Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Hanif Haque vs The West Bengal State Electricity ...
2023 Latest Caselaw 2148 Cal

Citation : 2023 Latest Caselaw 2148 Cal
Judgement Date : 30 March, 2023

Calcutta High Court (Appellete Side)
Hanif Haque vs The West Bengal State Electricity ... on 30 March, 2023
30th March,
  2023
  (AK)
   03
                                   W.P.A 7255 of 2023

                                   Hanif Haque
                                         Vs.
               The West Bengal State Electricity Distribution Company
                                Limited and others


                             Mr. Falguni Bandyopadhyay
                             Ms. Riya Ballav
                                                    ...for the petitioner.

                             Mr. Mihir Kundu
                                                        ...for the WBSEDCL.


                    Learned counsel for the petitioner argues that the

              petitioner is a cultivator and applied for a new electricity

              connection in order to operate his submersible pump,

              upon which the WBSEDCL, by a communication dated

              January 31, 2023, indicated that the Techno Commercial

              feasibility of the scheme is not viable as the total

              estimated cost of the scheme is more than Two Lakh

              Rupees.

                    It was further communicated that "so it is not

              possible to do the work by departmental cost".

                    The said communication is also relied on by learned

              counsel for the WBSEDCL, who also hands over a copy of

              the relevant Office Order No.52 dated May 5, 2012, which

              was   relied    on   in   the   said   communication   of   the

              WBSEDCL, as well as an estimate for conversion of 8MTR
                              2




DP substation to 4-Pole substation & augmentation of

DTR 63KVA to DTR 100KVA and erection of service poles.

     It is submitted that the total costs assessed for

constructing the substation necessary for giving the

electricity connection to the petitioner comes to about Rs.

2,65,319.65 p.

     However, on instruction, learned counsel submits

that the WBSEDCL, keeping in view the economic

condition of the petitioner, is agreeable to waive the cost

of Rs.2 lakh and take only Rs.65,000/- from the

petitioner.

     Upon a perusal of the communication-in-question

made by the WBSEDCL, which is annexed at page-35 of

the writ petition, it is seen that the same has relied on the

Office Order handed over by learned counsel for the

WBSEDCL.

     In the said Office Order, Clauses 4.4.1 to 4.4.5 of

Regulation 46 of the WBERC as well as Clause 2.8(b) of

another Office Order have been relied on by the

WBSEDCL.

     A cursory perusal of the said provisions indicate

that those provide for techno economic study in case the

feasibility of constructing a new substation is required to

be examined.

     In such case, two options are envisaged under the

Regulations. One, that the earnest money paid by the
                             3




petitioner shall remain with the licensee, in which case

the licensee shall hold a techno economic study as

referred to in Regulation 4.4.1.Upon such consideration,

if it is found from the detailed report of such techno

economic feasibility study that it will not be feasible to

erect/commission the new substation, the licensee is

required to communicate such decision under Clause

4.4.6(b) within the period of specified in Clause 4.4.5 in

writing to the applicant and refund the earnest money

along with interest.

     It is further stipulated that in the event the earnest

money is taken back by the applicant, no such techno

economic study will be undertaken and earnest money

will be refund.

     It is required to be considered in the matter as to

what is the exact interplay between the provisions of the

Regulations as indicated above, which have been relied on

by the WBSEDCL, vis-à-vis Section 43 of the Electricity

Act, 2003, read in conjunction with Article 21 of the

Constitution of India.

     For such consideration, judgment is reserved in the

matter.

     It is made clear that since factual aspects have not

been disputed as such and all the relevant documents are

mostly on record, no affidavits are being directed to be
                             4




filed. It will be deemed that the allegations made in the

writ petition have not been admitted by the respondents.

(Sabyasachi Bhattacharyya, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter