Citation : 2023 Latest Caselaw 3483 Cal
Judgement Date : 17 May, 2023
IN THE HIGH COURT AT CALCUTTA
Constitutional Writ Jurisdiction
Appellate Side
Present :-
The Hon'ble Justice Moushumi Bhattacharya
W.P.A 1050 of 2023
Sigma Rail Systems Private Limited & Anr
vs.
Research Designs & Standards Organization, Ministry of Railways & Ors.
For the petitioners : Mr. Kishore Datta, Sr. Adv.
Mr. Jishnu Saha, Adv.
Mr. Sakya Sen, Adv.
Mr. Somdutta Bhattacharyya, Adv.
Mr. P. Roy Chowdhury, Adv.
Ms. Roshni Deepta Acharya, Adv.
MR. Dhruv Chadha, Adv.
For the respondent nos. 1 to 3/RDSO : Mr. Pranit Kumar Roy, Sr. Adv.
Mr. Pratip Mukherjee, Adv.
Ms. Sarda Sha, Adv.
Ms. Atmaja Bandyopadhyay, Adv.
Last Heard on : 02.05.2023.
Delivered on : 17.05.2023.
2
Moushumi Bhattacharya, J.
1. The petitioner no. 1 is a manufacturer of a signalling device referred to
as MSDAC which is installed to detect movement of trains. The petitioners'
signalling equipment is required to be approved by the respondent no. 1
Research Designs and Standards Organisation (RDSO), Ministry of
Railways, before the equipment is sold to the Railways.
2. The petitioners claim, through learned counsel, that all the
parameters for approval were obtained by the petitioners as per the RDSO
Specification prior to the petitioner no. 1 being enlisted as a vendor. It is
also the petitioners' case that the petitioners' products have been inspected
and approved on 69 earlier occasions by the Executive Director of RDSO,
Kolkata/respondent no. 3 and no complaint was ever made by the
respondents or by any of the Zonal Railways in respect of the said products.
3. The facts relevant to the matter would appear from the following
paragraphs.
4. The petitioner no. 1 manufactures the MSDACs once an order is
placed by the Railways and thereafter places the equipment for inspection.
The respondent no. 3 was the authority who carried out the inspection of
the petitioners' products on all previous occasions, in terms of clause 11.4.1
of the RDSO Specification. The format of inspection is referred to as the
Acceptance Test Proforma (ATP) which is part of the records. The records
indicate that the Railways have always given a positive feedback with regard
to the petitioners' products. There are no contemporaneous letters to show
that the RDSO or any of the Railways made any complaint with regard to
the petitioners' products.
5. The correspondence exchanged between the parties shows that the
petitioners' products were rejected for the first time on 9.11.2022 on the
ground that MSDAC does not comply with clause 5.4.3 of the RDSO
Specification Version 3.0. This however appears to be a pre-determined
rejection since the inspection of the products was actually carried out on
10.11.2022, which is a day after the recorded rejection. Both these
documents are part of the records. This was followed by a letter of
14.11.2022, addressed to the respondent no. 1, where the Executive
Director, RDSO Kolkata complained that the petitioners' products were not
compliant with clauses 5.4.3 and 5.3.7 of the RDSO Specification. The letter
however accepted that the tests were not included in the ATP.
6. Significantly, RDSO replied to this by a letter of 15.11.2022
specifically stating that clause 5.4.3 had been examined in respect of the
resetting; that the Specification did not restrict the number of evaluators to
be used to achieve the track section-wise resetting preparatory
reset/conditional hard reset; compliance of clause 5.3.7 had been submitted
by the petitioners at the time of approval and that inspection of material
submitted by the petitioners should be carried out as per the RDSO
approved Test Format as was being done earlier. A letter of 15.12.2022 from
the North East Frontier Railways/respondent no. 4 also stated that clause
5.4.3 of the RDSO Specification does not specify the use of number of
evaluators and further stated that the resetting process may involve two
evaluators.
7. Notwithstanding the above certifications, the RDSO sent a letter to the
petitioners on 2.1.2023 stating that the Vigilance Cell had advised
Independent Safety Assessment (ISA) certification and testing of the
MSDACs in Indian conditions to ensure passengers safety, and that the
product inspection of the petitioners equipment would be withheld till the
ISA certification and testing is complete.
8. The petitioners approached the Court at this stage. The petitioners
were given interim protection by an order dated 9.2.2023 and the RDSO was
directed to file a Report regarding the number of evaluators and the
acclimatization of the petitioners' equipment to Indian condition. The
interim order contains certain findings including on the RDSO's letter of
15.11.2022 stating that the Specification did not restrict the number of
evaluators and that the petitioners had conformed with clauses 5.4.3 and
5.3.7 of the Specification and further that the impugned action of
withholding product inspection was contrary to the RDSO Vendor
Guidelines of 30.12.2022. The RDSO was also directed to continue with the
products inspection of the petitioners without prejudice to its rights and
subject to the final decision in the Writ Petition in the manner which had
been followed by the RDSO before the inspection was stopped.
9. The petitioners thereafter filed a contempt proceedings on RDSO's
alleged non-compliance of the direction dated 9.2.2023, which was later
agreed to be disposed of in favour of the final hearing of the writ petition.
10. Several documents were produced by the parties before the final
hearing of the writ petition which includes an Inspection Report of the
petitioners' products pursuant to inspections held on 29.03.2023 and a final
Report in the form of an affidavit was filed by the respondent nos. 1 to 3 in
reply to the petitioners' affidavit-in-reply. It appears from the totality of the
documents filed before the Court that the issue is of the petitioners' alleged
non-compliance and violation of clauses 5.4.3, 5.3.7 and 5.0.5 of the RDSO
Specification.
11. Clause 5.4.3 relates to track section wise resetting as preparatory
reset or conditional hard reset. The Specification does not mention the
number of evaluators to be used and the letters from the respondents dated
15.11.2022 and 26.11.2022 clarified that there is no restriction on the
number of evaluators to be used for achieving both types of resetting. The
letter of 26.11.2022 also stated that the petitioners are in compliance with
clause 5.4.3 of the RDSO Specification. The contents of this letter is also
reiterated by a letter of the North East Frontier Railways dated 15.12.2022.
It is undisputed that the Executive Director of RDSO, Kolkata, respondent
no. 3, tested and approved the petitioners' products using two evaluators on
69 previous occasions spread over a period of 3 years.
12. Since there has been no change in the products manufactured by the
petitioners which all along conformed to the ATP, the sudden refusal on the
part of the RDSO and respondent no. 3 to inspect the petitioners' products
is untenable and contrary to the conduct expected of a statutory authority.
13. Moreover, the so-called "joint inspection" which took place on
10.11.2022 was done unilaterally by the respondent no. 3. As stated earlier,
the alleged non-conformity Report was issued a day earlier on 9.11.2022.
The petitioners' bona fides would also appear from a letter dated 22.2.2023
whereby the petitioners offered to supply extra evaluators at no additional
cost in keeping with the requirements of the Railways. The petitioners have
also enclosed a document to show that the signalling equipment produced
by the petitioners' competitors at various places all over the country use two
evaluators and that such equipments have been approved by the RDSO.
14. The other area of alleged non-compliance is clause 5.3.7 of the RDSO
Specification. The letters of RDSO dated 15.11.2022 and 26.11.2022 have
already clarified that the petitioners are in compliance with the clauses of
the RDSO Specification including clause 5.3.7. The letter of 26.11.2022
further states that the joint inspection carried out on 11.11.2022 by the
Executive Director RDSO is not appropriate considering the Specification
clause. It is also significant that the respondent no. 3 admitted in his letter
dated 14.11.2022 addressed to the RDSO that the tests conducted to check
compliance are not part of the approved ATP.
15. The respondents have further alleged the violation of clause 5.0.5 of
the RDSO Specification. This is a new ground taken in the final Report in
the form of affidavit filed by the respondent nos. 1-3. The materials placed
before the Court show that the testing for clause 5.0.5 of the Specification
which requires the push trolley wheels to not be counted by MSDAC is also
covered since the tests for compliance of clause 5.0.5 have successfully been
conducted in laboratory conditions by the RDSO before giving approval of
the petitioners' equipment. There was a further field testing of the
equipment by the RDSO after approval and also by the respondent no. 3 on
69 earlier occasions. The tests were conducted by using standard wheel
diameter of 450 mm and the product was passed in accordance with the
ATP. The documents disclosed subsequently however show that the
Executive Director RDSO tested the equipment using a non-standard wheel
diameter of 560 mm which is not permitted since the RDSO itself has
specified uniform dimensions for trolley wheels used by the Indian Railways.
Moreover, the joint testing of the petitioners' products by the Southern
Railways and the South East Central Railway on 6.3.2023 and 10.3.2023
respectively, found the equipment to be satisfactory and the MSDAC units
were found to be in compliance with the RDSO Specification including
clause 5.0.5.
16. A significant fact which was taken into account by the Court at the
time of passing the interim order dated 9.2.2023 was the trigger for the
sudden volte face of the RDSO. Records show that the inspection of the
petitioners' products was stopped on a complaint received by a person
holding himself out to be an Advocate of Supreme Court. RDSO's conduct of
acting upon this stray compliant is contrary to the Indian Railways Vigilance
Manual and the Central Vigilance Commission Guidelines and stopping of
the inspection was also contrary to the RDSO Vendor Guidelines in this
regard.
17. It may also be pertinent to mention that the petitioner no. 1 sells its
equipment directly to the Railways at a cost of Rs. 300000/unit while its
competitors sell the same to traders who resell the equipment to the
Railways at Rs. 700000/unit. Hence resulting in an annual loss of
approximately Rs. 1100 crores to the Railways for 30,000 units of MSDAC
purchased by the Railways every year. The inexplicable refusal of the
respondents to inspect the petitioners' products and in essence render them
unviable without due cause, given that the petitioners' products have passed
the tests 69 times previously and by the same authorities, smacks of mala
fides. The presumable object of the entire exercise of refusing the inspection
of the petitioners' products is to prevent the petitioners from supplying the
equipment directly to the Railways and force the petitioners to route the
same through traders at a substantial higher price.
18. The arguments made by learned counsel appearing for the Railways
on the technical aspects of the matter including deployment of evaluators
according to detection points is outside of the pleadings and beyond the
RDSO Specification as well as the ATP.
19. WPA 1050 of 2023 is accordingly allowed and disposed of by by
cancelling the report dated 9.11.2022 and alleged joint report dated
10.11.2022. The respondent nos. 1, 2 and 3 are accordingly directed to
commence the inspection within a period of 7 days from today in accordance
with Specification framed by the RDSO and the ATP applying the identical
procedure for testing/inspection and with the same frequency as was being
done in the 69 prior occasions before the impugned documents dated
9.11.2022 and 10.11.2022 were issued. The petitioners' equipment shall be
inspected by the RDSO and respondent no. 3 within a period of 7 days as
directed from the date of this judgment.
20. Learned counsel appearing for the respondent no. 1 prays for stay of
the operation of the Judgment. Considering the facts and circumstances
discussed in the judgment and the proceedings where contempt initiated by
the petitioners was shelved for hearing of the main writ petition, the prayer
for stay is considered and refused.
Urgent photostat certified copies of this judgment, if applied for, be
supplied to the parties upon fulfillment of requisite formalities.
(Moushumi Bhattacharya, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!