Operational

Charges from CPPs under Regulation of 4.4.6 of the State Grid Code.

2. The petitioner is a company which manufactures steel and iron in the

State of Chhattisgarh. For the purpose of meeting the requirements of

electricity, it had established a 85 MW CPP. The CPP of the petitioner is

connected to the State Transmission Utility (STU), which is the respondent

No. 4.

3. Mr. Ankit Singhal, learned counsel for the petitioner submits that the

impugned regulation is inconsistent with the Grid Code specified by the

Central Electricity Regulatory Commission, for short, 'Central Regulatory

Commission', under Section 79(1)(h) of the Electricity Act as the concept of

"Parallel Operation Charges" as finding place in Regulation 4.4.6 is not

mentioned in the Indian Electricity Grid Code, 2010, for short, 'Central Grid

Code', as notified by the Central Regulatory Commission.

4. It is further submitted that the exercise of power under Section 181(zp)

of the Electricity Act is also a violation of express provision of Section 62(5)

read with Section 181(zf) of the Electricity Act as by exercising the general

power under Section 181(zp), the State Commission cannot over-ride the

express provision of Section 62(5) and Section 181(zf) of the Electricity Act. It

is further submitted that levy of Parallel Operation Charges only on CPP is

discriminatory and unjust as Independent Power Plants (IPPs) had not been

subjected to levy of Parallel Operation Charges.

5. Abiding by the stand taken in the reply filed, Mr. Anand K. Ganeshan

along with Mr. Anumeh Shrivastava, learned counsel, appearing for

respondent No. 1 submits that the issue is squarely covered by a judgment of

the Hon'ble Supreme Court in the case of Transmission Corporation of

Andhra Pradesh Limited v. M/s. Rain Calcining Ltd. and other, reported in

2019 SCC Online SC 1537. It is submitted that even prior to the impugned

regulation, the State Regulatory Commission had passed orders determining

Parallel Operation Charges, which had also been subjected to appeal before

the Appellate Tribunal for Electricity, established under Section 111 of the

Electricity Act, wherein the orders had been upheld and sustained. It is

submitted that the State Regulatory Commission had relied on a detailed

report on evaluation of Parallel Operation Charges by financial and technical

consultant. It is submitted that absence of a provision in the Central Grid

Code does not mean that existence of a provision in the State Grid Code

would amount to any inconsistency. Section 79 of the Central Commission

does not relate to consumption of electricity and all that is required under

Section 86(1)(h) is that the State Grid Code should be consistent with the

Central Grid Code. Section 62(5) of the Electricity Act has no relation

whatsoever with the exercise of power under Section 181(zp) and that

Section 62(5) read with Section 181(zf) only provide that a licensee or

generating company will be required to comply with the procedure specified

for calculating the revenue from tariff and charges which the licensee or

generating company is permitted to recover. He has submitted that the State

Regulatory Commission had published a Draft Regulation on 27.11.2011 on

its website as well as in newspapers inviting comments to be given within a

period of 22 days in response to which five stakeholders submitted their

comments. A public hearing had taken place on 21.12.2011 and thereafter

only, taking into account the view points and comments, the regulation was

notified on 31.12.2011. It is submitted that only because CPP is connected to

the STU does not mean that levy of Parallel Operation Charges is to be by

the Transmission Company. It is the respondent No. 3 i.e. CSPDCL, which

has given the contract load and therefore, the Distribution Company is

entitled to levy and collect the Parallel Operation Charges. It is also submitted

that amounts, which are levied and collected by the Distribution Company,

are duly taken note of by the State Regulatory Commission in the annual tariff

fixation exercise.

6. At this juncture, it is to be noted that in the writ petition as was originally

filed, no plea was taken that levy of Parallel Operation Charges only on CPP

is discriminatory as the same was not levied on IPPs. Such a plea was

brought in by way of an amendment, which was allowed on 26.08.2022.

7. After the amendment was allowed, the respondents No. 3 and 4 had

filed a reply seeking to justify as to why no Parallel Operation Charges are

levied or recovered from the IPPs.

8. Mr. K.R. Nair, learned counsel, appearing for respondents No. 3 and 4

submits that the respondents No. 3 and 4 had adopted the reply filed by the

respondent No. 1 and he seeks to adopt the submissions of Mr. Ganeshan.

In addition, he submits that there is no factual foundation to mount a

challenge on the ground of discrimination qua IPPs. He has submitted that

CPP is set up in compliance of conditions prescribed in Rule 3 of the

Electricity Rules, 2005, and the same does not apply to IPPs. While CPPs

generate electricity primarily for it is own use, IPPs generate electricity not for

its own use but for bulk sale to a distribution licensee as per power purchase

agreement. IPPs do not use the grid for generation of electricity but use the

grid for export. IPPs have to pay transmission / wheeling charges, which

CPPs do not have to pay. It is also submitted that transmission / wheeling

charges are much more than Parallel Operation Charges.

9. We have considered the submissions of the learned counsel for the

parties and have perused the materials on record.

10. At the outset, it will be appropriate to take note of some definitions.

Section 2 (8) defines "Captive generating plant" to mean a power plant set up

by any person to generate electricity primarily for his own use and includes a

power plant set up by any co-operative society or association of persons for

generating electricity primarily for use of members of such co-operative

society or association. Section 2 (32) defines "grid" to mean the high voltage

backbone system of inter-connected transmission lines, sub-station and

generating plants. Section 2 (33) defines "Grid Code" to mean the Grid Code

specified by the Central Commission under clause (h) of the section 79 (1).

Section 2 (64) defines "State Commission" to mean the State Electricity

Regulatory Commission constituted under section 82 (1) and includes a Joint

Commission constituted under section 83 (1). Section 2 (67) defines "State

Transmission Utility" to mean the Board or the Government company

specified as such by the State Government under Section 39 (1). Section 2

(76) defines "wheeling" to mean the operation whereby the distribution

system and associated facilities of a transmission licensee or distribution

licensee, as the case may be, are used by another person for the conveyance

of electricity on payment of charges to be determined under Section 62.

11. The functions of the Central Regulatory Commission under Section

79(1) read as follows:

"79. Functions of Central Commission.- (1) The

Central Commission shall discharge the following

functions, namely :-

(a) to regulate the tariff of generating companies

owned or controlled by the Central Government;

(b) to regulate the tariff of gene rating companies other

than those owned or controlled by the Central

Government specified in clause (a), if such generating

companies enter into or otherwise have a composite

scheme for generation and sale of electricity in more

than one State;

(c) to regulate the inter-State transmission of

electricity;

(d) to determine tariff for inter-State transmission of

electricity;

(e) to issue licenses to persons to function as

transmission licensee and electricity trader with

respect to their inter-State operations;

(f) to adjudicate upon disputes involving generating

companies or transmission licensee in regard to

matters connected with clauses (a) to (d) above and to

refer any dispute for arbitration;

(g) to levy fees for the purposes of this Act;

(h) to specify Grid Code having regard to Grid

Standards;The Electricity Act, 2003;

(i) to specify and enforce the standards with respect to

quality, continuity and reliability of service by

licensees;

(j) to fix the trading margin in the inter-State trading of

electricity, if considered, necessary;

(k) to discharge such other functions as may be

assigned under this Act."

12. Functions of the State Regulatory Commission are delineated in

Section 86 and the same read as follows:

"86. Functions of State Commission.- (1) The State

Commission shall discharge the following functions,

namely:-

(a) determine the tariff for gene ration, supply,

transmission and wheeling of electricity, wholesale, bulk

or retail, as the case may be, within the State:

Provided that where open access has been

permitted to a category of consumers under section

42, the State Commission shall determine only the

wheeling charges and surcharge thereon, if any, for

the said category of consumers;

(b) regulate electricity purchase and procurement

process of distribution licensees including the price at

which electricity shall be procured from the generating

companies or licensees or from other sources through

agreements for purchase of power for distribution and

supply within the State;

(c) facilitate intra-State transmission and wheeling of

electricity;

(d) issue licences to persons seeking to act as

transmission licensees, distribution licensees and

electricity traders with respect to their operations within

the State;

(e) promote co-generation and generation of electricity

from renewable sources of energy by providing suitable

measures for connectivity with the grid and sale of

electricity to any person, and also specify, for purchase

of electricity from such sources, a percentage of the

total consumption of electricity in the area of a

distribution licensee;

(f) adjudicate upon the disputes between the licensees,

and generating companies and to refer any dispute for

arbitration;

(g) levy fee for the purposes of this Act;

(h) specify State Grid Code consistent with the Grid

Code specified under clause (h) of sub-section (1) of

section 79; (i) specify or enforce standards with respect

to quality, continuity and reliability of service by

licensees;

(j) fix the trading margin in the intra-State trading of

electricity, if considered, necessary; and

(k) discharge such other functions as may be assigned

to it under this Act".

13. A perusal of functions of State Regulatory Commission and Central

Regulatory Commission would go to show that both the Commissions are

assigned different functions. However, both the Commissions are to specify

the Grid Code.

14. Section 62(5) provides that the Commission may require a licensee or a

generating company to comply with such procedure as may be specified for

calculating the expected revenues from the tariff and charges which it is

permitted to recover.

15. Section 181 deals with power of State Regulatory Commission to make

regulations. Section 181 (zf) enables the Commission to regulate the

methodologies and procedures for calculating the expected revenue from

tariff and charges under Section 62(5). Section 181(zp) enables the State

Commission to frame regulations for any other matter which is to be, or may

be specified.

16. The State Regulatory Commission had framed the State Grid Code

under Section 86(1)(h) of the Electricity Act read with Section 181(zp). It is

not understood how framing of the State Grid Code under the aforesaid two

provisions violate Section 62(5) and Section 181(zf). No specific power under

Section 181 is conferred on the State Regulatory Commission to make

regulations relating to State Grid Code and therefore, general power under

Section 181(zp) was referred to.

17. Clause 4.4 of the State Grid Code is on the subject of General

Principles and Conditions for Grid Connectivity.

18. Clause 4.4.6 reads as follows:

"Captive generators if having connectivity with STU system

may have to pay parallel operation charges to the

concerned licensee, as may be decided by the

Commission from time to time. "

19. It is not disputed by Mr. Ganeshan that in the Central Grid Code, there

is no mention of Parallel Operation Charges.

20. The State Regulatory Commission, in terms of Section 86(1)(h), is to

specify the State Grid Code which is consistent with the Central Grid Code

specified under Section 79(1)(h). It is not necessary that the State Grid Code

has to replicate what is there in the Central Grid Code specified under

Section 79(1)(h). Absence of such a provision in the Central Grid Code under

Section 79(1)(h) does not mean that existence of such a provision in the

State Grid Code framed would amount to inconsistency. Inconsistency would

arise when the provisions as enacted in the State Grid Code cannot co-exist

with the Central Grid Code framed under Section 79(1)(h). No material has

been placed before this Court by the petitioner to show how Regulation 4.4.6

is inconsistent with Central Grid Code framed under Section 79(1)(h) save

and except stating that concept of Parallel Operation Charges is not finding

place in the Central Grid Code.

21. The Full Bench of the Appellate Tribunal in the case of Chhattisgarh

State Power Distribution Co. Limited v. Godawari Power & Ispat Ltd

dated 08.02.2011, while upholding the levy of Parallel Operation Charges,

had observed as follows:

" 17. The parallel operation is a facility in the nature of a

Grid support to the Captive Power Plant. The Captive

Power Plant gets the following advantages owing to the

parallel operation with the Grid:

(i) The fluctuations in the load of CPP are absorbed

by the utility grid in the parallel operation mode. This

will reduce the stresses on the captive generator

and equipments. The CPP can operate his

generating units at constant power generation mode

irrespective of his load cycle.

(ii) Absorption of harmonics.

(iii) Negative phase sequence current is generated

by unbalance loads. The magnitude of negative

phase sequence current is much higher at the point

of common coupling than at generator output

terminal. This unbalance current normally creates

problem of overheating of the generators and other

equipments of CPP, if not running in parallel with

grid. When they are connected to the grid, the

negative phase sequence current flows into the grid

and reduces stress on the captive generator.

(iv) Captive Power Plants have higher fault level

support when they are running in parallel with the

grid supply. Because of the higher fault level, the

voltage drop at load terminal is less when connected

with the grid.

(v) The grid provides stability to the load of Captive

Power Plant to start heavy loads like HT motors.

(vi) The variation in the voltage and frequency at the

time of starting large motors and heavy loads, is

minimized in the industry, as the grid supply acts as

an infinite bus. The active and reactive power

demand due to sudden and fluctuating load is not

recorded in the meter.

(vii) The impact created by sudden load throw off

and consequent tripping of CPP generator on over

speeding is avoided with the grid taking care of the

impact.

(viii) The transient surges reduce the life of

equipment of the CPP. In some cases, the

equipment fails if transient is beyond a limit. If the

system is connected to the grid, it absorbs the

transient surges. Hence, grid enhances the life of

CPP equipments.

18. In short, the gain to the Captive Power Plant is quite

substantial in case there is grid support. Owing to the above

said substantial gains to the Captive Power Plant by

operating in parallel with the grid, the parallel operation

charges are levied from the Captive Power Plant."

22. Parallel Operation Charges is akin to grid support connectivity and that

it is a facility in the nature of grid support of CPP. The rationale behind

Parallel Operation Charges, as submitted, is that, it enables the industries to

export surplus electricity and the same is a source of imported power in

emergency.

23. Under Rule 3 of the Electricity Rules, 2005 framed in exercise of

powers conferred under Section 176 of the Electricity Act, it is provided,

amongst others, that no power plant shall qualify as a "Captive Generating

Plant" under Section 9 read with Section 2(8) of the Electricity Act unless in

case of power plant not less than 26 percent of the ownership is held by the

captive users and not less than 51 percent of the aggregate electricity

generated in such plant determining on an annual basis, is consumed for

captive use.

24. An order was passed by the State Regulatory Commission on

06.02.2006 in Review Petition No. 17/2005, reviewing Parallel Operation

Charges. Another Review Petition seeking review of the said order dated

06.02.2006 was rejected by an order dated 04.05.2006 as against which

some appeals were preferred before the Tribunal. While not interfering with

the order of the State Regulatory Commission, the Tribunal had remanded

back the matter to the Commission with a direction that the Parallel Operation

Charges may be fixed on the basis of data, materials and scientific input.

Accordingly, the State Regulatory Commission had taken up the task of

determination of Parallel Operation Charges and had registered Suo Motu

Petition No. 39 of 2006 (M). M/s Electrical Research and Development

Association (ERDA) was assigned the task to collect various data or

parameters of some representative CGPs in the State and to suggest the rate

of Parallel Operation Charges.

25. Ultimately, two options were available for determining the

methodologies for dealing with Parallel Operation Charges. The State

Regulatory Commission, at paragraph 18 of the order dated 30.04.2016

observed as follows:

"18. After analyzing the comments / suggestions above,

the Commission is of view that formula in Option #2 is

more appropriate for computation of POC. The total

generation in KVA deducted by KVA consumed in

auxiliaries and exported shall give use the exact KVA

consumed by industrial load of the CGP. Formula for

bulling of parallel operation charges shall be as follows;

POC = *Max differences in KVA in a 15 min time

block in a month x Rate of POC (Rs./KVA)

*Maximum difference = Max Σ (Average Gross

generation in KVA in 15 min time block - Aux

consumption in KVA in the same 15 min time

block - Average Power exported to grid in KVA in

the same 15 min time block)

Present Rate of POC is Rs. 21/KVA."

26. In the order dated 30.04.2016 passed by the State Regulatory

Commission, it is noted that on 15.06.2005, the Commission had fixed

Parallel Operation Charges for availing grid support.

27. In the Transmission Corporation of Andhra Pradesh Limited

(supra), one of the questions considered was regarding grid support charges,

which are levied on the HT consumers, who have rated contracted maximum

demand (CMD) and CPP capacity to meet their demands. It was observed

that the significant benefit which a CPP gets is in case of outage of CPP

generator, power is drawn from the grid and in case of tripping, the entire

load is transferred on to the grid. Such disturbance is catered by way of grid

support and equipment installed by the Distribution Companies and

investment through public exchequer. It is observed that the grid acts as a

cushion / big buffer when the generation from CPP is idled due to sudden

outage in the load, thereby mitigating the forced tripping of the CPP and this

support is known as grid support and CPPs running in parallel are known as

running with Parallel Grid Support. In the said case, the State Regulatory

Commission had held that the grid support charges would be payable at the

rate of 50% of prevailing demand charges on the differential CPP capacity

and CMD. The aforesaid decision was set aside by the High Court. In respect

of grid support charges, the Hon'ble Supreme Court observed as follows:

"IN RE:GRID SUPPORT CHARGES

71. With respect to Grid Support Charges, it has been

conceded by the learned counsel for the parties that the

decision in the aforesaid batch of matters as to wheeling

charges has to govern grid support charges as we have

upheld that order of the Commission with respect to

wheeling charges, the order of the High Court has to be set

aside.

72. Any Government Order or Incentive Scheme does

not govern the Grid Support Charges. Grid Code is the

basis for levy of the Grid Support Charges, which came to

be approved by the Commission on 26.05.2001. The same

is also reflected in the impugned order. Thus, in case of

installation of another CPP, that would be an additional load

on the grid, and there is no embargo for setting up

additional grid CPP in the form of expansion as grid acts as

cushioning. The Grid Support Charges can be levied, and

the order dated 8.2.2002 of the Commission is, thus on the

parity of the reasonings, has to be upheld considering the

provisions of Section 21(3) of the Reforms Act, 1998. Under

Section 11 read with Section 26 of the Reform Act, 1988, all

fixed charges under the distribution and Grid Support

Charges are leviable only at the instance of a distribution

company, and because of the discussion above, the

Commission has the powers to determine it. In the

agreements also there is a power where the Board could

have fixed the Grid Support Charge unilaterally, but

because of Reforms Act, 1998 came to be enacted, the

application was filed in the Commission. After that, the

Commission has passed the order in accordance with the

law. We find no fault in the same. Thus, the order of the

Commission concerning the Grid Support Charges has to

be upheld. The judgment and order of the High Court are

liable to be set aside concerning wheeling charges as well

as Grid Support Charges."

28. A perusal of the above would go to show that it was held by the Hon'ble

Supreme Court that grid support charges can be levied and that the same is

leviable at the instance of the Distribution Company. Although, the order of

the Commission was prior to coming into force of the Electricity Act, we are of

the considered opinion that the principles laid down by the Hon'ble Supreme

Court will also apply in the instant case.

29. We are inclined to accept the submission of Mr. Nair that except for

making a statement, that too, at a very belated stage after almost 5½ years

of filing of the writ petition, plea of discrimination vis-a-vis IPPs was taken

without stating how the CPPs and the IPPs are similarly or identically

situated. Question of discrimination will arise only when two entities similarly

or identically situated are differently treated.

30. In view of the above discussion, we find no merit in this petition and

accordingly, the same is dismissed.

                       Sd/-                                       Sd/-
            (Arup Kumar Goswami)                           (Sanjay Agrawal)
               (Chief Justice)                                   (Judge)


Hem
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter