Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sai Surfactants Private Limited vs Amrit Cement Limited
2026 Latest Caselaw 33 Cal/2

Citation : 2026 Latest Caselaw 33 Cal/2
Judgement Date : 8 January, 2026

[Cites 3, Cited by 0]

Calcutta High Court

Sai Surfactants Private Limited vs Amrit Cement Limited on 8 January, 2026

                     IN THE HIGH COURT AT CALCUTTA
                         (COMMERCIAL DIVISION)                                  2026:CHC-OS:2

                             ORIGINAL SIDE
                         RESERVED ON: 06.01.2026
                         DELIVERED ON: 08.01.2026
                                 PRESENT:
                      HON'BLE JUSTICE GAURANG KANTH
                             AP-COM- 545 OF 2025
                    SAI SURFACTANTS PRIVATE LIMITED
                                VERSUS
                         AMRIT CEMENT LIMITED

Mr. Chayan Gupta, Adv.
Mr. Uttam Sharma, Adv.
Mr. Ankit Prakash, Adv.
                                                       ..... for the petitioner

Mr. Jishnu Chowdhury, Sr. Adv.
Mr. Sankarsan Sarkar, Adv.
Ms. Bhawna Parasramka, Adv.
Mr. Udipt Daga, Adv.
                                                       ..... for the respondent

                                  JUDGMENT

Gaurang Kanth, J.:-

1. The Petitioner has preferred the present petition under Section 9 of the

Arbitration and Conciliation Act, 1996 seeking interim protection, inter

alia, by directing the Respondent to furnish security to the tune of Rs.

63,45,690/- so as to secure the monetary claim proposed to be pursued by

the Petitioner against the Respondent in the arbitral proceedings.

2. The facts leading to the present case are as follows:

3. The Petitioner is a registered MSME enterprise engaged in the manufacture

and supply of polypropylene (PP) woven bags. The Respondent is engaged

in the manufacture of cement.

4. Between May 2024 and June 2024, the Respondent placed purchase

orders upon the Petitioner for laminated polypropylene bags, PP woven

bags and Block Bottom Bags (PPC trade). Pursuant thereto, supplies

2026:CHC-OS:2 aggregating to 10,08,000 cement bags were effected, having an aggregate

invoice value of Rs.1,45,54,214.40/-. The contractual terms provided for

payment within 30 days from the date of the respective invoices.

5. Payments to the extent of Rs.88,78,288/- were made by the Respondent

against the said supplies. The balance amount of Rs.56,06,854/- remains

disputed. The record also reflects to a virtual meeting held on 18.09.2024

in connection with the issue of outstanding payments.

6. The Respondent issued a debit note dated 21.09.2024 for an amount of

Rs.55,65,287/-. Subsequent correspondence exchanged between the

parties, including emails dated 25.09.2024 and 12.10.2024, indicates that

objections were raised by the Respondent with regard to the quality of the

supplied bags.

7. Demand notices dated 19.12.2024 and 21.12.2024 were issued by the

Petitioner. The Respondent replied thereto on 02.01.2025, reiterating its

objections concerning the quality of the goods supplied.

8. On the basis of the materials placed on record, the Petitioner asserts that

as on 20.03.2025 a sum of Rs.63,45,690/-, inclusive of contractual

interest at the rate of 18% per annum, remains outstanding. Invoking the

arbitration clause providing for adjudication at Kolkata, the present

application has been filed under Section 9 of the Arbitration and

Conciliation Act, 1996 seeking interim measures pending commencement

and conclusion of arbitral proceedings.

Submission on behalf of the Petitioner

9. Mr. Chayan Gupta, learned counsel for the Petitioner submits that the

supplies were effected strictly in terms of the purchase orders and were

2026:CHC-OS:2 duly delivered and utilised by the Respondent. Part payments aggregating

to Rs.88,78,288/- were made, evidencing acceptance of the supplies. The

balance amount remained unpaid beyond the stipulated credit period,

notwithstanding discussions held on 18.09.2024 in relation to the

outstanding dues.

10. It is submitted that the Respondent was governed by a Standard Operating

Procedure (SOP) prescribing the mechanism for sampling, inspection,

acceptance and rejection of laminated polypropylene bags. The SOP

prescribes detailed protocols including Bag Inspection (page Nos. 35-36),

Breaking Strength and Weld Strength (page No. 38), Acceptance Criteria

(page No. 39), Assessment Procedures (page Nos. 39-40), Elongation Test

(page No. 40), Ash Content (page Nos. 40-41), and rejection norms on the

packing floor (page No. 45). It is the Petitioner's contention that the

Respondent failed to adhere to any of these mandatory procedures.

11. It is submitted that only a solitary joint inspection was undertaken on

11.07.2024. As per the inspection report, out of 6,31,695 bags examined,

only 3,336 were found damaged, amounting to 0.53%, which is well within

the permissible tolerance. No subsequent joint inspection was conducted,

nor was the Petitioner ever notified of any further defects. The Respondent

utilised the supplies, made part payment and acknowledged liability on

18.09.2024. However, on 21.09.2024, the respondent issued a debit note

for Rs. 55,65,287/-, seeking to nullify its obligation. It is contended that

the Respondent neither rejected the goods nor adhered to the SOP

mandated rejection procedure and, having appropriated the supplies, is

not entitled to withhold payment on belated quality objections.

2026:CHC-OS:2

12. It is submitted that as on 20.03.2025, a sum of Rs.63,45,690/-, inclusive

of contractual interest at the rate of 18% per annum, remains outstanding.

Invoking the arbitration clause providing for adjudication at Kolkata, the

present application has been filed under Section 9 of the Arbitration and

Conciliation Act, 1996 seeking interim protection. Reliance is placed on

Essar House Pvt. Ltd. v. Arcelor Mittal Nippon Steel India Ltd.,

reported as (2022) 20 SCC 178.

Submission on behalf of the Respondent

13. Per contra, Mr. Jishnu Chowdhury, learned Senior counsel appearing on

behalf of the Respondent submits that the present application under

Section 9 of the Arbitration and Conciliation Act, 1996 is misconceived and

not maintainable. It is contended that Section 9 does not mandate

furnishing of security in every case involving a monetary claim,

particularly where the alleged outstanding amount is seriously disputed.

14. Learned Senior Counsel appearing on behalf of the Respondent submits

that under a single purchase order, supplies were made in five

consignments dated 31.05.2024, 19.06.2024, 21.06.2024, 26.06.2024 and

29.06.2024. Attention is drawn to page 49 of the SOP, which sets out the

technical specifications of laminated polypropylene bags, including the

requirement that none of the sacks shall fail the drop impact strength test.

Learned Senior Counsel further refers to page 77, being the test report in

respect of the consignment supplied on 19.06.2024, to demonstrate that

the said lot failed the drop impact strength test and was, therefore,

rejected in its entirety. It is submitted that the rejected lot constituted

approximately 20% of the total quantity supplied.

2026:CHC-OS:2

15. Learned Senior Counsel further submits that the joint inspection

conducted on 11.07.2024 pertained only to three consignments and that

even during such inspection the drop impact strength test was found to be

unsatisfactory. It is contended that the Petitioner, in its own handwriting,

acknowledged the deficiencies, assured improvement in quality, and

requested the Respondent to utilise the bags. Reliance is placed on Clause

'M' of the SOP, which provides that where a rejected lot is nevertheless

utilised due to operational exigencies, the bags are to be accepted at 50%

of the contract price. In the present case, it is submitted that the

Respondent has already paid approximately 61% of the total value of the

supplies, which, according to the Respondent, is in excess of the amount

payable even on a discounted basis.

16. Learned counsel submits that the Respondent is a solvent and going

concern, fully capable of satisfying any award that may be passed in

arbitration. There is no material on record to suggest dissipation of assets

or any attempt to defeat enforcement of a prospective award. Mere

assertion of apprehension is insufficient to invoke the jurisdiction under

Section 9. It is contended that the principles underlying Order XXXVIII

Rule 5 of the Code of Civil Procedure, 1908 must be satisfied before

directing furnishing of security or attachment, which have not been met in

the present case.

17. It is accordingly submitted that the Petitioner has failed to establish a

prima facie case, balance of convenience, or irreparable prejudice

warranting grant of interim protection. The reliefs sought would, in effect,

amount to granting final relief at an interlocutory stage. The application is

therefore liable to be dismissed.

2026:CHC-OS:2 Legal Analysis

18. This Court has heard learned counsel for the parties at length and has

perused the pleadings, documents and materials placed on record.

19. From the record, it emerges that supplies were made by the Petitioner

pursuant to the purchase orders and that substantial part payments have

been effected by the Respondent. The surviving dispute relates to a sum of

Rs.56,06,854/-. According to the Respondent, the admitted liability stands

discharged and the balance claimed pertains to materials allegedly rejected

on account of quality issues, rendering the said amount disputed.

20. The SOP placed on record prescribes detailed technical specifications and

quality benchmarks, including the stipulation that none of the sacks shall

fail the drop impact strength test. It also provides a structured mechanism

for inspection, rejection and conditional acceptance at a discounted value.

The Respondent has relied upon the test report relating to the

consignment supplied on 19.06.2024 to contend that the said lot failed the

drop impact strength test and was rejected in its entirety, constituting

approximately 20% of the total supply. The Petitioner, on the other hand,

relies upon the joint inspection dated 11.07.2024, which records a defect

rate of 0.53%, and contends that no further inspection in accordance with

the SOP was undertaken thereafter.

21. The materials on record indicate that the joint inspection dated 11.07.2024

pertained only to certain consignments and that disputes exist as to

whether the allegedly rejected consignments were nevertheless utilised

and, if so, on what terms. The alleged handwritten assurance by the

Petitioner regarding improvement of quality, as well as the applicability of

Clause 'M' of the SOP providing for acceptance at a discounted rate, raise

2026:CHC-OS:2 issues requiring examination of contemporaneous records and evidence.

These matters cannot be conclusively determined at the present

interlocutory stage.

22. It is also evident that only one joint inspection was conducted. Prima facie,

the rejection of subsequent consignments without recourse to the

inspection mechanism contemplated under the SOP raises a triable issue.

At the same time, it is not in dispute that the Respondent has utilised at

least part of the goods supplied, which lends prima facie support to the

Petitioner's contention that the claim is not illusory. Conversely, the

Respondent's reliance on technical test failures and alleged non-conformity

with specifications cannot be brushed aside as frivolous. The dispute thus

involves mixed questions of fact and contractual interpretation, falling

within the domain of arbitral adjudication.

23. In proceedings under Section 9 of the Arbitration and Conciliation Act,

1996, this Court is not required to conduct a mini trial or return definitive

findings on the merits. The Court is required to assess whether interim

protection is necessary to preserve the efficacy of the arbitral process.

Where the claim is monetary, the Court must be satisfied that the

circumstances justify securing the claim without converting the interim

measure into final relief.

24. The balance of convenience, at this stage, leans in favour of the Petitioner.

The Petitioner, an MSME entity, asserts that more than Rs.63 lakh

remains outstanding despite supply and utilisation of the goods. Delay in

securing the claim may cause disproportionate hardship to the Petitioner,

whereas a calibrated protective direction is unlikely to prejudice the

Respondent, who asserts financial robustness. The apprehension that

2026:CHC-OS:2 enforcement of any eventual award may be rendered ineffective cannot be

discounted altogether.

25. The Respondent's contention that relief under Section 9 must strictly

satisfy the preconditions of Order XXXVIII Rule 5 CPC cannot be accepted

in absolute terms. As clarified by the Supreme Court in Essar House Pvt.

Ltd (supra)., while the principles underlying Order XXXVIII Rule 5 may

guide the exercise of discretion, they do not constitute rigid jurisdictional

limitations on the Court's powers under Section 9.

26. Balancing the rival equities and without expressing any opinion on the

merits of the dispute, this Court is of the view that limited interim

protection would subserve the ends of justice and safeguard the arbitral

proceedings from being rendered nugatory.

27. Accordingly, in order to secure the subject matter of the arbitration and

without expressing any opinion on the merits of the disputes between the

parties, the Respondent is directed to create an interest bearing fixed

deposit in the name of Registrar General, Original Side of this Court for a

sum of Rs.63,45,690/- with a nationalised bank within a period of two

weeks from date, for an initial period of six months. The said fixed deposit

shall be kept renewed and shall be placed before the Arbitral Tribunal

upon its constitution for appropriate custody and further directions.

Liberty is granted to the parties to seek modification or variation of this

order before the Arbitral Tribunal, in accordance with law.

28. With this direction, the present petition is allowed and disposed of.

(GAURANG KANTH, J.)

Sakil Amed P.A.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter