Citation : 2026 Latest Caselaw 33 Cal/2
Judgement Date : 8 January, 2026
IN THE HIGH COURT AT CALCUTTA
(COMMERCIAL DIVISION) 2026:CHC-OS:2
ORIGINAL SIDE
RESERVED ON: 06.01.2026
DELIVERED ON: 08.01.2026
PRESENT:
HON'BLE JUSTICE GAURANG KANTH
AP-COM- 545 OF 2025
SAI SURFACTANTS PRIVATE LIMITED
VERSUS
AMRIT CEMENT LIMITED
Mr. Chayan Gupta, Adv.
Mr. Uttam Sharma, Adv.
Mr. Ankit Prakash, Adv.
..... for the petitioner
Mr. Jishnu Chowdhury, Sr. Adv.
Mr. Sankarsan Sarkar, Adv.
Ms. Bhawna Parasramka, Adv.
Mr. Udipt Daga, Adv.
..... for the respondent
JUDGMENT
Gaurang Kanth, J.:-
1. The Petitioner has preferred the present petition under Section 9 of the
Arbitration and Conciliation Act, 1996 seeking interim protection, inter
alia, by directing the Respondent to furnish security to the tune of Rs.
63,45,690/- so as to secure the monetary claim proposed to be pursued by
the Petitioner against the Respondent in the arbitral proceedings.
2. The facts leading to the present case are as follows:
3. The Petitioner is a registered MSME enterprise engaged in the manufacture
and supply of polypropylene (PP) woven bags. The Respondent is engaged
in the manufacture of cement.
4. Between May 2024 and June 2024, the Respondent placed purchase
orders upon the Petitioner for laminated polypropylene bags, PP woven
bags and Block Bottom Bags (PPC trade). Pursuant thereto, supplies
2026:CHC-OS:2 aggregating to 10,08,000 cement bags were effected, having an aggregate
invoice value of Rs.1,45,54,214.40/-. The contractual terms provided for
payment within 30 days from the date of the respective invoices.
5. Payments to the extent of Rs.88,78,288/- were made by the Respondent
against the said supplies. The balance amount of Rs.56,06,854/- remains
disputed. The record also reflects to a virtual meeting held on 18.09.2024
in connection with the issue of outstanding payments.
6. The Respondent issued a debit note dated 21.09.2024 for an amount of
Rs.55,65,287/-. Subsequent correspondence exchanged between the
parties, including emails dated 25.09.2024 and 12.10.2024, indicates that
objections were raised by the Respondent with regard to the quality of the
supplied bags.
7. Demand notices dated 19.12.2024 and 21.12.2024 were issued by the
Petitioner. The Respondent replied thereto on 02.01.2025, reiterating its
objections concerning the quality of the goods supplied.
8. On the basis of the materials placed on record, the Petitioner asserts that
as on 20.03.2025 a sum of Rs.63,45,690/-, inclusive of contractual
interest at the rate of 18% per annum, remains outstanding. Invoking the
arbitration clause providing for adjudication at Kolkata, the present
application has been filed under Section 9 of the Arbitration and
Conciliation Act, 1996 seeking interim measures pending commencement
and conclusion of arbitral proceedings.
Submission on behalf of the Petitioner
9. Mr. Chayan Gupta, learned counsel for the Petitioner submits that the
supplies were effected strictly in terms of the purchase orders and were
2026:CHC-OS:2 duly delivered and utilised by the Respondent. Part payments aggregating
to Rs.88,78,288/- were made, evidencing acceptance of the supplies. The
balance amount remained unpaid beyond the stipulated credit period,
notwithstanding discussions held on 18.09.2024 in relation to the
outstanding dues.
10. It is submitted that the Respondent was governed by a Standard Operating
Procedure (SOP) prescribing the mechanism for sampling, inspection,
acceptance and rejection of laminated polypropylene bags. The SOP
prescribes detailed protocols including Bag Inspection (page Nos. 35-36),
Breaking Strength and Weld Strength (page No. 38), Acceptance Criteria
(page No. 39), Assessment Procedures (page Nos. 39-40), Elongation Test
(page No. 40), Ash Content (page Nos. 40-41), and rejection norms on the
packing floor (page No. 45). It is the Petitioner's contention that the
Respondent failed to adhere to any of these mandatory procedures.
11. It is submitted that only a solitary joint inspection was undertaken on
11.07.2024. As per the inspection report, out of 6,31,695 bags examined,
only 3,336 were found damaged, amounting to 0.53%, which is well within
the permissible tolerance. No subsequent joint inspection was conducted,
nor was the Petitioner ever notified of any further defects. The Respondent
utilised the supplies, made part payment and acknowledged liability on
18.09.2024. However, on 21.09.2024, the respondent issued a debit note
for Rs. 55,65,287/-, seeking to nullify its obligation. It is contended that
the Respondent neither rejected the goods nor adhered to the SOP
mandated rejection procedure and, having appropriated the supplies, is
not entitled to withhold payment on belated quality objections.
2026:CHC-OS:2
12. It is submitted that as on 20.03.2025, a sum of Rs.63,45,690/-, inclusive
of contractual interest at the rate of 18% per annum, remains outstanding.
Invoking the arbitration clause providing for adjudication at Kolkata, the
present application has been filed under Section 9 of the Arbitration and
Conciliation Act, 1996 seeking interim protection. Reliance is placed on
Essar House Pvt. Ltd. v. Arcelor Mittal Nippon Steel India Ltd.,
reported as (2022) 20 SCC 178.
Submission on behalf of the Respondent
13. Per contra, Mr. Jishnu Chowdhury, learned Senior counsel appearing on
behalf of the Respondent submits that the present application under
Section 9 of the Arbitration and Conciliation Act, 1996 is misconceived and
not maintainable. It is contended that Section 9 does not mandate
furnishing of security in every case involving a monetary claim,
particularly where the alleged outstanding amount is seriously disputed.
14. Learned Senior Counsel appearing on behalf of the Respondent submits
that under a single purchase order, supplies were made in five
consignments dated 31.05.2024, 19.06.2024, 21.06.2024, 26.06.2024 and
29.06.2024. Attention is drawn to page 49 of the SOP, which sets out the
technical specifications of laminated polypropylene bags, including the
requirement that none of the sacks shall fail the drop impact strength test.
Learned Senior Counsel further refers to page 77, being the test report in
respect of the consignment supplied on 19.06.2024, to demonstrate that
the said lot failed the drop impact strength test and was, therefore,
rejected in its entirety. It is submitted that the rejected lot constituted
approximately 20% of the total quantity supplied.
2026:CHC-OS:2
15. Learned Senior Counsel further submits that the joint inspection
conducted on 11.07.2024 pertained only to three consignments and that
even during such inspection the drop impact strength test was found to be
unsatisfactory. It is contended that the Petitioner, in its own handwriting,
acknowledged the deficiencies, assured improvement in quality, and
requested the Respondent to utilise the bags. Reliance is placed on Clause
'M' of the SOP, which provides that where a rejected lot is nevertheless
utilised due to operational exigencies, the bags are to be accepted at 50%
of the contract price. In the present case, it is submitted that the
Respondent has already paid approximately 61% of the total value of the
supplies, which, according to the Respondent, is in excess of the amount
payable even on a discounted basis.
16. Learned counsel submits that the Respondent is a solvent and going
concern, fully capable of satisfying any award that may be passed in
arbitration. There is no material on record to suggest dissipation of assets
or any attempt to defeat enforcement of a prospective award. Mere
assertion of apprehension is insufficient to invoke the jurisdiction under
Section 9. It is contended that the principles underlying Order XXXVIII
Rule 5 of the Code of Civil Procedure, 1908 must be satisfied before
directing furnishing of security or attachment, which have not been met in
the present case.
17. It is accordingly submitted that the Petitioner has failed to establish a
prima facie case, balance of convenience, or irreparable prejudice
warranting grant of interim protection. The reliefs sought would, in effect,
amount to granting final relief at an interlocutory stage. The application is
therefore liable to be dismissed.
2026:CHC-OS:2 Legal Analysis
18. This Court has heard learned counsel for the parties at length and has
perused the pleadings, documents and materials placed on record.
19. From the record, it emerges that supplies were made by the Petitioner
pursuant to the purchase orders and that substantial part payments have
been effected by the Respondent. The surviving dispute relates to a sum of
Rs.56,06,854/-. According to the Respondent, the admitted liability stands
discharged and the balance claimed pertains to materials allegedly rejected
on account of quality issues, rendering the said amount disputed.
20. The SOP placed on record prescribes detailed technical specifications and
quality benchmarks, including the stipulation that none of the sacks shall
fail the drop impact strength test. It also provides a structured mechanism
for inspection, rejection and conditional acceptance at a discounted value.
The Respondent has relied upon the test report relating to the
consignment supplied on 19.06.2024 to contend that the said lot failed the
drop impact strength test and was rejected in its entirety, constituting
approximately 20% of the total supply. The Petitioner, on the other hand,
relies upon the joint inspection dated 11.07.2024, which records a defect
rate of 0.53%, and contends that no further inspection in accordance with
the SOP was undertaken thereafter.
21. The materials on record indicate that the joint inspection dated 11.07.2024
pertained only to certain consignments and that disputes exist as to
whether the allegedly rejected consignments were nevertheless utilised
and, if so, on what terms. The alleged handwritten assurance by the
Petitioner regarding improvement of quality, as well as the applicability of
Clause 'M' of the SOP providing for acceptance at a discounted rate, raise
2026:CHC-OS:2 issues requiring examination of contemporaneous records and evidence.
These matters cannot be conclusively determined at the present
interlocutory stage.
22. It is also evident that only one joint inspection was conducted. Prima facie,
the rejection of subsequent consignments without recourse to the
inspection mechanism contemplated under the SOP raises a triable issue.
At the same time, it is not in dispute that the Respondent has utilised at
least part of the goods supplied, which lends prima facie support to the
Petitioner's contention that the claim is not illusory. Conversely, the
Respondent's reliance on technical test failures and alleged non-conformity
with specifications cannot be brushed aside as frivolous. The dispute thus
involves mixed questions of fact and contractual interpretation, falling
within the domain of arbitral adjudication.
23. In proceedings under Section 9 of the Arbitration and Conciliation Act,
1996, this Court is not required to conduct a mini trial or return definitive
findings on the merits. The Court is required to assess whether interim
protection is necessary to preserve the efficacy of the arbitral process.
Where the claim is monetary, the Court must be satisfied that the
circumstances justify securing the claim without converting the interim
measure into final relief.
24. The balance of convenience, at this stage, leans in favour of the Petitioner.
The Petitioner, an MSME entity, asserts that more than Rs.63 lakh
remains outstanding despite supply and utilisation of the goods. Delay in
securing the claim may cause disproportionate hardship to the Petitioner,
whereas a calibrated protective direction is unlikely to prejudice the
Respondent, who asserts financial robustness. The apprehension that
2026:CHC-OS:2 enforcement of any eventual award may be rendered ineffective cannot be
discounted altogether.
25. The Respondent's contention that relief under Section 9 must strictly
satisfy the preconditions of Order XXXVIII Rule 5 CPC cannot be accepted
in absolute terms. As clarified by the Supreme Court in Essar House Pvt.
Ltd (supra)., while the principles underlying Order XXXVIII Rule 5 may
guide the exercise of discretion, they do not constitute rigid jurisdictional
limitations on the Court's powers under Section 9.
26. Balancing the rival equities and without expressing any opinion on the
merits of the dispute, this Court is of the view that limited interim
protection would subserve the ends of justice and safeguard the arbitral
proceedings from being rendered nugatory.
27. Accordingly, in order to secure the subject matter of the arbitration and
without expressing any opinion on the merits of the disputes between the
parties, the Respondent is directed to create an interest bearing fixed
deposit in the name of Registrar General, Original Side of this Court for a
sum of Rs.63,45,690/- with a nationalised bank within a period of two
weeks from date, for an initial period of six months. The said fixed deposit
shall be kept renewed and shall be placed before the Arbitral Tribunal
upon its constitution for appropriate custody and further directions.
Liberty is granted to the parties to seek modification or variation of this
order before the Arbitral Tribunal, in accordance with law.
28. With this direction, the present petition is allowed and disposed of.
(GAURANG KANTH, J.)
Sakil Amed P.A.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!