Citation : 2023 Latest Caselaw 7209 Cal
Judgement Date : 17 October, 2023
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
W.P.A.NO. 21702 of 2023
Kamladityya Construction Private Limited and Another
Vs.
The Central Public Works Department and others
For the petitioners : Mr. Abhrajit Mitra,
Mr. Sakya Sen,
Mr. Satadeep Bhattacharya,
Ms. Sonia Sharma
For the Union of India : Mr. Indrajeet Dasgupta,
Mr. Subit Majumdar
Hearing concluded on : 10.10.2023
Judgment on : 17.10.2023
Sabyasachi Bhattacharyya, J:-
1. The Central Public Works Department (CPWD), respondent no.1, held
a tender for construction of a new campus of the Indian Institute of
Information Technology (IIIT) at Kalyani.
2. The petitioner no.1 participated and came out the successful bidder.
The work was entrusted to the petitioner no.1.
3. Subsequently, the petitioners could not complete the work within the
stipulated time. A termination notice was issued to the petitioners.
Challenging the same, the petitioners filed an application under
Article 226 of the Constitution, giving rise to WPA No. 16962 of 2022.
The petitioners were continued to be protected by an undertaking
given by the CPWD on July 29, 2022 that no steps would be taken
against the petitioners. Ultimately the writ petition was disposed of on
December 22, 2022. The court observed that the petitioners should
be directed to complete the remaining part of the project. It was
recorded that the admitted position was that the petitioners had
completed about seventy per cent of the project and only thirty per
cent remained to be completed. The apparent financial distress of the
petitioners, it was observed, may be addressed by a direction on the
CPWD to process the bill of Rs. 5 Cr., which was submitted by the
petitioners. It was also observed that the petitioners shall make every
effort to complete the remaining part of the work within a reasonable
time without further delay. The parties were directed to cooperate
with each other regarding the completion of the rest of the work.
4. Thereafter, on September 30, 2022, a Show-Cause Notice was issued
as to why the petitioners should not be debarred under Rule 13.6 of
the Rules of Enlistment of Contractors in CPWD, 2022.
5. The petitioners gave a written reply on October 14, 2022. Ultimately,
by the impugned Office Order dated August 28, 2023, the petitioner
no.1 was debarred for a period of two years from participating in
CPWD works.
6. The present challenge has been preferred against such debarment
order.
7. Learned senior counsel for the petitioners argues that in view of the
order of the coordinate Bench to continue the unfinished work and in
view of the extensions granted to that effect by the respondent-
Authorities, it is to be deemed that the grounds of proposed
termination were absolved.
8. It is argued that after having extended the time and conceded to the
order of the coordinate Bench and the termination having itself been
obliterated, the underlying breach which was the trigger for the
blacklisting/debarment lost force. The termination itself having been
effaced, the debarment based on the allegations for termination has to
go.
9. Placing reliance on Rule 13.6 of the Rules for Enlistment, it is argued
that the grounds for debarment of contractor invoked by the
respondents is that the petitioners failed to execute the contract or
violated any condition of the contract.
10. Under Clause 13.1 of the Rules, where the contractor has made
himself liable for disciplinary action, the enlisting authority shall have
the right to debar the defaulting contractor. Clause 13.2 says that the
enlisting authority shall initiate disciplinary case against an enlisted
contractor. Clause 13.4 provides that the disciplinary action against
an enlisted contractor may lead to penalties mentioned in Rule 13.6
and 13.7. Clause 13.7 speaks about debarment of contractor upon
service of a suitable show-cause notice. Clause 13.6 stipulates the
grounds for debarment.
11. In terms of Clause 13.4, it is argued that a disciplinary action had to
precede the debarment. The same having not been done, the
debarment itself is vitiated, being de hors the Rules which are binding
on the respondents.
12. Learned counsel for the respondents argues that the termination had
no nexus with the debarment and the two are independent processes.
By placing reliance on the last paragraph of the impugned debarment
order, it is pointed out that sub-clause (iii) stipulates that running
contracts would remain unaffected by the debarment.
13. Thus, even if extension of time was granted for completion of the
contract pursuant to the order of the coordinate Bench, the said
proceeding entirely related to the termination of the existing contract,
which was waived. However, the same does not have any bearing on
the debarment of the petitioners to participate in future contracts for
two years.
14. Learned counsel argues that the petitioner no.1 was repeatedly given
opportunities and extensions to complete the work. However, the
petitioners long exceeded the time and despite several extensions
could not complete the work in time which necessitated the
debarment order.
15. It is argued that the original work commenced from March 23, 2019
and was to be completed by February 22, 2021. The planning period
was five months and the next eighteen months were for execution of
the work. However, even recently, the petitioners could not complete
the work. The nature of the work was a public project relating to
education and the project got hampered severely due to the
incompetence of the petitioners, for which the debarment order had to
be made.
16. Heard learned counsel for the parties.
17. A salient feature of the present case is that the Show-Cause Notice
dated September 30, 2022 which preceded the impugned debarment
was based on Clause 13.6 of the Rules. The said Clause provides that
the contractor may be debarred if he fails to execute the contract or
executes it unsatisfactorily or violates any conditions of the contract.
The pre-condition is that the said grounds have to be established by
enquiry.
18. However, there is nothing in the Rules to read into such provision any
prior right of hearing before enquiry. The allegedly errant contractor
already has an opportunity of replying to the show cause before
debarment. There is no reason to read into the provisions of the
contract a further right of hearing/reply even for the purpose of
enquiry preceding a show cause. The enquiry is only for the purpose
of the authorities forming a preliminary opinion to decide whether a
show cause should be issued and the contractor cannot have a say
even at that stage, since ample opportunity of reply/show cause is
given after the show cause notice.
19. A show-cause is mandatorily to precede a debarment in terms of
Clause 13.7. Clause 13.7 of the Rules provides that whenever any
type of complaint listed in serial no. (a) to (t) under Clause 13.6, is
received from any officer of CPWD not below the rank of Executive
Engineer against an enlisted contractor and is considered serious by
the enlisting authority, he shall be served with suitable show-cause
notice by the enlisting authority and thereafter action for debarment
of contractor may be taken by the enlisting authority as deemed fit.
20. Thus, the only requirement is to give a show-cause notice to the
concerned contractor. In the present case, a show-cause notice was
issued and a reply thereto was given by the petitioners, which was
considered while passing the final order.
21. The argument of the petitioners that there was no preceding enquiry is
neither here nor there, since the petitioners assert that only upon
such enquiry was the step of issuing a show cause taken.
22. Insofar as the enquiry is concerned, no notice of hearing is
contemplated on the accused contractor. If such a provision were to
be incorporated into the Rules, the same would create unnecessary
paraphernalia which would paralyse the functioning of the authorities
themselves. The enquiry is internal. The requirement of Clause 13.7
is only for the CPWD to consider the complaint to be "serious".
23. Although Clause 13.4 stipulates that the disciplinary action against
an enlisted contractor may lead to penalties mentioned in Rules 13.6
and 13.7, it does not necessarily mean that the debarment under
Clause 13.7 must necessarily await the competition of a disciplinary
proceeding. A disciplinary action as comprised in the Rules is under
Clause 13.0 of the Rules. Clause 13.1 provides that where the
contractor "has made himself liable for disciplinary action" the
enlisting authority shall have the right to debar him.
24. Clause 13.2 provides that the enlisting authority shall initiate
disciplinary case against an enlisting contractor either suo-moto or on
the receipt of a written request from an officer not below the rank of
Executive Engineer and forward it to the Empowered Committee for
consideration.
25. The Empowered Committee shall consider the disciplinary case on the
basis of the documents, facts and circumstances and shall issue a
show-cause notice to the contractor and allow him personal hearing if
necessary and forward its recommendations to the enlisting authority.
The enlisting authority shall take a decision on the basis of the
recommendations of the Empowered Committee which shall be final
and binding on the contractor. Thus, in terms of the language of
Clause 13.2, a personal hearing will be afforded to the contractor "if
necessary". The same is not a mandate in terms of the Rules.
26. Section 114 of the Evidence Act raises a presumption of official works
having been duly done. Thus, in the absence of rebuttal by the
petitioners, there is nothing to show that the respondents failed to
comply with the prior enquiry as contemplated in Clause 13.2 of the
Rules.
27. In fact, the show-cause notice issued to the petitioners dated
September 30, 2022 specifically cites the grounds of debarment of the
petitioners.
28. Numerous letters written by the authorities to the petitioners for
completion of the work were cited. The grounds as mentioned in sub-
clauses (a) and (b) of 13.6 of the Rules were specifically mentioned and
the exact violation of conditions of contract even after repeated notice
of the engineer-in-charge were cited in the show-cause notice.
29. In the last sentence of the show-cause notice, it was categorically
mentioned that the notice was issued with the approval of the
Empowered Committee constituted as per Rule 13 of the Enlistment
Rules, 2022.
30. Thus, there was sufficient compliance of the provisions of Rule 13 and
its sub-rules.
31. Hence, there was no error on the part of the respondents in duly
complying with the provisions of the Rules, which have statutory
force, in issuing the show-cause notice and passing the order of
debarment.
32. Sufficient opportunity of representation was given to the petitioners,
which was availed by the petitioners and the representations of the
respondents were considered by the petitioners. Since personal
hearing was not mandatory, not giving the same does not vitiate the
order of debarment.
33. The impugned order of debarment, in fact, is well-reasoned and cites
the relevant provisions of the Rules. The exact flaws and breaches of
the petitioners were enumerated in detail in the order of debarment.
The petitioners, despite repeated opportunities, failed to complete the
work even after expiry of double the period than the period originally
contemplated for the work.
34. Insofar as the previous order of the coordinate Bench in WPA
No.16962 of 2022 is concerned, the same categorically pertained to
the competition of the current work by the petitioners.
35. The court categorically observed that since the petitioners had
admittedly completed about seventy per cent of the project and
keeping in view the apparent financial distress of the petitioners, the
coordinate Bench directed the work to be completed expeditiously.
However, the said directions or the extensions given to the petitioners
pursuant to such order do not, in any manner, exonerate the
petitioners for the inordinate delay already committed by the
petitioners over a prolonged period of time.
36. The respondent, thus, cannot be compelled to permit the petitioners to
participate, even after such gross incompetence, in the future
contracts to be floated by the respondents.
37. In any event, the debarment order is only for a period of two years and
is not a permanent impediment or slur on the petitioners.
38. Thus, there is no ground for interference with the impugned
debarment order.
39. Accordingly, WPA No. 21702 of 2023 is dismissed on contest without,
however, no order as to costs.
40. Urgent certified server copies, if applied for, be issued to the parties
upon compliance of due formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!