Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Biswanath Bhattacharjee vs Garrison Engineer (Central) And Anr
2026 Latest Caselaw 1322 Cal/2

Citation : 2026 Latest Caselaw 1322 Cal/2
Judgement Date : 24 February, 2026

[Cites 4, Cited by 0]

Calcutta High Court

M/S. Biswanath Bhattacharjee vs Garrison Engineer (Central) And Anr on 24 February, 2026

Author: Shampa Sarkar
Bench: Shampa Sarkar
 ORDER                                                               OCD - 21
                     IN THE HIGH COURT AT CALCUTTA
                          COMMERCIAL DIVISION
                             ORIGINAL SIDE

                            AP-COM/118/2026
                    M/S. BISWANATH BHATTACHARJEE
                                  VS
                 GARRISON ENGINEER (CENTRAL) AND ANR.

BEFORE:
The Hon'ble JUSTICE SHAMPA SARKAR
Date: 24th February 2026
                                                                    Appearance:-
                                                      Mr. Tanmoy Sett, Advocate
                                                   Mr. Pran Gopal Das, Advocate
                                                            ... for the petitioner.
                                                   Mr. Sunil Singhania, Advocate
                                                         Ms. Priti Jain, Advocate
                                                          ... for the respondents.

1. The petitioner is a registered partnership firm. The respondent no.1

issued a notice inviting tender on January 17, 2024. The tender was for

special repair work relating to sewage line at Strandline under GE

(Central), Kolkata. The petitioner submitted its bid. The petitioner was

the successful bidder. The respondent no.1 issued a letter of acceptance

on September 11, 2024. A formal contract was executed between the

parties on the same day as the letter of acceptance i.e. September 11,

2024. A work order was issued and the date of commencement of the

work was scheduled as October 5, 2024. It is contended that the General

Conditions of Contract (IAFW-2249) and its subsequent amendments were

made applicable to the subject contract.

2. According to the petitioner, complete work site was not handed over at any

point of time and as such, the petitioner could not commence the work

within the stipulated time. It is the specific contention of the petitioner

that although samples of the materials to be used for the work were sent

to the respondents, the same were never approved on time. Thus, the

delay occurred. The petitioner brought the delay in the approval of the

samples to the notice of the respondents, but the respondents did not take

any action and suddenly, by a letter dated December 4, 2024, the

petitioner was informed by the respondents that the petitioner was not

discharging its obligations under the contract and 15 days notice was

given to the petitioner to commence the work. The petitioner was asked to

show cause by a letter dated December 9, 2024, why the petitioner shall

not be banned from any future tendering process. The respondents

alleged that the petitioner had failed to commence the work and fulfill its

obligations under the contract. By a letter dated December 16, 2024, the

petitioner replied to the said letter and recorded that unless the complete

physical work site was handed over to the petitioner, the petitioner would

not be in a position to commence the work. The work site was handed

over on December 16, 2024 and the petitioner commenced work under the

contract on December 17, 2024. By a letter dated January 17, 2025, a

final notice was given to the petitioner. Meetings were held between the

parties. The disputes were not resolved and by a letter dated February 12,

2025, the agreement was cancelled and the contract was terminated with

effect from February 14, 2025. Although the petitioner requested the

respondent no.1 to revoke the letter of cancellation, the said respondent

did not do so. It is the specific contention of the petitioner that 30% of the

work had been completed to the satisfaction of the respondents and the

respondents had illegally ousted the petitioner from the work site and

tried to blacklist the petitioner. Another notice inviting tender was issued

on April 22, 2025, with respect to remaining works. The petitioner filed an

application under Section 9 of the Arbitration and Conciliation Act, 1996

before the appropriate civil court and an order was passed restraining the

respondents from branding / endorsing the petitioner with "slow progress"

or that the "petitioner was not entitled to more workload" etc. The

respondents were further restrained from preventing the petitioner from

taking up future contracts to be floated by the respondent no.1.

3. Disputes and differences arose not only with regard to termination, but

also with regard to non-payment of bills and the losses suffered by the

petitioner on account of such termination. The petitioner claims cost of

idle labour, non-refund of the performance guarantee, non-refund of

security deposit etc. and the petitioner has quantified the claim to be more

than Rs.20 lakh. Clause 70 of the GCC contains an arbitration clause, for

settlement of disputes by a sole arbitrator. The said clause also provides

that in cases of cancellation of the contract, reference shall not be made

until alternative arrangement has been made by the government to get the

work completed through another agency or contractor. In this case, it is

submitted that another agency had already been engaged for completion of

the work. It is further submitted that although the clause provides for

settlement of disputes by a serving officer of the respondents, the said

provision is no more permissible in law and the referral court must

appoint an arbitrator. The notice invoking arbitration was issued on

September 10, 2025. The respondents asked the petitioner to sign an

agreement thereby waiving the applicability of section 12(5) of the

Arbitration and Conciliation Act, 1996. The petitioner did not agree.

4. Mr. Singhania, learned advocate for the respondents, submits that the

dispute is not arbitrable. The petitioner was not entitled to any claim as

the petitioner did not commence the work on time. It is further submitted

that the GCC permitted termination of the contract upon notice, which

was done and the answer to the show cause notice was not found

satisfactory. The authority denied the claims of the petitioner.

5. Having heard the learned advocates for the respective parties, it is, prima

facie, evident that there are disputes between the parties. The arbitration

clause contained in the GCC applies to the subject contract. The

petitioner has duly invoked arbitration. Unilateral appointment of an

Arbitrator from an employee of the respondents is not legally permissible.

6. Under such circumstances, this application is allowed by appointing Mr.

Debasish Roy, Senior Advocate [9831173923], as the sole arbitrator, to

arbitrate upon the disputes between the parties. The learned Arbitrator

shall comply with the provisions of Section 12 of the Arbitration and

Conciliation Act, 1996. The learned Arbitrator shall be at liberty to fix his

remuneration as per the schedule of the Arbitration and Conciliation Act,

1996.

7. All questions as to the arbitrability of the issues, admissibility of the

claims, limitation etc, shall be decided by the learned arbitrator, if so

raised.

8. AP-COM 118 of 2026 is disposed of accordingly.

(SHAMPA SARKAR, J.)

S. Kumar

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter