Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Centex (India) Engineers (P) Limited vs Executive Engineer/Brl
2024 Latest Caselaw 3046 Cal/2

Citation : 2024 Latest Caselaw 3046 Cal/2
Judgement Date : 1 October, 2024

Calcutta High Court

Centex (India) Engineers (P) Limited vs Executive Engineer/Brl on 1 October, 2024

Author: Sabyasachi Bhattacharyya

Bench: Sabyasachi Bhattacharyya

                  IN THE HIGH COURT AT CALCUTTA
                  Ordinary Original Civil Jurisdiction
                           ORIGINAL SIDE


     The Hon'ble Justice Sabyasachi Bhattacharyya



                          A.P. No. 492 of 2021

                  Centex (India) Engineers (P) Limited
                                  Vs.
                       Executive Engineer/BRL,
                   Eastern Railway, Sealdah & Anr.



     For the Petitioner      :     Mr. D. Sahu, Adv.
                                   Mr. A. Nair, Adv.

     For the respondent      :     Ms. Sanjukta Gupta, Adv.
     Hearing concluded on    :     23.09.2024

     Judgment on             :     01.10.2024




     Sabyasachi Bhattacharyya, J:-

1. The petitioner participated in a tender floated by the Eastern Railway

and, being successful in the tender process, was awarded a Letter of

Award (LoA) on February 20, 2017. As per the terms of the tender, as

adopted in the LoA, the General Conditions of Contract (GCC) of the

Railways was a part of the contract. Clause 64 of the same having

contained an arbitration clause, a dispute which arose between the

parties was sought to be referred to arbitration. Such invocation was

by a notice dated July 16, 2021 issued by the petitioner to the General

Manager (GM), Eastern Railway.

2. The scope of the dispute was alleged non-payment of dues for work

done by the petitioner to the tune of Rs.74,81,490/-. The petitioner,

in its previous demand letters, had also sought for loss and damages

as well as interest.

3. The petitioner, in its invocation notice, stated that Clause 64 of the

GCC-2001 was no longer applicable since the Railway was not eligible

to appoint a serving Railway Official as arbitrator in view of the

restriction imposed by the Seventh Schedule introduced by the

Arbitration (Amendment) Act, 2015 and sent names as suggestions for

a three-Member arbitral panel. The Eastern Railway having not

agreed, the present application has been filed.

4. Learned counsel for the petitioner argues that Clause 64(3)(a)(ii) of the

GCC-2001, as modified in 2016, is in conflict with Section 12(5), read

with the Seventh Schedule, Entry No.1 of the Arbitration and

Conciliation Act, 1996 (hereinafter referred to as "the 1996 Act"). It is

further submitted that the petitioner has never waived, rather has

specifically refused to waive, applicability of Section 12(5) of the 1996

Act.

5. Learned counsel for the petitioner cites Rajpath Contractors and

Engineers Ltd. vs. Union of India and Anr. [AP/637/2023], a co-

ordinate Bench judgment of this Court, where the judgment of Central

Organization for Railway Electrification vs. ECI-SPIC-SMO-MCML (JV) A

Joint Venture Company, reported at (2020) 14 SCC 712 was considered

and Glock Asia-Pacific Limited vs. Union of India, reported at (2023) 8

SCC 226 was relied on. It is submitted that Clause 64 was considered

in the said judgment and it was observed that the same is violative of

Section 12(5) and, accordingly, an independent arbitrator was

appointed by the Court.

6. Learned counsel for the petitioner submits that, even assuming that

Clause 64 was modified by incorporating retired Railway officers

instead of serving officers to be nominated as arbitrators, since the

GM of the Eastern Railway is vested with the absolute power to

actually appoint one of such persons, it tantamounts to unilateral

appointment.

7. It is argued that the reasoning in Central Organization (supra) that the

advantage of one party in appointing its nominee arbitrator is counter-

balanced by the power of the other party to appoint its nominee

arbitrator is not applicable here as effectively the GM of the Eastern

Railway, under the modified Clause 64(3)(b)(ii), is bestowed with

absolute power to appoint all the three arbitrators.

8. Learned counsel also relies on another co-ordinate Bench judgment in

the matter of Mehrotra Buildcon Pvt. Ltd. vs. South Eastern Railway,

reported at 2023 SCC OnLine Cal 5050, where it was held that nothing

can be more one-sided than this and that the absence of consent and

choice is writ large in Clause 64(3)(b)(ii) of the GCC.

9. Regarding the argument of the respondents that the concerned GCC

clause was amended, as reflected in the Railway Board‟s letter dated

November 16, 2016, the petitioner argues that a contradictory stand

has been taken by the respondents. Nothing on record shows that

GCC-2001 was ever modified and the letter relied on by the

respondent mentions modification of GCC-2014 and not GCC-2001.

Moreover, the respondents, in their letters seeking waiver of Section

12 (5), relied on a modification of GCC-2020 which is post-termination

and does not mention any modification of GCC-2001.

10. Assuming but not admitting that there was modification in the

relevant clause of GCC-2001, it is argued that a party to the contract

cannot unilaterally modify or vary or amend any term or condition of a

contract. In support of such contention, learned counsel cites a

Division Bench judgment of this Court in Union of India vs.

Inschrotech, reported at 2017 SCC OnLine Cal 21549.

11. It is argued that circulars/notifications/letters cannot ipso facto

change any term or condition of contract unilaterally. The said issue,

it is argued, did not fall for consideration in Central Organization

(supra).

12. The petitioner, accordingly, prays for appointment of a sole arbitrator,

which is contended to have been agreed upon by learned counsel for

the respondent at the time of hearing.

13. Learned counsel for the petitioner further reiterates that the terms

and conditions of a contract cannot be changed unilaterally without

consent of both parties. Hence, applicability of the allegedly modified

Clause 64(3)(b) cannot be considered to be a part of the arbitration

agreement in terms of Section 7 of the 1996 Act. Learned counsel

relies in this regard on a co-ordinate Bench judgment in AP 297 of

2018 [Techma Engineering Enterprices Pvt. Ltd. vs. Union of India

through General Manager (Engineering) South Eastern Railway].

14. The modified Clause 64(3)(b), the petitioner submits, is contrary to the

judgments of the Supreme Court which deprecate unilateral

appointment of arbitrator. Learned counsel cites Gangotri Enterprises

Ltd. vs. General Manager Northern Railways, reported at 2022 SCC

OnLine Del 3556 in such context. It is argued that Central

Organization (supra) did not overrule other judgments such as Bharat

Broadband Network Ltd. vs. United Telecoms Ltd., reported at (2019) 5

SCC 755 and Perkins Eastman Architects DPC vs. HSCC (India) Ltd.,

reported at (2020) 20 SCC 760, which still govern the field, where

unilateral appointment of arbitration has been held to be violative of

the law.

15. Moreover, the Supreme Court in Union of India vs. M/s Tantia

Constructions Limited, reported at 2021 SCC OnLine SC 271, prima

facie expressed disagreement with Central Organization (supra), which

was also relied on by the Supreme Court in JSW Steel Limited vs.

South Western Railway, reported at 2022 SCC OnLine SC 1973.

16. Learned counsel appearing for the respondents, on the other hand,

submits, by handing over a list of suggested arbitrators comprised of

retired Railway officers, disclosing their dates of retirement and other

particulars, that the Eastern Railway does not have any objection if an

arbitrator is appointed from the said list. Having said so, the

respondents contend that the petitioner has prayed for appointment of

a sole arbitrator by relying on Clause 64 of the GCC and, as such,

have waived the bar under Section 12 within the contemplation of

sub-section (5) thereof.

17. A modification to Clause 64 of the GCC-2001 was brought about by a

Notification dated November 16, 2016 whereby, in cases where

applicability of Section 12 (5) has been waived, the Arbitral Tribunal

shall consist of a panel of three gazetted Railway officers not below

Junior Administrative Grade or two gazette officers not below GA

Grade and a retired Railway Officer, not below the rank of Senior

Administrative Grade officers.

18. Clause 64(3)(b) deals with situations where applicability of Section

12(5) has not been waived off, which stipulates that the arbitral panel

shall be of three Railway officers, not below the rank of Senior Grade

officers.

19. It is argued that the respondents have provided the petitioner with an

extensive panel consisting of retired senior Railway officers, which is

wide enough for the petitioner to choose from. In Mehrotra Buildcon

(supra), the learned Single Judge held that the panel was too narrow,

being comprised of four names, which has been taken care of by

furnishing a wide enough panel in the present case. Secondly, the

learned Single Judge failed to provide distinct reasons as to why the

particular facts and circumstances of the said case were different from

Central Organization (supra).

20. Learned counsel for the respondents next contends that Central

Organization (supra) dealt with the modified clauses of the GCC, being

Clause 64(3)(a)(ii) and Clause 64(3)(b) and, as such, the ratio laid

down in the said report is binding in the present case. The same has

also been followed by a learned Single Judge in ITD-ITD CEM Joint

Venture vs. Kolkata Metro Rail Corporation Ltd., reported at 2021 SCC

OnLine Cal 2337.

21. It is argued that in case of conflicting judgments by Benches of equal

strength of the Supreme Court, the earlier one is to be followed, as

held in National Insurance Co. Ltd. vs. Pranay Sethi, reported at (2017)

16 SCC 680. The respondents also cite the case of Union Territory of

Ladakh & Ors. vs. Jammu and Kashmir National Conference & Anr.,

reported at 2023 SCC OnLine SC 1140, where the Supreme Court

reiterated the same proposition.

22. Accordingly, it is submitted that the present application under Section

11(6) of the 1996 Act be dismissed.

23. Upon hearing learned counsel for the parties, the Court arrives at the

following conclusions:

24. Several issues have arisen in the present case which are as follows -

i) Whether the relevant Clauses of GCC-2001 contemplate a

unilateral appointment of arbitrators; if so, what would be the

effect thereof.

ii) Whether the appointment of retired employees of the Railways

as arbitrators can be construed to be a violation of the law as

embodied in Section 12(5) of the 1996 Act and the Fifth and

Seventh Schedules of the 1996 Act.

iii) Whether the modification in Clause 64 of GCC-2001 by the

Government Notification dated November 16, 2016 comprises a

unilateral alteration of the contract between the parties; if so,

what would be the effect of the same.

iv) Whether there has been a waiver under Section 12(5) of the

1996 Act in the present case.

Such issues are dealt with below.

i) Whether the relevant Clauses of GCC-2001 contemplate a

unilateral appointment of arbitrators; if so, what would be

the effect thereof.

25. Conflicting judgments of co-ordinate Benches of this Court have been

cited by both parties in this context. The petitioner cites Rajpath

Contractors (supra) and Mehrotra Buildcon (supra) whereas the

respondents cite Techma Engineering Enterprices (supra), M/s Tantia

Constructions and ITD-ITD CEM (supra).

26. In addition, the petitioners have also referred to Glock Asia-Pacific

Limited (supra).

27. The above judgments have to be appreciated in the backdrop of

Central Organization (supra), which is the plinth of the respondents‟

case, more so, since Clause 64 of the GCC of the Railways and its

sub-clauses, which fall for consideration in the instant case, were also

discussed there.

28. In M/s Tantia Constructions (supra), a Supreme Court Bench of the

same strength as Central Organization (supra), comprised of three

Judges of the Supreme Court, disagreed with the ratio laid down in

Central Organization (supra) for the basic reason that once the

appointing authority itself is incapacitated for referring the matter to

arbitration, it does not then follow that notwithstanding this yet

appointments may be valid depending on the facts of the case.

29. Another Bench of equal strength, in the matter of JSW (supra), relied

on M/s Tantia Constructions (supra) to refer the issue to a larger

Bench.

30. Thus, here we are faced with contradictory judgments of the Supreme

Court on the same issue by Benches of equal strength. Although in

JSW (supra) no specific reason was given for differing as such, in M/s

Tantia Constructions (supra), the court clearly differed from Central

Organization (supra) on a specific ground.

31. In Union Territory of Ladakh (supra), the Supreme Court observed that

High Courts are not deciding cases on the ground that the leading

judgment of Supreme Court on the subject is either referred to larger

Bench or a review petition relating thereto is pending. The Supreme

Court also considered cases where the High Courts refused deference

to judgments on the score that a later co-ordinate Bench had doubted

its correctness. While holding so, the Supreme Court held that when

faced with conflicting judgments by Benches of equal strength of the

said Court, it is the earlier one which is to be followed by the High

Courts, as held by a Five-Judge Bench in National Insurance Co. Ltd.

(supra). However, in the very next sentence, the Supreme Court in

Union Territory of Ladhak (supra) went on to hold that the High

Courts, of course, will do so with careful regard to the facts and

circumstances of the case before it.

32. While considering the judgment in Union Territory of Ladhak (supra),

we cannot lose sight of the fact that the principle of following earlier

judgments as precedent was not set down as an absolute proposition

and the High Courts were cautioned to advert to the facts and

circumstances of the case.

33. The law of precedence is clear on the subject.

34. In cases where there are two conflicting judgments of same-strength

Benches and the later judgment does not take into consideration the

earlier, there cannot be any doubt that the earlier judgment prevails

and has to be followed by the High Courts.

35. However, if a later judgment of the Supreme Court of co-equal

strength considers and explains or clarifies or deals with an earlier

judgment, it is the later judgment which has binding effect on the

High Courts.

36. There is also a third view which has been expressed often by the

Supreme Court itself in a certain line of judgments, it being that, faced

with two conflicting judgments of the Apex Court, the High Courts are

required to follow the one which is more appropriate in the facts and

circumstances of the case and/or considered to be more

appropriate/better on point of law.

37. In the present case, in M/s Tantia Constructions (supra), a co-equal

Bench of the Supreme Court not only took notice of Central

Organization (supra), but clearly differed from the same upon citing a

particular ground and referred the matter to a larger Bench. Hence,

this Court is faced with the unenviable but unavoidable conundrum of

choosing one of the judgments from the two in the facts and

circumstances of the case. Avoiding such exercise on convoluted

reasoning would only postpone the issue and it would be more

appropriate if this Court deals with the said issue first.

38. A careful perusal of Central Organization (supra) shows that the

premise of the reasoning therein is paragraph no. 38 of the said

judgment. After detailing the facts in the said case, it was observed by

the three-Judge Bench of the Supreme Court in paragraph no. 38 that

since the respondent (contractor) has been given the power to select

two names from out of the four names of the panel, the power of the

appellant (Railways) nominating its arbitrator gets counter-balanced

by the power of choice given to the respondent. Thus, it was held that

the power of the GM to nominate the arbitrator is counter-balanced by

the power of the respondent-contractor to select any of the two

nominees from out of the four names suggested from the panel of the

retired Railway officers. On such premise, the Supreme Court

proceeded to observe that the GM is not ineligible to appoint,

nominate or act as an arbitrator.

39. With utmost respect, however, one aspect of Clause 64 of the GCC did

not fall for consideration before the said court and, as such, the ratio

therein cannot be considered to be a binding precedent on such

omitted issue. As per the modified Clause 64, both in cases where

there has been a waiver under Section 12(5) of the 1996 Act and

where there has not been such waiver, the entry point and the end

point of discretion vests in the GM of the Railways. It is the GM who

sends four names at the outset to the contractor for the latter to select

two out of those four names, upon which selection, the same reverts

back to the GM, who again selects one out of the two short-listed

candidates. Thus, literally, the first and last word in appointment of

arbitrators, even the contractor‟s nominee-member in the arbitral

tribunal, lies with the GM. The role of the contractor is merely to

short-list, and not select, out of the options given in the first place by

the GM himself. Such sandwiched „option‟ of the contractor between

two choices of the Railway‟s GM, is, thus, a non-option or a pseudo

option at best and not an option in its true sense.

40. That apart, two out of the total three arbitrators are, in any event,

appointed by the GM, thereby skewing the outcome of the arbitration

in favour of the Railways in a lopsided manner. Even if the petitioner

was to choose one of the arbitrators independently, the majority

arbitrators are chosen unilaterally by the GM, thereby rendering any

counter-balance between the powers of nomination of the parties

illusory.

41. The way the modified Clause 64 of the GCC has been oriented, the GM

of the Railway (who himself is a serving employee of the Railway and is

ineligible) gets to appoint all three arbitrators. The Railway‟s nominee

and third arbitrator are appointed straightaway by the GM as per the

said clause. Even the purported contractor‟s nominee is actually

chosen by the GM, at the first instance by suggesting a four-member

panel of which two are merely short-listed by the contractor, and

thereafter selecting one out of the said two who were also, in the first

place, suggested by the GM himself.

42. Hence, in effect, a thorough perusal of the relevant provisions of

Clause 64 of the GCC-2001, as modified, indicates that the

appointment of the Arbitral Tribunal is completely unilateral, which is

violative of Section 12(5) and the Fifth and Seventh Schedules of the

1996 Act as well as the propositions laid down in Perkins Eastman

(supra) and Glock Asia-Pacific Limited (supra). Hence, such aspect

having not been considered in Central Organization (supra), it cannot

be held that the latter judgment is a binding precedent on the said

aspect of the matter.

43. Secondly, in M/s Tantia Constructions (supra), the Supreme Court

disagreed with the ratio laid down in Central Organization (supra) on

the ground that the GM himself, being ineligible under Section 12(5)

read with the Fifth and Seventh Schedules, of the 1996 Act, cannot

nominate arbitrators, which is the well-established position of law

even otherwise. The said ground, thus, was also not considered in

Central Organization (supra).

44. Accordingly, in the facts of the present case, as narrated above, out of

the two judgments - Central Organization (supra) and M/s Tantia

Constructions (supra) - in the humble opinion of this Court, the latter

is more apt on point of law vis-à-vis the issues involved herein and,

accordingly, the ratio laid down in the latter is to be followed.

45. The appointment of the Arbitral Tribunal being clearly unilateral at

the behest of the Railways, the same is violative of the ratio of Perkins

Eastman (supra) and Glock Asia-Pacific Limited (supra) as well as the

provisions of Section 12(5) and the Fifth and Seventh Schedule of the

1996 Act and hence, is bad in law.

ii) Whether the appointment of retired employees of the

Railways as arbitrators can be construed to be a violation

of the law as embodied in Section 12(5) of the 1996 Act

and the Fifth and Seventh Schedules of the 1996 Act.

46. The Supreme Court, in Central Organization (supra), followed

Voestalpine Schienen GMBH v. Delhi Metro Rail Corpn. Ltd., reported at

(2017) 4 SCC 665 and State of Haryana PWD Haryana (B and R)

Branch v. G.F. Toll Road (P) Ltd. and others, reported at (2019) 3 SCC

505, in all of which it was held that retired employees of one of the

parties are excluded from the bar under Section 12(5) of the 1996 Act.

Hence, it is well-settled that retired employees of the Railways fall

outside the pale of the said bar and cannot be considered to be

ineligible as arbitrators within the contemplation of the 1996 Act.

47. There is a further logic to such proposition. Current employees have a

direct conflict of interest inasmuch as they have a decision-making

power on behalf of the Railways on issues which are directly the

subject-matter of the arbitration. Secondly, current employees can

potentially be incentivized in various manners, since they are still in

service, to elicit a biased view in favour of the employer. Hence,

potentially, there is an element of control which can be exerted by the

Railway, one of the parties to the dispute, on its current employee who

acts as the arbitrator.

48. On the contrary, in case of retired employees, their only attachment to

the employer lies in pensionary and retiral benefits which are

statutory and/or contractual benefits, independent and irrespective of

the outcome of an arbitral proceedings. Retired employees are outside

the scope of any incentivization or disincentivization by the employer.

Additionally, being in the service of the Railways throughout their

careers spanning over a considerable period of time, retired Railway

employees should have the necessary expertise to deal with the

technical aspects of the matters involved in connection with works

done for the Railways, which may be essential components of the

dispute.

49. Even in the present case, the underlying refrain of the petitioner has

been that it has no objection to a retired employee of the Railways

being appointed. However, the unilateral texture of Clause 64 is the

sticking point.

50. Seen from such perspective, this issue is answered in the negative.

Nomination of retired employees as members of the Arbitral Tribunal

cannot be construed to be violative of the law, since they are otherwise

eligible to be so nominated.

iii) Whether the modification in Clause 64 of GCC-2001 by the

Government Notification dated November 16, 2016

comprises a unilateral alteration of the contract between

the parties; if so, what would be the effect of the same.

51. The Division Bench judgment of this Court in the matter of

Inschrotech (supra), was in a different factual context. It was observed

that it is elementary that a contract cannot be altered by one party

without the consent of the other party thereto. There cannot be any

quarrel with the said proposition.

52. In Mehrotra Buildcon (supra), the Learned Single Judge of this Court

had insinuated, although not in specific terms, that the modification

in Clause 64 of the GCC-2001 comprised a unilateral alteration of the

contract clause.

53. Certain documents were, however, not placed before the learned

Single Judge and as such could not, in all fairness, have been

considered by the said Court while coming to such finding.

54. The LoA issued to the petitioner herein accepts unequivocally that the

work shall be executed in accordance with the terms and conditions

laid down in the tender. Clause 2.0 of the "Instruction to Tenderers",

which is a part of the tender document, provides that the GCC-969,

GCC-2001 and the L&M Schedule-1987/1996/2005/Eastern Railway

USSOR-2011 shall be read with all correction slips issued thereto

from time to time and shall form integral part of the tender document.

55. Thus, the petitioner submitted to the primacy of the provisions of

GCC-2001 along with all correction slips which may be issued in

respect thereof from time to time. Accordingly, the subsequent

modification of 2016 to Clause 64 is not so unilateral as it has been

made out by the petitioner to be, being premised on the accession of

the petitioner to the provisions of the tender document which, in turn,

apply GCC-2001 along with all subsequent corrections/modifications

to the parties.

56. Another aspect of the matter ought also to be considered. The GCC is

a universal set of General Conditions applying to all contractors of the

Railways throughout the territories of India and cannot be construed

to be skewed against any particular contractor, including the

petitioner. Thus, it cannot be said the modification is not applicable in

the present case. This issue is decided accordingly.

iv) Whether there has been a waiver under Section 12(5) of the

1996 Act in the present case.

57. In the present case, the petitioner, in its invocation letter dated July

16, 2021 itself, made it clear that it was not waiving the bar under

Section 12(5) 1996 Act, by categorically alleging that Clause 64 is not

applicable since the Railway is no longer eligible to appoint a serving

Railway Officer in terms of Clause 64.

58. The respondents suggest that by seeking a reference to sole Arbitrator

from the panel, the said clause was accepted, thereby waiving the bar

under Section 12(5). However, the petitioner, despite refuting the

applicability of the clause, independently offered appointment of a sole

Arbitrator which, in any event, is beyond Clause 64, since the said

clause contemplates a three-member Arbitral Tribunal, and not a sole

arbitrator, being appointed.

59. In any event, the proviso to Clause 12(5) of the 1996 Act itself provides

that parties may subsequent to dispute having arisen between them,

waive the applicability of sub-section (5) of Section 12 by an express

agreement in writing. Here, there is no express agreement in writing

subsequent to the dispute having arisen (even before the dispute

arose, for that matter).

60. Thus, there was no waiver in writing under the proviso to Section

12(5) in the instant case.

61. This issue, thus, is answered in the negative.

62. In view of the above discussions, there cannot be any doubt that

Clause 64 of GCC-2001, as modified, which contemplates unilateral

appointment of arbitrators by the GM of the Eastern Railway, who

himself is ineligible under Section 12, read with the Fifth and Seventh

Schedules as well as contrary to the Perkins Eastman Architects DPC

(supra) judgments and the Glock Asia-Pacific Limited (supra) judgment,

is violative of the law and not binding on the petitioner insofar as the

composition of the tribunal is concerned.

63. However, fact remains that the parties have agreed to accept Clause

64 only so far as reference of the dispute between them under the

contract to be made to an Arbitral Tribunal is concerned. As the

clause contemplates a three-member Tribunal, which per se is not

illegal, there cannot be any reason why the said modality should be

deviated from by the Court.

64. In such context, since the petitioner itself has all along agreed to

appointment of at least one Arbitrator from the panel of the retired

Officer of the Railways, it would only to be appropriate if the

respondent‟s nominee is selected from the last panel of such retired

Officers handed over in court by the respondents. Insofar as the

petitioner‟s nominee is concerned, in the opinion of this Court, a

learned Advocate of this Court may be so appointed. A retired Judge of

this Court would be the appropriate choice, in such case, as the third

and presiding Arbitrator to complete the constitution of the Arbitral

Tribunal.

65. Accordingly, AP No. 492 of 2021 is allowed on contest, thereby

appointing Ms. Deblina Lahiri (Mobile No. 9831155553), a member of

the Bar Association, as the nominee arbitrator of the petitioner, Mr.

Alakes Bandyopadhyay, Ex. FA & CAO, Metro Railway, Kolkata, as the

nominee Arbitrator on behalf of the respondents, and Justice Md.

Nizamuddin, a retired Judge of this Hon‟ble Court, as the third and

presiding Arbitrator, the three of whom would comprise of the arbitral

panel to decide the disputes between the parties. The above

appointments shall be subject to disclosures being obtained from each

of the above Arbitrators under Section 12 of the 1996 Act. The Arbitral

Tribunal shall, in consultation with the parties, fix their own

remuneration in terms of the 1996 Act, read with its Fourth Schedule.

66. There will be no order as to costs.

67. Urgent certified server copies, if applied for, be issued to the parties

upon compliance of due formalities.

( Sabyasachi Bhattacharyya, J. )

Later :-

After the above judgment is passed in open Court, learned

counsels for both parties submit that they are agreeable to a sole

arbitrator being appointed.

In view of such submission, the above order is modified to the

limited extent that paragraph no. 65 of the same shall stand deleted.

Instead, the following paragraph would go in as part of the above

judgment:

"Accordingly, AP 492 of 2021 is allowed on contest, thereby

appointing Ms. Deblina Lahiri (Mob No. 9831155553), a member of

the Bar Association, as the sole Arbitrator to resolve the dispute

between the parties, subject to disclosure being obtained from her

under Section 12 of the 1996 Act. The learned Arbitrator shall, in

consultation of the parties, fix her own remuneration in terms of the

1996 Act, read with its Fourth Schedule."

( Sabyasachi Bhattacharyya, J. )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter