Citation : 2026 Latest Caselaw 1322 Cal/2
Judgement Date : 24 February, 2026
ORDER OCD - 21
IN THE HIGH COURT AT CALCUTTA
COMMERCIAL DIVISION
ORIGINAL SIDE
AP-COM/118/2026
M/S. BISWANATH BHATTACHARJEE
VS
GARRISON ENGINEER (CENTRAL) AND ANR.
BEFORE:
The Hon'ble JUSTICE SHAMPA SARKAR
Date: 24th February 2026
Appearance:-
Mr. Tanmoy Sett, Advocate
Mr. Pran Gopal Das, Advocate
... for the petitioner.
Mr. Sunil Singhania, Advocate
Ms. Priti Jain, Advocate
... for the respondents.
1. The petitioner is a registered partnership firm. The respondent no.1
issued a notice inviting tender on January 17, 2024. The tender was for
special repair work relating to sewage line at Strandline under GE
(Central), Kolkata. The petitioner submitted its bid. The petitioner was
the successful bidder. The respondent no.1 issued a letter of acceptance
on September 11, 2024. A formal contract was executed between the
parties on the same day as the letter of acceptance i.e. September 11,
2024. A work order was issued and the date of commencement of the
work was scheduled as October 5, 2024. It is contended that the General
Conditions of Contract (IAFW-2249) and its subsequent amendments were
made applicable to the subject contract.
2. According to the petitioner, complete work site was not handed over at any
point of time and as such, the petitioner could not commence the work
within the stipulated time. It is the specific contention of the petitioner
that although samples of the materials to be used for the work were sent
to the respondents, the same were never approved on time. Thus, the
delay occurred. The petitioner brought the delay in the approval of the
samples to the notice of the respondents, but the respondents did not take
any action and suddenly, by a letter dated December 4, 2024, the
petitioner was informed by the respondents that the petitioner was not
discharging its obligations under the contract and 15 days notice was
given to the petitioner to commence the work. The petitioner was asked to
show cause by a letter dated December 9, 2024, why the petitioner shall
not be banned from any future tendering process. The respondents
alleged that the petitioner had failed to commence the work and fulfill its
obligations under the contract. By a letter dated December 16, 2024, the
petitioner replied to the said letter and recorded that unless the complete
physical work site was handed over to the petitioner, the petitioner would
not be in a position to commence the work. The work site was handed
over on December 16, 2024 and the petitioner commenced work under the
contract on December 17, 2024. By a letter dated January 17, 2025, a
final notice was given to the petitioner. Meetings were held between the
parties. The disputes were not resolved and by a letter dated February 12,
2025, the agreement was cancelled and the contract was terminated with
effect from February 14, 2025. Although the petitioner requested the
respondent no.1 to revoke the letter of cancellation, the said respondent
did not do so. It is the specific contention of the petitioner that 30% of the
work had been completed to the satisfaction of the respondents and the
respondents had illegally ousted the petitioner from the work site and
tried to blacklist the petitioner. Another notice inviting tender was issued
on April 22, 2025, with respect to remaining works. The petitioner filed an
application under Section 9 of the Arbitration and Conciliation Act, 1996
before the appropriate civil court and an order was passed restraining the
respondents from branding / endorsing the petitioner with "slow progress"
or that the "petitioner was not entitled to more workload" etc. The
respondents were further restrained from preventing the petitioner from
taking up future contracts to be floated by the respondent no.1.
3. Disputes and differences arose not only with regard to termination, but
also with regard to non-payment of bills and the losses suffered by the
petitioner on account of such termination. The petitioner claims cost of
idle labour, non-refund of the performance guarantee, non-refund of
security deposit etc. and the petitioner has quantified the claim to be more
than Rs.20 lakh. Clause 70 of the GCC contains an arbitration clause, for
settlement of disputes by a sole arbitrator. The said clause also provides
that in cases of cancellation of the contract, reference shall not be made
until alternative arrangement has been made by the government to get the
work completed through another agency or contractor. In this case, it is
submitted that another agency had already been engaged for completion of
the work. It is further submitted that although the clause provides for
settlement of disputes by a serving officer of the respondents, the said
provision is no more permissible in law and the referral court must
appoint an arbitrator. The notice invoking arbitration was issued on
September 10, 2025. The respondents asked the petitioner to sign an
agreement thereby waiving the applicability of section 12(5) of the
Arbitration and Conciliation Act, 1996. The petitioner did not agree.
4. Mr. Singhania, learned advocate for the respondents, submits that the
dispute is not arbitrable. The petitioner was not entitled to any claim as
the petitioner did not commence the work on time. It is further submitted
that the GCC permitted termination of the contract upon notice, which
was done and the answer to the show cause notice was not found
satisfactory. The authority denied the claims of the petitioner.
5. Having heard the learned advocates for the respective parties, it is, prima
facie, evident that there are disputes between the parties. The arbitration
clause contained in the GCC applies to the subject contract. The
petitioner has duly invoked arbitration. Unilateral appointment of an
Arbitrator from an employee of the respondents is not legally permissible.
6. Under such circumstances, this application is allowed by appointing Mr.
Debasish Roy, Senior Advocate [9831173923], as the sole arbitrator, to
arbitrate upon the disputes between the parties. The learned Arbitrator
shall comply with the provisions of Section 12 of the Arbitration and
Conciliation Act, 1996. The learned Arbitrator shall be at liberty to fix his
remuneration as per the schedule of the Arbitration and Conciliation Act,
1996.
7. All questions as to the arbitrability of the issues, admissibility of the
claims, limitation etc, shall be decided by the learned arbitrator, if so
raised.
8. AP-COM 118 of 2026 is disposed of accordingly.
(SHAMPA SARKAR, J.)
S. Kumar
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!